1. Field of the Invention
The present invention relates to a system for aiding the preparation of an operation and maintenance plan for a power generation installation, and, in particular, relates to an operation and maintenance plan preparation aiding system for a power generation installation, in which a service center is provided. The service center manages operation and maintenance of a plurality of power generation units and prepares an operation and maintenance plan for respective power generation units by making use of plant data obtained from the respective power generation units through a communication network.
2. Conventional Art
Generally, many electric power generation companies, which operate an electric power generation business, own a plurality of power generation units. In order to manage the amount of power generated by these power generation units as a whole, comprise respective power generation systems are provided with a power supply command center (central supply) for every electric power generation company. In such power generation systems, the power supply command center assigns and adjusts the power generation amount for every power generation unit in response to power demand from consumers and each of the power generation units performs an operation while maintaining and adjusting the power generation amount assigned by the power supply command center. In such instances, the power supply command center prepares, in view of enhancing economy, an operation plan for the concerned power generation system so as to minimize fuel cost used in the power generation units, and to maximize power generation efficiency. As well, the command center prepares a plan, in view of placing priority on environmental protection, to keep the exhaust gas amount, such as nitrogen oxides and carbon dioxides exhausted from the power generation units, within an allowable range.
Now, the characteristics with regard to power efficiency and the exhaust gas amount which are used as references for the operation planning vary greatly depending on the kinds of fuel used and the power generation methods. With regard to fuels, in case of a thermal power generation, many kinds of fuels such as coal, petroleum and natural gas can be used, therefore, depending on the kind of fuels used, not only the power generation amount per unit fuel cost but also the amount and contents of the exhaust gas vary greatly. Further, with regard to power generation methods, the constitutions of machines and apparatuses of themselves such as power generation by a steam turbine, power generation by a gas turbine and a combined power generation combining thereof affect greatly their power generation efficiency. The power supply command center stores and preserves plant data (data representing the plant characteristics) obtained from these power generation units for every power generation unit, and uses the plant data when preparing operation plans for respective power generation units.
In the above referred to conventional power generation system, although the power supply command center stores and preserves the plant data for every power generation unit, these plant data were limited to the plant data at comparatively early stage of the respective power generation units, such as design values and those at the operation starting period of the power generation plants, however, the plant data varies gradually depending on passage of time as well as the contents of fuel being used, which also varies, therefore, it is difficult to prepare operation plans based on the current plant characteristics of the respective power generation units by making use only of the plant data.
Further, the above referred to conventional power generation system, since the machines and apparatuses such as a gas turbine constituting the power generating unit are always exposed to a high temperature, if load variation to the machines and apparatuses is frequently and repeatedly caused, deterioration of the machines and apparatuses due to thermal fatigue rapidly advances. For this reason, even if a fully economic operation which simply minimizes fuel cost for respective power generation units is employed, when the load variation to the machines and apparatuses is repeated, the lifetime of the machines and apparatuses is shortened, thus quickening the exchange time thereof, and therefore the total cost for the respective power generation units necessary for the plant operation, including the maintenance cost, is not necessarily minimized. Further, in the above referred to conventional power generation system, even if a plurality of power generation units having a high power generation efficiency are positively selected for the operation, when a provability of failure of the machines and apparatuses and the parts thereof constituting the power generation unit concerned is high, an unplanned outage is caused by a failure occurrence in the machines and apparatuses and the parts thereof which possibly causes an economic loss, therefore, even when an operation plan for a plurality of power generation units is prepared only based on fuel cost, the resultant cost was not necessarily minimized.
The present invention has been achieved in view of the above technical background, and an object of the present invention is to provide a system for aiding in the preparation of an operation and maintenance plan for a power generation installation in which an operation plan for a plurality of power generation units is prepared by making use of actual plant data, and being based on a total judgement, including a variety of circumstances of the machines and apparatuses and the parts thereof in the power generation units.
A first aspect of the present invention is to provide a system for aiding in the preparation of an operation and maintenance plan for a power generation installation in which a plurality of power generation units, a power supply command center and a service center are arranged and connected via communication networks, the service center obtaining plant data from the plurality of power generation units via the respective communication networks. For every power generation unit, the service center calculates power generation efficiency for the concerned power generation units in real time by making use of the obtained plant data and design data of the concerned power generation units and prepares operation and maintenance plans for the respective power generation units based on the calculated power generation efficiency.
According to the first aspect of the present invention, since the operation and maintenance plans for the respective power generation units are prepared in the service center based on the power generation efficiency evaluated and calculated in real time, a secular change and a performance degradation due to failure occurrence for the respective power generation units can be taken into account, thereby, the operation cost thereof can be reduced in comparison with the conventional power generation system in which the operation and maintenance plans for the respective power generation units are prepared by making use of the plant data.
A second aspect of the present invention is to provide a system for aiding in the preparation of an operation and maintenance plan for a power generation installation in which a plurality of power generation units, a power supply command center and a service center are arranged and connected via communication networks, the service center obtains plant data from the plurality of power generation units via the respective communication networks, and for every power generation unit, estimates process values in a machine and apparatus model by making use of the obtained plant data, determines deviation values between the estimated values and measured values, calculates from the determined deviation value a cost of economical loss caused by a power generation efficiency reduction of the concerned power generation unit, and prepares operation and maintenance plans for the respective power generation units through comparison between the calculated cost of economical loss and a cost relating to exchange of the machine and apparatus and the parts thereof in the concerned power generation unit.
According to the second aspect of the present invention, when preparing the operation and maintenance plans for the respective power generation units in the service center based on the power generation efficiency evaluated and calculated in real time, since the cost of economical loss due to the performance degradation is calculated from the deviation value between the process value estimated with the machine and apparatus model and the measured value, the cost of economical loss is compared with the cost relating to the exchange of the machine and apparatus and the parts thereof and the operation and maintenance plan of the respective power generation units are prepared by making use of the comparison result, the total cost for the operation and maintenance can be reduced.
A third aspect of the present invention is to provide a system for aiding in the preparation of an operation and maintenance plan for a power generation installation in which a plurality of power generation units, a power supply command center and a service center are arranged and connected via communication networks. The service center obtains plant data from the plurality of power generation units via the respective communication networks. For every power generation unit, the service center calculates remaining lifetime of the machine and apparatus and the parts thereof in the concerned power generation unit by making use of the obtained plant data and prepares operation and maintenance plans for the respective power generation units by determining exchange time of the machine and apparatus and the parts thereof in the concerned power generation unit based on the calculated remaining lifetime thereof.
According to the third aspect of the present invention, when preparing the operation and maintenance plans for the respective power generation units in the service center based on the power generation efficiency evaluated and calculated in real time, since the operation and maintenance planes are prepared based on the calculated remaining lifetime, an exchange timing of the machine and apparatus and the parts thereof can be determined with high accuracy in comparison with the conventional power generation system in which exchange of the machine and apparatus and the parts thereof is performed with reference to an accumulated operation time thereof, as a result, an abnormality occurrence due to use of the machine and apparatus and the parts thereof exceeding their lifetime and generation of economical loss due to unplanned outages caused by an abnormality of the machine and apparatus and the parts thereof can be prevented, moreover, an exchange at every predetermined period of the machine and apparatus even if there is a remaining lifetime is unnecessitated, thereby, the maintenance cost can be reduced.
A fourth aspect of the present invention is to provide a system for aiding in the preparation of an operation and maintenance plan for a power generation installation in which a plurality of power generation units, a power supply command center and a service center are arranged and connected via communication networks, the service center obtaining plant data from the plurality of power generation units via the respective communication networks and, for every power generation unit, calculating remaining lifetime of the machine and apparatus and the parts thereof in the concerned power generation unit by making use of the obtained plant data, comparing the calculated remaining lifetime with remaining lifetime of the machine and apparatus in the power generation unit determined in the other power generation unit, modifying the operation condition for the machine and apparatus and the parts thereof so as to enhance economy and prolong or shorten the remaining lifetime of the machine and apparatus and the parts thereof in the concerned power generation unit, thereby, preparing the operation and maintenance plans for the respective power generation units.
According to the fourth aspect of the present invention, when preparing the operation and maintenance plans for the respective power generation units in the service center based on the power generation efficiency evaluated and calculated in real time, since the operation condition for the machine and apparatus in its own power generation unit is modified based on the remaining lifetime of the machine and apparatus and the parts thereof not only in its own power generation unit but also in another power generation unit, the operation and maintenance plans can be prepared so that the total cost necessary for the operation and maintenance for the respective power generation units is minimized, the cost merit obtained by the electric power generation by the electric power generation company can be increased in comparison with the conventional power generation system.
Hereinbelow, embodiments of the present invention will be explained with reference to the drawings.
As shown in
The electric power generation company 2 requests the service center 1 to prepare an operation and maintenance plan for the power generation units 41 and 42 owned by the A power generation plant 4 and the power generation units 51 and 52 owned by the B power generation plant 5.
Now,
As shown in
Further, as shown in
In the power generation unit 41, when the process value transmission unit 417 transmits process data, which is transferred via the communication network 6 to the side of the service center 1, the service center 1 obtains via the fire wall 11 the process data, transfers the obtained process data from the process value receiving unit 12 to the process value database 13 and stores the same therein. Further, other process data transferred from other power generation units 42, 51 and 52 are likely stored in the process value database 13.
Herein,
As shown in
The power supply command center 3 transmits a power demand amount required to be supplied by the electric power generation company 2 as power demand information to the service center 1 via the communication network 6. Since the power demand information varies from time to time depending on power demand, the information is transmitted in a predetermined cycle, for example, every 1 sec. to the service center 1. The service center 1 receives the power demand information via the fire wall 11 at the power demand amount receiving unit 23, and supplies the received power demand information to the operation plan evaluation unit 25. In this instance, the operation plan evaluation unit 25 distributes power generation amounts for the respective power generation units 41, 42, 51 and 52 so that the summed value of the power generation amounts of the respective power generation unit 41, 42, 51 and 52 coincides with the required value, and supplies the distribution result to the operation plan information transmitting unit 24. The operation plan information transmitting unit 24 transmits the operation plan information, namely the power generation amount information distributed to the respective power generation units 41, 42, 51 and 52 to the power supply command center 3 via the communication network 6. The power supply command center 3 confirms the contents of the operation plan information sent from the service center 1 and outputs the command values of the power generation amount for the respective power generation units 41, 42, 51 and 52 according to the operation plan information.
The explanation until now relates to operation planning in response to power demand which varies from time to time in the operation and maintenance plan preparation aiding system for a power generation installation, however, other than the above, the present operation and maintenance plan preparation aiding system for a power generation installation also prepares a long term operational plan. For example, the system prepares such maintenance plans in which, based on the plant data obtained on-line, conditions of the machine and apparatus and the parts thereof in the power generation units are judged, such that disassembling and inspection of the power generation units and exchanging of the parts thereof are performed according to the judgement result, and the timing of the periodic inspection of the power generation units is adjusted.
The above is an outline of the service which the service center 1 provides to the electric power generation company 2.
Hereinbelow, details of processing steps performed by the service center 1 for preparing the operation and maintenance plan will be explained.
The service center 1 uses power generation efficiency in the respective power generation units as one of the parameters for preparing the operation plan. Hereinbelow, the processing for calculating the power generation efficiency will be explained.
In the service center 1 as shown in
As shown in
Further, the efficiency diagnosis unit 19 refers to a machine and apparatus model in the machine and apparatus model database 14 in order to calculate the power generation efficiency.
As shown in
The efficiency diagnosis unit 19 causes the program to operate according to the input and output specifications stored in the machine and apparatus model database 14.
Now, processing steps which perform the efficiency diagnosis by making use of the machine and apparatus model will be explained.
As shown in
The efficiency diagnosis unit 19 converts the performance calculation result determined by means of the machine and apparatus models into power generation cost and compares the same with the power generation cost determined from the actual measurement value from the plant data.
In
Subsequently, the preparation of the operation and maintenance plan by making use of the power generation cost calculated in the efficiency diagnosis unit 19 is performed in the operation plan evaluation unit 25. Hereinbelow, the processing performed in the operation plan evaluation unit 25 will be explained.
The operation plan evaluation unit 25 uses the power generation costs determined on-line for the respective power generation units 41, 42, 51 and 52, and prepares a plan from an economic point of view so as to positively operate a power generation unit or units having a lower power generation cost among the power generation units 41, 42, 51 and 52. For example, in the power generation unit 41 among the power generation units 41, 42, 51 and 52, if deterioration of, for example, the gas turbine among its constituting machines and apparatus advances and the efficiency thereof decreases, a deviation is caused between the power generation cost based on the actually measured value determined from the process data in the power generation unit 41 and the power generation cost determined from the estimation value by means of the machine and apparatus models as explained above. In such instance, the operation plan evaluation unit 25 evaluates the economic loss due to the performance deterioration according to the following equation (1);
L1=C×A×D1 (1)
wherein, L1: Economic loss due to performance deterioration (¥)
In the equation (1), the power generation amount A per day is determined by averaging the cumulative electric power output amount in respective operation days. When multiplying the power generation amount A per day with the remaining days D1 until the periodic inspection, an estimated possible power generation amount until the periodic inspection can be calculated. Information with regard to a plan on the periodic inspection is stored in the periodic inspection information database 26.
As shown in
Subsequently, the operation plan evaluation unit 25 judges, in view of the total cost incurred for the operation and maintenance, whether operation of one power generation unit, for example, the power generation unit 41 has to be stopped and the machines and apparatuses and the parts thereof have to be exchanged or the operation thereof has to be continued under the performance deteriorating condition. In this instance, the operation plan evaluation unit 25 calculates the cost in association with the change of the machines and apparatuses or the parts thereof with reference to the machine and apparatus information database 27.
As shown in
L2=P×(1·R)+A×D2 ×E (2)
wherein, L2: Economic loss (¥) in association with machine and apparatus/part exchange
In the equation (2), with regard to the purchase price (P) of the machine and apparatus and parts, the information stored in the machine and apparatus information database 27 is referred to. The depreciation is evaluated in view of the remaining lifetime and uses the already consumed lifetime (R) as a parameter therefor. The consumed lifetime value (R) is a normalized value, and under a brand-new condition when beginning use, the value is 0 and the value increases depending on the use years and becomes 1 when the exchange level has been reached. Namely, the consumed lifetime value (R) of 1 implies that the concerned machine and apparatus have been used up and no value remains there. A calculation method of the consumed lifetime value (R) will be explained later. Further, with regard to the loss of electric power sales opportunity, the power generation amount not generated because of the exchange of the machine and apparatus or the parts thereof can be calculated by multiplying the power generation amount (A) per day by the number of days (D2) required for installation work stored in the machine and apparatus information database 27, and when the electric power sales price (E) is multiplied by the above calculated non-power generation amount, the economic loss in association with the exchange of the machine and apparatus or the parts thereof can be calculated.
The operation plan evaluation unit 25 compares the economic loss (L1) due to the performance deterioration with the economic loss in association with the exchange of the machine and apparatus or the parts thereof. When the performance deterioration of the power generation unit advances and the economic loss (L1) exceeds the economic loss (L2), the operation plan evaluation unit 25 plans to stop the operation of the power generation unit and to exchange the machine and apparatus or the parts thereof, and further plans to compensate the power generation amount decreasing component due to the operation stoppage of the power generation unit with a power generation amount increasing by other power generation unit or units.
Further, the service center 1 uses the remaining lifetime of the machine and apparatus or the parts thereof as one of the parameters for preparing the operation plan. Hereinbelow, the processing of calculating the remaining lifetime will be explained.
In the service center 1, the remaining lifetime diagnosis unit 20 performs evaluation of the remaining lifetime of machines and apparatuses or the parts thereof, and evaluates the remaining lifetime of the power generation unit based on the remaining lifetime evaluation data for the respective power generation units stored in the material information database 15.
The parts such as the gas turbine, which are subjected to high temperatures during the operation thereof, are caused of thermal fatigue damage induced by thermal stress variation in association with the applied temperature as well as caused of creep damage which advances depending on the height of the applied temperature and duration time thereof. These damages induce damages such as cracks if a predetermined critical value is exceeded and can cause a significant accident.
As shown in
Further, in the graph representing the creep damage, the ordinate represents normalized creep damage value, the abscissa represents accumulated value of exhaust gas temperature for every 10 sec., and when the creep damage value reaches to 1, the material endurance with regard to the creep damage reaches to a critical value. The creep damage value simply increases depending on lapse of time. The consumed lifetime of a gas turbine is determined by the sum of the thermal fatigue damage value and the creep damage value by taking into account both influences by the thermal fatigue damage and by the creep damage. Namely, the consumed lifetime (R) is determined by the following equation (3);
R=H+C (3)
wherein, H: Thermal fatigue damage value (normalized value)
The consumed lifetime value of a brand-new gas turbine at the time of installation is 0 and the value gradually increases through repetition of such operations including temperature variation as starting up/stopping and load adjustment in addition to usual operation. In order to evaluate the remaining lifetime of a gas turbine, based on the consumed lifetime until now, a possible consumed lifetime thereafter is extrapolated and estimated according to the mathematical formula representing the consumed lifetime value, and the remaining lifetime is determined by the remaining time until the estimated result reaches to the consumed lifetime value of 1 representing the exchange level.
In the service center 1, the operation plan evaluation unit 25 obtains the remaining lifetime data evaluated by the remaining lifetime diagnosis unit 20 and prepares the operation plan by making use of the obtained remaining lifetime.
The flow chart will be explained with reference to
Subsequently, in step S2, the operation plan evaluation unit 25 determines the days until the subsequent periodic inspection for the concerned power generation unit with reference to the periodic inspection information database 26 and judges whether the calculated remaining lifetime days are larger or shorter than the determined days until the subsequent periodic inspection. Then, if it is judged that the remaining lifetime days are longer than the days until the subsequent periodic inspection (Y), the process moves to the next step S3, on the other hand, if it is judged that the remaining lifetime days are shorter than the days until the subsequent periodic inspection (N), the process moves to the next step S4.
Subsequently, in step S3, the operation plan evaluation unit 25 prepares an operation plan for the concerned power generation unit to perform a usual operation and ends the series of processings in the flow chart.
Further, in step S4, the operation plan evaluation unit 25 reduces the maximum power generation amount in the concerned power generation unit by 25% and sets the same at 75% of the current power generation mount, and further reduces the load adjustment amount which varies depending on the power demand by 25% and sets the same at 75% of the current load adjustment amount, and prepares an operation plan which intends to prolong the remaining lifetime of the concerned power generation unit.
In the subsequent step S5, the operation plan evaluation unit 25 judges whether or not the maximum power generation amount in the concerned power generation unit has been reduced by 100%. Then, if it is judged that the maximum power generation amount has been reduced by 100% (Y), the process moves to the subsequent step S6, on the other hand, if it is judged that the maximum power generation amount has not yet been reduced by 100% (N), the process moves to another step S7.
In step S6, the operation plan evaluation unit 25 repeats the process in step S4 four times which will be explained later, even through repeating the processings if the end of the lifetime is reached, the operation plan evaluation unit 25 prepares an operation plan to stop the operation of the concerned power generation unit and ends the series of processings in the flow chart.
Further, in step S7, the operation plan evaluation unit 25 prepares an operation plan which permits the continued operation of the concerned power generation unit for a week. Then, after a week when completing the operation plan, the process returns to step S1 and the operation plan evaluation unit 25 again causes to repeat steps following step S1.
In parallel with the above operation plan, the operation plan evaluation unit 25 prepares an operation plan in which another power generation unit having a higher power generation efficiency is positively selected for operation based on the power generation efficiency of the respective power generation units calculated in on-line. For example, as shown in
The above explanation shows an example in which, when preparing an operation and maintenance plan for power generation units by making use of the remaining lifetime data, deterioration of the machine and apparatus or the parts thereof advances more than that estimated and the exchange timing is hastened. When preparing a usual operation and maintenance plan for power generation units, it is planned based on the remaining lifetime data to exchange the machine and apparatus or the parts thereof at the time of the periodic inspection, however, if the end of the remaining lifetime comes earlier than that estimated because of changes in operational circumstances it is possible to prepare an operation plan which prevents the machine and apparatus or the parts thereof from exceeding their lifetime. Therefore, the operation and maintenance plan aiding system for a power generation installation according to the present embodiment can avoid unpredictable circumstances, which causes unplanned outages of the power generation unit due to an abnormality caused by the use of the machine and apparatus or the parts thereof exceeding their lifetimes, and can also avoid the economic loss caused by the unplanned outage of the power generation unit.
Contrary to the above example, an example can be prepared in which, based on remaining lifetime diagnosis result evaluated in real time, the exchange timing of the machine and apparatus or the parts thereof can be prolonged. For example, since a gas turbine is subjected to a high temperature and the deterioration thereof advances rapidly, an exchange standard time (for example, an accumulated operation time of 50,000 hours) is set in advance, and exchange of the machine and apparatus or the parts thereof is performed during the periodic inspection so as not to exceed the standard time. In such instance, if the remaining lifetime of the machine and apparatus or the parts thereof remains long, it is not necessarily required to exchange the machine and apparatus or the parts thereof when the standard time is reached, and the exchange timing can be extended. In such instance, in comparison with the exchange of the machine and apparatus or the parts thereof with reference to the standard time, the maintenance cost can be reduced.
Further, the service center 1 uses failure frequency of the machine and apparatus as one of the parameters for preparing an operation plan. Hereinbelow, the processing for calculating the failure frequency of the machine and apparatus will be explained.
In the service center 1, the failure frequency evaluation unit 21 evaluates the failure frequency of the machine and apparatus.
As shown in
The failure frequency evaluation unit 21 evaluates with how much probability (once in how many years) a failure of the respective machines and apparatuses or the parts thereof is caused by making use of the data stored in the failure information database 16 and supplies the evaluation result to the operation plan evaluation unit 25.
The operation plan evaluation unit 25 evaluates whether the machine and apparatus or the parts thereof in the respective power generation units can be used without failure up to which periodic inspection timing in the future by making use of the evaluation result supplied from the failure frequency evaluation unit 21 and the reference result of the periodic information database 26. Thereafter, when it is estimated according to the failure probability of the machines and apparatuses or the parts thereof that there are machine and apparatus or the parts thereof which only endures up to the timing of the subsequent periodic inspection, exchange of the machine and apparatus or the parts thereof is planned.
Further, the service center 1 uses a priority of manufacturers as one of the parameters for preparing the operation plan. Hereinbelow, the processing for calculating the priority of manufacturers will be explained.
In the service center 1, the manufacturer priority evaluation unit 22 evaluates priority of manufacturers based on the respective manufacturer information stored in the manufacturer information database 17.
As shown in
When the operation plan evaluation unit 25 selects a power generation unit for operation and if the manufacturer priority of the machine and apparatus or the parts thereof used in the power generation unit is high, the operation plan evaluation unit 25 prepares a plan which positively selects the concerned power generation unit for the operation.
As has been explained hitherto, the operation and maintenance plan aiding system for a power generation installation according to the present embodiment uses the performance diagnosis result, the remaining lifetime diagnosis result, the failure frequency and the priority of manufacturers when preparing an operation and maintenance plan for the respective power generation units.
In the embodiment as shown in
In
In this instance, since the rest of the operation of the system for aiding in the preparation of operation and maintenance plan for a power generation installation of the second embodiment as shown in
In the embodiment shown in
In the third embodiment, the service center 1 separately determines the power generation amount of the power generation units 41 and 42 which are under control of the power supply command center 3 and the power generation amount of the power generation units 51 and 52 which are under control of the power supply command center 7 in response to the power generation amount required by the respective power supply command centers 3 and 7 and being transmitted via the communication network 6, and transfers the determined result to the respective power supply command centers 3 and 7 via the communication network 6.
In this instance, since the rest of the operation of the system for a power generation installation of the third embodiment as shown in
In the embodiment as shown in
In this instance, since the rest of the operation of the operation and maintenance plan preparation aiding system for a power generation installation of the fourth embodiment as shown in
As shown in
The A electric power generation company 104 requests the service center 1 the business of preparing an operation and maintenance plan for the owning power generation units 41 and 42 as well as the B electric power generation company 105 requests the service center 1 the business of preparing an operation and maintenance plan for the owning power generation units 51 and 52.
Respective exemplary constitutions of the power generation unit 41 and the common service center 1 as shown in
As shown in
The power supply command center 43 of A electric power generation company 104 and the power supply command center 53 of B electric power generation company 105 transmit a power amount required to be supplied by the owning power generation units 41, 42, 51 and 52 as respective power demand information to the service center 1 via the communication network 6. Since this power demand information varies over time depending on power demand, the information is transmitted in a predetermined cycle, for example, every 1 sec. to the service center 1. The service center 1 receives the power demand information via the fire wall 11 at the power demand amount receiving unit 23, and supplies the received power demand information to the operation plan evaluation unit 25. In this instance, the operation plan evaluation unit 25 distributes for each electric power generation company 104 and 105 power generation amounts for the respective power generation units 41, 42, 51 and 52 so that the summed value of the power generation amounts of the respective power generation unit 41, 42, 51 and 52 coincides with the required value, and supplies the distribution result to the operation plan information transmitting unit 24. The operation plan information transmitting unit 24 transmits the operation plan information, namely the power generation amount information distributed to the owning respective power generation units 41, 42, 51 and 52 for respective electric power generation companies 104 and 105, to the power supply command centers 43 and 53 via the communication network 6. The power supply command centers 43 and 53 confirm the contents of the operation plan information sent from the service center 1 and outputs the command values of the power generation amount for the owning respective power generation units 41, 42, 61 and 52 according to the operation plan information.
The explanation until now relates to the operation planning for the owning power generation units 41, 42, 51 and 52 for each electric power generation company 104 and 105 in response to power demand which varies over time in the operation and maintenance planning preparation aiding system for a power generation installation, however, other than operating the owning power generation units, it is sometimes true that the total cost for the operation and maintenance can be reduced if the electric power is supplied from the power generation units owned by the other, in such instance the operation plan information transmission unit 24 in the service center 1 transmits the determined operation plan to the respective power supply command centers 43 and 53 for the respective electric power generation companies 104 and 105, and, after receiving agreement from the respective electric power generation companies 104 and 105, finalizes the operation plan. Thereafter, the power supply command centers 43 and 53 of the respective electric power generator companies 104 and 105 output power generation amount command values according to the operation plan to the respective owning power generation units.
Hereinbelow, the role of the service center 1 performed for a plurality of electric power generation companies will be explained.
As shown in
As shown in
Because of performance deterioration of a power generation unit when the operation of the power generation unit is stopped, it is necessary to increase the power generation amount of another power generation unit and to ensure that the power generation amount meets the electric power demand. In such instance, the following may happen in that the power generation cost (fuel cost per unit electric power output) increases, a power generation unit which is not used usually has to be operated and electric power has to be purchased from another electric power generation company.
The operation plan evaluation unit 25 investigates a method of obtaining the necessary power generation amount not only by taking into account the power generation cost of a company that owns the power generation unit that has been stopped, but also the power generation cost of a power generation unit owned by another electric power generation company. As has been explained above, the service center 1 calculates the power generation cost in real time based on the process values obtained from the power generation units. When stopping a power generation unit, at first with regard to respective power generation units owned by itself and others, respective power generation units having capacity to increase the power generation amount and having the minimum power generation cost are searched. Subsequently, with regard to the power generation cost of the other company, a cost is calculated by adding a predetermined price on the power generation cost of its own company and the calculated cost is compared with the power generation cost of its own company. When the power generation cost of the other company is cheaper even in view of the added total price, it is determined that the electric power is to be purchased from the other company. Namely, the operation plan evaluation unit 25 prepares an operation plan so as to increase the power generation amount of the power generation unit of the other company. As has been explained above, with regard to the power generation amount adjustment between, for example, A electric power generation company 104 and B electric power generation company 105, the service center 1 transmits the operation plan to the respective electric power generation companies 104 and 105 via the communication network 6 and, after obtaining agreement from the electric power generation companies 104 and 105, the operation plan is authorized. With regard to the agreement of the electric power generation companies 104 and 105, the service center 1 confirms the same via the communication network 6.
FIGS. 27(a) and 27(b) are characteristic diagrams showing a selection principle of the power generation units. Now, when the maximum power generation amount and the load adjustment amount of a certain power generation unit are decreased and if an electric power shortage as shown in FIG. 27(a) is caused, the electric power shortage is supplemented as shown in FIG. 27(b), while dividing the supplementing electric power into base increase and peak response. With regard to the base increase, a power generation unit with a low power generation cost is selected to increase the maximum power generation amount, and with regard to the peak response, a power generation unit having a longer remaining lifetime is selected to increase the load follow-up property.
In parallel with the above operation plan, the operation plan evaluation unit 25 prepares an operation plan in which another power generation unit having a higher power generation efficiency is positively selected for operation based on the power generation efficiency of the respective power generation units calculated in on-line. For example, as shown in
Generally, a power generation unit used for supplementing the power generation amount and the load adjustment is selected among the power generation units owned by itself, however, when such supplement can not be compensated by the power generation units commonly owned, an operation plan in which electric power is procured from the power generation units owned by another is prepared. In such instance, the price of the electric power is differentiated between a case wherein a predetermined amount of electric power is supplied for the base increase and a case wherein the supplied electric power varies depending on time for the peak response. Namely, with regard to the peak response, since the load is frequently varied which likely shortens the lifetime of the machine and apparatus or the parts thereof, therefore, the electric power price is determined by adding a predetermined value on the ordinary price.
The above explanation shows an example in which, when preparing an operation and maintenance plan for power generation units by making use of the remaining lifetime data, deterioration of the machine and apparatus or the parts thereof advances more than that estimated and the exchange timing is hastened. When preparing a usual operation and maintenance plan for power generation units, it is planned based on the remaining lifetime data to exchange the machine and apparatus or the parts thereof at the time of the periodic inspection, however, if the end of the remaining lifetime comes earlier than that estimated because of changes in operational circumstances, it is possible to prepare an operation plan which prevents usage of the machine and apparatus or the parts thereof exceeding their lifetime. Therefore, the operation and maintenance plan preparation aiding system for a power generation installation according to the present embodiment can avoid unpredictable circumstances which causes unplanned outage of the power generation unit due to an abnormality caused by the use of the machine and apparatus or the parts thereof exceeding their lifetimes, and can also avoid the economic loss caused by the unplanned outage of the power generation unit.
Contrary to the above example, an example can be prepared in which, based on remaining lifetime diagnosis result evaluated in real time, the exchange timing of the machine and apparatus or the parts thereof can be prolonged. For example, since a gas turbine is subjected to a high temperature and the deterioration thereof advances rapidly, an exchange standard time (for example, an accumulated operation time of 50,000 hours) is set in advance, and exchange of the machine and apparatus or the parts thereof is performed during the periodic inspection so as not to exceed the standard time. In such an instance, if the remaining lifetime of the machine and apparatus or the parts thereof remains long, it is not necessarily required to exchange the machine and apparatus or the parts thereof, when the standard time is reached and the exchange timing can be extended. In such an instance, in comparison with the exchange of the machine and apparatus or the parts thereof with reference to the standard time, the maintenance cost can be reduced.
Further, the service center 1 uses failure frequency of the machine and apparatus as one of the parameters for preparing an operation plan. Hereinbelow, the processing for calculating the failure frequency of the machine and apparatus will be explained.
In the service center 1, the failure frequency evaluation unit 21 evaluates the failure frequency of the machine and apparatus.
As shown in
The failure frequency evaluation unit 21 evaluates the probability (once in how many years) of a failure of the respective machines and apparatuses or the parts thereof by making use of the data stored in the failure information database 16 and supplies the evaluation result to the operation plan evaluation unit 25.
As has been explained hitherto, although the operation and maintenance plan preparation aiding system for a power generation installation according to the present embodiment uses the performance diagnosis result, the remaining lifetime diagnosis result, the failure frequency and the priority of manufacturers when preparing an operation and maintenance plan for the respective power generation units for every electric power generation companies 104 and 105, it is cost advantageous if adjusting the power generation units owned by another company and procuring the electric power from the other, and an operation and maintenance plan over the plurality of electric power generation companies 104 and 105 is prepared.
When the electric power is procured from the other company, payment of the electric power fee between the electric power generation companies 104 and 105 is necessitated, however, the electric power procurement usually occurs mutually between the plurality of electric power generation companies 104 and 105, it will be unnecessary to pay the electric power fee at every procurement, and it will be sufficient if, after offsetting debits and credits for a predetermined period, for example, every one year, the balance is paid as the electric power fee.
In this instance, the service center 1 settles the agreement between these electric power generating companies 104 and 105 and prepares a plan so that the total costs for operation and maintenance of the respective electric power generation companies 104 and 105 are minimized.
In the embodiment as shown in
In
In this instance, since the rest of the operation of the operation and maintenance plan preparation aiding system for a power generation installation of the sixth embodiment as shown in
In the embodiment as shown in
In this instance, since the rest of the operation of the operation and maintenance plan preparation aiding system for a power generation installation of the seventh embodiment as shown in
According to the first aspect of the present invention the following advantage is obtained, in that, since the operation and maintenance plans for the respective power generation units are prepared in the service center based on the power generation efficiency evaluated and calculated in real time, a secular change and a performance degradation due to failure occurrences for the respective power generation units can be taken into account, thereby, the operation cost thereof can be reduced in comparison with the conventional power generation system in which the operation and maintenance plans for the respective power generation units are prepared by making use of the plant data.
According to the second aspect of the present invention the following advantage is obtained, in that, when preparing the operation and maintenance plans for the respective power generation units in the service center based on the power generation efficiency evaluated and calculated in real time, since the cost of economical loss due to the performance degradation is calculated from the deviation value between the process value estimated using the machine and apparatus model and the measured value, the cost of economical loss is compared with the cost relating to the exchange of the machine and apparatus and the parts thereof and the operation and maintenance plan of the respective power generation units are prepared by making use of the comparison result, the total cost for the operation and maintenance can be reduced.
According to the third aspect of the present invention the following advantage is obtained, in that, when preparing the operation and maintenance plans for the respective power generation units in the service center based on the power generation efficiency evaluated and calculated in real time, since the operation and maintenance plans are prepared based on the calculated remaining lifetime, an exchange timing of the machine and apparatus and the parts thereof can be determined with a high accuracy in comparison with the conventional power generation system in which exchange of the machine and apparatus and the parts thereof is performed with reference to an accumulated operation time thereof, as a result, an abnormality occurrence due to the use of the machine and apparatus and the parts thereof exceeding their lifetime and generation of economical loss due to unplanned outages caused by an abnormality of the machine and apparatus and the parts thereof can be prevented, moreover, an exchange in every predetermined period of the machine and apparatus, even though there is a remaining lifetime, is unnecessitated, thereby, the maintenance cost can be reduced.
According to the fourth aspect of the present invention the following advantage is obtained, in that, when preparing the operation and maintenance plans for the respective power generation units in the service center based on the power generation efficiency evaluated and calculated in real time, since the operation condition for the machine and apparatus in its own power generation unit is modified based on the remaining lifetime of the machine and apparatus and the parts thereof not only in its own power generation unit but also in another power generation unit, the operation and maintenance plans can be prepared so that the total cost necessary for the operation and maintenance for the respective power generation units is minimized, the cost merit obtained by the electric power generation by the electric power generation company can be increased in comparison with the conventional power generation system.
Number | Date | Country | Kind |
---|---|---|---|
2001-052779 | Feb 2001 | JP | national |
Number | Name | Date | Kind |
---|---|---|---|
5122727 | Janssen et al. | Jun 1992 | A |
5371606 | Katayama et al. | Dec 1994 | A |
5621654 | Cohen et al. | Apr 1997 | A |
5761083 | Brown, Jr. et al. | Jun 1998 | A |
6122603 | Budike, Jr. | Sep 2000 | A |
20020072868 | Bartone et al. | Jun 2002 | A1 |
20020087220 | Tveit et al. | Jul 2002 | A1 |
20020169514 | Eryurek et al. | Nov 2002 | A1 |
20030004659 | Hayashi et al. | Jan 2003 | A1 |
20030216888 | Ridolfo | Nov 2003 | A1 |
Number | Date | Country | |
---|---|---|---|
20020120412 A1 | Aug 2002 | US |