An exterior curtain wall system is an outer covering of a building in which the outer walls are structural walls capable of resisting wind loads and sustaining inter-floor story drifts due to seismic loads and inter-floor deflection due to live floor loads. Curtain walls also have an aesthetic function representing the signature of the architect. Further, curtain walls have an interior environmental function by keeping weather out and keeping building occupants safe and comfortable. Curtain wall commonly is made from lightweight materials that reduce construction costs while maintaining a high-dollar appearance. Curtain walls sometimes are renovated to address water leakage and/or structural problems, to improve thermal and/or sound insulation, and/or to enhance a building's aesthetic appeal.
In high-rise curtain wall renovation projects, especially for projects undertaken in densely populated metropolitan areas that have limited available space for construction traffic, it is often desirable to implement top-down panel assembly methods. In top-down assembly, the curtain wall is progressively renovated from the top of the building toward the bottom of the building, thus renovating and enclosing the first or “bottom” floor last. Top-down renovation methods allow immediate re-occupancy of a renovated floor, prevent water and/or construction debris from falling into renovated lower floors, and avoid construction traffic going through renovated lower floors to upper floors undergoing renovation.
In addition to the overall cost of the materials and labor to install the new curtain wall, however, several additional costs should be considered by the building owner prior to commencing a curtain wall renovation. For example, the building owner should consider rental losses due to weather exposed areas (floors) and prolonged waiting periods for re-occupancy of the renovated floors during the renovation period. The building owner should also consider the cost of providing temporary weather shielding in the weather exposed areas during renovation. In addition, the building owner should consider the high cost of reusing previous curtain wall anchoring systems on existing floor slabs, especially in cases where existing embeds are unsafe for re-use.
Besides additional costs associated with curtain wall renovations, building owners should also keep in mind various technical factors that must be accounted for in renovating an existing curtain wall. For instance, the building owner should consider the architectural inflexibility for grid line design changes by using the previous curtain wall anchoring systems on existing floor slabs. In addition, the building owner should consider safety factors between removing the old wall and erecting the new wall, while maintaining a clean interior aesthetical feature of the new wall.
It is desirable to have a top-down curtain wall renovation method that addresses the foregoing cost and technical factors.
Disclosed are top-down curtain wall renovation systems and methods for an exterior of a building. In the disclosed systems and methods, curtain wall renovation occurs floor-by-floor, starting from the top floor of a building to subsequent lower floors until the renovation is complete. Old curtain wall panels and mullions are removed and replaced with new curtain wall panels and mullions. After old curtain wall panels and mullions are removed from a floor, a temporary weather shield system is installed to protect the floor while new curtain wall panels are installed on an above floor.
Some disclosed systems have a plurality of new mullions attached to a top surface of a first floor slab of a first floor and extending downwardly external to the first floor slab and below the first floor slab. A temporary weather shield system is assembled in a second floor below the first floor and inset from an outer edge of a second floor slab of the second floor. The temporary weather shield system includes a plurality of dry anchoring devices fastened to a top surface of the second floor slab, a plurality of temporary mullions supported on the top surface of the second floor, and a plurality of reusable panels, each reusable panel being secured to two laterally adjacent temporary mullions of the plurality of temporary mullions. The bottom of each temporary mullion is structurally interlocked to a corresponding one of the plurality of dry anchoring devices, and the top of each temporary mullion is structurally interlocked to a corresponding one of the plurality of new mullions.
The bottom of each temporary mullion may be structurally interlocked to a dry anchoring device using a bottom connection clip that engages both the temporary mullion and the dry anchoring device without using any fasteners. The top of each temporary mullion may be structurally interlocked to a new mullion using a top connection clip that engages both the temporary mullion and the new mullion without using any fasteners. Further, each temporary panel may be secured to two laterally adjacent temporary mullions without using any fasteners.
Once new curtain wall panels are installed on the first (upper) floor, the temporary mullions and reusable panels of the temporary weather shield system may be removed from the second (lower) floor and moved to a third floor below the second floor. Old curtain wall panels may be removed from the third floor, and new mullions secured to the dry anchoring devices that are fastened to the second floor slab. Dry anchoring devices may be fastened to a third floor slab of the third floor, and the temporary mullions of the temporary weather shield system may be installed in the third floor by securing the temporary mullions to the dry anchoring devices and new mullions in the same manner that the temporary mullions had been installed on the second floor. The reusable panels may then be secured between laterally adjacent temporary mullions to protect the third floor while new curtain wall panels are installed for the second floor.
Once new curtain wall panels are installed for the second floor, the process of disassembling the reusable panels and temporary mullions, removing old curtain wall panels and mullions from the below floor, installing new mullions, assembling a temporary weather shield system in the below floor, and installing new curtain wall panels may be repeated until the curtain wall renovation is complete.
The following figures are included to illustrate certain aspects of the present disclosure, and should not be viewed as exclusive embodiments. The subject matter disclosed is capable of considerable modifications, alterations, combinations, and equivalents in form and function, without departing from the scope of this disclosure.
The present disclosure is related to curtain wall systems of buildings and, more particularly, to top-down curtain wall renovation methods that incorporate a temporary weather shield system that incorporates an improved mullion anchoring system.
Exterior curtain wall systems for buildings typically consist of three main components, namely, wall panels providing weather protection, mullions providing structural support to the wall panels, and mullion anchoring systems providing a structural connection between the mullions and a building structural element. Mullion anchoring systems carry the dead load weight of the wall panels and transfer the load to the building structure, typically at the building base or at intermediate floor slabs. Mullion anchoring systems also absorb positive and negative wind loads acting on the wall panels.
The temporary weather shield systems described herein provide cost-effective reusable weather shielding during curtain wall renovation, and may be especially effective for use in top-down renovation methods. The temporary weather shield systems described herein also provide an inexpensive wall anchoring system that can be easily anchored to the top surface of existing floor slabs.
The renovation depicted in
In at least one embodiment, the renovation proceeds in the following manner. As shown in
To continue the renovation, the temporary mullions 306 and reusable panels 114 of the temporary weather shield system 112 may be removed from the nth-2 floor 102c. Then, old spandrel panels 116, old vision glass panels 118, and old mullions 602 (
New mullions spanning the nth-2 floor 102c and extending downwardly into the spandrel area past floor slab 110b then may be spliced with the previously-installed new mullions 108 spanning the above floor 102b, and secured to the dry anchoring devices that are secured to the floor slab 110b of the nth-2 floor 102c. The dry anchoring devices that are secured to the concrete floor slab 110b of the nth-2 floor 102c may be the same dry anchoring devices that previously were secured to the temporary mullions 306 of the temporary weather shield system 112.
A temporary weather shield system may be installed on the nth-3 floor 102d, and may reuse the temporary mullions and reusable panels that were removed from the nth-2 floor 102c. The temporary weather shield system may be installed by securing the bottom end of each temporary mullion to a corresponding dry anchoring device that is secured to the floor slab of the nth-3 floor 102d, and securing the top end of each temporary mullion to the bottom end of a corresponding new mullion spanning the nth-2 floor 102c and extending downwardly into the spandrel area past floor slab 110b. The temporary mullions may be installed at the same time that the corresponding new mullions are being installed on the nth-2 floor 102c. Next, reusable panels are installed between laterally adjacent temporary mullions to form the temporary weather shield system.
The temporary weather shield system protects the nth-3 floor 102d while new spandrel panels for the spandrel area between the nth-1 floor 102b and the nth-2 floor 102c and new vision glass panels for the nth-2 floor 102c are installed. Once those new panels have been installed, the top-down renovation process utilizing the disclosed dry anchoring devices and temporary weather shield system may be repeated for lower floors until the entire building curtain wall renovation is complete.
The nth-2 floor 102c is located below the nth-1 floor 102b. The previous curtain wall panels and mullions have been removed from the nth-2 floor 102c, and a temporary weather shield system 112 is assembled in the nth-2 floor 102c to provide temporary weather shielding. As illustrated, the temporary weather shield system 112 includes, among other component parts, one or more reusable panels 114 supported vertically on a second floor slab 110b, which forms part of the nth-2 floor 102c.
The nth-3 floor 102d is located below the nth-2 floor 102c and includes a row of old spandrel panels 116 and a row of old vision glass panels 118 positioned therebelow. In the illustrated application, the old spandrel panels 116 and old vision glass panels 118 comprise separate component parts, but may alternatively be combined into single units common to conventional unitized systems. As illustrated, the old curtain wall is depicted as a typical stick curtain wall system, where the old spandrel panels 116 and old vision glass panels 118 (or a combination thereof) are vertically supported using conventional slab edge embeds 120 anchored to the edges (ends) of the corresponding floor slabs. As will be appreciated, however, this is shown for illustrative purpose only and, therefore, should not be considered limiting to the scope of the present disclosure. Rather, the renovation methods described herein are applicable to unitized curtain wall systems that use embeds with protruding anchoring bolts above the floor slab surface, without departing from the scope of the disclosure.
When the old curtain wall panels and mullions are removed from a particular floor, the top-down renovation of the curtain wall system 100 results in the creation of a large vertical gap extending between the upper, renovated portions of the curtain wall system 100 and the lower, dated (old) portions of the curtain wall system 100. The resulting vertical gap is best seen in
As illustrated, the temporary weather shield system 112 is inwardly inset from the curtain wall system 100. More particularly, the reusable panels 114 may be supported by the underlying floor slab 110b at a location inward from the outer edge of the floor slab 110b. Positioning the reusable panels 114 structurally inward from edge of the floor slab 110b allows easy installation of the reusable panels. The near one floor height of the temporary mullions 306 helps prevent potential accidental damage to the erected new curtain wall during the process of removing the old wall.
The temporary weather shield system 112 may include reusable panels 114, and each reusable panel 114 may be secured to and otherwise interlocked between two adjacent, backward-facing temporary mullions 306. The temporary mullions 306 may have the same configuration as new mullions 108, but is placed in a backward-facing orientation.
In at least one embodiment, the reusable panels 114 may be secured to the adjacent temporary mullions 306 without using any fasteners (e.g., screws, bolts, etc.). The reusable panels 114 are installed between temporary mullions 306 in the same manner that a permanent wall panel would be installed between permanent mullions on the exterior of a building, except the reusable panels 114 and temporary mullions 306 are in a backward-facing (inward facing) orientation. Because the reusable panels 114 are on top of the floor slab 110b, the weight of the reusable panels 114 is supported by the floor slab 110b, and fasteners are not required to secure the reusable panels 114 to the temporary mullions 306. Structural engagement between the frames of the reusable panels 114 and the temporary mullions 306 provides wind load resistance without using any fasteners.
The temporary mullions 306 may be supported on a top surface 308 of the floor slab of the floor currently under renovation. In the illustrated embodiment, for example, the temporary mullions 306 are supported on the top surface 308 of the second floor slab 110b of the nth-2 floor 102c. The bottom or “lower” end of each temporary mullion 306 may be structurally interlocked to a corresponding dry anchoring device 310 using a bottom connection clip 312. The term “dry” anchoring device refers to a mullion anchoring device that is secured to a concrete floor slab after the concrete is cured, without the need to embed components in the concrete before it is cured. In at least one embodiment, the bottom connection clip 312 facilitates a structural interconnection between the bottom end of the temporary mullion 306 and a corresponding dry anchoring device 310 without using any fasteners.
The dry anchoring device 310 may not only be used to anchor the temporary mullions 306 to corresponding floor slabs, but may also comprise the main anchoring component of the mullion anchoring system 304. Accordingly, the dry anchoring device 310 may be secured to the top surface of the corresponding floor slab at a location suitable for anchoring a corresponding new mullion 108 onto the top surface. The dry anchoring device 310 then may be used to first anchor the temporary mullions 306 to the corresponding floor slab, and then to anchor the new mullions 108 to the corresponding floor slab.
The top or “upper” end of each temporary mullion 306 may be structurally interlocked with an adjacent new mullion 108 using a top connection clip 314. More specifically, and as described in more detail below, opposing ends of the top connection clip 314 may be slidably received within each of the temporary mullion 306 and the adjacent new mullion 108. In at least one embodiment, a slide block 316 may be coupled to the temporary mullion 306 to prevent the top connection clip 314 from sliding out of engagement (e.g., downwardly) with the new mullion 108. Accordingly, in at least one embodiment, the upper end of each temporary mullion 306 may be structurally interlocked with an adjacent new mullion 108 without using any fasteners (e.g., screws, bolts, etc.).
Once the floor under renovation is complete, the bottom or “lower” end of each new mullion 108 may be coupled to another new mullion (not shown) using a splice joint (not shown). The resulting splice joint connecting vertically adjacent new mullions may be located in the spandrel area of the resulting renovated curtain wall system 100 (
Referring now to
As illustrated, the mullion anchoring system 304 includes the dry anchoring device 310 and a mullion connector 402. The dry anchoring device 310 defines or otherwise provides a horizontal leg 404 and an upstanding load resisting lip 406. The dry anchoring device 310 may define one or more fastener holes 408 for receiving corresponding concrete anchors 410 (
The mullion connector 402 may be configured to slidably engage the new mullion 108 and be simultaneously received within the notch 412 of the dry anchoring device 310 to transfer reaction forces from the new mullion 108 to the building structure via the dry anchoring device 310. The web 414 of the mullion connector 402 may have a depth or length aligned in a direction perpendicular to the curtain wall (i.e., perpendicular to the face of the curtain wall panels) when installed.
The mullion connector 402 may have an integral negative wind load resisting leg 416a (
Under positive wind load conditions, the contact pressure between the inward-facing surface of the positive wind load resisting leg 416b and the outward-facing surface of the load resisting lip 406 resists positive wind load. Under negative wind load conditions, the contact pressure between the outward-facing surface of the negative wind load resisting leg 416a and the inward-facing surface of the load resisting lip 406 resists negative wind load. Alternative embodiments do not have a positive wind load resisting lip 416b. One of ordinary skill in the art would recognize alternative solutions for resisting positive wind load, such as by inserting a block between the load resisting lip and the back of the mullion.
Engagement of the web 414 of the mullion connector 402 in the notch 412 of the load resisting lip 406 facilitates engagement between the mullion connector 402 and the dry anchoring device 310 without a fastener. Alternatively, the load resisting lip 406 may not have a notch and the web 414 of the mullion connector may instead have a notch for engagement with the load resisting lip 406. In such embodiments, a fastener (not shown) may be used to secure the negative load resisting leg 416a to the load resisting lip 406 and thereby restrict lateral movement of the mullion connector 402.
At the distal end of the web 414 (e.g., the end toward the building exterior when installed), the mullion connector 402 may have a leg perpendicular to the web 414, with a female joint 420 (
If the anchoring location is designed to resist dead load, then a dead load block 424 may be arranged on top of the mullion connector 402 and fastened to the new mullion 108. As illustrated, the dead load block 424 may have the same joint configuration as the mullion connector 402 for engagement with the male joints 422 of the new mullion 108. Accordingly, the dead load block 424 may be slidably received by the male joints 422 and move into a desired position vertically above the mullion connector 402.
Because the dry anchoring device may be installed after the concrete slab is cured, lateral (left-and-right) and in-and-out construction tolerance adjustments may be made by simply determining the proper lateral and in-and-out location and securing the dry anchoring device 310 to the floor slab at that location. The proper in-and-out location for the dry anchoring device 310 may be determined by reference to a fixed dimension specified in the building design. For example, the architect's drawing will specify a fixed distance between the curtain wall panel and certain building features, such as the spandrel column line. That fixed distance is the same, regardless of the actual position of the concrete floor slab edge. Based on that fixed distance and the fixed dimensions of the curtain wall panel, mullion, mullion connector, and anchoring device, the in-and-out position of the anchoring device relative to the spandrel column line can be calculated.
Thus, the desired in-and-out position of the dry anchoring device 310 relative to a building feature (e.g., a spandrel column line) may be determined based on a fixed dimension of the dry anchoring device 310 (e.g., distance between the back edge of the dry anchoring device 310 and the load resisting lip 406), a fixed dimension of the mullion connector 402 (e.g., the length of the mullion connector 402), and the fixed distance between the building feature and the new mullion 108 (e.g., the distance between the new mullion 108 and the spandrel column line).
Based on that calculated position, and with reference to
The line 430 in
It is a common practice in the industry to specify ±1″ (or ±25 mm) in-and-out construction tolerance for buildings up to fifteen stories high and ±2″ (or ±50 mm) for buildings higher than fifteen stories high. Since the depth of the mullion connector 402 is designed for a specific “D” dimension, one mullion connector 402 can be designed for buildings up to fifteen stories high with “D” being equal to 2″ (or 50 mm), and another mullion connector 402 can be designed for buildings higher than fifteen stories high with “D” being equal to 4″ (or 100 mm). However, a mullion connector 402 designed for a specific “D” dimension can be used for any condition with a lesser “D” dimension by placing the reference line 426 father away from the theoretical slab edge line 430 in the inward direction. Therefore, a mullion connector 402 designed for a high-rise building can be used for all buildings.
The dry anchoring device 310 may comprise an extruded member. The fabrication of the extrusion for the dry anchoring device 310 may involve 1) cutting to length (dimension “A” in
The bottom end of each temporary mullion 306 may be structurally interlocked to a corresponding dry anchoring device 310 secured to the underlying floor slab (e.g., the second floor slab 110b) without using any fasteners (e.g., screws, bolts, etc.). This may be accomplished by using a bottom connection clip 312 that connects a temporary mullion 306 to a dry anchoring device 310. In at least one embodiment, the bottom connection clip 312 has a web and two perpendicular legs, with a similar configuration as the proximal end of the mullion connector 402 (
The bottom connection clip 312 is further configured to slidably engage the temporary mullion 306. In at least one embodiment, the bottom connection clip 312 has female joints corresponding to male joints of the temporary mullion 306, similar to the female joints 420 of the mullion connector and male joints of the new mullion 108 (
To secure a temporary mullion 306 to a dry anchoring device 310, a bottom connection clip 312 first is placed on the dry anchoring device 310 and engaged with the load resisting lip 406 of the dry anchoring device 310, as described above. Next, the temporary mullion 306 may be lifted above the corresponding connection clip 312 and advanced downwardly to slidably receive a portion of the bottom connection clip 312. In some embodiments, for example, the bottom of the temporary mullion and the bottom connection clip 312 may be mateable via a male-female sliding relationship.
Since the dry anchoring devices 310 are installed and used to temporarily secure the temporary mullions 306 and subsequently secure the new mullions 108 (
To accomplish this, the top connection clip 314 connects the bottom end of the new mullion 108 with the top end of the temporary mullion 306. The top connection clip 314 may be engaged with both the new mullion 108 and the temporary mullion 306 via a sliding mated engagement. In the illustrated embodiment, for example, the new mullion 108 and the temporary mullion 306 have the same configuration, with the temporary mullion 306 placed in a backward-facing orientation. The top connection clip 314 has a web with female joints on both ends of the web, similar to the female joints 420 of the mullion connector 402 (
To connect the new mullion 108 to the temporary mullion 306 using the top connection clip 314, the top connection clip 314 may be slidably engaged with the new mullion 108 and moved upwardly (e.g., by sliding) relative to the new mullion 108 to a position above the expected location of the upper end of the corresponding temporary mullion 306. After the bottom end of the temporary mullion 306 is engaged with the dry anchoring device 310 (
In some embodiments, the slide block 316 (
After two laterally adjacent temporary mullions 306 are secured at the top and bottom, as described herein, a reusable panel 114 may be installed to the laterally adjacent temporary mullions 306, as generally described above. Securing the temporary mullion 306 to the dry anchoring device 310 and the new mullion 108 in the manner described above resists wind load forces on the temporary weather shield system 112, in a similar manner to how securing a curtain wall to the dry anchoring device resists wind load forces, as described in U.S. Pat. No. 9,683,367.
Example assembly of the temporary weather shield system 112 of
The bottom connection clips 312 may be removably coupled to corresponding dry anchoring devices 310. More specifically, the bottom connection clips 312 may be slid into engagement with the corresponding dry anchoring devices 310 by being received into the notch 412 defined by the load resisting lip 406 of the dry anchoring device 310. A corresponding temporary mullion 306 may then be lifted above the top of the bottom connection clip 312 and advanced downwardly (e.g., dropped) such that a bottom 802a of the temporary mullion 306 comes into sliding engagement with the bottom connection clip 312. In at least one embodiment, a portion of the bottom connection clip 312 may be slidably received within a slot 804 defined in the temporary mullion 306. In other embodiments, however, the bottom connection clip 312 may define a slot or the like that slidably receives the bottom 802a of the temporary mullion 306.
A top 802b of each temporary mullion 306 may then be secured to a corresponding previously erected new mullion 108. More specifically, the top connection clip 314 may be received by a corresponding new mullion 108 via sliding engagement. In some embodiments, for example, the top connection clip 314 may be slidably received into the corresponding new mullion 108 at a lower end 806 thereof. The top connection clip 314 may then be moved (slid) upward relative to the new mullion 108 until the top connection clip 314 is positioned vertically above the top 802b of the corresponding temporary mullion 306. The corresponding temporary mullion 306 may then be aligned laterally with (i.e., in the same right-to-left position), but inwardly offset from, the new mullion 108, and the top connection clip 314 may be moved downwardly relative to the new mullion 108 to slidably engage the temporary mullion 306. In at least one embodiment, a portion of the top connection clip 314 may be received within the slot 804 defined in the temporary mullion 306. Alternatively, the top 802b of the temporary mullion 306 may be received within a corresponding aperture or slot defined by the top connection clip 314, without departing from the scope of the disclosure.
In some embodiments, the top connection clip 314 may be dropped vertically relative to the new mullion 108 until engaging the slide block 316, which may also be received within the slot 804 and fastened to the temporary mullion 306. As indicated above, the slide block 316 may prevent the top connection clip 314 from sliding downward and out of engagement with the lower end 806 of the new mullion 108. Once two laterally adjacent temporary mullions 306 are secured at the respective bottoms and tops 802a, 802b, as described above, a reusable panel 114 may be secured to the laterally adjacent temporary mullions 306, as generally described above.
To remove the temporary weather shield system 112, one need only reverse the execution order of the foregoing steps, except for the installation of the dry anchoring devices 310, which will be used to permanently attach the new mullions 108 of the renovated floors. Upon removal, all components of the temporary weather shield system 112 (except for the dry anchoring devices 310) may be delivered to the next (lower) floor for reuse. Notably, besides anchoring the dry anchoring devices 310, assembling the temporary weather shield system 112 does not require any fastener and, therefore, its erection and removal can be executed efficiently. Moreover, significant cost savings can be realized since the installed temporary weather shield system 112 occupies very little interior floor space.
Therefore, the disclosed systems and methods are well-adapted to attain the ends and advantages mentioned as well as those that are inherent therein. The particular embodiments disclosed above are illustrative only, as the teachings of the present disclosure may be modified and practiced in different but equivalent manners apparent to those skilled in the art having the benefit of the teachings herein. Furthermore, no limitations are intended to the details of construction or design herein shown, other than as described in the claims below. It is therefore evident that the particular illustrative embodiments disclosed above may be altered, combined, or modified and all such variations are considered within the scope of the present disclosure. The systems and methods illustratively disclosed herein may suitably be practiced in the absence of any element that is not specifically disclosed herein and/or any optional element disclosed herein. While compositions and methods are described in terms of “comprising,” “containing,” or “including” various components or steps, the compositions and methods can also “consist essentially of” or “consist of” the various components and steps. All numbers and ranges disclosed above may vary by some amount. Whenever a numerical range with a lower limit and an upper limit is disclosed, any number and any included range falling within the range is specifically disclosed. In particular, every range of values (of the form, “from about a to about b,” or, equivalently, “from approximately a to b,” or, equivalently, “from approximately a-b”) disclosed herein is to be understood to set forth every number and range encompassed within the broader range of values. Also, the terms in the claims have their plain, ordinary meaning unless otherwise explicitly and clearly defined by the patentee. Moreover, the indefinite articles “a” or “an,” as used in the claims, are defined herein to mean one or more than one of the elements that it introduces. If there is any conflict in the usages of a word or term in this specification and one or more patent or other documents that may be incorporated herein by reference, the definitions that are consistent with this specification should be adopted.
As used herein, the phrase “at least one of” preceding a series of items, with the terms “and” or “or” to separate any of the items, modifies the list as a whole, rather than each member of the list (i.e., each item). The phrase “at least one of” allows a meaning that includes at least one of any one of the items, and/or at least one of any combination of the items, and/or at least one of each of the items. By way of example, the phrases “at least one of A, B, and C” or “at least one of A, B, or C” each refer to only A, only B, or only C; any combination of A, B, and C; and/or at least one of each of A, B, and C.
The present application is related to and claims priority to U.S. Provisional Patent Application Ser. No. 62/615,268, filed on Jan. 9, 2018.
Number | Name | Date | Kind |
---|---|---|---|
3053353 | Miller | Sep 1962 | A |
3251168 | Waring et al. | May 1966 | A |
3321880 | Ferrell et al. | May 1967 | A |
3367077 | Johnston | Feb 1968 | A |
3791094 | Shannon, Jr. | Feb 1974 | A |
3903671 | Cuin et al. | Sep 1975 | A |
3978629 | Echols, Sr. | Sep 1976 | A |
4055923 | Biebuyck | Nov 1977 | A |
4449341 | Taglianetti | May 1984 | A |
4543755 | Crandell | Oct 1985 | A |
4555890 | Gartner | Dec 1985 | A |
4672784 | Pohlar | Jun 1987 | A |
4685263 | Ting | Aug 1987 | A |
4765107 | Ting | Aug 1988 | A |
4840004 | Ting | Jun 1989 | A |
4873805 | Ting | Oct 1989 | A |
4977717 | Niwata | Dec 1990 | A |
5035099 | Lapish | Jul 1991 | A |
5158392 | Takeda | Oct 1992 | A |
5452552 | Ting | Sep 1995 | A |
5481839 | Lang et al. | Jan 1996 | A |
5596851 | Ting | Jan 1997 | A |
5598671 | Ting | Feb 1997 | A |
5687524 | Ting | Nov 1997 | A |
6158182 | Biebuyck | Dec 2000 | A |
6393778 | Ting | May 2002 | B1 |
6591562 | Ting | Jul 2003 | B2 |
6598361 | Ting | Jul 2003 | B2 |
6715248 | Biebuyck | Apr 2004 | B2 |
6745527 | Sherman | Jun 2004 | B1 |
7043884 | Moreno | May 2006 | B2 |
7134247 | Ting | Nov 2006 | B2 |
7162842 | Ribic | Jan 2007 | B2 |
7681366 | De Gobbi | Mar 2010 | B2 |
8001738 | Ting | Aug 2011 | B2 |
8011146 | Krause | Sep 2011 | B2 |
8033066 | Griffiths | Oct 2011 | B2 |
8127507 | Bilge | Mar 2012 | B1 |
8166716 | Macdonald et al. | May 2012 | B2 |
8191325 | Ting | Jun 2012 | B2 |
8240099 | Hummel, III | Aug 2012 | B2 |
8365481 | Scully et al. | Feb 2013 | B2 |
8402714 | Labrecque | Mar 2013 | B2 |
8413403 | Walker, III et al. | Apr 2013 | B2 |
8613173 | Ander et al. | Dec 2013 | B2 |
9200444 | Ra | Dec 2015 | B2 |
9638367 | Ting | Jun 2017 | B2 |
20020124514 | Higgins | Sep 2002 | A1 |
20030033765 | Ting | Feb 2003 | A1 |
20030150179 | Moreno | Aug 2003 | A1 |
20030221381 | Ting | Dec 2003 | A1 |
20040079038 | Crooker, Jr. | Apr 2004 | A1 |
20050284053 | Grunewald et al. | Dec 2005 | A1 |
20060016137 | Ferro | Jan 2006 | A1 |
20080053015 | Matechuk | Mar 2008 | A1 |
20080222981 | De Gobbi | Sep 2008 | A1 |
20080313982 | Termohlen | Dec 2008 | A1 |
20090241444 | Griffiths | Oct 2009 | A1 |
20090241466 | Gussakovsky | Oct 2009 | A1 |
20100011687 | Arias | Jan 2010 | A1 |
20100037549 | Lynch | Feb 2010 | A1 |
20100132293 | Voegele, Jr. et al. | Jun 2010 | A1 |
20100257812 | Schultz et al. | Oct 2010 | A1 |
20110030296 | Joret | Feb 2011 | A1 |
20130014636 | Dehghanyar | Jan 2013 | A1 |
20130186031 | Ting | Jul 2013 | A1 |
20140157699 | Moeller et al. | Jun 2014 | A1 |
20140331579 | Evensen et al. | Nov 2014 | A1 |
20150275512 | Bertoldini | Oct 2015 | A1 |
20150284950 | Stramandinoli | Oct 2015 | A1 |
20160040702 | Broussard et al. | Feb 2016 | A1 |
20170241133 | Ting | Aug 2017 | A1 |
Number | Date | Country |
---|---|---|
201236597 | May 2009 | CN |
0476289 | Mar 1992 | EP |
2397310 | Jul 2004 | GB |
200616776 | Jan 2006 | JP |
10201000120867 | Nov 2010 | KR |
1596261 | Aug 2017 | TW |
Entry |
---|
International Searching Authority, International Search Report and Written Opinion of the International Searching Authority for International Application No. PCT/US16/33045, dated Oct. 7, 2016. |
Notification of Transmittal of the International Search Report and the Written Opinion of the International Searching Authority, or the Declaration, dated May 15, 2013, PCT Serial No. PCT/US2013/021893. |
Curtain Wall Anchoring Top of Slab Condition, Halfen Anchoring Systems advertising, date unknown. |
Wausaw Window and Wall System, Curtainwall Products, Performance and Practicality (A Wausaw AIA-CES Presentation, date unknown. |
Yakin, Victor J., “Anchoring curtain walls”, Glass Magazine, Jun. 1, 2008, pp. 1-3. |
Yakin, Victor J., “Glass Your Online Industry Resource”, Glass Magazine, Jun. 1, 2008, p. 1. |
Halfen, “Halfen HCW Curtain Wall” Technical Product Information, 2014, pp. 1-36. |
Harmon Innovative Facade Solutions, “SMU6000 Curtain Wall Anchorage Options”, Brochure, 2014, pp. 1-2. |
Harmon Innovative Facade Solutions, UCW8000 Curtain Wall System Brochure, 2013, pp. 1-2. |
Jordahl, “Design of Anchor Channels”, Brochure, Oct. 2010, pp. 1-67. |
Jordahl, “Anchor Channel Application”, Brochure, pp. 1-28, date unknown. |
Jordahl, “Anchor Channels jTA-CE”, Brochure, Nov. 2013, pp. 1-3, dale unknown. |
Jordahl, “Anchor Channels Guide to ETA Compatible Design”, Brochure, pp. 1-54, dale unknown. |
Jordahl, “Channels and Accessories Making Light Work of the Heaviest Loads”, Brochure, Feb. 2013, pp. 1-56. |
Knickerbocker, Chuck, Anchored in Reality: Getting Anchors and Embeds Right (http://www.usglassmag.com/fleldnoles/7p=280), Aug. 11, 2012, pp. 1-3. |
Yakin, Victor, “Dependable Connections the Anchoring Systems Used to Transmit the Loads . . . ”, http://www.glasscanadam.com/business-inlelligence/dependable-connections-889, Jul. 31, 2007, pp. 1-3. |
CFS Construction Fixing Systems, “Glass Facade Fixings”, Brochure, pp. 1-20, date unknown. |
Centre for Window and Cladding Technology, Chapter 8 Brackets and Fixings, “CWCT Curtain Wall Installation Handbook”, Handbook, Nov. 2001, pp. 1-7. |
Australian Engineered Fasteners and Anchors Council, “Technical Note: Selection of Cast-in Channel for Safety Critical Applications”, AEFAC Technical Note TN03-21/07/140D3, pp. 1-3, Jul. 21, 2014. |
International Searching Authority, Notification of Transmittal of the International Search Report and the Written Opinion of the International Searching Authority, or the Declaration, International Application No. PCT/US17/19100 (Apr. 3, 2017). |
Office Action Issued for TW Application No. 107109675, dated Jan. 9, 2019. |
Number | Date | Country | |
---|---|---|---|
20190211552 A1 | Jul 2019 | US |
Number | Date | Country | |
---|---|---|---|
62615268 | Jan 2018 | US |