The present application claims priority to Chinese Patent Application No. 202110619979.0, filed on Jun. 3, 2021, the content of which is incorporated herein by reference in its entirety.
The present application relates to the construction field of anchors, in particular to an anchor assembly having a pre-stressed mandrel.
In areas with abundant groundwater, there is a widespread problem of basement anti-floating. An anchor is an effective measure for anti-floating of underground structures in construction engineering, one end of which is connected with engineering structures, and the other end is deep into the stratum, which can transmit a tensile force to the stratum. In addition, anchors are also used to reinforce the main body of tunnels and dams, and to resist wind and capsize of high-rise buildings. The anchor is widely used, and has a very mature standardization system and construction process. Relevant national and industrial standards include Technical Specifications for Rock and Soil Anchor and Shotcrete Support Engineering (GB 50086-2015), Technical Specifications for Rock and Soil Anchor (Cable), and special chapters on anchor are also involved in Technical Specifications for Foundation Pit Support and Technical Standards for Anti-floating of Building Engineering.
In terms of types, anchors are divided into grouting and mechanical pre-stressed anchors, tension and pressure pre-stressed anchors, load dispersed anchors, full-length bonded anchors, resin roll and quick-hardening cement roll anchors, hollow grouting anchors and friction anchors, etc. The common feature of these anchors is that they are cast in situ.
For the convenience of construction, non-pre-stressed anchors are often used as anti-floating anchors in underground engineering, and the conventional construction process is as follows: anchor fabrication→drilling machine in place→emptying→anchor installation→pressure grouting→completion. The above anchors have the remarkable advantages of high bearing capacity, reliable quality, simple process and low comprehensive cost.
Because of its small diameter and relatively large tensile bearing capacity, a non-pre-stressed anchor is prone to durability problems due to cracks. Especially in the site where soil and water are corrosive to rebars, cracks in anchors cause rebars to rust expansion, resulting in overall anti-floating failure. According to the requirements of “Technical Standard for Anti-floating of Building Engineering” (JGJ476-2019), the anti-floating design grade A project should be designed according to the fact that the anchor anchorage slurry does not produce tensile stress; the project with an anti-floating design grade of B should be designed without cracks, and pre-stressed anchors must be adopted.
Pre-stressed technology can effectively control cracks and improve the durability of anchors, but pre-stressed anchors can only be tensioned after the bottom slab of the basement is poured, as shown in
Different from the characteristic that all concrete anchors are poured on site at present, the present application provides an anchor assembly having a pre-stressed mandrel, which comprises a prefabricated pre-stressed concrete mandrel and a cast-in-place anchoring slurry, wherein a grouting pipe is preformed in advance at the mandrel part, or a grouting pipe is bound outside the finished mandrel for secondary grouting, so as to improve the bonding performance between the anchor and the hole wall, thereby improving the pullout resistance of the anchor. The anchor can solve the problem that a pore canal must be preformed in the bottom slab in the existing pre-stressed anchor, thus causing water leakage in the basement.
The purpose of the present application is achieved by the following technical solution.
An anchor assembly having a pre-stressed mandrel includes:
Furthermore, an outer circumferential surface of the pre-stressed concrete mandrel is provided with a mandrel positioning device and a grouting pipe preformed groove.
Furthermore, there are three pre-stressed tendons in the pre-stressed concrete mandrel.
Furthermore, a radius R1 of the pre-stressed concrete mandrel is 50-75 mm, and a thickness of the anchoring slurry is 30-60 mm.
Furthermore, the anchoring slurry is a cement slurry.
Furthermore, in order to enhance the bonding performance between the pre-stressed concrete mandrel and the cast-in-place anchoring slurry, the outer peripheral surface of the pre-stressed concrete mandrel is provided with bamboo-like or point-like protrusions or recesses.
Furthermore, the pre-stressed concrete mandrel can be in the shape of a frustum with a small top and a large bottom.
A construction method of an anchor assembly having a pre-stressed mandrel includes the following steps:
Furthermore, an expansion agent is added to the concrete when pouring the concrete mandrel in S1.
The present application has the following beneficial effects:
Reference Signs: pre-stressed concrete mandrel 1, cast-in-place anchoring slurry 2, bottom slab 3, grouting pipe 4, mandrel positioning device 5, pre-stressed tendon 101, mandrel concrete 102, grouting pipe preformed groove 103, and point-like protrusions 104.
The purpose and effect of the present application will become more clear by describing the present application in detail according to the drawings and preferred embodiments. It shall be understood that the specific embodiments described here are only intended to explain the present application, and are not used to limit the present application.
The anchor assembly having a pre-stressed mandrel has three innovations:
As shown in
As shown in
As shown in
As shown in
In order to avoid the offset during the placing process of the mandrel, the mandrel body is preferably provided with a three-way positioning device, which can be 30×30×h protrusions (h is the distance from the mandrel to the hole wall −0.5 cm), with three protrusions arranged along the circumferential direction and two turns arranged along the longitudinal direction. At the same time, the mandrel is provided with a grouting pipe preformed groove for binding the grouting pipe before lowering the hole. There are 2 grouting pipes, which are used for primary grouting and secondary grouting respectively.
The construction method of the anchor assembly having a pre-stressed mandrel of the present application includes the following steps:
Different from the conventional pre-stressed members, because the diameter of the anchor is generally 150-240 mm and the length is 4-15 m, considering the peripheral anchoring slurry, the pre-stressed concrete mandrel 1 of the present application has a smaller diameter, and the application of the prestress must ensure the positioning accuracy of the pre-stressed tendons, avoid the additional bending moment caused by deviation, and better reflect the advantages of prefabricated production in factories.
Because of the small cross section of the mandrel, the prestress degree will be significantly higher than that of ordinary pre-stressed members, and the elastic compression deformation and later shrinkage and creep will further increase the prestress loss. At present, according to the current Specifications for Design of Concrete Structures, the prestress loss of pretensioned axial compression members is shown in the first four items in Table 1. The loss of prestress in the table does not include the loss caused by the compression of the mandrel body caused by the release of the tensioned rebar. In view of the small cross-section of the mandrel, the prestress loss σs is supplemented on the basis of existing specifications through analysis.
Next, an example is given to prove the superiority of the anchor assembly of the present application and calculate its prestress loss.
The prestress loss of a 8 m composite uplift pile is analyzed, and the calculation results are shown in Table 2, wherein the strength grade of the concrete is C40, and the diameter of pile mandrel is 150 mm; the diameter of the pre-stressed tendons is 12.6 mm, the number is 3, and the tension control stress is 994 Mpa.
The example shows that the elastic shrinkage deformation loss accounts for 24.4% of the total loss. In order to reduce this part of the prestress loss, it is preferable to add an appropriate amount of an expansion agent to the mandrel body. The compressive stress in the mandrel body can be ensured by the later expansion of the concrete, and the pressure between the composite pile and the rock and soil can also be increased, thus enhancing the uplift bearing capacity of the anchor assembly. Compared with the non-pre-stressed anchor, the steel consumption is 20-30% of the original consumption.
Those skilled in the art can understand that the above is only a preferred example of the present application, and is not used to limit the present application. Although the present application has been described in detail with reference to the aforementioned examples, for those skilled in the art, they can still modify the technical solutions described in the aforementioned examples, or replace some of the technical features equally. All modifications and equivalent substitutions within the spirit and principles of the present application shall be included in the scope of protection of the present application.
Number | Date | Country | Kind |
---|---|---|---|
202110619979.0 | Jun 2021 | CN | national |
Number | Name | Date | Kind |
---|---|---|---|
1708277 | Martin | Apr 1929 | A |
1759626 | Ockels | May 1930 | A |
3257767 | Lassy | Jun 1966 | A |
3449876 | Howlett | Jun 1969 | A |
3795949 | Shorter | Mar 1974 | A |
3909142 | Surr | Sep 1975 | A |
4055929 | Stancati | Nov 1977 | A |
4166347 | Pohlman | Sep 1979 | A |
4671034 | Rehm | Jun 1987 | A |
5269113 | Dreizler | Dec 1993 | A |
20160333583 | Gan | Nov 2016 | A1 |
20200240099 | Huo | Jul 2020 | A1 |
Number | Date | Country | |
---|---|---|---|
20220412089 A1 | Dec 2022 | US |