1. Field of the Invention
The present invention relates to an apparatus, assembly and process for permitting fluid to be conveyed into a subterranean well via retrievable equipment positioned in tubing below a packer, and more particularly, to such apparatus, assembly and process for permitting gas lift to be conducted in a subterranean well below a packer wherein wireline retrievable gas lift valves or a check valve with a restrictive orifice are employed below the packer.
2. Description of Related Art
To produce fluids, such as hydrocarbons, from a subterranean formation, a well is drilled from the surface to a depth sufficient to capture the fluids of interest. The well is typically completed by cementing a string of tubulars, i.e. a casing string, in the well and establishing fluid communication between the well and the formation(s) and/or zone(s) of interest by forming perforations through the casing and into the formation(s) and/or zone(s) of interest. Such perforations can be formed by any suitable means, such as by conventional perforating guns. Thereafter, production tubing is positioned within the well and the annulus between the production tubing and casing is sealed typically by means of a packer assembly. Fluids, such as oil, gas and/or water, are then produced from the formation(s) and/or zone(s) of interest into the well via the perforations in the casing and to the surface via production tubing for transportation and/or processing.
While the formation or reservoir pressure is often initially sufficient to force produced fluids to the surface after completion of the well, some form of artificial lift, for example rod pumps, electrical submersible pumps, or gas lift, usually becomes necessary to assist in producing fluids from the well when the reservoir pressure becomes insufficient to produce fluids to the surface. In its simplest form, gas lift consists of injecting gas from the surface under pressure into the annulus between the casing and production tubing in a well. This injected gas is isolated from the perforations in the casing by means of the packer assembly that seals the casing/tubing annulus above the perforations. The production tubing above the packer is equipped with metering valves that inject the pressurized gas from the casing/tubing annulus into the tubing in an upward flow. These metering valves are installed in mandrels that are included in the tubing. This injected gas lightens the produced fluid present in the production tubing and the upward flow thereof assists in producing fluid upwardly toward the surface wellhead. The number and spacing of gas lift valves used in the production tubing above the packer is calculated to produce fluids to the surface in light of well data, the packer depth and desired production rates. It is preferred to use retrievable metering valves that can be removed from the well by means of a wireline unit and specially designed tools thereby eliminating the need and expense of pulling the production tubing from the well to repair and/or replace metering valves.
Wells are being increasingly completed with long perforated intervals of casing below the packer, for example up to 1,500 feet or more, to maximize production of fluids from subterranean formation(s) and/or zone(s) of interest. Such wells can be produced by conventional gas lift using metering valves above the packer for so long as the reservoir pressure is sufficient enough to convey produced fluids above the first gas lift valve positioned above the packer assembly. However, the pressure in many wells is or becomes insufficient to permit the well to be produced by conventional gas lift techniques and equipment.
A specialized packer has been developed to install gas metering valves in tubing below the packer so as to extend gas lift operations along the perforated interval below the packer. The tubing is secured to the packer and requires that the packer be released and all of the tubing and the packer be removed from the well to repair or replace the metering valves that are positioned below the packer. This packer and the procedure for removing metering valves are expensive and result in lost production of reservoir fluids.
Thus, a need exists for apparatus, assemblies and processes to provide for gas lift in tubing below the packer assembly in a well so as to provide production from a perforated interval. A further need exists for such apparatus, assemblies and processes for performing gas lift operations below a packer in a well which permit gas lift metering valves, including check valves with restricted orifices, to be retrievable by wireline.
To achieve the foregoing and other objects, and in accordance with the purposes of the present invention, as embodied and broadly described herein, one characterization of the present invention may comprise an apparatus having an elongated member including an upper section, an intermediate section dimensioned to extend through a packer deployed in a subterranean well and a lower section. The elongated member has a generally axial bore extending through the lower section and the intermediate section and into the upper section and in fluid communication with at least one opening extending through a side wall of the upper section.
Another characterization of the present invention may comprise a process for conveying fluid into a subterranean well comprising injecting a fluid under pressure into the annulus defined between a tubing string positioned in a subterranean well and casing secured in the well, through an internal flow path defined through a packer assembly secured to the tubing string intermediate the length thereof, into the interior of the tubing string below the packer assembly, through the end of the tubing string and into the annulus defined between the tubing string and casing below the packer. Fluid is produced from a subterranean region penetrated by the well via the annulus between the tubing string below the packer assembly and the casing, an internal annular flow path through the packer assembly defined between the internal flow path and the packer assembly, and the interior of the tubing string above the packer assembly.
A further characterization of the present invention may comprise an assembly having a first section of a tubing string extending from the surface of the earth into a subterranean well bore and having a packer secured to the lower end thereof. The first section has a generally axial bore therethrough and at least one opening through the wall thereof. A second section of the tubing string is secured to the packer and extends into the subterranean well bore below the packer. The second section has a generally axial bore therethrough and at least one opening through the wall thereof. A segregation member is releasably secured to the first section and extends through the packer and into the second section of the tubing string. The segregation member has a bore extending through a portion thereof which is in fluid communication with the at least one opening through the wall of the first section so as to define a flow path from the surface of the earth through a first annulus defined between the first section and the well bore, the at least one opening through the wall of the first section, and the bore in the segregation member. A check valve having an orifice is positioned within the second section of tubing string.
A still further characterization of the present invention may comprise a subterranean well comprising a tubing string positioned within casing in a subterranean well and having a packer secured intermediate the length thereof and sealingly engaging the casing. The subterranean well has a generally vertical portion and a deviated portion. A portion of the one tubing string extends into the deviated portion of the subterranean well. At least one check valve having an orifice is releasably secured within the tubing string below the packer and is capable of being retrieved on slickline that is conveyed within the tubing string.
The accompanying drawings, which are incorporated in and form a part of the specification, illustrate the embodiments of the present invention and, together with the description, serve to explain the principles of the invention.
In the drawings:
Referring to
In accordance with the present invention, a tubing string 30 may be positioned in the well and may be made up of individual joints of tubing 31 secured together by collars 32 as illustrated in
The bypass mandrel 40 (
The assembly described above may be assembled as the components are being run into the well. Once the assembly and associated tubing strings 30 and 80 are positioned so that packer assembly 50 is above and gas lift valves 86 are appropriately positioned in relation to the perforated interval from which fluids from subterranean region 18 are to be produced, the slips 52 and generally annular seal 54 of packer assembly 50 may be hydraulically and/or mechanically expanded into sealing engagement with casing 16 so as to form a fluid tight seal across annulus formed between packer assembly 50 and casing 16. In this manner, the annulus 11 formed between casing string 16 and the tubing string 30 and associated components above the packer assembly 50 is segregated from the annulus 17 formed between the casing 16 and the lower tubing string 80 and associated components below the packer assembly.
In accordance with the present invention, a segregation member 90 may thereafter be conveyed into tubing 30 from the surface by any suitable means, such as by a wireline. Segregation member 90 functions to isolate separate fluid flow paths through the assembly of the present invention and has an upper end 91, a generally tubular lower end 95 connected together by a generally tubular intermediate portion 94 of reduced diameter. Segregation member 90 may be integrally formed or formed of multiple portions secured together by any suitable means, for example by welds or threaded connections. Generally tubular portions 94 and 95 define an axial bore 98 therethrough that extends into one end of upper portion 91. Upper portion 91 may be provided with one or more radial openings 93 that may have any suitable configuration, for example a slot or port, and that intersect with bore 98 and extend outwardly to the periphery of upper end 91. The other end of upper end 91 may be provided with an axially extending bore 92 to allow engagement of segregation member 90 by a fishing tool for deployment and removal from a well. The outer peripheral surface of upper end 91 may be provided with a cross sectional profile 97 that corresponds to cross sectional profile 45 of bypass mandrel 40. The upper end has generally annular seals 96 which may be spaced apart to provide a fluid tight seal for radial ports or openings 93 as hereinafter described. Annular seals 99 may be provided around the exterior of lower end 95. The length of segregation member 90 can vary depending upon the length of packer 50, for example about 5 to about 8 feet. The diameters of the various components of segregation member 90 are selected depending upon the pressure and rate of gas being injected and fluid produced through the assembly of the present invention.
Segregation member 90 may be conveyed through tubing 30 until profile 97 on the outer peripheral surface of upper end 91 thereof engages profile 45 on the inner surface of one end of inner tubular member 44 and releasably locks segregation member 90 into engagement with bypass mandrel 40. In the position as illustrated in
Once the segregation member 90 is secured within bypass mandrel 40, the wireline may be released from segregation member 90 and withdrawn to the surface and the well is ready for production. In operation, fluid may be produced from subterranean region 18 through perforations 19 in the perforated interval 20 and upwardly as indicated by arrows 100 through annulus 17, ports 62, annulus 67, annulus 48 and bore 39 to the surface. If fluid is not capable of being produced to the surface by the pressure of the subterranean region, gas may be injected under pressure into annulus 11 between upper tubing string 30 and casing 16 as indicated by arrows 110 (
When it is desired to remove gas lift valves 86 for repair or replacement, a wireline with a retrieving tool at the lower end thereof may be run into tubing string 30 so as to latch onto upper portion 91 of segregation member 90 via bore 92. The wireline, retrieving tool and segregation member 90 may then be removed from the well and wireline may then be run into the well to retrieve the desired gas lift valves 86 in a manner evident to a skilled artisan. Thereafter, refurbished and/or new gas lift valves may be secured in side pockets 85 of mandrels 84 via wireline and segregation member 90 is thereafter conveyed via tubing string 30 and locked in engagement with bypass mandrel 40.
The following example demonstrates the practice and utility of the present invention, but is not to be construed as limiting the scope thereof.
A workover rig is moved onto a well, blow out prevention equipment is installed and the existing 2.875 inch outside diameter (“OD”) production tubing is removed from the 5.5 inch OD production casing in the well. The well is cleaned of any debris by running a tubing bailer on the 2.875 inch tubing to the total depth of the well of 9,000 feet. The tubing and bailer are removed from the well. The integrity of the casing above the top of the perforations in the well is determined by running a 5.5 inch OD packer on the 2.875 inch tubing to a depth of 7,500 feet. The packer is mechanically set and the annulus between the 2.875 inch tubing and the 5.5 inch casing above the packer is filled with completion fluid. The blow out prevention equipment is closed at the surface and the fluid in the annulus is pressurized to 1,500 pounds per square inch to determine casing integrity. Once casing integrity has been established, the packer is released and the tubing and the packer are removed from the 5.5 inch casing.
The below packer gas lift assembly is then inserted into the 5.5 inch casing. The assembly consists of the following components starting from the bottom. The assembly consists of a 2.875 inch tubing bull plug, 1,500 feet of 2.875 inch OD tubing with three 2.875 inch by 4.5 inch OD side pocket gas lift mandrels ported for annular flow spaced approximately 400 to 500 feet apart. Each gas lift mandrel is eccentric in design with the end fittings having 2.875 inch OD so as to permit mating by screw threads with the 2.875 inch OD tubing and the body of the mandrel that defines the side pocket has a 4.5 inch OD. The side pocket mandrels are each equipped with a wireline retrievable gas lift valve designed to operate with the predetermined gas lift injection volume and pressure. This portion of the assembly is then connected to a 2.875 inch OD by 2.25 inch inner diameter (“ID”) by 1.5 foot long seal nipple, a 2.875 inch OD by 1 foot long ported sub and a 5.5 inch OD casing packer. On top of the packer a 4.5 inch OD by 2.313 inch ID bypass mandrel is installed. Above the bypass mandrel, 7,500 feet of 2.875 inch OD tubing including three 2.875 inch by 4.5 inch side pocket gas lift mandrels ported for tubing flow are installed. Each gas lift mandrel is eccentric in design with the end fittings having 2.875 inch OD so as to permit mating by screw threads with the 2.875 inch OD tubing and the body of the mandrel that defines the side pocket has a 4.5 inch OD. The placement of the side pocket mandrels are based on the well pressure, expected production rate, design gas lift injection rate and pressure. A wireline retrievable gas lift valve which is designed to operate with the predetermined gas lift pressure and volume is installed in each side pocket mandrel. When the entire gas lift and tubing assembly is installed in the 5.5 inch OD production casing in the well, the gas lift assembly below the packer is placed adjacent to the perforated portion of the wellbore between the depths of 7,500 to 9,000 feet. The packer is then mechanically set approximately 50 feet above the top of the upper most perforation in the production casing. The blow out prevention equipment is then removed from the well, the 2.875 inch OD tubing is connected to the 5.5 inch OD casing wellhead, the wellhead valves are installed and the workover rig is removed from the well.
A slickline (single element wireline) truck is moved in and rigged up on the well with a 2.875 inch OD lubricator installed on the wellhead. A segregation member having a 2.313 inch OD upper end with two sets of 2.313 inch OD seals located on either side of ports connected to a 1 inch OD intermediate portion approximately 12 feet long which then connects to a 2.25 inch OD lower end is attached to wireline running tools and installed into the lubricator on the wellhead. The valves on the wellhead are then opened and the segregation member is lowered into the 2.875 inch OD tubing in the well on the wireline to the bypass mandrel. The 2.25 inch OD lower seal of the segregation member is inserted through the bypass mandrel, through the center of the 5.5 inch OD packer and the ported sub into the 2.25 inch ID seal bore nipple. A profile on the 2.313 inch OD upper end of the segregation member is located and locked into a 2.313 inch ID profile in the bypass mandrel with the two sets of 2.313 inch OD seals spaced on either side of the ports in the bypass mandrel. The wireline setting tools are released from the segregation member and are then removed from the well by wireline. The lubricator and wireline truck are removed from the well. A high pressure gas line is connected to the annulus defined between the tubing and casing and the annulus is allowed to pressure up to the predetermined maximum kick off pressure. The tubing is connected to the appropriate production facilities and once the casing pressure has reached the predetermined level, the tubing is opened for flow to the production facilities. The well will go through a normal gas lift unloading sequence from the gas lift valves above the packer and will transfer downhole to the gas lift valves below the packer until injection reaches the lowest most operating gas lift valve.
If the producing character of the well changes or a problem develops which would necessitate a change in the design or repair of the gas lift valves, a wireline truck is moved back on the well and the 2.875 inch OD lubricator is installed on the wellhead. Retrieving tools are attached to the wireline and are installed into the lubricator. The valves on the wellhead are opened and the retrieving tools are lowered into the 2.875 inch OD tubing on wireline to the upper end of the segregation member located in the bypass mandrel located at a depth of approximately 7,500 feet. The upper end of the segregation member is engaged by the wireline retrieving tools and the segregation member is removed from the well by wireline. A gas lift valve retrieving tool along with a side pocket kick over tool is then attached to the wireline and lowered into the 2.875 inch OD tubing, through the bypass mandrel to the depth of the gas lift valve which needs to be repaired or replaced. The side pocket kick over tool is activated, the gas lift valve is engaged with the retrieving tool and the valve is released from the side pocket mandrel and removed from the wellbore by wireline. The gas lift valve retrieving tool is removed from the wireline and a gas lift valve running tool is installed along with the side pocket kick over tool. The redesigned or repaired gas lift valve is attached to the gas lift valve running tool and is inserted into the 2.875 inch OD tubing and run through the bypass mandrel on wireline to the depth of the side pocket gas lift mandrel into which it is to be installed. At the proper depth, the side pocket kick over tool is activated and the gas lift valve is inserted and releasably secured into the side pocket mandrel. The wireline gas lift valve setting tool is released from the gas lift valve and the wireline and tools are removed from the wellbore. The side pocket kick over tool and the gas lift valve setting tool are removed from the wireline and the cross over seal assembly running tool is connected to the wireline. The upper end of the segregation member is then attached to the segregation member running tool and inserted into the 2.875 inch OD tubing on wireline. The lower 2.25 inch OD seal is inserted through the bypass mandrel, the 5.5 inch OD packer, the ported sub, and into the 2.25 inch ID seal bore nipple. The profile on the 2.313 inch OD upper end of the segregation member is inserted and locked into the 2.313 inch ID profile in the bypass mandrel with the two sets of 2.313 inch OD seals located on either side of the ports in the bypass mandrel. The setting tool is released from the upper end of the segregation member and the setting tool is removed from the wellbore by wireline. The wireline truck and lubricator is removed from the well, high pressure gas injection is initiated on the annulus defined between the tubing and the casing, the tubing is opened to the production facilities and the gas lift unloading sequence through the gas lift valves is initiated until the gas injection reaches the operating gas lift valve.
In accordance with another embodiment of the present invention illustrated in
In this embodiment, the tubing string 30, bypass mandrel 40, packer assembly 50, flow crossover sleeve 60, generally tubular seal bore nipple 70 and segregation member 90 may be configured, assembled and positioned within the generally vertical section of well 10 as previously described and illustrated in
By including gas lift valves and associated mandrels in tubing that is supported on a packer assembly, the apparatus and process of the present invention permit long perforated intervals to be produced by gas lift. The tubing employed below the packer in accordance with the present invention may be up to 15,000 feet or more. Further, the apparatus and process of the present invention allow retrievable apparatus and equipment, for example gas lift valves, to be used over long perforated intervals below the packer assembly. In this manner, long perforated intervals may be effectively produced by gas lift and apparatus and equipment, such as gas lift valves, may be retrieved for repair or replacement without pulling the production tubing from the well. In addition, the embodiment of the present invention illustrated in
As noted above, the present invention may be deployed and practiced using retrievable equipment other than gas lift valves 36 and/or 86. For example, flow control valves, water flood regulators, chokes, orifices, pressure gauges, temperature gauges, measurement devices or combinations thereof may be employed in lieu of gas lift valves 36 or 86 in one or all of the mandrels 34 or 84 deployed in casing strings 30 and 80, respectively. Accordingly, operations such as chemical injection, foam injection to unload water from a well, fresh water injection to lower salt concentration of connate water, injection of scale inhibitor, may be performed using the apparatus, assembly and process of the present invention.
Although casing 16 is illustrated as being one continuous tubular having a substantially uniform diameter along the length thereof, casing 16 may be made up of several intervals of tubing having differing diameters as will be evident to a skilled artisan. For example, surface casing may extend from the surface of the earth to a given depth, intermediate casing having a diameter less than that of the surface casing may extend from generally the depth at which the surface casing ends to another given depth, and a liner having a diameter less than that of the intermediate casing may extend from generally the depth at which the intermediate casing ends to subterranean region of interest. The apparatus, assembly and process of the present invention may be used with various casing configurations as will be evident to a skilled artisan. Further, components of the assembly of the present invention may extend into one or more sections of casing of a well. For example, where a casing configuration having surface casing, intermediate casing and a liner is utilized, the elastomeric seal 54 and slips 55 of the packer assembly 50 may be set in intermediate casing while the lower tubing string 80 extends into a liner.
While the foregoing preferred embodiments of the invention have been described and shown, it is understood that the alternatives and modifications, such as those suggested and others, may be made thereto and fall within the scope of the invention.
Number | Name | Date | Kind |
---|---|---|---|
1067868 | Dunn | Jul 1913 | A |
1754945 | Haskell | Apr 1930 | A |
1852716 | Grinnell | Apr 1932 | A |
1852717 | Grinnell et al. | Apr 1932 | A |
1992424 | Halliburton | Feb 1935 | A |
2077912 | Van Voorhis | Apr 1937 | A |
2179226 | Bryan | Nov 1939 | A |
2227538 | Dorton | Jan 1941 | A |
2917004 | Davis et al. | Dec 1959 | A |
2954043 | Canalizo | Sep 1960 | A |
3016844 | Vincent | Jan 1962 | A |
3065793 | Page | Nov 1962 | A |
3090316 | Montgomery | May 1963 | A |
3106170 | Gray et al. | Oct 1963 | A |
3160113 | Meyers | Dec 1964 | A |
3182726 | Stone, Jr. | May 1965 | A |
3190357 | Kirk | Jun 1965 | A |
3215087 | McLeod, Jr. | Nov 1965 | A |
3268004 | Kiel | Aug 1966 | A |
3302581 | Burch | Feb 1967 | A |
3427651 | Bielstein et al. | Feb 1969 | A |
3427653 | Jensen | Feb 1969 | A |
3580332 | Dean et al. | May 1971 | A |
3580336 | Meldau | May 1971 | A |
3617152 | Cummings | Nov 1971 | A |
3625288 | Roeder | Dec 1971 | A |
3642070 | Taylor et al. | Feb 1972 | A |
3654949 | McMurry | Apr 1972 | A |
3659961 | Lamb et al. | May 1972 | A |
3718407 | Newbrough | Feb 1973 | A |
3735815 | Myers | May 1973 | A |
3746089 | Vencil | Jul 1973 | A |
3750753 | Bernard | Aug 1973 | A |
3754597 | Garrett | Aug 1973 | A |
3784325 | Coanda et al. | Jan 1974 | A |
3814545 | Waters | Jun 1974 | A |
3844352 | Garrett | Oct 1974 | A |
3851997 | Douglas | Dec 1974 | A |
3873238 | Elfarr | Mar 1975 | A |
3887008 | Canfield | Jun 1975 | A |
4294313 | Schwegman | Oct 1981 | A |
4545731 | Canalizo et al. | Oct 1985 | A |
4682656 | Waters | Jul 1987 | A |
4708595 | Maloney et al. | Nov 1987 | A |
4862964 | George et al. | Sep 1989 | A |
5022427 | Churchman et al. | Jun 1991 | A |
5048610 | Ross et al. | Sep 1991 | A |
5113939 | Ross et al. | May 1992 | A |
5257665 | Watkins | Nov 1993 | A |
5329999 | White et al. | Jul 1994 | A |
5425425 | Bankston et al. | Jun 1995 | A |
5501279 | Garg et al. | Mar 1996 | A |
5875852 | Floyd et al. | Mar 1999 | A |
6082452 | Shaw et al. | Jul 2000 | A |
7147059 | Hirsch et al. | Dec 2006 | B2 |
7367401 | Moffett et al. | May 2008 | B2 |
7588806 | Hirai | Sep 2009 | B2 |
7766085 | Stephenson et al. | Aug 2010 | B2 |
20050269095 | Fairbanks | Dec 2005 | A1 |
20060076140 | Rouen | Apr 2006 | A1 |
20060113082 | Moffett et al. | Jun 2006 | A1 |
20090065199 | Patel et al. | Mar 2009 | A1 |
20090145595 | Mazzanti | Jun 2009 | A1 |
20090194293 | Stephenson et al. | Aug 2009 | A1 |
Number | Date | Country |
---|---|---|
222536 | Sep 1924 | GB |
534850 | Mar 1941 | GB |
2009099744 | Aug 2009 | WO |
2012018772 | Feb 2012 | WO |
Entry |
---|
The Composite Catalog of Oil Field and Pipe Line Equipment, No. Thirteen, 1942 Edition; p. 1642; The Gulf Publishing Co., USA. |
The Composite Catalog of Oil Field and Pipe Line Equipment, 18th Edition (1951), vol. 1; p. 1056; The Gulf Publishing Co., USA. |
The Composite Catalog of Oil Field and Pipe Line Equipment, 18th Edition (1951), vol. 2; pp. 3971 and 3986; The Gulf Publishing Co., USA. |
The Composite Catalog of Oil Field and Pipe Line Equipment, 19th Edition (1952-1953), vol. 2; pp. 4047 and 4050; The Gulf Publishing Co., USA. |
The Composite Catalog of Oil Field and Pipe Line Equipment and Services, 23rd Revision (1958-59), vol. 1; pp. 1090-1091; The Gulf Publishing Co., USA. |
The Composite Catalog of Oil Field Equipment and Services, 24th Revision (1960-61), vol. 3; p. 4294-B; The Gulf Publishing Co., USA. |
Composite Catalog of Oil Field Equipment and Services, 27th Revision, 1966-67, vol. 2; p. 3320; The Gulf Publishing Co., USA. |
U.S. Office Communication from U.S. Appl. No. 12/025,465 dated Jul. 8, 2009. |
U.S. Office Communication from U.S. Appl. No. 12/025,465 dated Feb. 3, 2010. |
U.S. Office Communication from U.S. Appl. No. 12/025,465 dated Mar. 23, 2010. |
Number | Date | Country | |
---|---|---|---|
20110042097 A1 | Feb 2011 | US |
Number | Date | Country | |
---|---|---|---|
Parent | 12025465 | Feb 2008 | US |
Child | 12849496 | US |