This patent application claims priority from Australian Provisional Patent Application No. 2022900872, the contents of which are incorporated herein in their entirety by reference thereto.
The present invention relates to an arrangement for impeding or inhibiting flow of water across joints, particularly construction joints, of building elements such as between a footing and a structural wall. The present invention also relates to a method of assembling such arrangement. The invention has primarily been developed for use with basement structures or other below-ground structures, and will be described hereinafter with reference to this application.
Ingress of water into a building structure is a significant problem in the construction industry, particularly for building structures which have below-ground foundations or footings supporting a wall, such as a basement.
Basements of buildings are built within varying soil conditions. Regardless of the ground conditions, the soil will consist of some level of moisture and perhaps ground water presence on a temporary or permanent basis. Construction of the basement is required to keep the basement free from moisture and ground water.
Achieving a waterproof basement construction is dependent upon on the walls themselves being waterproof, the footing/slab being waterproof, and also the junction (footing/slab to wall junction) being waterproof. The footing/slab itself can be made waterproof through various methods such as the application of a membrane system, use of waterproofing concrete additives and/or applying waterproofing devices at the footing/slab joints. If footing/slabs have adequate waterproofing, water ingress to the basement can only occur at the wall and the wall-footing/slab junction. These components can also be made waterproof if the membrane system of the footing/slab is continued up the wall, generally to the top basement wall. Such an application of a membrane system is normally referred to as “full tanking”, which requires access/space along the periphery of basement walls. Waterproofing of a wall and footing/slab junction is readily achievable when there is an access space available at the earth face of a basement wall.
To gain access to the earth face of a basement wall during construction requires over excavation of the soil so that the waterproofing contractor/personnel can apply the waterproofing materials to the earth face of the wall. The provision of access space requires a safe shoring system or over excavation such as battering (which is normally not possible or practical in sandy conditions and particularly water-logged soil). Shoring or battering is required to prevent the soil collapsing onto the waterproofer who is working within the access space. The provision of access space in some instances may not be feasible due to the high associated costs, the additional time involved, and potential loss of commercial space.
It is an object of the present invention to at least substantially address one or more of the above disadvantages, or at least provide a useful alternative to the above-discussed waterproofing approaches.
In a first aspect the present invention provides an arrangement for inhibiting water ingress across a construction joint, the arrangement including:
Preferably, the support surface includes a recess adjacent the sidewall, the recess having a bottom, and wherein the first sealing member includes a recess arm configured to line the bottom of the recess to define a void.
Preferably, the recess extends below the support surface.
Preferably, the recess extends into the sidewall.
Preferably, the recess arm includes one or more frangible locations to allow a portion of the recess arm to be removed for providing access to the void.
Preferably, a distance between a body of the first sealing member and a first of the one or more frangible locations is less than a gap between the body of the first sealing member and the external skin of the structural wall element, to facilitate the penetration of the sealing material of the joint seal into the interface between the first sealing member and the external skin.
Preferably, the arrangement includes an adjacent structural wall element, similar to the structural wall element, the adjacent structural wall element being connected to the structural wall element by a set of interlocking elements, the interlocking elements being separated by a gap,
Preferably, the gap between the body of the first sealing member and the skin of the structural wall element is sized, and the frangible locations are located, such that, when a cement slurry filled into the structural wall element shrinks during curing to a cured concrete forming a fluid flow gap between the skin of the structural wall element and the cured concrete, a fluid path exists between a fluid flow gap and the void, when the portion of the recess arm has been removed.
Preferably, the arrangement further includes an injection hose positioned to allow injection of a sealing material into the void to form the sealing joint.
Preferably, the injection hose includes a perimeter tube with openings to allow the injection of sealing material into the void, the perimeter tube being located in the void and substantially surrounded by the recess arm.
Preferably, the injection hose includes an offtake extending from the perimeter tube through the structural wall member to a dry side of the cavity adjacent the structural wall member.
Preferably, the injection hose includes a corner fitting having a first opening adapted to receive a portion of the injection hose and a second opening adapted to receive a portion of the injection hose, the first opening and the second opening being oriented perpendicularly to each other so that the sealing material can flow between the first and second openings.
Preferably, the first sealing member includes a retention arm extending from the first sealing member into the sidewall and/or the footing to resist movement of the first sealing member relative to the footing. [nailed or screwed into form ply—interface with reinforcement or slab formwork to be installed correctly]
Preferably, the retention arm includes a series of crenellations to create a tortuous path for water invading along an interface between the retention arm and the sidewall and/or footing.
Preferably, a body of the first sealing member includes a series of crenellations to create a tortuous path for water invading along an interface between the body and the sidewall and/or footing.
Preferably, the wall element longitudinally extends between an upper end portion and a lower end portion, wherein the lower end portion has a base that is seated on the support surface within the cavity.
Preferably, the first sealing member includes a support arm extending from the sealing member away from the sidewall, and wherein the base of the wall element is at least partially seated on the support arm.
Preferably, the first sealing member includes polyvinyl chloride (PVC).
Preferably, the joint seal includes a hydrophilic compound that expands in volume when in contact with water and/or an adhesive compound.
Preferably, the first sealing member includes a chamfer at an upper end thereof, the chamfer facing the external skin of the structural wall element to create a funnel gap between the first sealing member and the external skin of the structural wall element.
Preferably, the first sealing member has a profile and is extruded along an extrusion path, and wherein the extrusion path includes one or more of:
In a second aspect, the present invention provides a method of assembling an arrangement for inhibiting water ingress across a construction joint, the method comprising steps of:
Preferably, the step of applying the joint seal to the junction of the first sealing member and the surface of the first concrete body within the rebate is performed after the step of pouring the concrete mixture into the formwork.
Preferred embodiments of the present invention will now be described by way of example, with reference to the accompanying drawings, wherein:
In
The arrangement 100 includes a first concrete body in the form of a slab or footing 102 to be supported by an underlying ground or soil structure. The footing 102 has a generally level floor surface which, in use, is an upper side 104 and a ground-engaging surface which, in use, is a lower side 106. The footing has a thickness or height dimension 108 extending perpendicularly between the upper and lower sides 104, 106. The footing 102 also has a periphery or exterior edge 110 which, in use, faces or is adjacent to the supporting ground structure.
Formed through the upper side 104 of the footing 102 is a cavity or rebate 112. The rebate 112 is positioned adjacent to but spaced from the exterior edge 110 and extends through the footing 102 toward the lower side 106 to a predetermined depth. The rebate 112 defines a support surface 114 recessed relative to the upper side 104, and a pair of upwardly projecting lateral edges or sidewalls 116, 118 extending between the support surface 114 and the upper side 104. The pair of sidewalls 116, 118 includes an outer sidewall 116 and an inner sidewall 118. The outer sidewall 116 provides a vertical face 117 (
Secured to the vertical face 117 of the outer sidewall 116 is a first sealing member 120, as shown in
With particular reference to
The arrangement 100 further includes a structural wall element 124. In one embodiment, the structural wall element 124 includes a pre-cast wall element, such as an in-situ or pre-cast concrete element. In another embodiment, the structural wall element 124 includes a blockwork (Besser Blocks) section, for example laid from clay, concrete, or insulating material. In a preferred embodiment, the structural wall element 124 includes a permanent or lost formwork element 124 to form an upright structural wall to be supported by the footing 102. The element 124 has a body 126 longitudinally extending between an upper end portion (not shown) and a lower end portion 128. The body 126 provides two generally parallel coextensive sidewalls 130, 132 joined by transverse webs 134. The webs 134 have apertures 136 to facilitate insertion of reinforcing bars or the like and the flow of concrete infill. The first sidewall 130 provides an internal skin 138 to face an interior of the building structure. The second sidewall 132 provides an external skin 140 to face or be adjacent to the surrounding ground or earth. Preferably, the element 124 is formed of extruded plastics material such as polyvinyl chloride so as to provide a permanent waterproof finish. The element 124 includes panel joints (not shown) which inhibit water ingress. Further details of the element 124 are described in detail in the Applicant's earlier International Application No. PCT/AU2002/001382, filed on 10 Oct. 2002, or the Applicant's earlier International Application No. PCT/AU2012/000358. In the interest of brevity, the entire content of these International Applications is incorporated herein by cross-reference.
The element 124 is configured to receive a concrete pour to form a second concrete body defining the wall. The element 124 (and therefore the wall) is supported by the footing 102 via seating of the lower end portion 128 within the rebate 112 of the footing 102 such that a base 142 (
Preferably, the arrangement 100 further includes a drainage channel 144 installed in the rebate 112 along the vertical face 119 of the inner sidewall 118 to drain any excess water moving towards the internal skin 138. Drainage means 146 fluidly connects the drainage channel 144 to a pump-out pit or the like. The drainage channel 144 is primarily used to drain water before completion of the arrangement 100, when the joint seal 122 has not yet been completed or in the event of water spillage in the surrounding area, usually a basement, such as for example caused by a fire sprinkler failure, or use of water for car washing, after the joint seal 122 has been completed.
Moving now to
In this arrangement, the support surface 414 of the footing 402 includes a recess 413 adjacent the outer sidewall 416. The recess 413 has a bottom 415 and preferably extends below the support surface 414. However, in another embodiment, as shown in
The first sealing member 420 includes a vertical body 421 adapted to line the vertical face 417 of the outer sidewall 416. Extending from the vertical body 421 are, in the direction of the outer sidewall 416, one or more retention arms 423, adapted to be embedded in the sidewall 416 and/or footing 402, to resist movement of the first sealing member 420 relative to the footing 402. To this end, the retention arm 423 includes a portion parallel to the vertical body 421. The retention arm 423 is particularly useful for resisting movement of the first sealing member 420 while the footing 402 is curing. The vertical portion of the retention arm 423 may also be used to affix the first sealing member 420 to formwork used to construct the footing 402 by a fastener through the retention arm 423 into the formwork.
Extending from the vertical body 421, preferably toward the element or structural wall member 424, is a recess arm 425 configured to line the bottom of the recess 413 to define a void 427. Preferably, the recess arm 425 lines the entire support surface 414 of the recess 413. Preferably, the first sealing member 420 may be secured to the footing 402 using a fastener (not shown), such as a bolt, screw. In some embodiments the first sealing member 420 may be secured to temporary formwork, such as plywood formwork, used to cast the footing.
The first sealing member 420 also includes a support 429 extending from the vertical body 421 toward the element 424, at a location vertically above the recess arm 425.
Returning to
As shown in
Moving briefly to
Returning to
As shown in
In yet another embodiment, the first sealing member 420 includes a chamfer 455 at an upper end 457 thereof. The chamfer 455 is configured to face the external skin 440 of the element 424 to create a funnel gap 459 between the first sealing member 420 and the external skin 440. Prior to pumping of the sealing material 433, concrete may be poured into the funnel gap 459 to create a plug between the first sealing member 420 and the external skin 440 to inhibit movement of the sealing material 433 between the first sealing member 420 and the external skin 440. Preferably, a retention wall 471 used in the casting of the footing 402, may extend higher that the sidewall 416 of the footing 402 is being cast, such that when concrete is poured into the funnel gap 459 the concrete is retained at the funnel gap 459 to allow flow of the concrete into the funnel gap 459. The retention wall 471 may be temporary formwork made from plywood, or sheet piling. Sheet piling is preferred in sandy soil conditions.
As shown in
The element 424 may then be filled with concrete, as shown in
Due to the seating of the element 424 on the support 429 of the first sealing member 420, the gap 467 is open or filled fully or partially with concrete slurry, at a bottom thereof, to the void 427. Due to the inhibition of the sealing material 433 flowing out of the void 427 under high pressure between the first sealing member 420 and the element 424, the sealing material 433 is also pumped upwards and into the gap 467, forming a seal between adjacent elements 424. Further, a wall gap (not shown) may open between an interior surface (not shown) of the element 424 and the concrete filled into the element 424, due to shrinkage of the cement slurry as it cures. The wall gap is located at a similar point to the gap 467 and is therefore similarly open to the void 427 such that the sealing material 433 is pumped under high pressure upwards from the void 427 into the wall gap. Thus, while a fluid path gap may exist between the skin of the structural wall element 424 and the concrete infill within the structural wall element 424, at both the wet side of the element 424 (facing the sidewall 416) and the dry side of the element 424 (facing the away from the sidewall 416) when the concrete infill shrinks during curing to a cured concrete, preferably the sealing material 433 may be pumped under high pressure upwards from the void 427 into the fluid path gap located at the wet side of the structural wall element. The sealing material 433 under pressure may also reach to the fluid path gap between the element 424 and the shrunk concrete infill at the dry side of the structural wall element.
As shown in
As shown in
As shown in
A method 200 of assembling the arrangement 100 will now be described with reference to
In a next step 204, provision is made to create connection points or anchor points with the reinforcement to secure the waterstop 120 in position as well as to secure shuttering 222 required to form the rebate 112 within the footing 102. The waterstop 120 may also be temporarily affixed to the shuttering 222 for the rebate 112 for additional anchorage of the waterstop 120.
In a following step 206, a concrete mixture is prepared, subsequently poured into the formwork 214 and allowed to cure to form the footing 102. The concrete mixture may comprise a mixture of fine and coarse aggregate in a fluid cement binder, such as Portland cement. Once the concrete pour for the footing 102 has cured, the formwork 214, 222 is removed revealing the rebate 112 and the waterstop 120 cast-in-situ in the footing 102.
Using a caulk gun or other suitable means, the joint seal 122 (that is, the hydrophilic compound) is then applied (at step 208) as a controlled triangular bead to the junction of the waterstop 120 and the support surface 114.
In a subsequent step 210, the element 124 is installed to form the structural wall. The lower edge of the external skin 140 of the element 124 is pressed into the hydrophilic compound 122 to cause dispersion of the hydrophilic compound 122 underneath the external skin 140 and against the waterstop 120. High slump concrete is poured into the assembled element 124 and sufficiently vibrated to minimise air voids. Alternatively, self-compacting concrete may be poured into the element 124 to form the wall. The concrete is cured in the assembled element 124 to form the structural wall. Together, the second concrete body defining the structural wall and the first concrete body defining the footing 102 form a construction joint at the interface of the base 142 and the support surface 114.
In an optional step 212, the drainage channel 144 and associated drainage means 146 is installed.
Further, by virtue of the placement of the waterstop 306 in the prior art approach 300, water ingress is only prevented along one plane at a time and only once water has already entered the construction joint. In contrast, the presently disclosed arrangement 100 inhibits or prevents water ingress in both a vertical plane and a horizontal plane in one application and prior to any water entering the construction joint.
Moreover, the prior art approach 300 requires provision of access space adjacent the external skin of the wall 304 to apply a waterproofing membrane 308 to the external face of the wall 304 and the footing 302. In contrast, the presently disclosed arrangement 100 eliminates the need for this access space, thereby saving time and costs whilst providing a safer solution.
| Number | Date | Country | Kind |
|---|---|---|---|
| 2022900872 | Apr 2022 | AU | national |
| Filing Document | Filing Date | Country | Kind |
|---|---|---|---|
| PCT/AU2023/050073 | 2/6/2023 | WO |