The present disclosure relates systems, devices, assemblies, and methods for use in erecting structures. More particularly, the present disclose relates to modular elevator shafts, stairwells, and associated assembly techniques.
Concrete structures (e.g., elevator shafts, stairwells, stair shafts, etc.) are an important part of any mid-rise multistory building project.
However, conventional elevator shafts are time consuming and expensive to build—requiring heavy labor to be repeated the entire height of the shaft. For example, reinforced Concrete Masonry Units (CMUs) are laid up to an elevation not to exceed 5′4″ above the top of the elevator pit with a conventional low-lift grout technique and 12′8″ above the top of elevator pit with inspection windows at the first course of the vertical reinforcement locations utilizing a conventional high-lift grout technique. With conventional methods, deformed billet mild steel (e.g., rebar) must then be placed in the vertical and horizontal CMU reinforcement locations, inspected, and in the case of the high-lift grout technique, the inspection windows must be cleaned of mortar droppings and debris, and formed closed prior to grouting by method of concrete pumping the reinforced cells with the project-specified cell-fill concrete mix. At the vertical elevations where elevator rail bracket receivers are located and built into the wall, CMU reinforced bond beams must be incorporated into the wall requiring reinforcement, inspection, and grouting to provide strength to resist pull out of the bracket receiver.
This conventional process repeats itself in the described sequence to the full height of the elevator shaft. The conventional process requires scaffolding around the elevator shaft to the full height of the elevator shaft to provide access for the block masons, mason tenders, and other associated trades. At the top of the elevator shaft, a hoist beam is required to be set in the grout reinforced pocket incorporating a horizontal weld plate and welded, inspected, formed, and grouted to achieve the full 2-hour CMU fire rating. The CMUs are then “topped out” at the bearing height of the elevator cap with a CMU bond beam assembly, inspected and grouted. The elevator cap, typically a 6″ cast in place concrete slab is then formed, inspected, and poured to complete the assembly. This lengthy process is the reason the erection of elevator shafts often negatively impacts a building schedule and make it difficult to meet project deadlines.
Similarly, stair shafts (e.g., stairwells) are time consuming and expensive to build, requiring a heavy laborious sequence to be repeated the entire height of the shaft. For example, reinforced Concrete Masonry Units (CMUs) are laid up to an elevation not to exceed 5′4″ above the ground floor elevation with a conventional low-lift grout technique and 12′8″ above the ground floor elevation with inspection windows at the first course of the vertical reinforcement locations utilizing a conventional high-lift grout technique. With conventional methods, deformed Billet mild steel (e.g., rebar) must then be placed in the vertical and horizontal CMU reinforcement locations, inspected, and in the case of the high-lift grout technique, the inspection windows must be cleaned of mortar droppings and debris, and formed closed prior to grouting by method of concrete pumping the reinforced cells with the project specified cell-fill concrete mix.
This conventional process repeats itself in the described sequence to the full height of the stairwell shaft. The conventional process requires scaffolding around the stairwell to the full height of the stairwell for access for the block masons, mason tenders, and other associated trades. The CMUs are then “topped out” at the bearing height of the stair cap with a CMU bond beam assembly, inspected and grouted. A stairwell cap, typically a 6″ cast in place concrete slab is then formed, inspected, and poured to complete the assembly. This lengthy process is the reason the erection of stairwells often negatively impacts a building schedule and make it difficult to meet project deadlines.
The disclosure provides, in one aspect, an assembly comprising: a first precast concrete structure including a first rebar member and a second precast concrete structure including a second rebar member. The second rebar member is aligned with the first rebar member along an axis. The assembly further includes a sleeve with an aperture, the sleeve coupled to the first rebar member; a connecting member coupled to the second rebar member; and a rebar dowel coupled to the connecting member. The rebar dowel extends through the aperture in the sleeve and is at least partially received within the sleeve. The assembly further includes a grout positioned within the sleeve; a gasket positioned between the sleeve and the connecting member; a seal positioned between the first precast concrete structure and the second precast concrete structure; and a shim positioned between the first precast concrete structure and the second precast concrete structure.
In some embodiments, the first precast concrete structure includes a first surface, and the second precast concrete structure includes a second surface, and wherein the seal is positioned between the first surface and the second surface.
In some embodiments, the first precast concrete structure further includes a lifting anchor assembly with an aperture formed in the first surface.
In some embodiments, the sleeve is aligned with the axis and the axis extends through the aperture.
In some embodiments, the sleeve is coupled to the first rebar member with a threaded connection.
In some embodiments, the sleeve includes a cylindrical wall extending along the axis, a cavity, a first charge port in fluid communication with the cavity, and a second charge port in fluid communication with the cavity.
In some embodiments, the first charge port extends along a first charge port axis and the second charge port extends along a second charge port axis, wherein the first charge port axis is perpendicular to the axis and the second charge port axis is perpendicular to the axis.
In some embodiments, the sleeve is coupled to the first rebar member at a first end of the sleeve, and the aperture is positioned at a second end of the sleeve, wherein the second end is opposite the first end.
In some embodiments, the connecting member has a first end coupled to the second rebar member and a second end coupled to the rebar dowel, where the first end is opposite the second end.
In some embodiments, the rebar dowel has a threaded end coupled to the connecting member.
In some embodiments, the gasket includes a gasket aperture, and the rebar dowel extends through the gasket aperture.
In some embodiments, the seal is a polyurethane foam.
In some embodiments, the seal includes a first ridge, a second ridge, and a portion extending between the first ridge and the second ridge.
In some embodiments, the shim is positioned between the first ridge and the second ridge.
In some embodiments, the shim has a thickness within a range of 0.25 inches to 0.75 inches.
In some embodiments, the seal and the shim are part of a joint assembly with at least a 2-hour fire-rating.
In some embodiments, the first precast concrete structure includes an opening and a plurality of rebar members extending through the opening.
In some embodiments, the first precast concrete structure or the second precast concrete structure includes a first notch, a second notch, and a hoist beam at least partially positioned with the first notch and the second notch.
In some embodiments, the second precast concrete structure is a cap.
In some embodiments, the first precast concrete structure and the second precast concrete structure at least partially form an elevator shaft or a stairwell.
The disclosure provides, in one aspect, a method of erecting a structure, the method comprising: positioning a seal on a first precast concrete structure; raising a second precast concrete structure; coupling a rebar dowel to the second precast concrete structure; aligning the second precast concrete structure with the first precast concrete structure; and lowering the second precast concrete structure onto the first precast concrete structure. The seal is positioned between the first precast concrete structure and the second precast concrete structure.
In some embodiments, the method further includes positioning a plurality of shims on the seal.
In some embodiments, raising the second precast concrete structure includes attaching a crane to a plurality of lifting anchors in the second precast concrete structure.
In some embodiments, coupling the rebar dowel to the second precast concrete structure includes threading the rebar dowel into a connecting member in the second precast concrete structure.
In some embodiments, aligning the second precast concrete structure with the first precast concrete structure includes aligning the rebar dowel with a sleeve formed in the first precast concrete structure.
In some embodiments, lowering the second precast concrete structure onto the first precast concrete structure includes lowering the rebar dowel into a sleeve formed in the first precast concrete structure.
In some embodiments, the method further includes injecting a grout into a sleeve formed in the first precast concrete structure prior to lowering the second precast concrete structure onto the first precast concrete structure.
In some embodiments, the method further includes forming the first precast concrete structure and the second precast concrete structure at an offsite facility and transporting the first precast concrete structure and the second precast concrete structure to a jobsite.
In some embodiments, the first precast concrete structure and the second precast concrete structure form one story of a building when joined together.
In some embodiments, the method further includes positioning a second seal on the second precast concrete structure; raising a third precast concrete structure; coupling a second rebar dowel to the third precast concrete structure; aligning the third precast concrete structure with the second precast concrete structure; and lowering the third precast concrete structure onto the second precast concrete structure. The second seal is positioned between the second precast concrete structure and the third precast concrete structure.
In some embodiments, the method further includes cutting a plurality of rebar from an opening formed in the first precast concrete structure.
In some embodiments, the method further includes adding masonry to the opening.
In some embodiments, no scaffolding is required for the method.
In some embodiments, no backer-rod and fire caulk joint assembly are positioned between the first precast concrete structure and the second precast concrete structure.
Other aspects of the disclosure will become apparent by consideration of the detailed description and accompanying drawings.
As used herein, “about” and “approximately” are used to provide flexibility to a numerical range endpoint by providing that a given value may be “slightly above” or “slightly below” the endpoint without affecting the desired result.
The term “coupled,” as used herein, is defined as “connected,” although not necessarily directly, and not necessarily mechanically. The term coupled is to be understood to mean physically, magnetically, chemically, fluidly, electrically, or otherwise coupled, connected or linked and does not exclude the presence of intermediate elements between the coupled elements absent specific contrary language.
The terms “comprise(s),” “include(s),” “having,” “has,” “can,” “contain(s),” and variants thereof, as used herein, are intended to be open-ended transitional phrases, terms, or words that do not preclude the possibility of additional acts or structures. The singular forms “a,” “an” and “the” include plural references unless the context clearly dictates otherwise. The present disclosure also contemplates other embodiments “comprising,” “consisting of” and “consisting essentially of,” the embodiments or elements presented herein, whether explicitly set forth or not.
For the recitation of numeric ranges herein, each intervening number there between with the same degree of precision is explicitly contemplated. For example, for the range of 6-9, the numbers 7 and 8 are contemplated in addition to 6 and 9, and for the range 6.0-7.0, the number 6.0, 6.1, 6.2, 6.3, 6.4, 6.5, 6.6, 6.7, 6.8, 6.9, and 7.0 are explicitly contemplated.
In the foregoing description of preferred embodiments, specific terminology has been resorted to for the sake of clarity. However, the invention is not intended to be limited to the specific terms so selected, and it is to be understood that each specific term includes all technical equivalents which operate in a similar manner to accomplish a similar technical purpose. Terms such as “top” and “bottom”, “front” and “rear”, “inner” and “outer”, “above”, “below”, “upper”, “lower”, “vertical”, “horizontal”, “upright” and the like are used as words of convenience to provide reference points.
Before any embodiments are explained in detail, it is to be understood that the invention is not limited in its application to the details of construction and the arrangement of components set forth in the following description or illustrated in the following drawings. The invention is capable of other embodiments and of being practiced or of being carried out in various ways.
Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art. In case of conflict, the present document, including definitions, will control. Preferred methods and materials are described below, although methods and materials similar or equivalent to those described herein can be used in practice or testing of the present disclosure. All publications, patent applications, patents and other references mentioned herein are incorporated by reference in their entirety. The materials, methods, and examples disclosed herein are illustrative only and not intended to be limiting.
Disclosed herein are constructions techniques for use in erecting mid-rise multi-story wood framed or steel stud framed buildings. In one aspect, the present disclosure relates to a modular elevator shaft structure with a 2-hour fire rated assembly and associated assembly techniques. In another aspect, the present disclosure relates to a modular stairwell (e.g., stair shaft) with a 2-hour fire rated assembly and associated assembly techniques. The disclosed assemblies and methods achieve the technical aspects and dimensional requirements of elevator or manufacturer and building codes, while resulting in a significantly reduced erection duration (e.g., days) when compared to the typical time required to complete a conventional reinforced CMU 2-hour fire rated stairwell or elevator shaft (e.g., weeks).
With reference to
With reference to
As detailed further herein, segments (e.g., segments 26, 30, 34, 38, 42) of the elevator shaft structure 10 are precast segments that are formed and produced at an offsite facility. These segments are transported to a jobsite and erected to full height by joining upper and lower segments together. In the illustrated embodiment, each lower and upper segment, when joined together, are equivalent to one story of the building. Using precast concrete monolithic elevator segments simplifies and expedites the construction process exponentially. In some embodiments, the entire elevator shaft structure is erected in less than a single day each. As a result, the disclosed assemblies and methods result in substantial time savings over traditional methods employing reinforced concrete masonry, which requires days and weeks to construct a single shaft.
With reference to
With continued reference to
In the illustrated embodiment, the first portion 50 of the opening 46 formed in each of the lower segments 30 is pre-formed from reinforced concrete and includes rebar 58 (e.g., #6 rebar) positioned within the opening 46. In other words, the lower segment 30 includes an opening 46 and a plurality of rebar members 58 extend through the opening 46. The rebar 58 position within the opening 58 advantageously provides fall protection for workers working near the elevator shaft structure 10. In some embodiments, a grout recess 62 is formed in each upper segment 34 to accommodate installation of an elevator door sill, for example.
With reference to
With continued reference to
With reference to
In the illustrated embodiments, the shims 98 are positioned between the first ridge 102 and the second ridge 106 of the seal 94. In other words, the shims 98 are positioned on top of the portion 110 of the seal 94. In some embodiments, the shims 98 are multipolymer bearing pads available from Korolath. In some embodiments, the shims 98 are 4-inch×4 inch squares that are 0.5 inches thick. In some embodiments, the shims 98 have a thickness within a range of approximately 0.25 inches to approximately 0.75 inches. In some embodiments, the shims 98 maintain a spacing between opposing surfaces of adjacent concrete segments. In other words, the shims 98 are positioned between a first precast concrete structure and a second, adjacent, precast concrete structure. In some embodiments, the shims 98 maintain a half inch space between adjacent segments. In other words, the shims 98 control the amount of compression on the seal 94 positioned between adjacent concrete segments (e.g., lower segment 30 and upper segment 34).
In some embodiments, the seal assembly 90 further includes a gasket 114. In some embodiments, the gasket 114 is a compressible gasket available from Dayton Superior. In the illustrated embodiment, the gasket 114 includes a gasket aperture 118 configured to receive a rebar portion (e.g., the rebar dowel 134).
With continued reference to
With reference to
The sleeve 126 is coupled at a first end 150 of the sleeve 126 to a rebar member 146 positioned within the concrete structure. In some embodiments, the sleeve 126 is coupled to the rebar member 146 with a threaded connection. The connecting member 130 is coupled to a rebar member 146 positioned within the concrete structure. In some embodiments, rebar members 146 includes a sleeve 126 at one end of the rebar member 146 and a connecting member 130 at the opposite end of the rebar member 146. In some embodiments, the rebar members 146 includes a sleeve 126 at both end of the rebar member 146 (e.g., lowest segment 26).
With reference to
With reference to
In some embodiments, the grout 138 is a non-shrink grout. In some embodiments, the grout 138 is a non-shrink, non-corrosive, and non-metallic cementitious grout. In some embodiments, the grout 138 is high strength grout that develops at least 12,000 PSI. In some embodiments, the grout 138 is Turbo Grout HP 12® available from Dayton Superior.
In one embodiment, #5 taper-threaded rebar (e.g., rebar 146) is mechanically connected to the sleeve 126 with the sleeve uniquely inverted to allow the insertion of the gasket 114 and for pre-filling the sleeve 126 with grout 1380. A 6-inch length #5 threaded rebar dowel 134 is mechanically connected to a connecting member 130. The tension connection assembly 122 is fixed in the form system and cast in precise vertical alignment with the concrete elements, except for the gasket 114, grout 138, and rebar dowel 134 that are installed during the erection process.
With reference to
To begin assembly (e.g., erection) of the elevator shaft structure 10, the lowest segment 26 is aligned with the elevator pit 192. The elevator pit 192 includes rebar portions 200 extending from the top surface 196. Sleeves 126 in the lowest segment 26 are aligned with the rebar portions 200. In the illustrated embodiment, the lowest segment 26 has sleeves 126 at both ends of the rebar 146. After the lowest segment 26 is lowered onto the elevator pit 192, the rebar portion 200 is received within the sleeve 126 (e.g., the lower sleeves) and the grout 138 is injected into the sleeve 126 via the charge ports 170, 174. In other words, in the lowest segment 26, the sleeve 126 is filed with grout 138 via the charge ports 170, 174 after the lowest segment 26 has been positioned on top of the elevator pit 192.
With reference to
The segments 26, 3034, 38, 42 includes lifting anchor assemblies 204 located at the top surface of each segment for handling and erection purposes. For example, the lower segment 30 includes a lifting anchor assembly 204 with an aperture 206 formed in the upper surface 70.
With reference to
With reference to
The method 300 further includes (STEP 303) coupling a rebar dowel (e.g., rebar dowel 134) to the second precast concrete structure (e.g.,
The method 300 further includes (STEP 304) aligning the second precast concreate structure with the first precast concrete structure (e.g.,
After (STEP 304), the method 300 includes (STEP 305) lowering the second precast concrete structure onto the first precast concrete structure. In some embodiments, (STEP 305) lowering the second precast concrete structure onto the first precast concrete structure includes lowering the rebar dowel into a sleeve (e.g., sleeve 98) formed in the first precast concrete structure. In some embodiments, the method 300 includes injecting a grout (e.g., grout 138) into a sleeve (e.g., sleeve 126) formed in the first precast concrete structure prior to (STEP 305) lowering the second precast concrete structure onto the first precast concrete structure. With the second precast concrete structure lowered, the seal is positioned between the first precast concrete structure and the second precast concrete structure. In some embodiments, the shim maintains at least an approximately 0.5-inch distance between the adjacent concrete structures. In some embodiments, the first precast concrete structure and the second precast concrete structure form one story of a building when joined together.
Steps of the method 300 may be repeated to erect additional stories of the structure. For example, in some embodiments, the method 300 further includes positioning a second seal on the second precast concrete structure; raising a third precast concrete structure; coupling a second rebar dowel to the third precast concrete structure; aligning the third precast concrete structure with the second precast concrete structure; and lowering the third precast concrete structure on the second precast concrete structure. With the third precast concrete structure lowered, the second seal is positioned between the second precast concrete structure and the third precast concrete structure. In other words, first the second precast concrete structure is lowered onto and secured to the first precast concrete structure and then the third precast concrete structure is lowered onto and secured to the second precast concrete structure.
In some embodiments, the method 300 further includes cutting a plurality of rebar (e.g., rebar 58) from an opening formed in the first precast concrete structure. In other words, the method 300 includes cutting out the rebar from the opening when the door assemblies, for example, are ready to be installed. In some embodiments, the method 300 further includes adding masonry (e.g., door assemblies 14, masonry assembly 22) to the opening. In other words, after completion of installing the elevator car, the rebar is removed to accommodate the elevator door installation. The void between the rough openings and the finished door frame are then infilled with the masonry assembly (e.g., a 2-hour rated reinforced CMU). Advantageously, no scaffolding is required for the method 300. Advantageously, no conventional backer-rod and fire caulk joint assembly is positioned between the first precast concrete structure and the second precast concrete structure.
The method 300 is repeated until the last upper segment is installed at which point the riser segment 38 is installed next.
With reference to
With continued reference to
With reference to
The pre-cast concrete elevator structure and erection method disclosed herein include at least the following advantages. The disclosed construction method 300 provides an advantage by allowing elevator shafts to be rapidly assembled at a jobsite prior to the first-floor slab being poured, finished, and cured by erecting the shaft directly on the elevator pit walls or prior to the start of framing the walls and elevated floors after the first level slab is poured, finished, and cured. No scaffolding is required for access as would be required with CMU construction, allowing immediate access of following trades to the area upon completion of the erection of the shaft. Temporary bracing, which is disruptive to following trades, is not required, as the precast concrete structures disclosed herein are monolithic “boxes” which will withstand construction wind loads due to geometry, self-weight, and the fact that the permanent connections are made at the elevator pit walls and segment-to-segment during the sequential erection process. The 2-hour UL rated joint assembly 90 is installed between the segments during the erection of the segments and cap, contributing to the short time duration by eliminating the common backer-rod and fire caulk joint assembly installed in joints after the wall completion. The wide flange hoist beam 218, required by all elevator manufacturers to be installed at the top of the shaft for the purpose of building the elevator and later servicing the elevator is installed in the precast element offsite, eliminating the onsite activities of setting, welding, inspecting, and grouting around the beam within the thickness of the wall. The concrete cap segment 42 is produced offsite and installed during the final step of the precast erection. In some embodiments, the erection method 300 requires 4 workers for a much shorter duration, (a CMU shaft requires double the manpower for a much longer duration), reducing overall risks and hazards associated with working on scaffolding at significant heights. Rebar 58 is installed in the lower segment door openings offsite to ensure fall protection per OSHA guardrail guidelines for following trades working near the elevator shafts. The inspection process for the elevator shaft 10 is reduced to minimal requirements, which will save additional time over the reinforced CMU method which requires multiple inspections.
With reference to
With reference to
With reference to
With reference to
With reference to
With reference to
The pre-cast concrete stairwell structure and erection method disclosed herein include at least the following advantages. The erection method 300 provides an advantage by allowing stairwell structure to be rapidly assembled at a jobsite prior to the first-floor slab being poured, finished, and cured by erecting the shaft directly on the foundation or—prior to the start of framing the walls and elevated floors after the first level slab is poured, finished, and cured. No scaffolding is required for access as would be required with CMU construction, allowing immediate access of following trades to the area upon completion of the erection of the shaft. The stairs can be immediately installed offering safe first responder and gurney access to all floors as they progress vertically. A fire protection standpipe can be immediately installed allowing access to pressurized water in the event of a fire during the construction process. The permanent stairs installed immediately allows vertical access to all tradesman, inspectors and supervisors, eliminating the need for vertical access by ladder, which is a risk hazard. Temporary bracing (which is disruptive to following trades) is not required, as the precast elements are monolithic “boxes” which will withstand construction wind loads due to geometry, self-weight, and the fact that the permanent connections are made at the ground floor slab and segment-to-segment during the sequential erection process. The 2-hour UL rated joint assembly 534 is installed between the segments during the erection of the segments and cap, contributing to the short time duration by eliminating the common backer-rod and fire caulk joint assembly installed in joints after the wall completion. The concrete caps 526, 530 are also produced offsite and installed during the final step of the precast erection. The erection process requires 4 men for a much shorter duration, (a CMU shaft requires double the manpower for a much longer duration), reducing overall risks and hazards associated with working on scaffolding at significant heights. The inspection process is reduced to minimal requirements, which will save additional time over the reinforced CMU method which requires multiple inspections.
Various features and advantages are set forth in the following claims.
The present application claims priority to U.S. Provisional Application No. 63/518,187, filed Aug. 8, 2023, which is incorporated herein by reference in its entirety.
Number | Date | Country | |
---|---|---|---|
63518187 | Aug 2023 | US |