This disclosure relates generally to the field of wellbore drilling operations ancillary to actions that lengthen (drill) the wellbore. More specifically, the disclosure relates to method for providing operating guidance to drilling unit operating personnel for optimum speed of movement of a drill string in and out of a wellbore (“tripping”), and for collecting and comparing actual tripping measurement data to benchmark tripping data to evaluate and improve efficiency of particular drilling unit operating personnel (“crews”).
Wellbore drilling operations include activities ancillary to drilling the wellbore, including, e.g., tripping a drill string (i.e., assembly of drill pipe segments as “stands” and/or “joints”) out of the wellbore and back into the wellbore for the purposes, among others, of changing drill bits or other drilling tools, setting a conduit (e.g., a casing or liner) in the wellbore and circulating drill cuttings out of the wellbore along its entire length.
Tripping may be speed constrained by reason of hydrostatic fluid pressure changes in the wellbore caused by removal of the drill string from the wellbore or insertion of the drill string into the wellbore. Fluid displacement by such movement of the drill string, combined with viscous effects of the drilling fluid (“mud”) in the wellbore may cause corresponding decreases or increases in the hydrostatic pressure of the mud. If the hydrostatic pressure is increased by excessive speed “tripping in” (i.e., moving the drill string into the wellbore), it is possible to exceed fracture pressure of one or more exposed formations in an uncased part of the wellbore (called “surge”). Conversely, decrease in hydrostatic pressure caused by excessive speed “tripping out” (i.e., removing the drill string from the wellbore) may result in the hydrostatic pressure being reduced below the formation fluid pressure of some exposed formations (called “swab”). Either of the foregoing may result in a wellbore pressure control emergency situation.
It is well known in the art how to calculate increases and decreases in hydrostatic pressures caused by tripping if the drill string configuration is known and the mud properties (e.g., density, viscosity) are known.
Tripping may also be speed constrained by reason of shock and vibration of the drill string as it moves through the wellbore. If shock and vibration limits are exceeded for certain drill string components, then they may be susceptible to failure during drilling operations.
It is desirable to communicate such information to a drilling unit operating crew in an easy to use form so that their operating procedures can be guided and improved. It is also desirable to accumulate statistical information over a wellbore and in some cases compare to benchmark operating procedures from other wellbores in order to improve drilling unit operating crew performance
There may be differences between an original well plan, which may include a detailed sequence of specific drilling actions and ancillary actions, and an actual well construction schedule as a result of actions such as the foregoing being performed more or less quickly than originally intended, or where the originally planned sequence of specific actions is altered as a result of conditions encountered during wellbore construction. It may be desirable to be able to revise the detailed sequence to correspond to the actual performance of part of the detailed sequence and the actual wellbore conditions encountered.
A method according to one aspect for scheduling wellbore construction activities includes entering a well plan into a computer. The well plan includes estimated start and stop times for a plurality of activities in a predetermined sequence. Progress of selected ones of the plurality of activities is measured during their performance. In the computer, expected ending time of at least one of the plurality of activities is recalculated based on progress thereof during that activity. In the computer, expected start and stop times are recalculated for each activity subsequent to the activity in progress based on the recalculated expected ending time. The recalculated start and stop times for each subsequent activity are displayed.
Other aspects and advantages will be apparent from the description and claims that follow.
A drill string 112 is suspended within the wellbore 111 and has a bottom hole assembly (BHA) 151 which includes a drill bit 155 at its lower (distal) end. The surface portion of the drilling and measurement system includes a platform and derrick assembly 153 positioned over the wellbore 111. The platform and derrick assembly 153 may include a rotary table 116, kelly 117, hook 118 and rotary swivel 119 to suspend, axially move and rotate the drill string 112. In a drilling operation, the drill string 112 may be rotated by the rotary table 116 (energized by means not shown), which engages the kelly 117 at the upper end of the drill string 112. Rotational speed of the rotary table 116 and corresponding rotational speed of the drill string 112 may be measured un a rotational speed sensor 116A, which may be in signal communication with a computer in a surface logging, recording and control system 152 (explained further below). The drill string 112 may be suspended fin the wellbore 111 from a hook 118, attached to a traveling block (also not shown), through the kelly 117 and a rotary swivel 119 which permits rotation of the drill string 112 relative to the hook 118 when the rotary table 116 is operates. As is well known, a top drive system (not shown) may be used in other embodiments instead of the rotary table 116, kelly 117 and swivel rotary 119.
Drilling fluid (“mud”) 126 may be stored in a tank or pit 127 disposed at the well site. A pump 129 moves the drilling fluid 126 to from the tank or pit 127 under pressure to the interior of the drill string 112 via a port in the swivel 119, which causes the drilling fluid 126 to flow downwardly through the drill string 112, as indicated by the directional arrow 156. The drilling fluid 126 travels through the interior of the drill string 112 and exits the drill string 112 via ports in the drill bit 155, and then circulates upwardly through the annulus region between the outside of the drill string 112 and the wall of the borehole, as indicated by the directional arrows 163. In this known manner, the drilling fluid lubricates the drill bit 155 and carries formation cuttings created by the drill bit 155 up to the surface as the drilling fluid 126 is returned to the pit 127 for cleaning and recirculation. Pressure of the drilling fluid as it leaves the pump 129 may be measured by a pressure sensor 158 in pressure communication with the discharge side of the pump 129 (at any position along the connection between the pump 129 discharge and the upper end of the drill string 112). The pressure sensor 158 may be in signal communication with a computer forming part of the surface logging, recording and control system 152, to be explained further below.
The drill string 112 typically includes a BHA 151 proximate its distal end. In the present example embodiment, the BHA 151 is shown as having a measurement while drilling (MWD) module 130 and one or more logging while drilling (LWD) modules 120 (with reference number 120A depicting a second LWD module 120). As used herein, the term “module” as applied to MWD and LWD devices is understood to mean either a single instrument or a suite of multiple instrument contained in a single modular device. In some embodiments, the BHA 151 may include a rotary steerable directional drilling system (RSS) and hydraulically operated drilling motor of types well known in the art, collectively shown at 150 and the drill bit 155 at the distal end.
The LWD modules 120 may be housed in one or more drill collars and may include one or more types of well logging instruments. The LWD modules 120 may include capabilities for measuring, processing, and storing information, as well as for communicating with the surface equipment. By way of example, the LWD module 120 may include, without limitation one of a nuclear magnetic resonance (NMR) well logging tool, a nuclear well logging tool, a resistivity well logging tool, an acoustic well logging tool, or a dielectric well logging tool, and so forth, and may include capabilities for measuring, processing, and storing information, and for communicating with surface equipment, e.g., the surface logging, recording and control unit 152.
The MWD module 130 may also be housed in a drill collar, and may contain one or more devices for measuring characteristics of the drill string 112 and drill bit 155. In the present embodiment, the MWD module 130 may include one or more of the following types of measuring devices: a weight-on-bit (axial load) sensor, a torque sensor, a vibration sensor, a shock sensor, a stick/slip sensor, a direction measuring device, and an inclination and geomagnetic or geodetic direction sensor set (the latter sometimes being referred to collectively as a “D&I package”). The MWD module 130 may further include an apparatus (not shown) for generating electrical power for the downhole system. For example, electrical power generated by the MWD module 130 may be used to supply power to the MWD module 130 and the LWD module(s) 120. In some embodiments, the foregoing apparatus (not shown) may include a turbine-operated generator or alternator powered by the flow of the drilling fluid 126. It is understood, however, that other electrical power and/or battery systems may be used to supply power to the MWD and/or LWD modules.
In the present example embodiment, the drilling and measurement system may include a torque sensor 159 proximate the surface. The torque sensor 159 may be implemented, for example in a sub 160 disposed proximate the top of the drill string 112, and may communicate wirelessly to a computer (see
The operation of the MWD and LWD instruments of
1. General Description of Methods
A Guidance and Statistical Processing Method according to the present disclosure may operate with, for example, two levels of granularity: on a stand by stand (or joint by joint) basis and for an entire trip (i.e., a complete removal from or insertion into the wellbore of a drill string as set forth in the Background section herein). Different users of the method and system may use different levels of granularity. For example, the Driller (drilling unit operator) is likely to be interested in stand by stand information, while the wellbore operator or wellbore designer is more likely to be interested in the overall trip information.
It will be appreciated by those skilled in the art that tripping operations are most commonly conducted by assembling or disassembling multiple segment assemblies, typically each consisting of three segments or joints of drill pipe and/or drill collars, heavy weight drill pipe and/or drilling tools. Each such multiple segment assembly is referred to as a stand. It should be clearly understood that while the present description is made in terms of stands, the use of the methods described herein is not limited to tripping by stands. The methods are equally applicable to single joints or stands having more or fewer than three segments (joints) of the above described items.
While tripping a joint or stand, the Guidance and Statistical Processing Method according to the present disclosure calculates acceleration/deceleration and maximum speed within a selected window or range to either trip in or out of the well without incurring corresponding surge or swab effects or damaging shock and vibration effects. The acceleration/deceleration and maximum speed may be presented to the drilling crew as an idealized target speed profile over time for tripping a particular stand. Such idealized speed profile may then be compared to an actual speed profile obtained by the drilling crew operating the drilling unit, both while and after tripping the particular stand, so that the drilling crew can observe how well their performance matches the idealized speed profile in order to make adjustments so that they improve or maintain performance within a so-called “fast and safe” operating range. Fast and safe in the present context may be used to mean the highest acceleration/speed that may be attained without risk of swab or surge, within a preselected error of uncertainty range. While tripping, the system may display indicators as to when to speed up or slow down movement of the drill string to meet the idealized speed profile. Additionally, the system may generate an alert (visual, audible or otherwise) when predetermined swab or surge conditions or excessive shock and vibration conditions have been met and may provide indication how to mitigate the foregoing alerted conditions. Performance measures of the actual pipe movement may be calculated with respect to the idealized speed profile and occurrence of actual swab and surge and excessive shock and vibration events. Connection time (amount of time used to assemble or disassemble one joint or stand of pipe from the drill string) performance may also be measured and presented along with an expected connection time profile.
For an entire trip, the Guidance and Statistical Processing Method according to the present disclosure may calculate a target average speed profile to be attained at each point in the wellbore (according to drill bit depth). The target average speed profile may represent an ideal speed profile so as to trip the pipe as fast as possible without incurring dangerous (e.g., swab or surge) conditions and may also account for target connection time, acceleration/deceleration, and speed constraints that avoid swab and surge effects and shock and vibration effects. Performance measures may be calculated with respect to the idealized profile and actual swab and surge and shock and vibration events. Actual connection time performance may also be tracked and presented against a predetermined target connection time performance.
In another aspect, a schedule forecast may project delay/advance of other planned drilling activities based on current well state and forecast completion time for the current activity based on current performance calculated as described above. For example, tripping completion may be forecast based on current progress and projections of the current tripping performance to the end of the trip. Additionally, drilling completion may be forecast based on current drilling progress and projections of the current drilling performance to the end of the current wellbore section. These projections may be adjusted by forecast limits or changing conditions.
2. Description of an Example Implementation
a) Length, size, unit weight of drill pipe
b) Length, size, unit weight of the drill collars
c) Wellbore diameter (drill bit size)
d) Drilling Fluid viscosity and gel strength;
e) Drilling Fluid density
Any value changes in Drilling Fluid parameters (e.g., viscosity, gel strength, density) may require recalculation of surge and swab acceleration and speed ranges. The other values may be expected not to change during any single trip in or out of the wellbore.
Additional, optional inputs, also shown at 10, to the swab and surge calculations may enable more accurate acceleration and speed range calculations. Examples of such additional inputs may include, without limitation:
f) Inclination, azimuth, curvature of the wellbore
g) Heavy weight drill pipe included in the drill string
h) Bottom hole assembly (BHA) component sizes and weights, stabilizer locations, drill bit configuration
i) Drilling Fluid parameters at with respect to temperature
j) Wellbore temperature with respect to depth
k) Measured or offset Formation data
The swab and surge calculation may use the foregoing inputs to calculate a drill string speed and acceleration at each depth in the wellbore such that swab and surge and/or excessive shock and vibration events are likely to occur. Swab and surge calculation techniques using any or all of the forgoing inputs are known in the art. Shock and vibration calculation techniques using any or all of the foregoing inputs are also known in the art. The foregoing calculation results in a maximum safe pipe movement speed with respect to depth. The “Calculate Speed Profile” calculation, shown at 12, calculates the speed at each bit depth for the stand that would induce a swab or surge pressure, or induce excessive shock and vibration. The Ideal Speed Profile may be the lower of the swab/surge inducing speed and the excessive shock and vibration speed profile minus a safety factor that ensures that the maximum drill string speed is as fast as possible without incurring the stated adverse conditions. The safety factor may be determined in a number of different ways, the simplest way being user preference. The Ideal Speed profile may be displayed as a band or range of speeds from the maximum safe movement speed to the maximum safe movement speed less the safety margin.
As a stand is tripped, the measured pipe movement speed, from beginning of drill string movement to cessation thereof, may be compared to the ideal speed profile, as shown at 14. Drill string movement speed may be measured by suitable sensors that measure, e.g., height (i.e., vertical position) of a swivel or top drive above the drill floor, wherein such measurements of position made with respect to time may be converted to indication of speed. Such sensors are well known in the art. The depth of the drill string in the wellbore is generally calculated by the length of the assembled drill string components less the measured swivel or top drive height above the drill floor. Speed may be inferred, as explained above, by using the height measurement with respect to time, or may be measured directly by different types of sensors, for example, rotary encoders that measure rotational speed of a winch drum used to extend and retract a drill line used to raise and lower the swivel or top drive (which rotation speed will be related to vertical movement speed of the swivel or top drive). The foregoing information may be entered into a computer and display system which will be described in more detail with reference to
When the actual drill string speed with respect to the ideal speed is outside of a “Fast and Safe” operating envelope (i.e., the above described speed range), an indicator may be displayed to the user to speed up or slow down longitudinal movement of the drill string in order to adjust the speed to be within the “Fast and Safe” operating range.
The comparison (14 in
a) Fast and Safe
b) Too Fast (above the “Fast and Safe” operating envelope)
c) Too Slow (below the “fast and safe” operating envelope
d) Generate Swab/Surge conditions
e) Generate excessive Shock and Vibration conditions
Additionally, the calculated statistics may show the number and the percentage of stands or fractions thereof that have been moved:
a) fully “fast & safe”
b) too fast or too slow, in whole or in part
c) with swab or surge conditions
d) with shock and vibration conditions
e) fraction too fast which is calculated by comparing the total time to trip the stand to the ideal time if it were tripped in a “fast & safe” manner
f) fraction too slow which is calculated by comparing the total time to trip the stand to the ideal time if it were tripped in a “fast & safe” manner
g) number of times swab or surge conditions were incurred
h) number of times shock and vibration conditions were incurred
i) relative overall speed from stand to stand
An example of such statistical displays is shown in
a) user input
b) average from offset wells
c) average top quartile performance from offset wells
d) best performance so far on current well
e) average performance so far on current well
An aggregation process at 20 accepts as input the ideal connection time and the ideal speed for each (joint or) stand) as calculated at 12 in
An “Ideal Averaged Speed Profile for Trip” may be calculated, at 22, from the “Ideal Detailed Speed profile for Trip” at 20. The actual averaging algorithm may be selected from among a number of different algorithms and is not intended to limit the scope of the present disclosure. One example is a moving average with a window large enough to encompass exactly one connection. The purpose for calculating an average is to allocate the connection time across the entire trip time so that the individual connection events need not be accounted for as discrete events in the trip speed profile but are in fact accounted for in the trip speed profile.
The “Actual Averaged Speed Profile for Trip” may be calculated using the same averaging algorithm for actual measured connection times.
The Compare process element at 24 compares the ideal averaged trip speed profile to the actual trip speed profile to provide substantially instantaneous feedback to the drilling crew while tripping and to calculate statistics. Alerts may be provided to the drilling crew with respect to values outside the ideal speed profile range similar to those provided as explained with reference to
a) Speed is slower than the “fast and safe” zone, please speed up.
b) Speed is faster than the “fast and safe” zone, slow down now.
c) Surge or Swab conditions have been met, slow down immediately.
d) Excessive shock and vibration conditions have been met, slow down immediately.
The statistics may be calculated at 26 in
a) within the “fast and safe” zone
b) too fast
c) too slow
The statistics calculation 26 may also include calculating and communicating the number and magnitude of any swab and surge events. One example embodiment of displaying the calculations above is shown in
Referring to
Referring to
Each activity 32, 34, 36 will have a forecasting procedure applied to it that takes into account the original drilling plan data and the current progress of each activity with respect to the original drilling plan. Each activity may optionally have a target speed profile for that particular activity. The forecasting procedure may use the current progress and current speed of each activity to estimate when the particular activity is likely to be complete. The overall drilling plan, i.e., the forecast start and stop times, may be adjusted (either delayed or advanced) based on the completion time estimates for each activity. Forecast start and stop times may be based on a number of criteria, for example:
a) equal the plan when activity has not yet begun or is proceeding according to plan
b) be calculated from offset well data based on the activity speed on similar wells
c) be recalculated from the original plan by using the current performance to predict when the activity will complete if the current performance is maintained
d) be calculated by using planned performance from this point to predict when the activity will complete.
The schedule forecasting activity may be updated continuously or on demand before or after drilling in order to have a better understanding of when activities are likely to begin and end so that logistics may be planned. The process may be applied to the original drilling plan or any revised drilling plans.
A processor can include a microprocessor, microcontroller, processor module or subsystem, programmable integrated circuit, programmable gate array, or another control or computing device.
The storage media 106 may be implemented as one or more computer-readable or machine-readable storage media. Note that while in the example embodiment of
It should be appreciated that computing system 100 is only one example of a computing system, and that computing system 100 may have more or fewer components than shown, may combine additional components not depicted in the example embodiment of
Further, the elements in the processing methods described above may be implemented by running one or more functional modules in information processing apparatus such as general purpose processors or application specific chips, such as ASICs, FPGAs, PLDs, or other appropriate devices. These modules, combinations of these modules, and/or their combination with general hardware are all included within the scope of the present disclosure.
While the invention has been described with respect to a limited number of embodiments, those skilled in the art, having benefit of this disclosure, will appreciate that other embodiments can be devised which do not depart from the scope of the invention as disclosed herein. Accordingly, the scope of the invention should be limited only by the attached claims.
This application is a continuation of a co-pending U.S. patent application having Ser. No. 16/371,732, filed 1 Apr. 2019, which is a continuation of Ser. No. 14/535,200, filed 6 Nov. 2014 (issued as U.S. Pat. No. 10,248,920 on 2 Apr. 2019), which is incorporated by reference herein, which claims priority to and the benefit of a U.S. Provisional Application having Ser. No. 61/903,418, filed 13 Nov. 2013 (expired), which is incorporated by reference herein.
Number | Date | Country | |
---|---|---|---|
61903418 | Nov 2013 | US |
Number | Date | Country | |
---|---|---|---|
Parent | 16371732 | Apr 2019 | US |
Child | 17654718 | US | |
Parent | 14535200 | Nov 2014 | US |
Child | 16371732 | US |