Abstract
An oil drilling barge stabilization system and method provide that an array of substantially vertically-oriented piles is formed in the sea bed to a depth beneath the sea bed that finds solid support. A barge is towed into position over the array of piles, and the barge is partially flooded with ballast to lower it in the water so that a set of cylindrical tubes is positioned to surround top ends of at least some of the piles. Air is then forced into the tubes to force the water out the bottom of the tubes, to create a dry environment for workers. Workers weld the tubes to the piles. The air pressure is removed from the interior of the tubes so that water may again flood the bottom of the tubes. The joints between the tubes and piles secure the barge to the array of piles, even in the face of varying tides, currents, and ice flow conditions. The barge may be used to support oil rigs and a variety of other support facilities. When work at a given site is complete, air is forced into the tubes again to force the water out so that welders can disconnect the joints between the tubes and the piles. Disconnecting the joints allows the barge to rise in the water, permitting the barge to be towed to a different location.
Description




BACKGROUND OF THE INVENTION




1. Field of the Invention




The present invention relates to systems and methods for stabilizing barges used for drilling for undersea oil. More specifically, the invention is directed to stabilizing such barges despite a variety of harsh environmental conditions.




2. Related Art




In the field of continental shelf oil drilling, various techniques have been employed to attempt to stabilize oil drilling platforms. However, conventional stabilization systems have not efficiently dealt with extreme conditions, such as soft sea bottoms, earthquake survivability, high winds, ice flows, and substantial differences between high tide and low tide. The damage to or loss of a drilling platform is extremely costly in both monetary and human terms. With the ongoing depletion of fossil fuel reserves in readily-accessible and friendlier environments, there is a growing need to provide systems and methods for stabilizing and protecting oil drilling platforms, despite extreme environmental conditions.




The invention described hereinafter fulfills this need. Conventional arrangements are not believed to disclose the combination of features, or provide the advantages, that are provided by the invention. U.S. Pat. No. 3,859,806 and Re. 30,823 (Guy et al.) disclose pumping water out of tubes so that workers can weld parts of a leg together (see FIG. 13 and bottom half of column 6 of the text). FIGS. 100-102 and the text bridging columns 33 and 34 of U.S. Pat. No. 3,874,180 (Sumner) disclose how water is forced out of a chamber using forced air, to allow a worker to apply sealant between a piling 185 and a lower guide member 186. More generally, U.S. Pat. No. 4,257,720 (Ostgaard) and Ostgaard shows the general concept of welding sections of legs together. U.S. Pat. No. 4,575,282 (Pardue, Sr. et aL) discloses a system of driving a pile that involves forcing compressed air into a hollow pile that has already penetrated the marine floor, and then venting the air to allow resulting hydrostatic pressure to further drive the pile.




Despite these disparate teachings, no conventional arrangement is believed to provide a practical, comprehensive system and method of stabilizing an oil drilling platform in a variety of hostile environmental conditions.




SUMMARY OF THE INVENTION




The inventive oil drilling barge stabilization system and method provide that an array of piles is formed in the sea bed to a depth beneath the sea bed that finds solid support. A barge is towed into position over the array of piles, and the barge is partially flooded with ballast to lower it in the water so that a set of cylindrical tubes is positioned to surround top ends of at least some of the piles. Air is then forced into the tubes to force the water out the bottom of the tubes, to create a dry environment for workers. Workers weld the tubes to the piles. The air pressure is removed from the interior of the tubes so that water may again flood the bottom of the tubes.




The joints between the tubes and piles secure the barge to the array of piles, even in the face of varying tides, currents, and ice flow conditions. The barge may be used to support oil rigs and a variety of other support facilities.




When work at a given site is complete, air may be forced into the tubes again to force the water out so that welders can disconnect the joints between the tubes and the piles. Disconnecting the joints allows the barge to rise in the water, permitting the barge to be towed to a different location.




Other objects, features and advantages of the present invention will be apparent to those skilled in the art upon a reading of this specification including the accompanying drawings.











BRIEF DESCRIPTION OF THE DRAWINGS




The invention is better understood by reading the following Detailed Description of the Preferred Embodiments with reference to the accompanying drawing figures, in which like reference numerals refer to like elements throughout, and in which:





FIG. 1

is a plan view of an oil drilling site at which the present invention may be used.





FIG. 2

is a side view, taken along section


2





2


in

FIG. 1

, showing features of a breakwater.





FIG. 3A

is a side view of a lower barge that may be used in conjunction with the present invention.

FIG. 3B

is a side view of the lower barge, supporting an oil rig and various support facilities.





FIG. 4A

illustrates an example of an array of piles formed in a sea bed to anchor barges according to the present invention, and

FIG. 4B

shows a cross-sectional view of one such exemplary pile.





FIG. 5

is a side view showing a pile with guide plates, that may be used to attach to the barge when a tube is not used to extend downward from the barge.





FIG. 6

shows a tube attached to a pile by attachment plates in accordance with the present invention.











DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS




In describing preferred embodiments of the present invention illustrated in the drawings, specific terminology is employed for the sake of clarity. However, the invention is not intended to be limited to the specific terminology so selected, and it is to be understood that each specific element includes all technical equivalents that operate in a similar manner to accomplish a similar purpose.





FIG. 1

is a plan view of an oil drilling site at which the present invention may be used. A generally U-shaped breakwater


110


that substantially surrounds a protected area


112


from current and ice flows moving in the direction of arrow


113


. The breakwater may carry a heliport


114


and an abandonment platform


116


, as well as a bridge network


118


leading to various structures in the protected area


112


.




A drilling and production unit vessel


120


, which will be the focus of the present invention, is illustrated at the end of one branch of the bridge network. In addition to a drilling and production unit, the drilling and production unit vessel


120


may contain a heliport, crew quarters, as well as production and power facilities that are illustrated in the side view of FIG.


3


B. Two work boats


122


A,


122


B are illustrated alongside vessel


120


. At another end of the bridge network are two crude oil transportation barges


124


A,


124


B.





FIG. 2

illustrates is a side view, taken along section


2





2


in

FIG. 1

, showing features of the

FIG. 1

breakwater


110


. The breakwater is generally inverse-V in cross section, with a first surface


210


having a 1/3 rise-to-run ratio, a second surface


212


having a 1/4 rise-to-run ratio, a flat top surface


214


on which the heliport and abandonment platform are situated, and a fourth surface


216


having a 1/3 rise-to-run ratio. The breakwater is preferably made of boulders or the like, arranged in a U-shaped configuration that serves to break up and deflect sheets of ice that would otherwise endanger the structures in protected area


112


(FIG.


1


).




Dimensions of the embodiment illustrated in

FIGS. 1 and 2

are provided for the sake of illustration and not to limit the invention:




A: 514 feet




B: 563 feet




C: 63 feet




D: 53 feet




E: 20 feet




F: 500 feet




G: 250 feet




H: 60 feet




I: 49 feet




J: 136 feet




K: 21 feet




L: 20 feet





FIG. 3A

is a side view of a lower barge that may be used in conjunction with the present invention.

FIG. 3B

is a side view of the lower barge, supporting an oil rig and various support facilities. The lower barge


310


is preferably a double-skin vessel capable of carrying a large capacity (for example, 72,800 barrels) of oil. The lower barge


310


has a network of pillars


312


(typical diameter: 42 inches) that form an air gap


320


and support an upper platform


330


. The air gap


320


allows surface waves and ice flows to pass through the vessel rather than impacting it.




Atop the upper platform


330


may be a variety of units, such as the following non-limiting examples: a quarters package


340


with a topside heliport, a production/power package


350


(including waste heat recovery and fuel handling, electric generators, storage, supplies, metering, separator and heat treater, water treatment and chemical injection, separators), a self-contained drilling rig


360


, and a substructure


370


.




Dimensions of the embodiment illustrated in

FIG. 3A

are provided for the sake of illustration and not to limit the invention:




M: 396 feet




N: 22 feet




O: 23 feet





FIG. 4A

illustrates an example of an array of piles formed in a sea bed to anchor barges according to the present invention, and

FIG. 4B

shows a cross-sectional view of one such exemplary pile.




As shown in

FIG. 4A

, the piles may be arranged in a five-row by sixteen-column array of eighty piles. In the illustrated example to which the invention should not be limited, the center-to-center distances between rows are 17.5 feet, 22.5 feet, 22.5 feet, and 17.5 feet. Within the rows, the center-to-center distances are (from left to right in the

FIG. 4A

example) 17.5 feet, 17.5 feet, 35 feet, 35 feet, 35 feet, 35 feet, 35 feet, 21 feet, 21 feet, 21 feet, 14 feet, 18.92 feet, and 16.08 feet.





FIG. 4B

shows a pile


400


to have a circular cross-section fifty-four inches in diameter. A one-inch thick steel circular cylinder


410


contains concrete


420


in its interior. Preferably, longitudinally-extending steel reinforcement bars (rebars)


430


are embedded at regular circumferential angles in the concrete. In the illustrated example, eight rebars are situated at 45° intervals around the pile, about four-fifths of the distance from the axis of the pile to the pile's outer periphery. Of course, the dimensions and constitution of the pile may be varied while still remaining within the scope of the invention.




A set of tubes slightly larger in diameter than the piles is provided in the bottom portion of the lower barge. In a preferred embodiment, not all eighty piles are matched to tubes, but a suitable smaller number (for example, twenty) of the eighty piles are matched with tubes for attachment as described below. The particular piles that are designated for attachment to the barge's tubes may be chosen to be evenly distributed throughout the array of piles so as to stabilize the barge on the piles.





FIG. 5

is a side view showing a pile


400


with guide plates, that may be used to attach a particular pile to the barge


310


when a tube is not used to extend downward from the barge. The pile


400


projects upward from the sea floor


500


through a fill layer


501


into water (or mud)


502


to contact a bottom plate


510


of the barge. The barge is provided with an interior sheet of angle framing material


520


that generally parallels the bottom plate


510


. Isolation material


530


extending around the top of the pile cushions the area of contact between the pile and the barge's bottom plate.




A gusset plate


540


, extending axially from the pile's interior, extends upwardly through the angle framing


520


. The gusset plate


540


is attached through a bulkhead


550


in the interior of the barge. An annular guiding and stabilization portion formed by a guide plate


560


and a stiffener


570


are provided around the circumference of the point at which the pile contacts the bottom plate


510


. When installed, collectively, the gusset plate


540


, the guide plate


560


, and the stiffener


570


stabilize the barge to the pile.




The arrangement shown in

FIG. 5

does not possess the advantages provided by an arrangement in which a tube extends downwardly from the barge to encompass and be attached to a pile.

FIG. 6

shows a tube attached to a pile by plates in accordance with the present invention.




The pile


400


, sea bed


500


, fill


501


, barge bottom plate


510


, barge angle framing


520


, guide plate


560


and stiffener


570


, illustrated in

FIG. 6

, are substantially the same as shown and described above with reference to FIG.


5


. However, the inventive embodiment of

FIG. 6

additionally provides a tube


600


that extends downwardly from the barge to surround the top of the pile. Although not specifically illustrated in

FIG. 6

, it is preferred that the tubes are part of, or are arranged directly below, pillars


312


(FIG.


3


A), so as to provide solid support for the structural units


340


,


350


,


360


,


370


that are situated atop upper platform


330


(FIG.


3


B). In a preferred embodiment, the diameter of the tube (example: sixty inches) is larger than the diameter of the pile (example: fifty-four inches).




Significantly, the inner surface of the tube is connected to the outer surface of the pile by a set of attachment plates


610


. The attachment plates


610


are preferably shaped as ⅝-inch-thick trapezoids, with the longer (sixty inches) parallel end being attached to the tube and the shorter parallel end being attached to the pile. The attachment plates are welded to the tube and pile, being arranged at regular circumferential intervals. In a particular embodiment, there are eight attachment plates arranged at regular 45° intervals.




When the barge is being loaded with ballast water during site set-up, the angle GG (example: 45°) of the guide plate


560


serves to guide the pile into position in the tube. The angled sides of the trapezoidal attachment plates


610


also serve to center the pile in the tube.




Dimensions of the illustrated embodiment of

FIGS. 5 and 6

are provided for the sake of illustration and not to limit the invention:



















AA:




130




feet (varies, based on subsurface conditions)






BB:




7.167




feet






CC:




5.5




feet






DD:




2.0




inches






EE:




5.0




inches






FF:




1.167




feet






GG:




45°






HH (

FIG. 6

only):




1.667




feet














The inventive structure of an embodiment of the barge stabilization system having been described above, an inventive method of stabilizing the barge is now described in greater detail.




The array of piles (for example, as shown in

FIG. 4A

) is formed in the sea bed to a depth beneath the sea bed that finds solid support. The barge is towed into position over the array of piles, and the barge is partially flooded with ballast water to lower the barge in the water so that a set of cylindrical tubes is positioned to surround top ends of at least some of the piles. The angled guide plates


560


and the angled (non-parallel) sides of the trapezoidal attachment plates


610


serve to guide and center the pile in the tube.




In a particular embodiment, the top of the pile is provided with a shock-absorbing material to avoid damage when it contacts the barge. The shock absorbing material may be similar to isolation material


530


(FIG.


5


).




Air is then forced into the tubes to force the water out the bottom of the tubes, to create a dry environment for workers. Workers enter the dry environment in the interior of the tubes, and weld the tubes to the piles by the attachment plates


610


. Afterwards, the air pressure is removed from the interior of the tubes so that water may again flood the bottom of the tubes. The ballast water in the partially-flooded barge is pumped out to make way for the crude oil that is pumped from beneath the sea bed.




The joints between the tubes and piles secure the barge to the array of piles, even in the face of varying tides, currents, and ice flow and earthquake conditions. The ballast water is no longer needed to maintain the barge's position. The barge may be used to support oil rigs and a variety of other support facilities, not merely those shown in FIG.


3


B.




When work at a given site is complete, air may be forced into the tubes again to force the water out so that welders can disconnect the attachment plates between the tubes and the piles. Disconnecting the attachment plates allows the barge to rise in the water, permitting the barge to be towed to a different location.




Modifications and variations of the above-described embodiments of the present invention are possible, as appreciated by those skilled in the art in light of the above teachings. For example, the configuration of the array of piles, the choice of which piles are matched with tubes for attachment, and the physical dimensions of the elements described above may be varied while not departing from the scope of the invention. It is therefore to be understood that, within the scope of the appended claims and their equivalents, the invention may be practiced otherwise than as specifically described.



Claims
  • 1. A method of stabilizing a barge above a sea bed, the barge having plural hollow tubes extending downwardly therefrom, the method comprising:placing an array of piles extending upward from the sea bed; moving the barge into position over the array of piles; at least partially flooding the barge to lower it in the water so that the tubes are positioned to surround top ends of respective piles; forcing air into the tubes to force water out the bottom of the tubes and create an air environment inside the tubes; attaching the tubes to the piles in the air environment; and removing forced air pressure from the interior of the tubes so that water may again flood the bottom of the tubes.
  • 2. The method of claim 1, further comprising:forcing air into the tubes to force the water out of the tubes; and disconnecting joints between the tubes and the piles to allow the barge to rise in the water, unconnected to the piles.
  • 3. The method of claim 1, further comprising:providing a generally U-shaped breakwater upstream from the barge to protect the barge from ice flows.
  • 4. The method of claim 1, wherein the placing of the array of piles includes:placing piles that include a steel tube having an interior containing steel reinforced concrete.
  • 5. The method of claim 1, wherein:less than all the piles are connected to tubes.
  • 6. The method of claim 1, wherein the attaching step includes:welding plural attachment plates to connect and extend radially between an outer surface of the pile and an inner surface of the tube.
  • 7. The method of claim 1, wherein the attaching includes:welding eight trapezoidal attachment plates to connect and extend radially between an outer surface of the pile and an inner surface of the tube, at regular circumferential intervals of about forty-five degrees.
  • 8. The method of claim 1, wherein:the tubes have diameters that are greater than diameters of respective piles.
Parent Case Info

This application claims benefit of Prov. No. 60/086,618 filed May 22, 1998.

US Referenced Citations (19)
Number Name Date Kind
RE. 30823 Guy et al. Dec 1981
3001370 Templeton Sep 1961
3593529 Smulders Jul 1971
3605669 Yu Sep 1971
3859806 Guy et al. Jan 1975
3872679 Fischer Mar 1975
3874180 Sumner Apr 1975
4069680 Erler Jan 1978
4257720 Ostgaard Mar 1981
4417664 Gordon Nov 1983
4456404 Evans Jun 1984
4575282 Pardue, Sr. et al. Mar 1986
4611953 Owens Sep 1986
4907912 Smith Mar 1990
4973200 Kaldenbach Nov 1990
5219451 Datta et al. Jun 1993
5241572 Matthews Aug 1993
5522680 Hoss et al. Jun 1996
5855455 Williford et al. Jan 1999
Provisional Applications (1)
Number Date Country
60/086618 May 1998 US