Not Applicable.
The present invention relates to a system for processing barges. The present invention has particular utility with respect to transporting and refurbishing unpowered river barges. As used herein, the term “river barge” means a barge adapted for use on an inland waterway, including an intracoastal waterway.
River barges are large, having a length of about 100-450 feet (about 30 to about 135 meters), a width of about 30-75 feet (about 9 to about 23 meters), and a depth of about 8-30 feet (about 2.5 to about 9 meters). Most river barges in the United States come in two sizes, standard or jumbo. A standard river barge has a hull which is 195 feet (59 meters) long, 35 feet (10.7 meters) wide, and 10-14 feet (3 to 4.3 meters) deep. The hull thickness for a standard barge is approximately ⅜ inch- 1/2 inch (about 0.95 to about 1.25 cm). A jumbo river barge typically has a hull 297 feet (90.5 meters) long, 54 feet (16.5 meters) wide, and 12 feet (3.7 meters) deep. The thickness of the sides and bottom varies according to construction specifications of a particular barge. Based on construction differences, all these sizes may vary by ±5%. The standard river barge has a typical unfilled weight of 300 U.S. tons (272,000 kg). The jumbo river barge has a typical unfilled weight of 1,000 U.S. tons (907,000 kg).
River barges are typically generally rectangular as viewed in plan, with a length greater than their width. Their hulls are generally flat-bottomed, and one or both ends may be square (box hull) or sloped (rake hull). They may have internal structures and superstructures adapted for carrying particular types of cargo, and may be classified, for example, as a hopper barge, a tank barge, or a deck barge. A hopper barge typically has a coaming of from eighteen inches to six feet in height. A cover, such as a fiberglass cover or steel cover may be provided to secure the cargo hopper from the elements, may be provided over the coaming.
The exterior surfaces of river barges are sometimes painted to protect them from corrosion. Over time, however, the exterior surface, and in particular the hull, of the barge begins to corrode because of contact with the water and the atmospheric environment. To refurbish these barges, a typical process comprises manual sand blasting and manual spray-painting the barge surfaces. The current methods for blasting and painting are either performed on a dry-dock or on marine ways. In a dry-dock, water is drained, the barge is manually blasted with abrasive, as much abrasive is cleaned up as can easily be accomplished, the barge is painted manually, the barge is floated over sufficiently that when water is again drained the spots where it was supported can be recoated.
In one marine ways process, the barge is partially pulled from an inland waterway and the surface is processed (sand blasted and painted) on the landside surface and on as much as the stern and bow of the barge as accessible. As such, this current process may still position part of the barge within the waterway. After the paint has dried, the barge is lowered back into the waterway and shifted around by a boat so that the other side can be exposed when pulled from the waterway. This manipulation of the barge on a flowing river or in a confined bay is extremely difficult and labor intensive. Once pulled from the waterway, this exposed side is blasted and painted to match the other processed side of the barge. Besides being inefficient with respect to processing only one side of the exterior surface of the barge at a time, these sandblasting and painting processes result in spent materials falling on the ground and being exposed to the waterway. An alternative marine ways process is to pull the barge up level, sufficiently far from the waterway to erect scaffolding, and the barge is processed from the embankment and from the scaffolding. Again, spent materials are largely exposed to the ground and to the waterway. The inefficiencies and hazardous environmental conditions produced by all these methods are further exacerbated by the size of the jumbo barges. The current methods are extremely expensive and very few environmental controls can be incorporated into the processes.
The present invention provides methods for refurbishing barges efficiently and, in accordance with certain preferred embodiments, with little environmental contamination, and systems for carrying out the methods. In view of the following invention, various novel features of the methods and systems will be apparent to those skilled in the art and are set out in the appended claims.
In the accompanying drawings which form part of the specification:
a is a side elevational view of a lift system supporting the barge in a raised position;
b is a side elevational view of a lift system contacting and raising the barge to provide clearance under the barge for contact with a third transport system;
a is an isometric view of a switch rail assembly;
b is an isometric view of the third transport system;
a is a schematic view of the barge positioned in a drying area of a housing containing the blast media discharge system and manual coating discharge system;
a is another schematic view of the coating discharge system of
a is a cross-sectional view of the third transport systems and supported barge positioned on transfer platforms; and
Corresponding reference characters indicate corresponding parts throughout the several views of the drawings.
The following detailed description illustrates the invention by way of example and not by way of limitation. The description clearly enables one skilled in the art to make and use the invention, and describes several embodiments, adaptations, variations, alternatives, and uses of the invention, including what is presently believed to be the best mode of carrying out the invention.
The first illustrative embodiment of the present invention transports barges completely out of a waterway and into a covered refurbishing system that is positioned on land. Within the covered refurbishing system, the hull of the barge is abrasively blasted and then coated. Once the barge has been refurbished, the system transports the barge back into the waterway. The system eliminates or greatly reduces contamination of the ground and/or of the waterway from discharged blast material and/or coating overspray since the refurbishing system collects the discharged blast material and/or coating overspray. The system further permits much faster refurbishment of barges by treating more than one exterior surface at a time. For illustrative purposes, the following description relates to an unpowered river barge.
Referring to the drawings, the processing system 5 (
Turning to
The refurbishing system 26 comprises a housing 44 having a first end 46 and a second end 48, a blast system 50, a transition system 52 and a coating system 54. The housing 44 may be in the form of a building. In this illustrative embodiment, the housing 44 has a length of 325 feet (99 meters). The housing 44 covers the blast system 50, the transition system 52 and the coating system 54 to substantially isolate these areas from the outdoor environment while the first end 46 allows access within the housing 44. The second end 48 is preferably closed but may be open to allow access within the housing 48. The refurbishing system 26 also comprises a control system 56, a reclamation system 58 and a filter system 60.
Turning to
Still referring to
As shown, for example, in
Turning to
The berth 78 has a height that is taller than any predicted flood level such as a one hundred year level. An embankment 80 (
Turning to
The lift system 38 of the transportation system 24 comprises jacks 82 or pylons that reciprocate between a retracted position 84 (
Returning to
Referring to
Turning to
The compressor system 98 transfers the abrasive media 96 from the blast storage tank 88 through the piping and out of the discharge nozzles 100. The discharge nozzles 100 propel the abrasive media 96 against both sides and the underside of the exterior surface 22 of the barge 10. The discharge nozzles 100 automatically reciprocate back and forth at 45° angles. The distribution pattern of the abrasive media 96 overlaps so as to spray the exterior surface 22 of the barge 10. The plurality of discharge nozzles 100 is configured to uniformly distribute the abrasive media 96 against the exterior surface 22 of the barge 10 as the barge is pulled through the blast system 50 at a rate of about 200 feet per hour as controlled by the control system 56. Accordingly, the control system 56 controls the rate of movement of the barge 10.
As shown, the blast media discharge system 90 simultaneously processes both sides of the barge 10 while processing the bottom 20. The bow 16 and the stern 18 are processed as the barge 10 enters and exits the blast system 50, respectively. The blast media discharge system 90 may supply 6,000 cfm (170 cubic meters per minute), via air compressors, during the blasting process. The components of the blast media discharge system 90 such as the piping, fittings, valves and discharge nozzles 100 are all designed to withstand the flow rate of the abrasive media 96.
The reclamation system 58 is positioned underneath the portion of the rails 72b positioned within the covered blast system 50. The reclamation system 58 collects the applied abrasive media 96 and any blasted portions of the exterior surface 22 of the barge 10. Accordingly, a grated floor covers the reclamation system 58 such that the grated floor allows the discharged abrasive media 96 and blasted surface components 104 of the barge 10 to pass through and into the reclamation system 58. The grated floor allows personnel access to walk over pit 106. The blasted surface components 104 comprise debris, rust, corrosion, etc., removed from the exterior surface 22 by the discharged abrasive media 96. The reclamation system 58 comprises a means to collect the discharged abrasive media 96 and blasted surface components 104 of the exterior surface 22 of the barge 10. In one embodiment, the reclamation system 58 includes the pit 106, which channels the discharged abrasive media 96 and blasted surface components 104 to augers 108. The augers 108 of the reclamation system 58 move the discharged abrasive media 96 to a cross augur 109 that in turn moves the discharged abrasive media 96 to an elevator 110. The elevator 110, in turn, lifts the discharged abrasive media 96 and blasted surface components 104 for recycling.
The reclamation system 58 also includes a separator 112 that reclaims re-useable abrasive media 96 while discarding unusable abrasive media 96 from the transported media from the elevator 110. The separator 112 also discards blasted surface components 104. The separator 112 discards the waste abrasive media 96 and blasted surface components 104 to the media disposal means 114 such as a waste drum. The separator 112 then moves the reusable abrasive media 96 into a hopper 116 that feeds the blast discharge system 90 to repeat the blasting process. As shown, the control system 56 operatively controls at least the blast storage tank 88, the blast media discharge system 90, the discharge nozzles 100, and the transportation system 26.
The covered blast system 50 (
Turning to
The covered transition system 52 comprises the manual processing system that includes hand held discharge nozzles 100. These discharge nozzles 100 may be controlled and supplied by the blast media discharge system 90 of the covered blast system 50. Personnel handle these discharge nozzles 100 to abrasively blast the barge 10 in areas that the covered blast system 50 may have missed as the barge 10 continues moving through the covered transition system 52. The discharge nozzles 100 may be positioned on both sides of the rail system 34 and underneath the portion of the rails 72b that is positioned within the covered transition system 52. The manual transition system 52 includes augers 108 also in communication with the reclamation system 58 such that the reclamation system 58 can collect applied abrasive media 96 that has fallen through the grated floor of the manual transition system 52.
The covered transition system 52 also includes an air discharge system 118. The air discharge system 118 includes an air source, an air pump, nozzles and associated piping which connects the air source, the pump and the nozzles. The air discharge system 118 is configured to apply high pressure air to the prepared exterior surface 22 of the barge 10 in order to remove any abrasive media 96 adhered to the exterior surface 22 of the barge 10. In the covered transition system 52, workers further process the barge 10 as the barge 10 continuously moves through by spraying the exterior surface 22 with compressed air to remove abrasive media 96 adhered to the exterior surface 22 during the abrasive blasting of the exterior surface 22, and make whatever other repairs and preparation may be required.
After air blowing the barge 10, the third transport system 32 then moves the prepared portion of barge 10 through the covered coating system 54. The drive system 36 pulls the barge 10 completely through the blast system 50 and the transition system 52. The drive system 36 then continues to pull the barge 10 past the unactivated coating system 54. The drive system 36 pulls the blasted barge 10 into the drying area of the housing 44 (
The coating storage tank 120 holds an amount of the coating 128. In one embodiment, the coating 128 comprises a solvent-based paint or a two-component epoxy coating. The coating discharge system 122 communicates with the coating storage tank 120 via piping. The coating discharge system 122 comprises a compressor 130 and a plurality of coating nozzles 132 positioned on both sides of the rails 72b and underneath the portion of the rails 72b that is positioned within the covered coating system 54. The rails 72b suspend over pit 106 by I-beam support. The coating nozzles 132 are standard, manually operated airless paint guns that are connected by appropriate hoses to the coating discharge system 122 for use by painters. The compressor 130 transfers the coating 128 from the coating storage tank 120 through the piping and out of the coating nozzles 132. The painters spray the coating 128 against both sides of the exterior surface 22 of the barge 10 and the underside of the exterior surface 22 of the barge 10 as the barge 10 rolls through the coating system 54 at a speed of approximately 200 feet per hour (60 meters per hour). Accordingly, the control system 56 controls the speed of the barge 10 through the coating system 54. Additionally, the ventilation system 126 and filter system 60 properly handles any fumes created by the coating discharge system 122.
The coating system 54 is also covered to prohibit rain/snow/moisture from contacting the now coated exterior surface 22 of the barge 10. As such, the coated barge 10 is not exposed to the outside environment that may interfere with the drying or curing of the coating 128.
Referring still to
The transportation system 24 then moves the barge 10 into the refurbishing system 26 for processing. The blast system 50, transition system 52 and coating system 54 are in communication with each other to allow the transportation system 24 to move the barge 10 within the refurbishing system 26 under control of the control system 56. In this illustrative embodiment, a curtain C is provided at the front end 46 of the housing 44 (
In particular, the transportation system 24 moves the barge 10 out of and away from the waterway 12 (
As shown in
After the refurbishing system 26 processes the barge 10, the transportation system 24 moves the barge 10 away from the refurbishing system 26. As shown in
Since the embankment 80 positions the refurbishing system 26 inland from the waterway 12, moving the barge 10 out of and away from the waterway 12 system comprises moving the barge 10 up the embankment 80 (
The following description will describe in detail the transporting by the first transport system 28, the second transport system 30 and the third transport system 32. The method comprises connecting the first transport system 28 to the top of the second transport system 30 (
The drive system 36 moves the second transport system 30, the connected first transport system 28 and river barge 10, in a transverse or lateral direction out of the waterway 12 along rails 72 up the embankment 80. (
Near the intersections of rails 72a and rails 72b, the lift system 38, via the jacks 82, lifts the river barge 10 off of the first transport system 28 to allow the third transport system 32 to travel underneath the raised barge 10 (
The third transport system 32 continues to move the river barge 10, in the level orientation, within the refurbishing system 26 (
The post processing area 138 may be optionally covered. The post processing area 138 includes a work area (not shown) such as elevated decks to allow workers to further refurbish and coat surfaces of the river barge 10 such as the superstructure or coaming. For example, the workers may coat the coaming or may weld the exterior surface 22 while the workers are positioned in the work areas. If so desired, the rail system 34 connects with multiple post processing areas 138 to allow multiple river barges 10 to dry and to allow workers to post process the multiple river barges 10.
In this embodiment, the rail system 34 is configured to move the river barges 10 without having to rotate the barges 10. Additionally, the rail system 34 may include switch tracks (not shown) to allow interchangeability of unprocessed barges 10 and processed barges 10 to move along the rail system 34. The transportation system 24 handles multiple barges 10 to allow simultaneous refurbishing of one barge 10 and post processing of other barges 10. The transportation system 24 handles barges 10 to allow other barges 10 to move to respective locations within the transportation system 24. For example, one refurbished barge 10 is moved to the post processing area 138 to allow an un-refurbished barge 10 access to the refurbishing system 26. As such, the processing areas 138 provide a matrix of spaces to move multiple barges 10 on the transportation system 24.
After drying and any post processing, the third transport system 32 moves the barge 10 back over the jacks 82 of the lift system 38. The jacks 82 move from the retracted position 84 to the extended position 86. In the extended position 86, the jacks 82 lift the river barge 10 off the third transport system 32. The drive system 36 then moves the third transport system 32 away from the suspended river barge 10 and moves the first transport system 28 underneath the suspended river barge 10 via the switch track assembly (
As shown in
Referring to
In this embodiment, the barge 10 is moved in a first direction out of the waterway 12 by a first transport system 158 and a second transport system 160 toward an inland position as previously described. The barge 10 is then moved by the first transport system 158 to lift system 162. The lift system 162 raises the barge 10 to allow third transport system 164 to move under the suspended barge 10. The third transport system 164 moves along rails 166 as shown. The third transport system 164 moves the supported barge 10 in a second direction into the refurbishing system 142. The second direction is perpendicular to the first direction. As shown, the third transport system 164 longitudinally moves the barge 10 within the covered blast system 146. The covered blast system 146 abrasively processes the barge 10 as previously discussed. Subsequent to abrasive blasting, the third transport system 164 moves the barge 10 through the transition system 148 wherein workers can process the barge 10 as previously described.
The third transport system 164 then moves the barge 10 into the transfer system 150. As shown in
The platforms 168 move the third transport system 164 in alignment with the rails 167. The drive system then drives the third transport system 164 in the direction opposite of the second direction. The third transport system 164 longitudinally moves the barge through the covered coating system 152. The covered coating system 152 processes the barge 10 as previously discussed. After the coating process, the third transport system 168 moves the barge 10 into the drying area 172.
After drying, the third transport system 164 moves the barge 10 to another lift system 174 that is positioned beyond the drying area 172 along rails 176. The other lift system 174 unloads the barge off the third transport system 164 and loads the barge 10 on the first transport system 158 positioned on rails 176. The first transport system 158 then reconnects with the second transport system 160 to lower the barge back into the waterway 12 previously described.
Referring to
Upon exiting the second end 48, other jacks 82 (
When the drive system 36 properly positions the fourth transport system 178 underneath the barge 10, the lift system 38 lowers the jacks 82 to the retracted position 84. In the retracted position 84, the jacks 82 lower the barge 10 onto the transport system 178 so that the transport system 178 supports the barge 10.
The drive system 36 then moves the transport system 178 and the supported barge 10 toward the fifth transport system 180. The transport system 178 connects with the fifth transport system 180. The drive system 36 then lowers the fifth transport system 180, the connected transport system 178 and supported barge 10 down the embankment 80 and back into the waterway 12 as previously discussed. At the waterway 12, the barge 10 releases from the transport system 178 and floats free within the inland waterway 12.
In the embodiments of
Numerous other variations in the present invention, within the scope of the appended claims, will occur to those skilled in the art in light of the foregoing invention. Merely by way of example, the transportation system may be utilized in other ways, for example with other types of refurbishment systems, including different surface preparation systems and different coating systems, and further including refurbishment systems for the interior of the hull of the barge, refurbishment systems for the superstructure, and systems for more major refurbishment, such as replating some or all of the barge hull to repair more major damage or to re-outfit the hull for different uses. Likewise, the abrasive blasting process or the coating process of the invention may be carried out individually without the other process. Either or both of the processes may be carried out in a suitable enclosure using different types of transport systems. Some aspects of the invention may be carried out with a modified dry-dock system, and some may be carried out with a movable abrasive system or a movable coating system for blasting or coating a stationary barge. Furthermore, the control system is configured to time the movement of any particular barge and time the activation of the blast system, the transition system and the coating system, including automated coating systems. Some of the advantages of the present invention may be obtained without the use of an enclosure for the surface preparation and/or the coating processes. These variations are merely illustrative.
In view of the above, it will be seen that the several objects of the invention are achieved and other advantageous results are obtained. As various changes could be made in the above constructions without departing from the scope of the invention, it is intended that all matter contained in the above description or shown in the accompanying drawings shall be interpreted as illustrative and not in a limiting sense.
This application claims priority under 35 U.S.C. §119(e) of U.S. Provisional Patent Application No. 60/730,788 filed Oct. 27, 2005, in the name of the present inventors and entitled “River Barge Refurbishment System And Method Of Refurbishing River Barges”, this provisional application being incorporated herein by reference.
Number | Name | Date | Kind |
---|---|---|---|
2543348 | Briese | Feb 1951 | A |
3390657 | Schneider | Jul 1968 | A |
3548541 | Miller | Dec 1970 | A |
3681926 | Thatcher et al. | Aug 1972 | A |
3752109 | Seiple | Aug 1973 | A |
3817041 | Pownall | Jun 1974 | A |
4003329 | Robinson | Jan 1977 | A |
4027433 | Hockett | Jun 1977 | A |
4048956 | Estebanez et al. | Sep 1977 | A |
4615641 | Novay | Oct 1986 | A |
4641996 | Seal | Feb 1987 | A |
4714375 | Stevenson et al. | Dec 1987 | A |
4808931 | Ling | Feb 1989 | A |
5185183 | Gonda et al. | Feb 1993 | A |
5199228 | Beausoleil | Apr 1993 | A |
5353729 | Goldbach et al. | Oct 1994 | A |
5355823 | Goldbach et al. | Oct 1994 | A |
5398632 | Goldbach et al. | Mar 1995 | A |
5445101 | Koch | Aug 1995 | A |
5695388 | Lyras | Dec 1997 | A |
5716261 | Watkin | Feb 1998 | A |
5807168 | Goldbach | Sep 1998 | A |
5823291 | Goldbach | Oct 1998 | A |
5988093 | Ni | Nov 1999 | A |
6102157 | Goldbach et al. | Aug 2000 | A |
6173669 | Staerzl | Jan 2001 | B1 |
6186273 | Goldbach et al. | Feb 2001 | B1 |
6260499 | Steel et al. | Jul 2001 | B1 |
6276292 | Soulek | Aug 2001 | B1 |
6327991 | Eichert | Dec 2001 | B1 |
6571635 | Baltzersen et al. | Jun 2003 | B1 |
6877452 | Hudd | Apr 2005 | B1 |
7013821 | Sakurai | Mar 2006 | B2 |
H002159 | McGoldrick | Jul 2006 | H |
7444952 | McGann | Nov 2008 | B1 |
20040121181 | Call | Jun 2004 | A1 |
Number | Date | Country | |
---|---|---|---|
20070098499 A1 | May 2007 | US |
Number | Date | Country | |
---|---|---|---|
60730788 | Oct 2005 | US |