BATTERY CHARGER

Information

  • Patent Application
  • 20140253039
  • Publication Number
    20140253039
  • Date Filed
    March 08, 2013
    11 years ago
  • Date Published
    September 11, 2014
    10 years ago
Abstract
A battery charger can include a charger controller configured to determine a total charge time that characterizes a time needed to charge a battery, the total charge time being based on a received state of charge (SOC) of the battery that characterizes a present SOC of the battery. The charger controller can also be configured to determine a charging start time for the battery based on a predetermined full charge time and the total charge time.
Description
TECHNICAL FIELD

This disclosure relates to a battery charger. More particularly, this disclosure relates to a battery charger that includes a charger controller.


BACKGROUND

Portable electronic devices are powered by batteries that generate a voltage based on chemical reactions. As a battery provides power to the portable electronic device, the ability of the battery to provide the power becomes diminished. Many batteries that power portable electronic devices are rechargeable. However, charging such batteries can form deposits inside an electrolyte of the battery that can inhibit ion transport thereby increasing the battery's internal resistance. The increase in internal resistance reduces the cell's ability to deliver current. Thus, recharging the battery can diminish the battery's total capacity.


SUMMARY

One example relates to battery charger that includes a charger controller configured to determine a total charge time that characterizes a time needed to charge a battery. The total charge time can be based on a received state of charge (SOC) of the battery that characterizes a present SOC of the battery. The charger controller can also be configured to determine a charging start time for the battery based on a present time, a predetermined full charge time and the total charge time.


Another example relates to a non-transitory machine readable medium having instructions for performing a method. The method can include determining a total charge time of a battery based on a received SOC of the battery that characterizes a present SOC of the battery. The total charge time of the battery can also be based on a battery time constant of the battery that characterizes the product of a resistance and a capacitance of an equivalent circuit of the battery. The method can also include delaying a charging of the battery until a charging start time that is based on the total charge time and a predetermined full charge time.


Yet another example relates to a battery charging system that includes a battery pack that includes a battery. The battery charging system can also include a battery gauge configured to determine a present state of charge (SOC) of the battery. The battery charging system can further include a battery charger configured to provide a charging signal to the battery pack. The battery charger can include a charger controller configured to determine a constant current-constant voltage transition point for the battery based on a battery time constant and a full charge capacity of the battery. The battery time constant can characterize the product of a resistance and a capacitance of an equivalent circuit of the battery. The charger controller can also be configured to determine a total charge time for the battery based on the present SOC of the battery, the battery time constant and the full charge capacity of the battery. The charger controller can further be configured to determine a charging start time based on the total charge time and a predetermined full charge time. The charger controller can still further be configured to control the charging signal such that the present SOC of the battery prior to the charging start time is maintained and the present SOC of the battery is increased after the charging start time such that the present SOC of the battery is about 100% at the predetermined full charge time.





BRIEF DESCRIPTION OF THE DRAWINGS


FIG. 1 illustrates an example of a battery charging system.



FIG. 2 illustrates an example a graph that depicts a time to full charge of a battery plotted as a function of a state of charge of a battery.



FIG. 3 illustrates an example of a graph that depicts experimental results of a time to full charge plotted as a function of a state of charge of a battery.



FIG. 4 illustrates a graph that plots an error of the plots in FIG. 3 as a function of a state of charge of a battery.



FIG. 5 illustrates another example of a graph that depicts experimental results of a time to full charge plotted as a function of a state of charge of a battery.



FIG. 6 illustrates a graph that plots an error of the plots in FIG. 5 as a function of a state of charge of a battery



FIG. 7 illustrates yet another example of a graph that depicts experimental results of a time to full charge plotted as a function of a state of charge of a battery.



FIG. 8 illustrates a graph that plots an error of the plots in FIG. 7 as a function of a state of charge of a battery.



FIG. 9 illustrates a flowchart of an example method for charging a battery.



FIG. 10 illustrates an example of a battery charger.



FIG. 11 illustrates another example of a flowchart of an example method for charging a battery.





DETAILED DESCRIPTION

A battery charger can include a charger controller that can control how and when a battery is charged. In particular, upon connecting the battery charger to an external power source (e.g., a power outlet), the charger controller can delay a charging of the battery until after a charging start time is reached. The charging start time can be determined from a predetermined full charge time and a total charge time for the battery. In this manner, the time the battery is at or near a full charge state can be reduced, which can extend a life of the battery.



FIG. 1 illustrates an example of a battery charging system 2. The battery charging system 2 can include a battery gauge 4 that can determine a state of charge (SOC) of a rechargeable battery, which can be simply referred to as a battery 6. The battery charging system 2 could be employed for example, in a wireless phone, a smartphone, a laptop computer, a tablet computer, an automobile (e.g., an electric automobile) or nearly any portable device that needs electrical power to operate.


In some examples, the battery gauge 4 can be integrated with a battery pack 8 that stores the battery. In other examples, the battery gauge 4 can be separate from the battery pack 8. The SOC of the battery 6 can change in real time (or near real-time). To determine the SOC of the battery 6, the battery gauge 4 can be configured to continuously sample a voltage VBAT of the battery 6 at each of a plurality of sampling periods to provide the SOC of the battery 6 at each of the sampling periods based on the voltage VBAT, a temperature of the battery 6, predetermined data associated with steady-state and transient behaviors of the battery 6 relative to a depth of discharge (DOD) of the battery 6. In the example of FIG. 1, the battery 6 is demonstrated as a single battery. However, it is to be understood that the battery 6 can represent a plurality of batteries (or battery cells) electrically connected in series, such that the voltage VBAT could represent an aggregate voltage of all of the batteries. Therefore, the SOC calculated by the battery gauge 4 can be an average SOC of the plurality of batteries.


The SOC of the battery 6 can be provided to a battery charger 10. In some examples, the battery charger 10 can be implemented, for example, as hardware (e.g., an integrated circuit (IC) chip) coupled to discrete circuit components. In some examples, the battery charger 10 (or some components thereof) can be implemented as machine readable instructions stored in a non-transitory computer readable medium, such as a memory 12 wherein a processing unit (e.g., a processor core) can access the memory 12 and execute the machine readable instructions. In still other examples, the battery charger 10 can be implemented as a combination of hardware and software, such as firmware.


Upon connecting (e.g., “plugging in”) the battery charging system 2 to a power source (e.g., an external power source), the battery charger 10 can receive a power signal (labeled in FIG. 1 as “POWER SIGNAL”). As one example, the power source could be a 110 Volt (V) power source or a 220 V power source (e.g., an electrical outlet). In another example, the power source could be a 5 V direct current (DC) power source (e.g., a universal serial bus (USB) connection). The power signal can be a signal that corresponds to a signal provided at the power source. For instance, in some examples, the power signal can be a stepped down and rectified version of the signal provided by the power source (e.g., a 12 V DC signal). In other examples, the power signal could be a pass through of the signal at the power source (e.g., a 5 V DC signal). At or near time a of connecting the battery charger 10 to the external power source, an initial SOC of the battery 6 can be received (labeled in FIG. 1 as “SOC”). Such an initial SOC can represent a present SOC of the battery (SOCp) at the time of the connection.


The battery charger 10 can provide and control a charge signal (labeled in FIG. 1 as “CHARGE SIGNAL”) to the battery 6 via the battery pack 8. In response to the charge signal, the battery 6 can be charged at a predetermined rate. Moreover, the battery gauge 4 can provide the SOC of the battery 6 as feedback for the charge signal. As explained herein, by controlling the charge signal, the SOC of the battery 6 can be increased up to about 100%. At an SOC of about 100%, the battery 6 can be considered to be in a fully charged state. Moreover, the battery 6 can have a full charge capacity (FCC) of the battery 6 that can initially be approximately equal to an SOC of about 100% for the battery 6. However, as the capacity of the battery 6 degrades over time (due to repeated charging), the difference between an SOC of about 100% for the battery 6 and the FCC of the battery 6 can increase. The FCC of the battery 6 can be a predetermined, measured value in milliamps per hour (mA/h).


The battery 6 charge signal can be controlled by a charger controller 14 of the battery charger 10. In some examples, the charger controller 14 can be implemented, for example, as an IC chip, such as an application specific integrated circuit (ASIC) chip. In other examples, the charger controller 14 could be implemented as a microcontroller with embedded instructions (e.g., firmware). In still other examples, the charger controller 14 can include a processing unit (e.g., a processor core) and a non-transitory machine readable medium such as the memory 12 that stores machine executable instructions. In such a situation, the memory 12 could be implemented as volatile memory (e.g., random access memory (RAM)), non-volatile memory (e.g., a solid state drive, flash memory, a hard disk drive, etc.) or a combination thereof. Moreover, in such an example, the processing unit can access the memory 12 and execute the machine readable instructions.


For many batteries, such as a lithium ion battery, the more time that the battery 6 is at an SOC of about 100% (e.g., at or near FCC of the battery 6), the total capacity of the battery 6 degrades. For instance, if the battery 6 is kept at or near an SOC of about 100%, the battery's 6 charging capacity will degrade faster than if the battery 6 is kept at an SOC of about 50%. Thus, the battery charger 10 can be configured to limit a percentage of time that the battery 6 is kept at or near an SOC of about 100%, thereby extending the life (e.g., reducing the degradation rate of the battery 6).


The battery charger 10 can include battery data 16 that can characterize information about the battery 6. The battery data 16 can be stored, for example, in the memory 12. The battery data 16 can include a full charge time 18 for the battery 6. The full charge time 18 can be a time of day that the battery 6 is to be at or near a SOC of about 100%. In some examples, the full charge time 18 can be set, for example, in response to user input (labeled in FIG. 1 as “USER INPUT”). For instance, in examples where the battery charger 10 is implemented on a smartphone, the user can set a full charge time 18 via a graphical user interface (GUI). In a given example, the full charge time 18 of the battery 6 can be set to 7:00 A.M. Moreover, in the given example, the full charge time 18 can be representative of a time in the morning that a portable electronic device (e.g., a wireless phone) would typically need to be at a fully charged state (e.g., the start of a work day). In some examples, the user input can set the full charge time 18 to a setting that indicates that the battery 6 is to be charged immediately.


The battery 6 can have an equivalent circuit that can be modeled as a resistor in series with a capacitor. The battery data 16 can also include a battery time constant (τ) 20 that can characterize the product of the resistance and the capacitance of the equivalent circuit (e.g., an RC time constant for the battery 6). In some examples, the battery time constant (τ) 20 can be derived from experimental data employed to generate the equivalent circuit of the battery 6. In some examples, the battery time constant (τ) 20 can be a fixed value that can be based on physical properties of the battery 6. In other examples, the battery time constant (τ) 20 can vary as a function of a temperature of the battery 6.


The charge signal provided to the battery charger 10 can have three different states. In a first state, the charge signal can maintain the SOC of the battery 6 at the present SOC (SOCp). Thus, in the first state, the charge signal is provided with a current that can maintain the SOC of the battery 6, but does not significantly increase the SOC of the battery 6. As an example, in the first state, the charge signal can be provided intermittently, such that the SOC of the battery 6 increases by a relatively small amount (e.g., about 2% or less), and then the charge signal is terminated until the SOC of the battery 6 returns to the previous SOC. In this manner, the battery 6 charging system 2 can ensure that the SOC of the battery 6 does not decrease when the battery charger 10 is connected to a power source.


Additionally, in a second state, the charge signal can be provided at a constant current. Moreover, at some point in time, the charge signal can switch to a third state that provides a constant voltage. The switch between the second state and the third state of the charge signal can be referred to as a constant current-constant voltage (CC/CV) transition point 22, which can be a specific SOC of the battery 6. To determine the CC/CV transition point 22, the charger controller 14 can employ Equation 1.











SOC
CV



(
τ
)


=


FCC
-

τ


(


I
st

-

I
tap


)



FCC





Equation





1







wherein:

    • τ is the battery time constant 20 for the battery 6;
    • SOCCV is the SOC of the battery 6 at the CC/CV transition point 22;
    • Ist is the constant current provided during the second state of the charge signal;
    • Itap is a tapper current provided after termination of a charging of the battery 6; and
    • FCC is the full charge capacity of the battery 6.


In some examples, the values of the constant current the second state (Ist) and the taper current (Itap) can be fixed parameters of the battery charger 10. The charger controller 14 can store the CC/CV transition point 22 in the battery data 16. Additionally, Equation 2 can characterize an amount of time to provide the charge signal (at a constant current) in the second state until the CC/CV transition point 22 is reached.











t
cc



(


SOC

p
,



τ

)


=



FCC


(

1
-

SOC
p


)


-

τ


(


I
st

-

I
tap


)




I
st






Equation





2







wherein:

    • tcc is the time remaining (in seconds) for providing the charge signal at the second state (e.g., at a constant current) before the CC/CV transition point 22 is reached; and
    • SOCp is a present value of the SOC of the battery 6.


Further, Equation 3 can characterize an amount of time to provide the charge signal at the third state (e.g., at a constant voltage) after the CC/CV transition point 22 is reached.











t
cv



(


SOC
p

,
τ

)


=

τ


(


ln


(


FCC
-

FCC
*

SOC
p


+


I
tap

*
τ




I
st

*
τ


)


-

ln


(


1

I
st


*

I
tap


)



)






Equation





3







wherein:

    • tcv is the time remaining (in seconds) for providing the charge signal the third state before the SOC of the battery 6 is about 100%.



FIG. 2 illustrates an example of a graph 50 that plots a time to full charge (e.g., an amount of time needed to reach about 100% SOC of the battery 6) as a function of an SOC of the battery 6 illustrated in FIG. 1. Moreover, a point 52 on the graph can represent the CC/CV transition point of the battery 6. That is, in the present example, the CC/CV transition point 52 can occur when the SOC of the battery 6 reaches about 68%, which can correspond to a time to full charge of about 3.3×103 seconds (about 55 minutes). Moreover, at an SOC before the CC/CV transition point 52, the charge signal can be provided in the second state (e.g., at a constant current), and the SOC of the battery 6 and the time to full charge of the battery 6 have a substantially linear relationship. After the CC/CV transition point 52, the charge signal can be provided in the third state (e.g., at a constant voltage) and the SOC of the battery 6 and the time to full charge of the battery have a substantially non-linear relationship (e.g., a logarithmic relationship).


Referring back to FIG. 1, Equation 2 can be employed to determine a total time that the charge signal is provided in the second state (e.g., at constant current) when the SOC of the battery 6 is initially at 0%, which can result in Equation 5. Additionally, Equation 3 can be employed to determine a total time that the charge signal is provided in the third state (e.g., at constant voltage) when the SOC of the battery 6 is at or near the CC/CV transition point 22, which can result in Equation 6.











t
cc



(


0

%

,
τ

)


=


FCC
-

τ


(


I
st

-

I
tap


)




I
st






Equation





5








t
cv



(


SOC
-
CV

,
τ

)


=


t
tap

=

-

τ


(

ln


(


1

I
st


*

I
tap


)


)








Equation





6







wherein:

    • ttap is the remaining charge time from the CC/CV transition point 22 to an SOC for the battery 6 of about 100%.


By solving Equation 3 for the battery time constant (τ) 20, Equation 7 can be derived.









τ
=



FCC


(

1
-

SOC
st


)


-


I
st

*

t
last





I
st

-

I
tap

+


I
st

*

ln


(


I
tap


I
st


)









Equation





7







wherein:

    • tlast is a measured charging time for charging the battery 6 from a starting SOC of the battery 6 (SOCst) to an SOC of about 100%; and SOCst is less than SOCCV.


Accordingly, by measuring the total charge time (ttot) 24 and employing Equation 7, in some examples, the charger controller 14 can determine the battery time constant (τ) 20, which can be stored in the battery data 16. In some examples, the battery time constant (τ) 20 can be an average of multiple battery time constants (τ) derived from Equation 7. Additionally, in some examples, the battery time constant (τ) 20 can be updated in the battery data 16 by the charger controller 14 after completing a full charging of the battery 6 by employing Equation 7.


Furthermore, Equations 1, 2 and 3 can be combined to derive Equation 8, such that a total charge time (ttot) 24 can be calculated (e.g., by the charger controller 14) from the present SOC of the battery 6 (SOCp).











t
tot



(


SOC
p

,
τ

)


=

{









t
cv



(


SOC
p

,
τ

)


,






SOC
p



SOC
-
CV













t
cc



(


SOC
p

,
τ

)


-

τ
*

ln


(


I
tap


I
st


)




,






SOC
p

<

SOC
-
CV










Equation





8







wherein:


ttot is the total charge time 24 from the present SOC of the battery 6 (SOCp) to a SOC for the battery 6 of about 100%.


By employing substitution, Equation 8 can be expanded to derive Equation 9.











t
tot



(


SOC
p

,
τ

)


=

{





τ


(


ln


(


FCC
-

FCC
*

SOC
p


+


I
tap

*
τ




I
st

*
τ


)


-

ln


(


1

I
st


*

I
tap


)



)


,





SOC
p



SOC
-
CV











FCC


(

1
-

SOC
p


)


-

τ


(


I
st

-

I
tap


)




I
st


-

τ
*

ln


(


I
tap


I
st


)




,





SOC
p

<

SOC
-
CV










Equation





9







Accordingly, the charger controller 14 can calculate the total charge time (tot) 24 by employing Equation 9 in response to receiving the present SOC for the battery 6 (SOCp). The charger controller 14 can store the total charge time (ttot) 24 in the battery data 16. Additionally, in some examples, the charger controller 14 can output a total charge time signal (labeled in FIG. 1 as “TOTAL CHARGE TIME”) to an external system (e.g., a host system). The total charge time signal can include data that characterizes the total charge time (ttot) 24 such that the external system can implement further processing of the total charge time (ttot) 24. In such a situation, the total charge time signal can be provided to the external system over a bus, such as the Inter-Integrated Circuit (I2C) bus coupled to the battery charger 10.


The charger controller 14 can determine a charging start time 26 based on the total charge time (ttot) 24 and the full charge time 18. To determine the charging start time 26, the charger controller 14 can subtract the total charge time (ttot) 24 from the full charge time 18. For instance, in the given example where the full charge time 18 is 7:00 A.M., and the total charge time (ttot) 24 is determined to be about 1.5 hours, the charging start time 26 can be set to about 5:30 A.M. The charging start time 26 can be stored, for example, in the battery data 16.


Additionally, the battery charger 10 can receive a present time signal (labeled in FIG. 1 as “PRESENT TIME”) that characterizes a present time. In some examples, the present time signal could be provided from an external source (e.g., a telecommunications tower or a network server). In other examples, the present time signal could be provided from an internal component (e.g., an internal clock). The charger controller 14 can cause the battery charger 10 to provide the charge signal in the first state to maintain the present SOC (SOCP) of the battery 6 from the present time until the present time is the same (or nearly the same) as the charging start time 26. Accordingly, the charger controller 14 can cause the battery charger 10 to delay charging the battery 6 until the charging start time 26. At (or after) the charging start time 26, the charger controller 14 can cause the battery charger 10 to charge the battery 6 in a manner described herein.


At the charging start time 26, if the present SOC (SOCP) of the battery 6 is less than the CC/CV transition point 22, the charger controller 14 can cause the battery charger 10 to provide the charge signal in the second state (e.g., at a constant current) until the CC/CV transition point 22 is reached. Moreover, upon reaching the CC/CV transition point 22, the charger controller 14 can cause the battery charger 10 to change the charge signal from the second state (e.g., at a constant current) to the third state (e.g., at a constant voltage). If the present SOC (SOCP) of the battery 6 is greater than or equal to the CC/CV transition point 22, the charger controller 14 can cause the battery charger 10 to provide the charge signal in the third state until the SOC of the battery 6 reaches a fully charged state of about 100%. Upon reaching the fully charged state, the charger controller 14 can cause a battery charger 10 to provide the charge signal in the first state to maintain charge of the battery 6 at the fully charged state of about 100% until the power signal is ceased, which can indicate that the battery charger 10 has been disconnected from the power source (e.g., unplugged).


By employing the battery charging system 2, the time at which the battery 6 is at or near the fully charged state of about 100% can be reduced. Such a reduction can slow a degradation of the charging capacity of the battery 6. In this manner, the benefits of having a fully charged battery can be achieved at a desired full charge time 18 that can be specified without the consequences (e.g. battery capacity degradation) of having the battery 6 at the fully charged state for an excessive amount of time. Furthermore, prior to the charging start time 26, the SOC of the battery 6 is maintained, but not significantly increased. Accordingly, upon connecting the battery charger 10 to the power source, the SOC of the battery 6 does not decrease such that a user could, in some examples, employ the portable device associated with the battery 6 while the battery charger 10 is connected to the power source.


Moreover, the derived Equations 1-9 are relatively simple and the variables (e.g., parameters) for the Equations 1-9 are easily obtained such that the battery charger 2 can be implemented relatively easily and without advanced mathematical techniques (e.g., curve fitting). Furthermore, since the battery charger 10 switches from the charging signal from the second state (e.g., a constant current) to the third state (e.g., a constant voltage) at the transition point, the battery 6 can be charged at an optimal rate, which can be referred to as a “healthy rate” that does not damage or degrade the battery 6. In comparison, some conventional battery chargers simply charge batteries at a fastest possible rate (e.g., not the optimal rate) thereby degrading a charge capacity of the battery.



FIGS. 3-8 depict experimental data derived from observation of charging a battery. In particular, FIGS. 3, 5 and 7 illustrate graphs 100, 110 and 120 that depict experimental data that plots a time to full charge as a function of an SOC of a battery (e.g., the battery 6 illustrated in FIG. 1). In FIGS. 3, 5 and 7, two plots are illustrated, a first plot depicts a time to full charge (labeled in FIGS. 3, 5 and 7 as “MEASURED TIME”) that characterizes an experimentally measured amount of time to charge the battery. A second plot depicts an estimated time to full charge (labeled in FIGS. 3, 5 and 7 as “ESTIMATED TIME”) that characterizes a time to full charge estimated for the battery with an SOC of about 0%, wherein the estimated time to full charge is based on Equation 9. Moreover, in Equation 9, a battery time constant for the battery is calculated using Equation 7. In FIG. 3, to charge the battery, a constant current is applied to the battery at a rate to fully charge the battery in one hour, which can be referred to as a rate of about 1 C. In FIG. 5, to charge the battery, a constant current is applied to the battery at a rate of about 1.2 C, which would be about 20% more current than the charge rate of 1 C. In FIG. 7, to the charge the battery, a constant current is applied to the battery at a rate of about 1.8 C, which would be about 80% more current than the charge rate of 1 C.



FIGS. 4, 6 and 8 illustrate graphs 102, 112 and 122 that illustrate an error percentage (%) plotted as a function of the SOC of the battery. In FIG. 4, the error percentage corresponds to the difference between the first and second plots in FIG. 3. In FIG. 6, the error percentage corresponds to the difference between the first and second plots in FIG. 5. In FIG. 8, the error percentage corresponds to the difference between the first and second plots in FIG. 7. As illustrated in FIGS. 3-8, by employing Equations 7 and 9, the estimated time for charging the battery can have a high degree of accuracy (less than 0.5% error). Moreover, as illustrated in FIGS. 4, 6 and 8, the error percentage tends toward 0% at as the SOC of the battery approaches 100%.


In view of the foregoing structural and functional features described above, example methods will be better appreciated with reference to FIGS. 9 and 11. While, for purposes of simplicity of explanation, the example methods of FIGS. 9 and 11 are shown and described as executing serially, it is to be understood and appreciated that the present examples are not limited by the illustrated order, as some actions could in other examples occur in different orders and/or concurrently from that shown and described herein. Moreover, it is not necessary that all described actions be performed to implement a method. The example methods of FIGS. 9 and 11 can be implemented as instructions stored in a non-transitory machine-readable medium. The instructions can be accessed by a processing resource and executed to perform the methods disclosed herein.



FIG. 9 illustrates a flow chart of an example method 200 for charging a battery. The method 200 could be implemented, for example, by the battery charging system 2 illustrated in FIG. 1. At 210, upon detecting a power signal, a battery charger (e.g., the battery charger 10 illustrated in FIG. 1) can receive an initial SOC for a battery (e.g., the battery 6 illustrated in FIG. 1) from a battery gauge (e.g., the battery 4 illustrated in FIG. 1). The initial SOC for the battery can be referred to as the present SOC for the battery (SOCp). At 220, a charger controller (e.g., the charger controller 14 illustrated in FIG. 1) of the battery charger can determine a battery time constant (τ) for the battery. The battery time constant (τ) can be determined, for example, by employment of Equation 7.


At 230, the charger controller can determine a CC/CV transition point (SOCCV) for the battery. To determine the CC/CV transition point (SOCCV), the charger controller can employ, for example, Equation 1. At 240, the charger controller can determine a total charge time (ttot) for the battery. To determine the total charge time (ttot), the charger controller can employ, for example, Equation 9.


At 250, the charger controller can determine a charging start time. To determine the charging start time, the charger controller can examine a stored full charge time and subtract the total charge time from the full charge time. For instance, if the full charge time is 9:30 A.M. and the total charge time is about 2 hours and 20 minutes, the charging start time can be about 7:10 A.M.


At 260, the charger controller can make a determination as to whether a present time is at (or past) the charging start time. If the determination at 260 is negative (e.g., NO), the method 200 can proceed to 270. If the determination at 260 is positive (e.g., YES), the method 200 can proceed to 280. At 270, the charger controller can control a charge signal provided by the battery charger to the battery and causes the battery charger to provide the charge signal in a first state, such that the present SOC (SOCp) of the battery is maintained, but not significantly increased. At 280, the charger controller can cause the battery charger to provide the charge signal in a second state (e.g., a constant current) or third state (e.g., a constant voltage) to charge the battery until the SOC of the battery reaches about 100%. By employment of this method, the amount of time that the battery is at or near an SOC of about 100% is reduced, since the charging of the battery is delayed until the charging start time is reached.



FIG. 10 illustrates an example of a battery charger 300. The battery charger 300 could be employed to implement the battery charger 10 illustrated in FIG. 1. The battery charger 300 can include a charger controller 302 that can be configured to determine a total charge time (ttot) that characterizes a time needed to charge a battery. The total charge time can be based on a received SOC (labeled in FIG. 10 as “SOC”) of the battery that characterizes a present SOC of the battery. The battery charger can also determine a charging start time for the battery based on a predetermined full charge time and the total charge time.



FIG. 11 illustrates an example of a method 400 for charging a battery. The method 400 could be implemented, for example, by the charger controller 14 illustrated in FIG. 1. At 410, a total charge time (ttot) of a battery can be determined (e.g., by the charger controller) based on a received state of charge (SOC) of the battery that characterizes a present SOC of the battery and the total charge time (ttot) of the battery can also be based on a battery time constant (τ) of the battery that characterizes the product of a resistance and a capacitance of an equivalent circuit of the battery. At 420, a charging of the battery can be delayed (e.g., by the charger controller) until a charging start time that is based on the total charge time (ttot) and a predetermined full charge time.


What have been described above are examples. It is, of course, not possible to describe every conceivable combination of components or methodologies, but one of ordinary skill in the art will recognize that many further combinations and permutations are possible. Accordingly, the disclosure is intended to embrace all such alterations, modifications, and variations that fall within the scope of this application, including the appended claims. As used herein, the term “includes” means includes but not limited to, the term “including” means including but not limited to. The term “based on” means based at least in part on. Additionally, where the disclosure or claims recite “a,” “an,” “a first,” or “another” element, or the equivalent thereof, it should be interpreted to include one or more than one such element, neither requiring nor excluding two or more such elements.

Claims
  • 1. A battery charger comprising: a charger controller configured to: determine a total charge time that characterizes a time needed to charge a battery, the total charge time being based on a received state of charge (SOC) of the battery that characterizes a present SOC of the battery; anddetermine a charging start time for the battery based on a predetermined full charge time and the total charge time.
  • 2. The battery charger of claim 1, wherein the charger controller is further configured to cause the battery charger to provide a charge signal to the battery in a given state that causes the battery to maintain the present SOC of the battery if a present time is prior to the charging start time.
  • 3. The battery charger of claim 2, wherein the charger controller is further configured to cause the battery charger to provide the charge signal to the battery in another state that causes the battery to increase the SOC of the battery if a present time is at or past the charging start time.
  • 4. The battery charger of claim 3, wherein the battery comprises a lithium ion battery.
  • 5. The battery charger of claim 4, wherein the charger controller is further configured to determine a constant current-constant voltage transition point for the battery.
  • 6. The battery charger of claim 5, wherein:
  • 7. The battery charger of claim 5, wherein the charger controller is further to cause the battery charger to provide the charge signal at a relatively constant current if the present SOC of the battery is less than the constant current-constant voltage transition point for the battery.
  • 8. The battery charger of claim 5, wherein the charger controller is further to cause the battery charger to provide the charge signal at a relatively constant voltage if the present SOC of the battery is greater than or equal to the constant current-constant voltage transition point for the battery.
  • 9. The battery charger of claim 1, wherein the total charge time is also based on a battery time constant for the battery, wherein the battery time constant characterizes the product of a resistance and a capacitance of an equivalent circuit for the battery.
  • 10. The battery charger of claim 9, wherein the charger controller is further configured to determine or update the battery time constant at the time of the charge termination, wherein:
  • 11. The battery charger of claim 9, wherein:
  • 12. The battery charger of claim 1, wherein the predetermined full charge time is set based on user input, and the predetermined full charge time designates a time that the battery is to have an SOC of about 100%.
  • 13. The battery charger of claim 1, wherein the charger controller is further configured to output a total charge time signal on a bus, wherein the total charge time signal characterizes the total charge time.
  • 14. A non-transitory machine readable medium having instructions for performing a method, the method comprising: determining a total charge time of a battery based on a received state of charge (SOC) of the battery that characterizes a present SOC of the battery and based on a battery time constant of the battery that characterizes the product of a resistance and a capacitance of an equivalent circuit of the battery; anddelaying a charging of the battery until a charging start time that is based on the total charge time and a predetermined full charge time.
  • 15. The non-transitory machine readable medium of claim 14, wherein the method further comprises determining the battery time constant based on a measured time for charging the battery from an SOC of about 0% to about 100%.
  • 16. The non-transitory machine readable medium of claim 14, wherein the method further comprises determining a constant current-constant voltage transition point for the battery based on the battery time constant.
  • 17. The non-transitory machine readable medium of claim 14, wherein the method further comprises charging the battery at or after the charging start time.
  • 18. The non-transitory machine readable medium of claim 17, the wherein the charging further comprises: providing a charge signal to the battery at a substantially constant current if the present SOC of the battery is less than the constant current-constant voltage transition point; andproviding a charge signal to the battery at a substantially constant voltage if the present SOC of the battery is greater than or equal to the constant current-constant voltage transition point.
  • 19. A battery charging system comprising: a battery pack that includes a battery;a battery gauge configured to determine a present state of charge (SOC) of the battery; anda battery charger configured to provide a charging signal to the battery pack, the battery charger comprising a charger controller configured to: determine a constant current-constant voltage transition point for the battery based on a battery time constant and a full charge capacity of the battery, wherein the battery time constant characterizes the product of a resistance and a capacitance of an equivalent circuit of the battery;determine a total charge time for the battery based on the present SOC of the battery, the battery time constant and the full charge capacity of the battery;determine a charging start time based on the total charge time and a predetermined full charge time; andcontrol the charging signal such that the present SOC of the battery prior to the charging start time is maintained and the present SOC of the battery is increased after the charging start time such that the present SOC of the battery is about 100% at the predetermined full charge time.
  • 20. The battery charging system of claim 19, wherein the battery charger is further configured to determine the battery time constant for the battery based on a measured time to fully charge the battery from an SOC of about 0% to about 100%.