This application claims priority to Chinese Patent Application No. 202410934456.9, filed on Jul. 12, 2024, which is herein incorporated by reference in its entirety.
The disclosure relates to the technical field of prefabricated modular building structures, and more particularly to a beam-slab integrated prefabricated waffle slab structure and a construction method thereof.
In current high-tech electronic factories, such as chip processing factories or panel factories, the floor slabs need to meet the requirements of anti-micro-vibration, that is, the floor slabs cannot vibrate slightly during the production process to avoid affecting product production and ensure the yield rate of products. In order to achieve the anti-micro-vibration effect, a thickness of the factory floor slabs is much higher than that of ordinary buildings. In addition, since most high-tech electronic factories are high-cleanliness factories, it is necessary to open multiple through-holes on the floor slabs to control the air flow in the factory and ensure the requirements for air cleanliness.
At present, the floor slabs of the high-tech electronic factories are mainly cast-in-place, and the cast-in-place process requires the floor slabs to meet the following requirements. 1. The flatness of the slab surface is high, and the error within two meters (m) does not exceed two millimeters (mm). 2. The surface needs to be leveled. 3. During the construction process, in addition to laying out the external formwork, it is also necessary to lay out the circular hole mold, and then tie the rebars for overall pouring.
However, the above requirements have the following problems.
1. Due to the high construction requirements, for example, the flatness of the lower surface of the floor slab requires the use of a black plastic template, and the upper surface of the floor slab needs to be leveled, the on-site construction is difficult, the construction period is long, and the quality of the construction personnel is required to be high.
2. The floor slabs of the high-tech electronic factories are large in area and high in height, the cast-in-place process requires a large-scale support system, which is slow and expensive to construct.
3. The cast-in-place process requires that the formwork and support be removed only after the concrete has hardened, and only then can the equipment be installed. The construction period is long, which seriously affects the project delivery time and it is difficult to meet the requirements for high-tech production lines to be put into production as soon as possible.
A Chinese patent publication No. CN109469326A discloses a construction method for special-shaped lattice panels, and the lattice panels disclosed therein are used as floor slabs of wafer factories. A Chinese patent publication No. CN109695345A discloses a structural construction method of building, and the precast floors disclosed therein are used as floor slabs of factories. However, both the lattice panels and the precast floors have a planar size close to the column grid size. According to the current technology, the column grid size is usually 6 m*6 m, thus they are basically not suitable for road transportation. In addition, the floor slabs disclosed in the above patents are large in size and have few post-cast layers, thus they are heavy overall, and the corresponding transportation and installation costs are high.
A purpose of the disclosure is to provide a beam-slab integrated prefabricated waffle slab structure, which achieves the construction site without support and formwork through prefabricated assembly while meeting requirements of anti-micro-vibration, significantly accelerating construction progress and reducing construction costs.
A beam-slab integrated prefabricated waffle slab structure includes columns, prefabricated frame beams and prefabricated waffle beam-slab units.
The columns are arranged in an array, and a beam and slab support element and a beam support element are disposed on an upper end of each of the columns.
A cross section of each of the prefabricated frame beams is generally rectangular, two ends of each of the prefabricated frame beams are respectively disposed on the beam support elements of adjacent columns on left and right sides of each of the prefabricated frame beams, and a main support element is disposed on front and rear sidewalls of each of the prefabricated frame beams.
Each of the prefabricated waffle beam-slab units includes a reinforced concrete slab, ribbed beams, annular bars, cylindrical inner molds and a pre-embedded steel plate. The ribbed beams are respectively disposed on left and right sides of the reinforced concrete slab, and are disposed facing upwards and extend forwards and backwards. The reinforced concrete slab defines through-holes arranged in an array. The annular rebars extending out of the reinforced concrete slab are disposed on front and rear sides and left and right sides of any one of the through-holes, and the annular rebar between any adjacent two of the through-holes is the same. An upper end of each of the through-holes is provided with the cylindrical inner mold to obtain array arranged cylindrical inner molds. The pre-embedded steel plate is disposed on each of inner sidewalls of front and rear ends of each of the ribbed beams. One of the ribbed beams of each of the prefabricated waffle beam-slab units is disposed on the beam and slab support elements, and another of the ribbed beams of each of the prefabricated waffle beam-slab units is disposed on the main support elements of two mutually parallel prefabricated frame beams.
Each of the ribbed beams is provided with stirrups B, and the stirrups B extend out of an upper surface of each of the ribbed beams, and are arranged in a front to back sequence. A post-installed ribbed beam top rebar skeleton is disposed on adjacent two of the ribbed beams of two of the prefabricated waffle beam-slab units.
A top surface of each of the prefabricated frame beams defines a groove extending along a length direction of each of the prefabricated frame beams. Each of the prefabricated frame beams is provided with opening hoops extending out of the groove, and is provided with connecting rebars extending out of front and rear sides of each of the prefabricated frame beams. The connecting rebars are provided in multiple rows, and the multiple rows of the connecting rebars are arranged in a left to right sequence. Each of the prefabricated frame beams is provided with longitudinal rebars A therein, and each of the longitudinal rebars A extends into beam-column nodes of the columns and the prefabricated frame beams.
Post-installed main beam top rebar skeletons are disposed on the prefabricated frame beams, each of the main beam top rebar skeletons is disposed continuously to cover all of the prefabricated frame beams in a same extension direction, and each of the main beam top reinforcement skeletons and the opening hoops cooperate to form a closed hoop structure.
An L-shaped connecting element is disposed between the pre-embedded steel plate and a corresponding one main support element, and the L-shaped connecting element is welded with the pre-embedded steel plate and the corresponding one main support element. In the array arranged cylindrical inner molds, horizontal slab rebars are disposed between horizontal gaps of the array arranged cylindrical inner molds, and longitudinal slab rebars are disposed between longitudinal gaps of the array arranged cylindrical inner molds.
Concrete is poured on site at the beam-column nodes of the columns and the prefabricated frame beams, at the ribbed beam top rebar skeletons, at the main beam top rebar skeleton, at the horizontal slab rebars and at the longitudinal slab rebars, and the poured-on-site concrete is configured to cover the ribbed beam top rebar skeletons, the main beam top rebar skeletons, the horizontal slab rebars and the longitudinal slab rebars.
A construction method of the beam-slab integrated prefabricated waffle slab structure, including:
Compared to the related art, beneficial effects of the disclosure are as follows.
1. The disclosure replaces a composite slab area of an existing beam-slab integrated unit with a prefabricated waffle beam-slab unit. Compared with the traditional construction method, the disclosure can achieve support-free and formwork-free construction on the construction site, significantly improving the installation speed. In addition, the prefabricated waffle beam-slab unit is prefabricated using factory standardization, which significantly reduces the difficulty of later plate surface leveling and maximizes the construction speed.
2. The combination of the prefabricated waffle beam-slab units and post-poured concrete is convenient and has good integrity, which can ensure the anti-micro-vibration and waterproof performance of the prefabricated floor.
3. The prefabricated waffle beam-slab units are lighter in weight than fully prefabricated waffle slabs, can meet the size restrictions for road transportation, are cheap in transportation costs and are easy to install.
4. The main support element adopts an inverted T-shaped structural design to ensure that the prefabricated frame beam is flush with the bottom of the main support element, which does not affect the installation of subsequent production equipment. At the same time, it has a large bearing capacity and is easy to install.
5. The ribbed beam top rebar skeletons, the main beam top rebar skeletons, the horizontal slab rebars, and the longitudinal slab rebars are connected with the corresponding structures, which is convenient for installation and ensures the reliability of the connection between each component.
The disclosure is described in detail in conjunction with embodiments and drawings below.
As shown in
The columns 1 are arranged in an array, and a beam and slab support element 11 and a beam support element 12 are disposed on an upper end of each of the columns 1.
A cross section of each of the prefabricated frame beams 2 is generally rectangular, two ends of each prefabricated frame beam 2 are respectively disposed on the beam support elements 12 of adjacent columns 1 on left and right sides of each prefabricated frame beam 2, and a main support element 4 is disposed on front and rear sidewalls of each prefabricated frame beam 2.
Each prefabricated waffle beam-slab unit 3 includes a reinforced concrete slab 31, ribbed beams 32, annular bars 34, cylindrical inner molds 35 and a pre-embedded steel plate 36. The ribbed beams 32 are respectively disposed on left and right sides of the reinforced concrete slab 31, and are disposed facing upwards and extend forwards and backwards. The reinforced concrete slab 31 defines through-holes 33 arranged in an array. The annular rebars 34 extending out of the reinforced concrete slab 31 are disposed on front and rear sides and left and right sides of any one of the through-holes 33, and the annular rebar 34 between any adjacent two of the through-holes 33 is the same. An upper end of each of the through-holes 33 is provided with the cylindrical inner mold 35 to obtain array arranged cylindrical inner molds 35. The pre-embedded steel plate 36 is disposed on each of inner sidewalls of front and rear ends of each of the ribbed beams 32. One of the ribbed beams 32 of each prefabricated waffle beam-slab unit 3 is disposed on the beam and slab support elements 11, and another of the ribbed beams 32 of each prefabricated waffle beam-slab unit 3 is disposed on the main support elements 4 of two mutually parallel prefabricated frame beams 2.
Each of the ribbed beams 32 is provided with stirrups B 321, and the stirrups B 321 extend out of an upper surface of each of the ribbed beams 32, and are arranged in a front to back sequence. A post-installed ribbed beam top rebar skeleton 5 is disposed on adjacent two of the ribbed beams 32 of two of the prefabricated waffle beam-slab units 3.
A top surface of each prefabricated frame beam 2 defines a groove 21 extending along a length direction of each prefabricated frame beam 2. Each prefabricated frame beam 2 is provided with opening hoops 22 extending out of the groove 21, and is provided with connecting rebars 23 extending out of front and rear sides of each prefabricated frame beam 2. The connecting rebars 23 are provided in multiple rows, and the multiple rows of the connecting rebars 23 are arranged in a left to right sequence. Each prefabricated frame beam 2 is provided with longitudinal rebars A 24 therein, and each of the longitudinal rebars A 24 extends into beam-column nodes (i.e., the connection points between the columns 1 and the prefabricated frame beams 2) of the columns 1 and the prefabricated frame beams 2.
Post-installed main beam top rebar skeletons 6 are disposed on the prefabricated frame beams 2, each of the main beam top rebar skeletons 6 is disposed continuously to cover all of the prefabricated frame beams 2 in a same extension direction, and each of the main beam top reinforcement skeletons and the opening hoops 22 cooperate to form a closed hoop structure.
An L-shaped connecting element 9 is disposed between the pre-embedded steel plate 36 and a corresponding one main support element 4, and the L-shaped connecting element 9 is welded with the pre-embedded steel plate 36 and the corresponding one main support element 4. In the array arranged cylindrical inner molds 35, horizontal slab rebars 7 are disposed between horizontal gaps of the array arranged cylindrical inner molds 35, and longitudinal slab rebars 8 are disposed between longitudinal gaps of the array arranged cylindrical inner molds 35.
Concrete is poured on site at the beam-column nodes of the columns 1 and the prefabricated frame beams 2, at the ribbed beam top rebar skeletons 5, at the main beam top rebar skeletons 6, at the horizontal slab rebars 7 and at the longitudinal slab rebars 8, and the poured-on-site concrete is configured to cover the ribbed beam top rebar skeletons 5, the main beam top rebar skeletons 6, the horizontal slab rebars 7 and the longitudinal slab rebars 8.
The columns 1 and the prefabricated frame beams 2 here are not much different from the traditional beam-slab integrated unit structure. The main difference lies in the structure of the prefabricated waffle beam-slab unit and the design of related configurations.
The prefabricated waffle beam-slab unit 3 remains a breathable channel, and the cylindrical inner molds 35 are directly poured on the prefabricated waffle beam-slab unit 3. The concaved area in the middle of the prefabricated waffle beam-slab unit 3 is matched with horizontal slab rebars 7 and longitudinal slab rebars 8, and are poured with concrete on site, thereby ensuring the thickness of the formed floor slab and the anti-micro-vibration effect, while ensuring that the prefabricated components are not too heavy.
Rebars in each prefabricated waffle beam-slab unit 3 include: multiple slab bottom horizontal rebars 37, multiple slab bottom longitudinal rebars 38 and ribbed beam rebars 39.
The multiple slab bottom horizontal rebars 37 are arranged horizontally in parallel intervals, the multiple slab bottom longitudinal rebars 38 are arranged longitudinally in parallel intervals, and the multiple slab bottom horizontal rebars 37 and the multiple slab bottom longitudinal rebars 38 are arranged in a staggered manner and are poured with the concrete, with reservation of the through-holes 33 to form the reinforced concrete slab 31. The ribbed beam rebars 39 are poured with the concrete to form the ribbed beams 32.
Each of the multiple slab bottom horizontal rebars 37 includes lower horizontal rebars 371 and lower horizontal stirrups 372. Multiple lower horizontal rebar 371 extend left and right and are bent at two ends to form an anchorage structure extending into the ribbed beams 32, multiple lower horizontal stirrups 372 are arranged in a left to right sequence, and the lower horizontal rebars 371 are connected to bottoms of the lower horizontal stirrups 372.
Each of the multiple slab bottom longitudinal rebars 38 includes lower longitudinal rebars 381 and lower longitudinal stirrups 382. Multiple lower longitudinal rebars 381 extend left and right, multiple lower longitudinal stirrups 382 are arranged in a front to rear sequence, and the lower longitudinal rebars 381 are connected to bottoms of the lower longitudinal stirrups 382.
Each of the ribbed beam rebars 39 includes longitudinal rebars B 322 and ribbed beam stirrups 391. Tops of the ribbed beam stirrups 391 extend out of the upper surface of each of the ribbed beams 32 to form the stirrups B 321. The ribbed beams 32 cooperating with the beam and slab support elements 11 are provided with the longitudinal rebars B 322 therein, and the longitudinal rebars B 322 extend into the beam-column nodes of the columns 1 and the prefabricated frame beams 2.
Front and rear end surfaces of the ribbed beams 32 cooperating with the beam and slab support elements 11 each define a shear resistant keyway B 323.
Left and right end surfaces of each prefabricated frame beam 2 each define a shear resistant keyway A 25. The shear resistant keyway B 323 and the shear resistant keyway A 25 here are mainly used to ensure the intensity of the connections of the pouring nodes.
As shown in
Front and rear edges of the connecting bottom plate 43 each extend out of the front and rear side surfaces of each prefabricated frame beam 2. Each of the vertical steel plates 44 is connected to a middle of the connecting steel plate 43 and is connected to an outer side surface of each of the two anchor plates 41 to form an inversed T-shaped support structure, to thereby make two sides of each of the vertical steel plate 44 respectively support the ribbed beams 32 of corresponding reinforced concrete slabs 31.
Since the shear resistance of the inverted T-shaped support structure is lower than that of the trough-shaped support structure of the existing beam-slab integrated slab, it is considered to provide the L-shaped connecting element 9 between the pre-embedded steel plate 36 and the main support element 4 and weld them to improve the shear resistance.
As shown in
As shown in
As shown in
As shown in
As shown in
In step S1, array construction of the columns 1 is completed.
In step S2, the beam and slab support element 11 and the beam support element 12 are installed on each of the columns 1 according to heights of the prefabricated frame beams 2 and the prefabricated waffle beam-slab units 3.
In step S3, each prefabricated frame beam 2 is installed on two of the columns 1 to make ends of each prefabricated frame beam 2 be supported on the beam support elements 12 of the two of the columns 1.
In step S4, each prefabricated waffle beam-slab unit 3 is installed on two of the prefabricated frame beams 2 to make the ribbed beam 32 on a side of each prefabricated waffle beam-slab unit 3 be supported on the beam-slab support elements 11 and make the ribbed beam 32 on another side of each prefabricated waffle beam-slab unit 3 be supported on the main support element 4.
In step S5, the L-shaped connecting element 9 is welded with the pre-embedded steel plate 36 and the main support element 4. The main beam top rebar skeletons 6 is installed in the groove 21 of each prefabricated frame beam 2, and the main beam top rebar skeletons 6 cover all of the prefabricated frame beams 2 in the same extension direction. The ribbed beam top rebar skeleton 5 is installed in the adjacent two of the ribbed beams 32 of two of the prefabricated waffle beam-slab units 3.
In step S6, the horizontal slab rebars 7 and the longitudinal slab rebars 8 are installed into each prefabricated waffle beam-slab unit 3 in sequence.
In step S7, the concrete is poured at the beam-column nodes of the columns 1 and the prefabricated frame beams 2, at the ribbed beam top rebar skeletons 5, at the main beam top rebar skeletons 6, at the horizontal slab rebars 7 and at the longitudinal slab rebars 8 on site, and the poured-on-site concrete is configured to cover the ribbed beam top rebar skeletons 5, the main beam top rebar skeletons 6, the horizontal slab rebars 7 and the longitudinal slab rebars 8.
Finally, it should be noted that the above descriptions are merely some of the embodiments of the disclosure and are not intended to limit the disclosure. Although the disclosure has been described in detail with reference to the aforementioned embodiments, it is still possible for those skilled in the art to modify the technical solutions described in the aforementioned embodiments, or to make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, and improvements made within the spirit and principles of the disclosure should be included in the protection scope of the disclosure.
Number | Date | Country | Kind |
---|---|---|---|
202410934456.9 | Jul 2024 | CN | national |
Number | Name | Date | Kind |
---|---|---|---|
924703 | Streed | Jun 1909 | A |
1314271 | Kopp | Aug 1919 | A |
1353373 | Allbright | Sep 1920 | A |
1360669 | Jacob | Nov 1920 | A |
1657964 | Groves | Jan 1928 | A |
1924044 | MacDougall | Aug 1933 | A |
2199152 | Edge | Apr 1940 | A |
2373409 | Wilbur | Apr 1945 | A |
2645114 | Amirikian | Jul 1953 | A |
3495367 | Kobayashi | Feb 1970 | A |
3613325 | Yee | Oct 1971 | A |
3672022 | York | Jun 1972 | A |
3693308 | Trezzini | Sep 1972 | A |
3918222 | Bahramian | Nov 1975 | A |
4001992 | Rohss | Jan 1977 | A |
4023315 | Stucky | May 1977 | A |
4040220 | Henager | Aug 1977 | A |
4138833 | Townend | Feb 1979 | A |
4164831 | Messick | Aug 1979 | A |
4231199 | Gomez | Nov 1980 | A |
4372906 | del Valle | Feb 1983 | A |
4409764 | Wilnau | Oct 1983 | A |
4472331 | Kida | Sep 1984 | A |
4788809 | Koukourou | Dec 1988 | A |
4942707 | Huettemann | Jul 1990 | A |
4945695 | Majurinen | Aug 1990 | A |
4996816 | Wiebe | Mar 1991 | A |
5119606 | Graham | Jun 1992 | A |
5421136 | Van De Peer | Jun 1995 | A |
6000194 | Nakamura | Dec 1999 | A |
6003279 | Schneider | Dec 1999 | A |
6101779 | Davenport | Aug 2000 | A |
6119425 | Shimonohara | Sep 2000 | A |
6266938 | Sheu | Jul 2001 | B1 |
6293063 | Van Doren | Sep 2001 | B2 |
6295770 | Sheu | Oct 2001 | B1 |
6543371 | Gardner | Apr 2003 | B1 |
6745532 | Vazquez Ruiz del Arbol | Jun 2004 | B1 |
7121061 | Jazzar | Oct 2006 | B2 |
7226033 | Foucher | Jun 2007 | B2 |
7685789 | Houben | Mar 2010 | B2 |
7980042 | Polk, Jr. | Jul 2011 | B2 |
8110134 | Scott | Feb 2012 | B2 |
8505267 | Martin Hernandez | Aug 2013 | B2 |
8782993 | Lawley | Jul 2014 | B2 |
8844224 | Lindquist | Sep 2014 | B2 |
8844238 | Baldoni | Sep 2014 | B2 |
8898992 | Rahimzadeh | Dec 2014 | B2 |
8943776 | Strickland | Feb 2015 | B2 |
9096999 | Rahimzadeh | Aug 2015 | B2 |
9506266 | Foldenauer | Nov 2016 | B2 |
9683361 | Timberlake | Jun 2017 | B2 |
9708812 | Jeske | Jul 2017 | B2 |
10094101 | Jazzar | Oct 2018 | B1 |
10125457 | Yin | Nov 2018 | B1 |
10145130 | Yin | Dec 2018 | B1 |
10151111 | Porter | Dec 2018 | B1 |
10202770 | Rapperstorfer | Feb 2019 | B2 |
10239228 | Hertz | Mar 2019 | B2 |
10260225 | Lee | Apr 2019 | B2 |
10309108 | Sanabra Loewe | Jun 2019 | B2 |
10378197 | Kurosawa | Aug 2019 | B2 |
10400450 | Kim | Sep 2019 | B2 |
10538384 | Crowther | Jan 2020 | B2 |
10597863 | Slaven, Jr. | Mar 2020 | B2 |
10709917 | An | Jul 2020 | B2 |
10801201 | Pfeffer | Oct 2020 | B2 |
10808393 | Yin | Oct 2020 | B2 |
10837175 | Kim | Nov 2020 | B2 |
11053675 | Santandreu | Jul 2021 | B1 |
11105084 | Cui | Aug 2021 | B1 |
11352786 | Rahimian | Jun 2022 | B2 |
11414863 | Royce | Aug 2022 | B2 |
11566424 | Dinmore | Jan 2023 | B2 |
11578491 | Shaw | Feb 2023 | B2 |
11598084 | Foley | Mar 2023 | B2 |
11598091 | Mirkhani | Mar 2023 | B2 |
11702836 | Shiohara | Jul 2023 | B2 |
11851870 | Lee | Dec 2023 | B2 |
11866935 | Ebisawa | Jan 2024 | B2 |
12012756 | Hulsizer | Jun 2024 | B2 |
12098539 | Zhang | Sep 2024 | B2 |
12129653 | Kang | Oct 2024 | B2 |
20020092249 | Yin | Jul 2002 | A1 |
20030115822 | Lejeune | Jun 2003 | A1 |
20170051506 | An | Feb 2017 | A1 |
20190177964 | Yousefi Darestani | Jun 2019 | A1 |
20240109224 | Yin | Apr 2024 | A1 |
20240110374 | Searles | Apr 2024 | A1 |
Number | Date | Country |
---|---|---|
108678252 | Oct 2018 | CN |
109469326 | Mar 2019 | CN |
109695345 | Apr 2019 | CN |
210238897 | Apr 2020 | CN |
113123516 | Jul 2021 | CN |
Entry |
---|
CNIPA, Notification of First Office Action for CN202410934456.9, Aug. 29, 2024. |
Fujian Construction Engineering Prefabricated Building Research Institute Co., Ltd. (Applicant), Replacement claims (allowed) of CN202410934456.9, Sep. 19, 2024. |
CNIPA, Notification to grant patent right for invention in CN202410934456.9, Sep. 27, 2024. |