1. Field of the Invention
The present invention relates generally to offshore drilling operations, and more specifically to an apparatus for removing and installing drilling equipment.
2. Background of the Invention
An offshore drilling facility includes a drilling rig for various operations performed while drilling a subsea well. A conductor casing extends from the subsea well to an elevation above the surface of the water, where a working platform is connected to an upper portion of the conductor casing for drilling operators to work. On many facilities, the drilling rig is often supported by a drilling platform or cantilever that extends from a side of the drilling facility, over the water, to a location above the drilling platform and conductor casing.
A string of drill pipe is lowered from the drilling rig, through an opening in the cantilever, into the conductor casing for conducting drilling operations. A blow out preventer (BOP), typically located within the cantilever, engages the upper end of the conductor casing. The BOP regulates fluid flow out of the conductor casing from the subsea well. There are numerous types of BOPs. For example, some have rams that clamp down on the conductor casing. Others are annular which contract to enclose around a drill sting. The term “BOP” as used in this application is not meant to designate either device, but rather to encompass each type known or foreseeable in the art. BOPs can weigh up to 40,000 lbs., and have large pieces that are cumbersome while being moved between various positions.
During some operations, the BOP must be removed. During these operations, the BOP is typically hoisted and slid along rails to another location within the cantilever. Should a BOP need replacing or to be removed from the drilling facility, the upper surface of the cantilever prevents a crane from lifting the BOP from the storage or stowed position. Rather, the BOP must be moved to a location below the opening the drill pipe typically extends through for engaging the conductor casing.
The drilling rig cannot lift the BOP and continue drilling operations through the same opening in the upper surface of the cantilever. Therefore, the drilling rig discontinues drilling operations and disconnects from the conductor casing to lift the BOP out of the cantilever. Accordingly, the cantilever and drilling rig must be lifted, or “jacked up”, relative to the conductor casing in order to disconnect from the conductor casing and allow room for the BOP over the conductor casing. In order to lower the BOP onto a vessel, the drilling rig is then slid on the cantilever so that the BOP is at a position that is not directly above the conductor casing. Because the BOP is being lowered from the drilling rig, the vessel is in close proximity to the conductor casing and the supports of the facility. This creates a dangerous environment for the workers and the facilities. During normal weather conditions, this removal process can take two to three days. Under rough weather conditions, the process can take four to six days.
An offshore well drilling assembly includes a drilling facility or support platform for location at sea. A drilling platform is connected to the support platform such that the drilling platform is cantilevered from the support platform. The drilling platform extends from the support platform, and is positioned over the sea, for positioning over a subsea well. The well drilling assembly includes a staging platform for use in loading and unloading of wellhead equipment. The staging platform is mounted to the drilling platform. The staging platform moves along a side of the drilling platform in directions toward and away from the support platform to a distance over the sea.
The drilling assembly can also include a rail for the staging platform to move along. The platform can be driven by a motor located on the support platform or on the staging platform. The staging platform can be move along the outside of the drilling platform or along an inside of the drilling platform and extend onto the support platform. The drilling platform can include an opening for the drilling rig to conduct operations on the subsea well. The platform moves along between the support platform and a distance at least as far away from the support platform as the opening.
The drilling facility can also include a lower rail to help guide the staging platform along the side of the drilling platform. A plurality of columns, extending from a wall located along the drilling platform, can support the rails such that the lower rail is farther away from the drilling platform. The lower rail can guide a roller located on the staging platform.
Referring to
During typical drilling operations, a blow out preventer (BOP) 23 is located within cantilever 17, below drilling rig 19. BOP 23 engages an upper end of conductor casing 14 to regulate or prevent fluid flow through the upper end of conductor casing 14 during specific operations, or during emergencies. In some operations, BOP 23 is removed from conductor casing 14. For example, this may be while a tree is being installed. BOP 23 is moved within cantilever 17 to a stowed or storage position away from conductor casing 14, as shown in
Previously, when installing or removing BOP 23 within cantilever 17, BOP 23 was lifted through opening 20 because crane 24 cannot reach BOP 23 below the deck of cantilever 17. Therefore, during replacement and removal operations, BOP 23 was positioned within opening 20, and drilling rig 19 disengaged from drilling operations for lifting and lowering BOP 23 to vessel 25. This is a time consuming, dangerous, and expensive operation.
Referring to
A drive assembly, comprising a motor 39 and gear assembly 41, engage a tensionable draw line 43 for moving staging platform 27 between aft and bow positions. Gear assembly 41 can comprise a toothed end of a shaft extending from motor 39 that directly engages draw line 43, or a plurality of toothed gears that are rotated by a shaft from motor 39 and engage draw line 43. In the preferred embodiment, motor 39 is a bi-directional motor in order to engage draw line 43 to move staging platform both toward and away from facility 11. In either embodiment, the toothed surface is rotated by motor 39, and acts as a pinion for engaging draw line 43.
Draw line 43 can be any known apparatus for engaging a toothed gear or pinion. For example, draw line 43 can be a loop of chain links that loop around gear assembly 41 to pull either the upper or lower portions of the chain loop, depending on the direction of rotation of the pinion, to slide platform between aft and bow positions. Alternatively, draw line 43 could also be a metal rod with a toothed profile for tangentially engaging the pinion, so that the rod and staging platform 27 slide between aft and bow positions depending upon the direction of rotation of the pinion. As is readily apparent by those skilled in the art, there are numerous alternatives for moving an object closer or farther away from motor 39 located on facility 11.
In the embodiment shown in
In operation, BOP 23 is removed from conductor casing 14 in a manner readily known in the art, and drilling rig 19 can continue with operations. BOP 23 is loaded onto staging platform 27 from within cantilever 17. Preferably this is performed with the assistance of rails 26 and a side opening in cantilever 17 near a stowed position for BOP 23. After securing BOP 23 to staging platform 27, motor 39 engages draw line 43 through gear assembly 41, to move staging platform 27 away from facility 11 to the bow of cantilever 17. Rollers 35 turn along rails 37 to allow for easier movement of staging platform 27 relative to the side of cantilever 17. Staging platform 27 slides along rails 37 and wall 28 to a position farther away from facility 11 than opening 20, rig 19, and conductor casing 14.
Crane 24 offloads BOP 23 from staging platform 27 to vessel 25. Vessel 25 remains a greater distance away from facility 11 than conductor casing 14, which reduces collision dangers previously associated with loading an unloading a BOP from an offshore facility. Using crane 24 from vessel 25 allows the operator to continue using rig 19 for drilling operations rather than lifting and lowering BOP 23. Using crane 24 also allows vessel 25 to load and unload BOP 23 from a position that is not as close to conductor casing 14 as leg 15 was previously required when using rig 19 to load and unload BOP 23.
The description and figures are merely illustrative of various embodiments. While the invention has been shown in only some of its forms, it should be apparent to those skilled in the art that it is not so limited, but is susceptible to various changes without departing from the scope of the invention. For example, while the equipment being transferred by platform has been described as BOP 23, it will be readily apparent to those skilled in the art that staging platform 27 can be used for transferring a variety of wellhead equipment, like rams and swivels.
This nonprovisional patent application claims the benefit of co-pending, provisional patent application U.S. Ser. No. 60/515,342, filed on Oct. 29, 2003, which is hereby incorporated by reference in its entirety.
Number | Name | Date | Kind |
---|---|---|---|
3031167 | Roussel | Apr 1962 | A |
3043255 | Bauer et al. | Jul 1962 | A |
3177954 | Rand | Apr 1965 | A |
3189093 | de Vries | Jun 1965 | A |
3333562 | Deal, Jr. et al. | Aug 1967 | A |
3433024 | Diamond et al. | Mar 1969 | A |
3662822 | Wakefield, Jr. | May 1972 | A |
3699988 | Weber | Oct 1972 | A |
3739736 | Carreau et al. | Jun 1973 | A |
3740957 | McKenzie | Jun 1973 | A |
3766874 | Helm et al. | Oct 1973 | A |
3802209 | Weaver | Apr 1974 | A |
4007782 | Nybo et al. | Feb 1977 | A |
4081163 | Guinn et al. | Mar 1978 | A |
4090368 | Bell et al. | May 1978 | A |
4108318 | Rode et al. | Aug 1978 | A |
4208158 | Davies et al. | Jun 1980 | A |
4230190 | Guinn et al. | Oct 1980 | A |
4367796 | Bolding | Jan 1983 | A |
4401398 | Remson | Aug 1983 | A |
4658903 | Tateishi | Apr 1987 | A |
4716972 | Makinen et al. | Jan 1988 | A |
5139367 | Ingle | Aug 1992 | A |
5407302 | Springett et al. | Apr 1995 | A |
5490364 | Desai et al. | Feb 1996 | A |
5647443 | Broeder | Jul 1997 | A |
5697446 | Giannesini | Dec 1997 | A |
6481931 | Welsh | Nov 2002 | B1 |
6705414 | Simpson et al. | Mar 2004 | B2 |
6729804 | Roodenburg et al. | May 2004 | B1 |
6766860 | Archibald et al. | Jul 2004 | B2 |
7083004 | Roodenburg et al. | Aug 2006 | B2 |
Number | Date | Country | |
---|---|---|---|
20050092497 A1 | May 2005 | US |
Number | Date | Country | |
---|---|---|---|
60515342 | Oct 2003 | US |