The present invention relates to the field of bridge construction.
Bridges need replacement from time to time. This is often very expensive. Environmental concerns can complicate many bridge projects; a factor in this is that many bridges span watercourses and many jurisdictions discourage the placement of support works in and near watercourses.
A method for replacing a bridge forms one aspect of the invention. The bridge which may be replaced by the method is the type which includes a deck supported at its ends by a pair of spaced-apart concrete abutments, each abutment having a pair of wing walls. The method comprises the steps of: removing the deck and excavating a footing hole behind each abutment; casting a concrete footing in each footing hole; and providing a foundation pier on each footing. The method further comprises the step of providing a brace assembly and at least a pair of cambered beams. The beams are provided such that each beam spans between and is supported by the pair of piers and the beams are substantially parallel and coplanar. The brace assembly is provided to reinforce the camber of said beams. The method further comprises the step of placing, on each adjacent pair of beams, a plurality of precast deck elements, such that each deck element of said plurality spans the pair of beams, thereby to define at least transverse gaps between the deck elements and put the upper surfaces of the deck elements in compression in a transverse direction. The method further comprises the steps of grouting the gaps; and after the grout has cured, adjusting the brace assembly to reduce the camber of the beams and cause the upper surface of the deck elements to also be put into compression in a direction parallel to the beams, to form a crack-resistant cementitious deck.
According to another aspect of the invention, the abutments and wingwalls can be cut down in height prior to the providing step.
According to another aspect of the invention, in the providing step, the beams can be temporarily supported by jacks on the abutments; and while supported by the jacks, the beams can be secured to the piers.
According to another aspect of the invention, at each end of each beam there can be provided a bearing; and the piers can have provided therein sockets for receiving the bearings, such that, when the beams are temporarily supported by the jacks, each bearing is disposed in a respective socket.
According to another aspect of the invention, the beams can be secured to the piers by cementing the bearings into the sockets.
According to another aspect of the invention the brace assembly can comprise a brace subassembly for each beam, the brace subassembly being secured to said each beam prior to the providing step.
According to another aspect of the invention, at least three beams can be positioned to span the piers to define a pair of outer beams and at least one inner beam, and such that the deck elements define a longitudinal gap along each inner beam.
According to another aspect of the invention at least one of the deck elements can be a standard deck element, the standard deck element having four sides, two opposite sides of said four sides having a plurality of recesses therein and the other two sides having defined therein grooves.
According to another aspect of the invention the standard deck element can be planar and have a hook bar for each recess, the hook bar being in the form of a u-shaped rebar element, the open ends of the hook bar being cast in the standard deck element, the rebar lying substantially coplanar with the standard deck element and the looped end of said hook bar protruding into said each recess.
According to another aspect of the invention each beam can have on its upper convex surface a plurality of Nelson studs.
According to other aspects of the invention: each outermost beam can have the studs disposed in a single row and each inner beam, can have the studs disposed in a pair of rows; in the course of assembly, the looped-ends can be placed over the Nelson studs, thereby to provide a mechanical connection between the deck elements and beams; and closed hooks can be laid upon adjacent hook bars to mechanically connect laterally-adjacent Nelson studs.
According to another aspect of the invention, the pier can be a pre-cast concrete pier.
According to another aspect of the invention, the method can further comprise the step of: securing a pair of parapet walls to the deck.
According to another aspect of the invention, the deck can have a plurality of reinforcing members extending vertically therefrom; the parapet walls can be defined in part by precast cementitious elements, the precast elements having defined therein, for each reinforcing member, a bore, the bore having an irregular girth; and the parapet walls can be secured to the deck by: positioning the cementitious elements on the deck with each bore in receipt of the reinforcing member for which it is provided; and cementing the bores.
A bridge forms yet another aspect of the invention. The bridge comprises: a pair of spaced-apart concrete abutments; a cast in situ concrete footing behind each abutment; a pre-cast concrete foundation pier on each footing; at least a pair of substantially parallel and coplanar cambered beams, each beam spanning between and supported by the pair of piers; and on each adjacent pair of beams, a plurality of precast deck elements, each deck element spanning the pair of beams, the deck elements being grouted together, the upper surfaces of the deck elements being in compression in a direction transverse to the beams and in a direction parallel to the beams, to form a crack-resistant cementitious deck.
Advantages of the invention will become apparent to persons of ordinary skill in the art upon review of the appended claims and upon review of the following detailed description of an exemplary embodiment of the invention and the accompanying drawings, the latter being described briefly hereinafter.
The Bridge
A bridge 20 according to an exemplary embodiment of the invention is illustrated in
The abutments 22 are concrete, and spaced-apart across a watercourse.
The footings 24 are concrete, cast in situ, behind each abutment 22. Footing construction is a matter of routine to persons of ordinary skill in the art, and as such, details are neither required nor provided herein.
The piers 26 are pre-cast concrete, positioned one on each footing 24. Pier construction is a matter of routine to persons of ordinary skill in the art, and as such, details are neither required nor provided herein.
The beams 28 are substantially parallel and coplanar. Each beam 28 spans between the pair of piers 26. Parapet walls 31 are defined by pre-cast cementitious elements and also span between the pair of piers 26. The beams 28 are steel I-beams. The beams 28 and parapet walls 31 are adapted to carry their own loads, the loads of the deck elements 30 and any loads to be carried by the bridge 20. Load calculation is a matter of routine to persons of ordinary skill in the art, and as such, details are neither required nor provided herein. The parapet walls 31 shown extend to piers 26 and as such, piers 26 bear the loads of the beams 28, deck elements 30, parapet walls 31 and any loads carried by the bridge. The beams 28 are secured to the piers 26 by conventional bearings, indicated by 37 on
The deck elements 30 are precast concrete. As indicated in
Standard Deck Element
An exemplary embodiment of a standard deck element 30 is shown in solid line in
The concrete employed in the exemplary embodiment has the following physical properties:
Concrete having these performance characteristics can be readily produced by persons of ordinary skill in the art, and thus, is not described herein in detail.
Construction of the Bridge
Construction of the bridge shown in
Initial steps in the replacement process involve:
Demolition of decks, digging holes, casting footings and installing concrete piers are skills within the knowledge of persons of ordinary skill in the art, and as such, detailed description is neither required nor provided.
The remainder of the exemplary method involves the following steps set forth below in point form, and described fully in subsequent paragraphs.
Some flexibility in terms of the order of steps (i)-(vii) is permissible, but it is contemplated that the brace subassemblies will normally installed prior to the placement of the beams on the jacks, and removed after the deck grout has cured.
The purpose of the plurality of brace subassemblies, which collectively define a brace assembly, is to ensure that, after the deck elements are placed on the beams, the beams do not substantially sag; the brace assembly is sized accordingly. The manner of construction of such a brace assembly is a matter of routine to persons of ordinary skill in the art, and as such, detail is neither required nor provided. However, reference is made to
With respect to (ii), the beams are positioned on the piers such that each beam spans between the pair of piers and the beams are substantially parallel and coplanar. Normally, at least three beams are positioned to span the piers to define a pair of outer beams and at least one inner beam. The camber in the beams is such that each beam, when installed, is slightly higher at its midpoint than at its ends. Each beam has, on its upper convex surface, a plurality of Nelson studs: each outermost beam has the studs disposed in at least a single row and each inner beam has the studs disposed in a pair of rows. At the end of each beam, a conventional bearing is secured, with a depending anchor which projects into a socket of the pier. Temporary jacks 53 which temporarily support the beams 28 and permit beams 28 to be maintain level until the bearing is fully connected are indicated in
With respect to (iii), the cement holding the bearing is shown in
With respect to (iv) on each adjacent pair of beams 28, a plurality of precast deck elements 30 are placed, as indicated in
On the outermost beams of the bridge, longitudinal gaps 50 are present. Also, in the context of bridges having more than two beams, i.e. as in the usual case and as shown in
With steps (i)-(iv) complete, the gaps 48, 50 between the deck elements, i.e. along each beam, will be filled with grout 60, and the grout 60 will be allowed to cure. Thereafter, the brace assembly will be adjusted i.e. released, to generate a composite profile by reducing the camber of the beams 28, thereby to cause the upper surface of the deck elements 30 to also be put into compression in the direction Y parallel to the beams. These aforementioned biaxial compressive stresses tend to avoid crack propagation in the concrete upper surface. Once the stresses have been removed from the brace assembly, it will be removed. Temporary forms and foam inserts are used to hold the grout in place while it cures.
With respect to (vi),
With respect to (vii), once the pre-cast elements 51 have been lowered into place, a fluid cementious mixture is used to fill the bores 49. The irregular shape of the bores 49 ensure that the solidified mixture forms a solid plug, that resists extraction. This mechanically ties the pre-cast element 51 to the deck, such that parapet walls 31 define beams that substantially reinforcing the bridge deck against sagging.
With the parapet walls 31 in place, an impermeable waterproofing topping will advantageously be applied at least over the grout, as the upper surface of the grout over the longitudinal gaps is under tension and otherwise susceptible to cracks and associated water and salt infiltration, which would otherwise promote corrosion and generally reduce the expected lifespan of the structure.
Various dimensions in respect of this structure are as specified below, in mm:
Variants
Whereas but a single exemplary embodiment of the method is described herein, it will be evident that variations are possible without departing from the invention.
For example, whereas in the exemplary embodiment, it is indicated the brace subassemblies is positioned along with the beams, this is not necessary; the beams could readily be secured initially to the piers and then tensioned by the brace assembly.
As well, whereas a specific geometry for the standard deck element is described with reference to
As well, other deck elements can be utilized.
As well,
Further, whereas in the exemplary embodiment, the parapet walls are constructed out of precast elements, and extend only to the piers, variations are possible. The precast elements could extend beyond the piers, in which case some of the loads to be carried by the bridge could be carried by the adjacent earth. As well, the parapet walls could be cast in situ, in which case, this could require the bridge to be built more robustly, to carry the load of the concrete associated with the parapet walls until cured. The parapet walls could also be constructed otherwise than from cementitious materials, or conceivably omitted altogether for some applications. Further, whereas the parapet walls are indicated to be cemented to the bridge, it should be understood that materials other than cement could be used to file the bores and lock the parapet walls in place.
Accordingly, the invention should be understood as limited only by the accompanying claims, purposively construed.
Number | Date | Country | Kind |
---|---|---|---|
2702546 | Apr 2010 | CA | national |
2708769 | Jun 2010 | CA | national |
This application claims priority of U.S. Provisional Application 61/313,932 filed Mar. 15, 2010; U.S. Provisional Application 61/329,591 filed Apr. 30, 2010; Canadian Patent Application 2,702,546 filed Apr. 30, 2010; Canadian Patent Application 2,708,769 filed Jun. 3, 2010; and U.S. Provisional Application 61,351,589 filed Jun. 4, 2010. The contents of each of these applications are incorporated herein by reference.
Number | Name | Date | Kind |
---|---|---|---|
4493177 | Grossman | Jan 1985 | A |
4709456 | Iyer | Dec 1987 | A |
4710994 | Kishida et al. | Dec 1987 | A |
4972537 | Slaw, Sr. | Nov 1990 | A |
5301483 | Grossman | Apr 1994 | A |
5471694 | Meheen | Dec 1995 | A |
5617599 | Smith | Apr 1997 | A |
5655243 | Kim | Aug 1997 | A |
5850653 | Mufti | Dec 1998 | A |
6065257 | Nacey et al. | May 2000 | A |
6588160 | Grossman | Jul 2003 | B1 |
7296317 | Grace | Nov 2007 | B2 |
20040216249 | El-Badry | Nov 2004 | A1 |
20110138549 | He | Jun 2011 | A1 |
Number | Date | Country |
---|---|---|
01210510 | Feb 1988 | JP |
Number | Date | Country | |
---|---|---|---|
20110219554 A1 | Sep 2011 | US |
Number | Date | Country | |
---|---|---|---|
61313932 | Mar 2010 | US | |
61329591 | Apr 2010 | US | |
61351589 | Jun 2010 | US |