A construction methodology specially designed for the construction of bridges is proposed. It is based on clips placed along the deck-support beams for the placement of a lost form, slab, made by steel, commonly named precast metal deck (PMD) or steel in place (SIP). The bridge thus formed is also an object of the invention.
A bridge construction method is known in the state of the art in which several !-beams are placed in parallel, two longitudinal angular profiles are welded to clips embedded in the longitudinal edges of concrete beams. This process is done manually with the workers on top of the beams.
One of the problems is the location of the angular profiles should be done precisely according to the final camber of the beams, each profile on the bridge has its own elevation. In actual practice, once the beams have been positioned, some workers must go through the beams lengthwise, surveying the real elevation of the beams and then manually weld the angular profiles in the exact position. This involves a large amount of labor and time and, above all, a high risk of accident due to working at heights and on narrow structures. It is necessary to reduce this risk of accident, improve the construction time and the accuracy in the positioning of the slabs. The need of correctly welding the angular profiles to several clips, means that the workers need to stay for a long time close to the edge of the beam, crouched, so the chance of an accidents is relatively high. This process can be found in U.S. Pat. No. 9,279,244.
U.S. Pat. No. 5,218,795, where the form is supported on the beam by adjustable screws is cited as a close prior art. Another method is shown in U.S. Pat. No. 5,025,522, where a bar is placed on the upper surface of the beam for the placement of the slab. The applicant is also aware of GB2585534 and CN112411385, which are of lesser relevance. The applicant is not aware of any solution equivalent to the one claimed.
Due to all this, a construction method and special designed clips are proposed that allow for the easy, fast, and safe construction of bridges.
The beams that form the bridges in which the invention is applied are usually of the “I” type. However, it has to be considered that the method is applicable on any beam with a substantially horizontal upper part. In the figures I-beams have been shown, but the beams of the invention may be of square section, T-beams, C-beams . . . . The beams will usually be made of concrete, but steel beams are also applicable to the method.
The bridge construction method allows for the construction of a bridge formed by a series of beams, between which forms are placed. The forms are lost forms and are supported by angular profiles affixed to the beams.
The construction steps are as follows:
Optionally, first a set of clips are fixed to the edges of the upper surface of the beams. They can be welded to a metal beam or inserted in a concrete beam at the precast factory. The clips may create a series of threaded studs on the upper surface of the beam.
The correct position of the angular profiles is calculated according to the shape or position of the beams. This shape or position may be measured before the placement of the beams or after.
The effective height of each angular profile is determined according to the calculated positions. That is, each individual angular profile may be joined to the beam at a different height, or angle, regarding the top or lower surface of the beam.
Then, angular profiles are affixed to the clips, so that the angular profiles hang at the edges of the beams. If the clips are in place, the angular profiles are affixed to the clips. If not, a bolt gun can be used to directly attach the angular profile to the beam. Other fixing methods are possible. The angular profiles can be placed at the beam before or after it is raised to its final position.
Once the beam and the adjoining beam are placed on their supports (columns . . . ) to form the bearing structure of the bridge, the form is placed on the angular profiles, and concrete is cast on the structure thus formed.
The angular profile may be a “Z” profile. In that case, the height of the angular profile corresponds to the height of the middle part of the “Z” profile. Therefore, the “Z” profiles are made once their height is calculated, by plying a flat o “L” shaped profile.
The angular profile may be a “L” profile attached to a fastener, which in turn is affixed to the clip. In that case, the fasteners may be affixed to the clips with a set of nut and washer, or any fast method.
In a preferred embodiment, the individual height of each angular profile is calculated by surveying the beam at the precast factory.
In another preferred embodiment, the individual height of each angular profile is calculated once the beam is placed on its supports.
The invention is also the bridge formed with this method. This bridge is therefore formed by at least two beams, and a series of forms between any pair of adjacent beams. The forms are supported by angular profiles joined to the upper surface of the beams through a series of threaded protrusion carrying clips in said upper surface. On that upper surface a set of fasteners, affixed to the angular profiles, are joined.
Other variants and embodiments will be appreciated in the remainder of the specification.
To complement the description below and in order to provide a better understanding of the invention, a set of drawings is attached as an integral part of said description according to a preferred example of its practical embodiment. In those drawings, with an illustrative and non-limiting nature, the following has been represented:
The angular profiles (3) are disposed at the side of the beam (1), as shown in
In order to ensure the correct placement of the form (2), each fastener (5) is joined to the angular profiles (3) at different heights (see
As specially seen in
The “Z” profiles are disposed at the side of the beam (1), as shown in
The adjustment can be calculated by surveying the beam at the precast factory, so any error is measured and can be corrected. It can also be measured on site. In this case, once the beam (1) is placed on the columns, the position of the beam (1) is determined. A GPS, a system of radio beacons, a survey prism on the robot in combination with a total station for providing coordinates or any other high-precision system, as a 3D survey scanner to have the real elevation of the beam (1) can be used. This elevation is compared to the theoretical position of the beam (1) or the form (2). For example, using a BIM (Building Information Modeling) database can be used to find out the theoretical position of the beam (1) or the from (2) in the bridge manufacturing plans, or any other model may be used to calculate the theoretical position.
This knowledge allows to determine the distance between the edge of the beam (1) and the theoretical position of the form (2). Therefore, the distance between the edge of the beam (1) and the angular profile (3) can be defined at each point of the beam (1). Once those distances are calculated, the fasteners (5) can be joined to the angular profiles (3) at the right position or height. This way, the forms (2) are placed at exactly the right position, and so are the angular profiles (3) at each side (see
The third alternative (
As shown in the figures, the fastener (5) can be joined to the “L” profiles in several ways. They can be welded together, joined by a nut and bolt, adhered to each other . . . . The only two requisites are the exactitude of the placement and the mechanical resistance. In
The fasteners (5) are joined to the “L” profiles on the ground, so the workers can do their tasks safely. Once joined, they can be placed on the clips (4) and fixed with a nut and bolt. This manipulation on site is fast and can be done with powered tools, so the time spent on top of the beam (1) is greatly reduced. In a similar way, the “Z” profiles will be made on the ground, so the operations on top of the beam (1) are also reduced. The need to be on top of the beam can be eliminated if the angular profiles (3) are attached to the beams (1) even before erecting the beams (1). In this manner we reduce the risk of the worker to the minimum.
In
Number | Name | Date | Kind |
---|---|---|---|
4709435 | Stemler | Dec 1987 | A |
5025522 | Eskew | Jun 1991 | A |
5218795 | Horstketter | Jun 1993 | A |
8234827 | Schroeder, Sr. | Aug 2012 | B1 |
9279244 | Miller | Mar 2016 | B1 |
10280635 | Apostolopoulos | May 2019 | B1 |
20120291378 | Schroeder, Sr. | Nov 2012 | A1 |
20180298601 | Brodowski | Oct 2018 | A1 |
20200392719 | Brodowski | Dec 2020 | A1 |
Number | Date | Country |
---|---|---|
112411385 | Feb 2021 | CN |
102021108117 | Oct 2022 | DE |
2585534 | Jan 2021 | GB |