The present invention relates to a traffic crash attenuation system or crash cushion system. More particularly, the present invention relates to a system, method and apparatus for absorbing kinetic energy from an impacting vehicle in a controlled and safe manner. The system is used with roadside safety devices such as guardrails and median barrier end treatments. Even more specifically, the present invention is a system applied to shield bridge piers in the median of divided highways.
Current safety treatments at bridge pier sites include installation of guard rails on each side of the piers to form an envelope with W-beam bullnose ends. In some applications, crash cushions are installed on the two ends of the pier configuration with concrete walls constructed in the spaces between adjacent piers.
The present system consists of two energy-absorbing crash cushions combined with a tubular frame or structure to envelop the bridge piers. The crash cushions provide protection for end-on impacts while the tubular side structure shields the bridge piers from oblique impacts by errant vehicles. The tubular structure around the bridge piers is modular in nature and can be adjusted to accommodate different number, size, and spacing of bridge piers. The energy-absorbing capabilities of this new crash cushion are based on tube bursting technology described in U.S. Pat. Nos. 6,308,809 and 6,437,570 and incorporated herein by reference. This basic “guardrail envelope” treatment has some limitations which the present invention addresses.
Initial testing of prototypes of the present invention indicated snagging of the engine hood and the left-front fender on the upstream side of the bridge pier, thus causing the engine hood to be pushed backward and into the base of the windshield. This engine hood to windshield contact resulted in noticeable damage to the windshield. Based on the engine hood snag and resulting windshield damage, there was a potential for penetration of the occupant compartment during impact. The present invention avoids the hazards posed by interaction of vehicles with the bridge piers. This has been evidenced by crash testing utilizing a pickup truck weighing approximately 2,000 Kg impacting the present invention system at a speed of 100 km/h and at an angle of 25 degrees at the critical impact point (CIP) of the system.
Testing revealed that there must be sufficient space between the guardrail side structure and the adjacent face of any of the bridge piers to allow for the dynamic deflection of the guardrail. Without this space, an impacting vehicle may reach and impact the pier. An excessive space between the guardrail side structure and the pier, such as may occur when the guardrail is installed on a sloping grade away from the pier, may adversely effect the performance of the guardrail.
The present invention solves these problems of protecting vehicles from impacting bridge piers.
The tube bursting concept, as previously described in U.S. Pat. Nos. 6,308,809 and 6,437,570, operates on the principal that the energy associated with the initiation and propagation of cracks along the length of a tube can be carefully controlled and utilized to dissipate the energy of an impacting vehicle. This concept incorporates a tapered mandrel that is forced inside a tube of slightly smaller dimensions. As the tapered mandrel is forced inside the tube, hoop stresses develop in the tube, and these stresses then initiate and propagate cracks along the length of the tube. The cracks propagate in front of the mandrel such that there is no direct contact between the mandrel and the crack surfaces, thereby limiting friction.
When the crash cushion is impacted end-on by an errant vehicle, the impact head engages and interlocks mechanically with the front of the vehicle. As the vehicle proceeds forward, the impact head is pushed forward along the box-beam rail element. The impact head then contacts the post breaker beam and breaks off the first (end) steel breakaway post, thus releasing the cable anchorage. Shortly after the fracture of the first (end) post, the tapered mandrel contacts the end of the stage one energy-absorbing tube and is forced inside the tube. Cracks are initiated at the corners of the tube, the locations of which are controlled by notches cut into the end of the tube. As the vehicle proceeds forward and pushes the impact head into the tube, the cracks continue to propagate in front of the impact head until a) the vehicle comes to a controlled and safe stop; b) the vehicle yaws away and loses contact with the tubes; or c) the entire length of the stage one tube is used up.
Upon complete bursting of the stage one energy-absorbing tube, the process is repeated with the stage two energy-absorbing tube until, again, a) the vehicle comes to a controlled and safe stop; b) the vehicle yaws away and loses contact with the tube/terminal; or c) the stage two tube is used up.
For impacts that are end-on but at an angle, bursting of the tubular rail element proceeds until the vehicle yaws out and/or buckles the rail element and gates behind the crash cushion. Similarly, for impacts near the end of the crash cushion (e.g., between post nos. 1 and 2), the impacting vehicle breaks off the end post, buckles the rail element, and gates behind the crash cushion.
For impacts into the side of the crash cushion downstream of the beginning of the length-of-need (selected to be post no. 3 or 2.9 m (9 ft-6 in.) from the end of the crash cushion), the crash cushion contains and redirects the impacting vehicle. The cable attachment provides the necessary anchorage to resist the tensile forces acting on the rail element to contain and redirect the vehicle.
As will be described further below, for impacts into the side of the tubular frame shielding the bridge piers in the present inventive system, the tubular frame contains and redirects the impacting vehicle. Anchorage for the tubular frame is provided by two cable anchorage mechanisms, one on each side of the frame. In addition, the tubular frame is stiffened by a double rail, a reduced post spacing around the bridge piers, and diagonal end struts.
Turning to the figures, the present inventive crash cushion system is shown generally in several configurations.
The impact head assembly as fully described in the aforementioned patents includes: a front impact plate, a mandrel tube that inserts into the energy-absorbing tube, and a tapered mandrel. The front impact plate has a dimension of 508×508 mm (20×20 in.) with 51-mm (2-in.) wide protruded edges to provide a mechanical interlock with the impacting vehicle and to distribute the impact load. The mandrel tube may be fabricated from a 1168-mm (46-in.) long section of 114-mm×114-mm×4.8-mm (4½-in.×4½-in.× 3/16-in.) tube. The upstream end of the mandrel tube may be welded to the back of the impact plate. The downstream end of the mandrel tube is inserted into the stage one energy-absorbing tube 101 for a distance of approximately 559 mm (22 in.). A tapered end is formed on the downstream end of the mandrel tube by welding 9.5-mm (⅜-in.) thick bent plates to the end, which acts like a plunger to shear off bolts at connections to the posts and at splices. Two sets of 12.7-mm (½-in) thick straps are welded around the mandrel tube to control the clearance of the mandrel tube within the energy-absorbing tube) and the second set approximately 559 mm (22 in.) upstream from the plunger end. The cross-sectional dimension of the mandrel increases from 114 mm×114 mm (4½ in.×4½ in.) to a maximum of 168 mm×168 mm (6.6 in.×6.6 in.). The inside dimensions of the energy-absorbing tube is 146 mm×146 mm (5¾ in.×5¾ in.).
The stage one energy-absorbing tube 101 is approximately a 2438-mm (8-ft) long section of 152-mm×152-mm×3.2-mm (6-in.×6-in.×⅛-in.) box-beam rail. A cable anchor bracket 119 for one end of the anchor cable 117 is welded to the bottom of the rail. The cable anchor bracket consists of a 12.7-mm (½-in.) thick plate with a 29-mm (1⅛-in.) diameter hole for the cable anchor and reinforced with gussets. Two 64-mm×64-mm×6.4 mm (2.5-in.×2–5-in.×¼-in.) angles are welded 51 mm (2 in.) upstream from the downstream end of the tube for connection to the standard box-beam rail section. The stage two energy-absorbing tube 103 is approximately a 4940-mm (16-ft 2½-in). long section of 152-mm×152-mm×4.8-mm (6-in.×6-in.× 3/16-in.) box-beam rail.
Presently, the standard splice mechanism (
This initial splice mechanism requires the mandrel to shear off only two bolts at one time, thus greatly reducing the energy and associated force level. Also, the splice plates are outside of the tubers and do not interfere with the mandrel. However, the moment capacity of this splice mechanism is limited by the bolts connecting the splice plates to the angles, rendering the BEAT terminal design somewhat sensitive to redirectional type of impacts.
The present invention maintains the advantages of the early design, but provides a greater moment capacity of the splice and improving the performance of the barrier or crash system for redirectional types of impacts.
The splice mechanism of the present invention, shown in
The first post 1 in the system is a steel breakaway end post consisting of an upper section 1a and a lower section 1b (see
Post nos. 2 through 6 are standard 1829-mm (6-ft) long breakaway steel posts (see
Turning to
A post breaker 115, as shown in
The 6096-mm (20-ft) long by 6.4-mm (¼-in.) diameter steel cable 122 is used to retain the impact head 104 in case of a reverse direction impact. One end of the cable 122 is attached to the impact head and the other end of the cable is attached to the upstream end of the anchor cable 117 at the end post. The cable 122 is bundled and tied to the impact head to eliminate dangling of the cable.
Shielding of the bridge piers is provided by a tubular envelope or frame 106, as shown in
As shown in
The tubular frame forms an envelope 106 around the bridge piers. For each bridge pier, there is a double rail section 110 and 100′ on each side. The double rail sections are joined by connecting rail sections 112 and 112′ to form a continuous rail in front the bridge piers. Again remember that more than one double rail section maybe used. The two rails are then joined by angled struts 114 or 114′ on both ends to form a parallelogram. This may readily be seen in
The double rail sections 110 and 110′, as shown in
The double rail sections 110 at the bridge piers are joined with connecting rail sections 113 and 113′, also fabricated from TS 152-mm×152-mm×4.8-mm (6-in.×6-in.× 3/16-in.) structural tubing. The length of the connecting rail sections may vary, depending on the spacing between the bridge piers. Standard box-beam rail splice plates 110 are used to join the rail sections. Each connecting rail section has one or more supporting posts (post nos. 13 and 14 shown in
The two sides of the envelope 106 rails are joined by angled struts 114 and 114′ on both ends to form a parallelogram. The angle has been selected to be approximately 34 degrees. The angled strut is connected to the back rail with a bent splice 134 or 134′. The bent splice is fabricated from welding two short sections of TS 127-mm×127-mm×4.8-mm (5-in.×5-in.× 3/16-in.) structural tubing together. The welded end of each section have an angle of approximately 17 degrees for a total of approximately 34 degrees. The length on the short side of the section is 328 mm (12.9 in.). The angled strut 114 is attached to the front rail section 112 or 112′ and the stage two energy-absorbing tube 103 of the crash cushion with a Y connector 116 or 116′.
The Y connector 116, as shown in
Anchorage for the tubular frame is provided by a pair of cable anchorage 118 and 118′. The cable anchors are located inside of the tubular frame and attach to the box-beam rail 132 260-mm (10¼-in.) downstream of post no. 10 (
The overall system shown in the
Although the invention has been described with reference to a specific embodiment, this description is not meant to be construed in a limiting sense. On the contrary, various modifications of the disclosed embodiments will become apparent to those skilled in the art upon reference to the description of the invention. It is therefore contemplated that the appended claims will cover such modifications, alternatives, and equivalents that fall within the true spirit and scope of the invention.
This invention was made in part during work supported by a grant/contract Contract No. DTR557-98-C-00079 from DOT/RSPA/Volpe National Transportation System Center. The government may have certain rights in this invention.
Number | Name | Date | Kind |
---|---|---|---|
3672657 | Young et al. | Jun 1972 | A |
3674115 | Young et al. | Jul 1972 | A |
3779192 | Gonzalez | Dec 1973 | A |
3933111 | von Bose et al. | Jan 1976 | A |
3981486 | Baumann | Sep 1976 | A |
4009676 | Kura | Mar 1977 | A |
4338046 | Thomerson | Jul 1982 | A |
4655434 | Bronstad | Apr 1987 | A |
4674911 | Gertz | Jun 1987 | A |
4804296 | Smath | Feb 1989 | A |
4884919 | Moore | Dec 1989 | A |
5022782 | Gertz et al. | Jun 1991 | A |
5391016 | Ivey et al. | Feb 1995 | A |
6505820 | Sicking et al. | Jan 2003 | B1 |
6536985 | Albritton | Mar 2003 | B1 |
6715735 | Bligh et al. | Apr 2004 | B1 |
Number | Date | Country | |
---|---|---|---|
20050023095 A1 | Feb 2005 | US |