Claims
- 1. A method for installing a platform below the deck of a bridge for supporting persons performing work on the bridge and for collecting debris resulting from the work, said method comprising the steps of:
- a) providing a plurality of cables;
- b) providing a pair of compression clamp assemblies each comprising a pair of members for contacting opposite surfaces of a bridge structure and compression force applying means connected to the members for forcing the members against the opposite surfaces of the bridge structure;
- c) installing said pair of compression clamp assemblies on a corresponding pair of spaced-apart bridge structures at locations below the deck of the bridge by placing the members in contact with the opposite surfaces of the bridge structures and forcing the members against the opposite surfaces of the bridge structures by means of the compression force applying means;
- d) connecting said cables to said compression clamp assemblies so as to secure the cables to the bridge so that they extend along the bridge and in spaced relation to each other and in a plane substantially parallel to the deck at a distance below the portion of the bridge upon which work is to be performed;
- e) providing a plurality of flooring sections each comprising corrugated elongated rectangular decking panels wherein the corrugations extend along the length of the panel and each flooring section having at least one opening therein;
- f) placing the flooring sections on the cables with the corrugations extending transversely of the cables and with the sections in end-to-end and side-to-side contacting relation to each other; and
- g) fastening the flooring section to the cables by means of releasable connector assemblies each engaging the flooring sections and a corresponding one of the cables by placing a first part of a connector assembly so that a portion thereof is in engagement with the upper surface of the flooring section and another portion thereof is in engagement with the cable through an opening in the flooring section, placing a second part of the connector assembly in engagement with the upper surface of the flooring section and releasably connecting the first and second parts together so that each individual flooring section can be removed to allow access through the flooring.
- 2. A method according to claim 1, wherein the cables are secured to neighboring piers of the bridge so that the platform extends between the neighboring piers.
- 3. A method according to claim 1, wherein said flooring sections are arranged in end-to-end overlapping relation transversely of the cables and in side-to-side overlapping relation longitudinally of the cables.
- 4. A method according to claim 1 further including providing a plurality of auxiliary supporting cables, connecting one end of each auxiliary supporting cable to a selected one of said connector assemblies and securing the other end of each auxiliary supporting cable to the bridge to provide additional support for said platform.
- 5. A method according to claim 1 further including providing tarpaulin enclosures extending between said platform and the bridge for defining region between said platform and the bridge which enhances containment of the debris.
- 6. A method according to claim 1 further including disconnecting one or more connector assemblies and removing one or more flooring sections to allow access through the flooring.
- 7. A method for installing a platform below the deck of a bridge for supporting persons performing work on the bridge and for collecting debris resulting from the work, said method comprising the steps of:
- a) providing a plurality of cables;
- b) providing a pair of compression clamp assemblies each comprising a pair of members for contacting opposite surfaces of a bridge structure and compression force applying means connected to the members for forcing the members against the opposite surfaces of the bridge structure;
- c) installing said pair of compression clamp assemblies on a corresponding pair of spaced-apart bridge structures at locations below the deck of the bridge by placing the members in contact with the opposite surfaces of the bridge structures and forcing the members against the opposite surfaces of the bridge structures by means of the compression force applying means;
- d) connecting said cables to said compression clamp assemblies so as to secure the cables to the bridge so that they extend along the bridge and in spaced relation to each other and in a plane substantially parallel to the deck at a distance below the portion of the bridge upon which work is to be performed;
- e) providing a plurality of flooring sections each comprising elongated rectangular decking panels and each flooring section having at lease one opening therein;
- f) placing the flooring sections on the cables extending transversely of the cables and with the sections in end-to-end and side-to-side contacting relation to each other; and
- g) fastening the flooring section to the cables by means of releasable connector assemblies each engaging the flooring sections and a corresponding one of the cables by placing a first part of a connector assembly so that a portion thereof is in engagement with the upper surface of the flooring section and another portion thereof is in engagement with the cable through an opening in the flooring section, placing a second part of the connector assembly in engagement with the upper surface of the flooring section and releasably connecting the first and second parts together so that each individual section can be removed to allow access through the flooring.
- 8. A method according to claim 7 further including providing a plurality of auxiliary supporting cables, connecting one end of each auxiliary supporting cable to a selected one of said connector assemblies and securing the other end of each auxiliary supporting cable to the bridge to provide additional support for said platform.
- 9. A method according to claim 7 further including providing tarpaulin enclosures extending between said platform and the bridge for defining a region between said platform and the bridge which enhances containment of the debris.
- 10. A method according to claim further including disconnecting one or more connector assemblies and removing one or more flooring sections to allow access through the flooring.
Parent Case Info
This is a continuation divisional of copending application(s) Ser. No. 08/506,685 filed on Jul. 25, 1995, U.S. Pat. No. 5,730,248, issued Mar. 24,1998.
US Referenced Citations (3)
Divisions (1)
|
Number |
Date |
Country |
Parent |
506685 |
Jul 1995 |
|