The present technology relates to a charger, a charging system, and a charging method. More particularly, the present technology relates to a charger, a charging system, and a charging method using power generated by natural energy.
Recently, effectively utilizing power (hereinafter referred to as “natural energy power”) generated by natural energy such as sunlight, wind power, water power, or ground heat has become important in a point of view of environmental protection. The natural energy is also referred to as green energy or renewable energy. Because an amount of power generation of natural energy power usually depends upon the weather, a power transmission scheme using stably supplied commercial power regardless of the weather in combination with natural energy power is commonly used in power transmission.
For example, a charging apparatus that performs charging by commercial power until a remaining capacity of a secondary battery reaches a constant amount when the secondary battery is charged, and performs charging by a solar battery after the remaining capacity reaches the constant amount has been proposed (see Patent Literature 1). This charging apparatus estimates the remaining capacity from a battery voltage or a charging time in charging control. Specifically, the charging apparatus continues charging by the commercial power by determining that the remaining capacity does not reach the constant amount when the battery voltage is less than a threshold value or when a time for charging by commercial power is less than a predetermined time.
However, the natural energy power is not effectively used in the above-described related art. For example, even when there is ample time until the time charging should be completed, the charging apparatus performs the charging by commercial power as long as the remaining capacity does not reach the constant amount. In the charging apparatus described above, there is a problem in that natural energy power generated by power generation is useless if unused in charging of the secondary battery within a period until the remaining capacity reaches the constant amount.
The present technology has been made in view of the above-described circumstances, and an object of the present technology is to provide a charger that effectively uses natural energy power when there is ample time until the time charging should be completed.
According to the first aspect of the present invention in order to achieve the above-mentioned object, there is provided a charger including: a setting section for setting a completion time that is a time at which charging of a secondary battery is completed; an output value acquisition section for acquiring an output value of a voltage or a current from a natural energy power supply apparatus, which is a power supply apparatus that generates natural energy power from natural energy; a power amount acquisition section for acquiring an amount of power that is supplied until the charging of the secondary battery is completed; a predicted time calculation section for calculating a time at which the charging of the second battery is completed by only the natural energy power based on the output value and the power amount as a predicted time; and a control section for causing the secondary battery to be charged with only the natural energy power when the predicted time is earlier than the completion time, and a charging method using the charger. Thereby, there is also provided a function of causing the secondary battery to be charged with only the natural energy power when the predicted time is earlier than the completion time.
According to the first aspect of the present invention, the control section may cause the secondary battery to be charged with power generated by a power supply apparatus other than the natural energy power supply apparatus when the predicted time is the completion time or later. Thereby, there is also provided a function of causing the secondary battery to be charged with the power generated by the power supply apparatus other than the natural energy power supply apparatus when the predicted time is the completion time or later.
According to the first aspect of the present invention, the control section may cause the secondary battery to be charged by further supplying the natural energy power when the predicted time is the completion time or later. Thereby, there is also provided a function of further supplying the natural energy power to the secondary battery when the predicted time is the completion time or later.
According to the first aspect of the present invention, the charger may further include a charging data generation section for generating and outputting information indicating a charging capacity of the secondary battery by the natural energy power and a charging capacity of the secondary battery by power other than the natural energy power as charging data. Thereby, there is also provided a function of outputting the charging data indicating the charging capacity of the secondary battery by the natural energy power and the charging capacity of the secondary battery by the power other than the natural energy power.
According to the first aspect of the present invention, the power supply apparatus other than the natural energy power supply apparatus may receive alternating current (AC) power in which a power supply identification signal for identifying a supply source of power is superimposed on an AC waveform, the charger may further include a separation section for separating the power supply identification signal from the AC waveform, and the charging data generation section may generate the charging data based on the separated power supply identification signal. Thereby, there is also provided a function of generating the charging data based on the power supply identification signal.
According to the first aspect of the present invention, the control section may cause the secondary battery to be charged with only the natural energy power when a remaining time, which is a time from a current time to the completion time, is greater than or equal to a predetermined time. Thereby, there is also provided a function of causing the secondary battery to be charged with only the natural energy power when the remaining time is greater than or equal to the predetermined time.
According to the first aspect of the present invention, the control section may cause the secondary battery to be charged with only the natural energy power when a remaining capacity of the secondary battery is greater than or equal to a predetermined capacity. Thereby, there is also provided a function of causing the secondary battery to be charged with only the natural energy power when the remaining capacity is greater than or equal to the predetermined capacity.
In addition, according to the first aspect, the setting section may further set weather forecast data indicating forecast weather, the output value acquisition section may include a predicted value storage section for storing a predicted value for the output value for each weather and a predicted value acquisition section for reading the predicted value corresponding to the weather indicated by the weather forecast data from the predicted value storage section, and the predicted value calculation section may calculate the predicted time based on the read predicted value and the power amount. Thereby, there is also provided a function of calculating the predicted time based on the predicted value corresponding to the forecast weather and the power amount.
According to the second aspect of the present invention in order to achieve the above-mentioned object, there is provided a charging system including: a charger; and a battery pack, wherein the charger includes: a setting section for setting a completion time that is a time at which charging of a secondary battery is completed; an output value acquisition section for acquiring an output value of a voltage or a current from a natural energy power supply apparatus, which is a power supply apparatus that generates natural energy power from natural energy; a power amount acquisition section for acquiring an amount of power that is supplied until the charging of the secondary battery is completed; a predicted time calculation section for calculating a time at which the charging of the second battery is completed by only the natural energy power based on the output value and the power amount as a predicted time; a control section for causing the secondary battery to be charged with only the natural energy power when the predicted time is earlier than the completion time and causing the secondary battery to be charged with power generated by a power supply apparatus other than the natural energy power supply apparatus when the predicted time is the completion time or later; and a charging data generation section for generating and outputting information indicating a charging capacity of the secondary battery by the natural energy power and a charging capacity of the secondary battery by power other than the natural energy power as charging data, and wherein the battery pack includes: a charging data storage section for storing the output charging data; and the secondary battery. Thereby, there is also a function of causing the secondary battery to be charged with only the natural energy power when the predicted time is earlier than the completion time and storing the charging data indicating the charging capacity of the secondary battery by the natural energy power and the charging capacity of the secondary battery by the power other than the natural energy power.
According to the second aspect of the present invention, the power supply apparatus other than the natural energy power supply apparatus may receive AC power in which a power supply identification signal for identifying a supply source of power is superimposed on an AC waveform, the charger may further include a separation section for separating the power supply identification signal from the AC waveform, and the charging data generation section may generate the charging data based on the separated power supply identification signal. Thereby, there is also provided a function of generating the charging data based on the power supply identification signal.
According to the second aspect of the present invention, the charging system may further include a display section for displaying the charging capacity of the secondary battery by the natural energy power and the charging capacity of the secondary battery by the power other than the natural energy power based on the charging data. Thereby, there is also provided a function of displaying the charging capacity of the secondary battery by the natural energy power and the charging capacity of the secondary battery by the power other than the natural energy power in a table.
According to the present technology, there is an excellent effect in that natural energy power is effectively used when there is ample time until the time charging should be completed.
Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the appended drawings. Note that, in this specification and the drawings, elements that have substantially the same function and structure are denoted with the same reference signs, and repeated explanation is omitted.
Hereinafter, modes (hereinafter referred to as embodiments) for carrying out the present technology will be described. Description will be given in the following order.
1. First Embodiment (Charging Control: Example in which Completion Time Is Compared to Predicted Time)
2. Second Embodiment (Charging Control: Example in which Remaining Time and Remaining Battery Capacity Are Monitored)
3. Third Embodiment (Charging Control: Example in which Weather Forecast Data Is Used)
4. Fourth Embodiment (Charging Control: Example in which Metadata Is Generated)
5. Fifth Embodiment (Charging Control: Example in which Power Supply Identifier Is Acquired)
6. Sixth Embodiment (Charging Control: Example in which Charging Is Performed via Electronic Device)
7. Modified Example
The solar battery 110 generates natural energy power from solar energy. The solar battery 110 supplies the generated natural energy power to the boost converter 310. The power outlet 210 supplies AC power to the AC adapter 330. This AC power is commercial power generated from combustion energy of petroleum or the like, not natural energy power.
The boost converter 310 boosts a voltage of the DC power to a constant voltage. In detail, the boost converter 310 receives the natural energy power from the solar battery 110, converts its voltage into a constant voltage, and outputs the constant voltage to the diode 320. The converted voltage is set to a voltage that is higher than a battery voltage Vb of the battery 710. The diode 320 is an element for passing a current in only one direction. An anode of the diode 320 is connected to the boost converter 310, and a cathode is connected to the charging circuit 500. Thus, backflow of the current from the charging circuit 500 to the boost converter 310 is prevented. A direct current (DC) from the solar battery 110 is supplied to the charging circuit 500 via a signal line 802 by way of the diode 320.
The AC adapter 330 converts the AC power output from the power outlet 210 into DC power. The AC adapter 330 supplies the DC power after the conversion to the charging circuit 500 via a signal line 803.
The completion time setting section 400 sets a time (hereinafter referred to as “completion time Ts”) at which charging of the battery 710 should be completed. In the setting of the completion time Ts, for example, a user inputs a time until the charging is completed based on a current time Tc. The completion time setting section 400 acquires the current time Tc, and sets the completion time Ts by adding the input time to the current time Tc. The current time Tc is acquired, for example, in units of hours, minutes, and seconds. The set completion time Ts is output to the charging circuit 500 via a signal line 801.
The charging circuit 500 charges the battery 710 by controlling the charger 300. Specifically, the charging circuit 500 determines whether or not the charging of the battery 710 will be completed by the completion time Ts by supplying only the natural energy power to the battery 710. When the completion is determined, the charging circuit 500 charges the battery 710 with only the natural energy power. When the completion is not determined, the charging circuit 500 charges the battery 710 with the natural energy power and power of an AC power supply (that is, the power outlet 210).
The solar battery 110 is an example of a natural energy power supply apparatus disclosed in the claims. The completion time setting section 400 is an example of a setting section disclosed in the claims. The battery 710 is an example of a secondary battery disclosed in the claims.
The output current measurement section 510 measures a value of an output current Ig output from the solar battery 110 via the signal line 802. As a unit of the measured value, for example, milliamperes (mA) are used. The output current measurement section 510 outputs the measured value of the output current Ig to the predicted time calculation section 530 via a signal line 811.
The power amount acquisition section 520 acquires an amount Q of power that should be supplied until charging of the battery 710 is completed. As a unit of the power amount Q, for example, milli-watt-hours (mWh) are used. A method of acquiring the power amount Q will be described later. The power amount acquisition section 520 outputs the acquired power amount Q to the predicted time calculation section 530 via a signal line 813. In addition, the power amount acquisition section 520 measures the battery voltage Vb of the battery 710, and outputs its voltage value to the charging completion determination section 640 via a signal line 812. As a unit of the battery voltage Vb, for example, volts (V) are used.
The predicted time calculation section 530 calculates a time (hereinafter referred to as “predicted time Tg”) at which the charging of the battery 710 will be completed by only the natural energy power. The predicted time Tg is calculated, for example, in units of seconds. Specifically, the predicted time calculation section 530 receives values of the output current Ig and the power amount Q from the output current measurement section 510 and the power amount acquisition section 520. The predicted time calculation section 530 divides a value obtained by converting the unit of the power amount Q into milli-ampere-hours (mAh) by the output current Ig, adds the current time Tc to the value obtained by the division, and designates a time after the addition as the predicted time Tg. The predicted time calculation section 530 outputs the calculated predicted time Tg to the comparison section 610 via a signal line 814.
The switch 650 opens and closes a signal line between the AC adapter 330 and the battery 710 according to control of the power transmission control section 630. The switch 650 closes the signal line, so that power from the AC adapter 330 is supplied to the battery 710. The switch 650 opens the signal line, so that the power supply from the AC adapter 330 is interrupted. One terminal of the switch 650 is connected to the AC adapter 330, and the other terminal is connected to the switch 660.
The switch 660 opens and closes the signal line between the power supply (that is, the solar battery 110 and the power outlet 210) and the battery 710 according to control of the charging completion determination section 640. The switch 660 closes the signal line, so that power from the power supply is connected to the battery 710. The switch 660 opens the signal line, so that the power supply to the battery 710 is interrupted. One terminal of the switch 660 is connected to the switch 650 and the diode 320, and the other terminal is connected to the battery 710.
The comparison section 610 compares the completion time Ts to the predicted time Tg. The comparison section 610 outputs the comparison result to the power transmission control section 630.
The control cycle timer 620 counts a time within a control cycle. Here, the control cycle is a cycle for determining whether or not to switch a charging scheme. For example, the control cycle is set to 60 sec, and the control cycle timer 620 counts the time within the control cycle in units of seconds.
The power transmission control section 630 determines whether or not to switch the charging scheme for each control cycle, and switches the charging scheme based on the determination result. Specifically, the power transmission control section 630 refers to a timer value Tc of the control cycle timer 620, and refers to the comparison result of the comparison section 610 if the timer value Tc is a predetermined value (for example, 60 sec). When the comparison result indicates that the predicted time Tg is earlier than the completion time Ts (that is, when the charging will be completed by only the natural energy power by the completion time Ts), the power transmission control section 630 causes the switch 650 to open the signal line. As a result, only the natural energy power from the solar battery 110 is supplied to the battery 710. On the other hand, when the comparison result indicates that the predicted time Tg is the completion time Ts or later (that is, when the charging will not be completed by only the natural energy power by the completion time Ts), the power transmission control section 630 causes the switch 650 to close the signal line. As a result, power from the solar battery 110 and the AC adapter 330 is supplied to the battery 710.
The charging completion determination section 640 determines whether or not the charging of the battery 710 has been completed for each control cycle. Specifically, the charging completion determination section 640 refers to the timer value Tc of the control cycle timer 620, and determines whether or not the charging has been completed based on a value of the battery voltage Vb measured by the power amount acquisition section 520 if the timer value Tc is a predetermined value (for example, 60 sec). For example, if the battery voltage Vb is greater than or equal to a predetermined threshold value Vth, the charging completion determination section 640 determines that the charging of the battery 710 has been completed. When determining that the charging has been completed, the charging completion determination section 640 ends the charging by causing the switch 660 to open the signal line. When determining that the charging has not been completed, the charging completion determination section 640 continues the charging by causing the switch 660 to close the signal line.
The output current measurement section 510 is an example of an output value acquisition section disclosed in the claims.
The battery voltage measurement section 521 measures the battery voltage Vb. The battery voltage measurement section 521 outputs a measured voltage value to the power amount calculation section 522 and the charging completion determination section 640.
In the charging rate conversion table 523, the battery voltage Vb and the charging rate R are associated and stored. The charging rate R is a rate of the remaining capacity to the total capacity of the battery 710, and an example of a unit of the charging rate is percent (%). The battery voltage Vb and the charging rate R measured in advance are associated and stored in the charging rate conversion table 523.
The power amount calculation section 522 calculates the power amount Q from the battery voltage Vb. Specifically, first, the power amount calculation section 522 reads the charging rate R corresponding to the battery voltage Vb from the charging rate conversion table 523. The power amount calculation section 522 calculates the power amount Q by substituting the read charging rate R into the following Expression (1).
Q[mWh]=C[mWh](1−R[%]/100) (1)
In the above-described Expression (1), C is the total capacity of the battery 710. The power amount calculation section 522 outputs the calculated power amount Q to the predicted time calculation section 530.
An operation example of the charger 300 will be described with reference to
The charger 300 determines whether or not a constant time (for example, 60 sec) has elapsed (step S970). If the constant time has not elapsed (step S970: No), the charger 300 returns to step S970. If the constant time has elapsed (step S970: Yes), the charger 300 determines whether or not the charging has been completed (step S980). If the charging has not been completed (step S980: No), the charger 300 returns to step S910. If the charging has been completed (step S980: Yes), the charger 300 ends the charging.
As described above, according to the first embodiment of the present technology, if the completion time Ts is set, the charging circuit 500 calculates the predicted time Tg at which charging of the battery 710 will be completed by only the natural energy power based on the output current Ig and the power amount Q. When the predicted time Tg is earlier than the completion time Ts, the charging circuit 500 charges the battery 710 with only the natural energy power. According to this configuration, when there is ample time until the time the completion time Ts is reached, the natural energy power is effectively used because the battery 710 is charged with only the natural energy power.
In addition, the charging circuit 500 reliably completes the charging by the completion time Ts because the charging is performed with the power from the AC power supply and the natural energy power when the predicted time Tg is the completion time Ts or later.
Although the charger 300 performs the charging with the natural energy power generated by the solar battery 100, the charging may be performed with natural energy power generated by a power supply apparatus other than the solar battery 110. For example, the charger 300 may use the natural energy power generated by a wind power generation apparatus or a water power generation apparatus.
In addition, although the charger 300 performs constant-voltage charging and measures the output current Ig from the solar battery 110, the charger 300 may perform constant-current charging and measure an output voltage from the solar battery 110. In this case, the predicted time calculation section 530 calculates the predicted time Tg from the measured output voltage and the power amount Q.
In addition, although the power amount acquisition section 520 reads the charging rate R corresponding to the battery voltage Vb from the charging rate conversion table 523, it is possible to define a relational expression indicating a relationship between the battery voltage Vb and the charging rate R and obtain the charging rate R by a calculation based on the relational expression.
In addition, although the power amount acquisition section 520 calculates the power amount Q from the charging rate R, it is possible to provide a table storing a pre-calculated power amount Q for each battery voltage Vb instead of the charging rate conversion table 523, and read the power amount Q from the table.
In addition, although the charging completion determination section 640 determinates whether or not the charging has been completed by comparing the battery voltage Vb to a threshold value, it is possible to determine whether or not charging by another scheme has been completed based on characteristics of the battery 710. For example, when the battery 710 has a characteristic that a battery voltage drops to a small extent if full charge is reached, the charging completion determination section 640 can use a −ΔV control scheme of ending the charging when the voltage drop (−ΔV) has been detected. Alternatively, when there is a characteristic that heat is generated if the battery 710 is close to the full charge, the charging completion determination section 640 can use a temperature detection control scheme of measuring a temperature of the battery 710 and ending the charging when the temperature has reached a constant value.
Next, the second embodiment of the present technology will be described with reference to
The remaining time determination section 670 determines whether or not the remaining time Tr is greater than or equal to a predetermined set time (for example, 12 hr). The remaining time determination section 670 outputs the determination result to the power transmission control section 631.
The remaining battery capacity determination section 680 determines whether or not the remaining battery capacity Cr is greater than or equal to a predetermined set capacity (for example, a capacity of 10% of the total capacity). An example of a unit of the remaining battery capacity Cr is mWh. The remaining battery capacity determination section 680 outputs the determination result to the power transmission control section 631.
The power transmission control section 631 causes the charging to be performed with only natural energy power when the remaining time Tr is greater than or equal to a set time, the remaining battery capacity Cr is greater than or equal to the set capacity, and the predicted time Tg is earlier than the completion time Ts. Otherwise, the power transmission control section 631 causes the charging to be performed by the natural energy power and power from the AC power supply.
The operation example of the charger 300 according to the second embodiment will be described with reference to
If the predicted time Tg is calculated (step S953), the power transmission control section 631 determines whether or not the remaining time Tr is greater than or equal to the set time (step S954). When the remaining time Tr is greater than or equal to the set time (step S954: Yes), the power transmission control section 631 determines whether or not the remaining battery capacity Cr is greater than or equal to the set capacity (step S955). When the remaining battery capacity Cr is greater than or equal to the set capacity (step S955: Yes), the power transmission control section 631 determines whether or not the predicted time Tg is earlier than the completion time Ts (step S956). The case in which the remaining time Tr is less than the set time (step S954: No), the remaining battery capacity Cr is less than the set capacity (step S955: No), or the predicted time Tg is the completion time Ts or later (step S956: No) will be described. In this case, the power transmission control section 631 causes the battery 710 to be charged with power from the solar battery 110 and the AC power supply (step S958).
According to the second embodiment of the present technology as described above, the power transmission control section 631 causes the battery 710 to be charged with the power from the solar battery 110 and the AC power supply when the remaining time Tr is less than the set time. Thereby, the charging is prevented from not being completed by the completion time Ts.
In addition, when the remaining battery capacity Cr is less than the set capacity, the power transmission control section 631 causes the battery 710 to be charged with the power from the solar battery 110 and the AC power supply. Thereby, a charging time until the set capacity is reached is shortened and the convenience of the user is improved.
Next, the third embodiment of the present technology will be described with reference to
The completion time setting section 402 further sets weather forecast data in addition to a completion time Ts. The weather forecast data is information indicating a forecast period and weather forecast in the forecast period. For example, when fine weather is forecast on January 1, weather forecast data indicating “January 1” as the forecast period and “Fine” as the weather is set. The completion time setting section 402 outputs the set weather forecast data to the function acquisition section 511 via a signal line 805.
The function table 512 stores a function representing characteristics of a predicted output current Ig for each weather. Because an amount of power generation of the solar battery 110 increases/decreases according to an amount of sunlight, a value of the output current Ig generally increases according to the passage of time from early morning to midday and decreases according to the passage of time from midday to evening. It is possible to approximate a time-series change in a value of the predicted output current Ig to a function (for example, a quadratic function) of the time t based on the characteristics of the output current Ig. In addition, the amount of sunlight fluctuates according to weather. Thus, a different function is defined for each weather and stored in the function table 512.
The function acquisition section 511 acquires a function Ig(t) corresponding to weather. Specifically, when acquiring weather forecast data, the function acquisition section 511 reads the function Ig(t) corresponding to weather indicated by the weather forecast data from the function table 512 via a signal line 915. The function acquisition section 511 outputs the read function Ig(t) and a forecast period indicated by the weather forecast data to the predicted time calculation section 531 via a signal line 916.
Upon receipt of the function Ig(t) and the forecast period, the predicted time calculation section 531 calculates the predicted time Tg from the function Ig(t). Specifically, the predicted time calculation section 531 calculates a time t at which a value of a power amount into which an integral value of Ig(t) in a period until the forecast period has elapsed from the current time Tc is converted is equal to a power amount Q. If the power amount corresponding to the integral value within the forecast period is less than the power amount Q, the predicted time calculation section 531 calculates a time t at which a power amount corresponding to a sum of the integral value of the function Ig(t) until the forecast period has elapsed and the integral value of the function Ig(t) after the forecast period has elapsed is equal to the power amount Q. The predicted time calculation section 531 designates a value obtained by adding the calculated time t to the current time Tc as the predicted time Tg. On the other hand, when the function Ig(t) has not been received, the predicted time calculation section 531 calculates the predicted time Tg from a measured output current Ig.
The function acquisition section 511 is an example of a predicted value acquisition section disclosed in the claims. The function table 512 is an example of a predicted value storage section disclosed in the claims.
The operation example of the charger 300 according to the third embodiment will be described with reference to
The charging circuit 502 determines whether weather forecast data has been acquired (step S951). If the weather forecast data has been acquired (step S951: Yes), the predicted time calculation section 531 calculates the predicted time Tg based on the function Ig(t) corresponding to weather indicated by the weather forecast data (step S952). If the weather forecast data has not been acquired (step S951: No), the predicted time calculation section 531 calculates the predicted time Tg based on a measured output current Ig (step S953). After step S952 or S953, the control section 600 determines whether or not the predicted time Tg is earlier than the completion time Ts (step S956).
As described above, according to the third embodiment of the present technology, if the weather forecast data is set, the charging circuit 502 reads a predicted value corresponding to the weather indicated by the weather forecast data from the function table 512, and calculates the predicted time Tg based on the predicted value and the power amount Q. Thereby, the charging circuit 502 can more accurately calculate the predicted time Tg based on fluctuation in natural energy power according to the weather.
Although the weather forecast data is configured to be input by the user, the charger 300 can be configured to acquire the weather forecast data by performing wireless or wired communication.
In addition, although the charging circuit 502 is configured to store the function of the output current Ig for each weather, the charging circuit 502 can be configured to store a predicted value for each weather instead of the function. For example, the charging circuit 502 can store an average value or a median value of the output current Ig for each weather.
In addition, the charging circuit 502 is configured to include both a set of the function acquisition section 511 and the function table 512 and the output current measurement section 510. However, the charging circuit 502 can be configured to include only one of the set of the function acquisition section 511 and the function table 512 and the output current measurement section 510.
Next, the fourth embodiment of the present technology will be described with reference to
The charging circuit 503 generates information indicating a charging capacity by natural energy power and a charging capacity by power other than the natural energy power as metadata. The charging circuit 503 outputs the metadata to the memory 720 via a signal line 806. The memory 720 stores the metadata.
The metadata stored in the memory 720 is read by an electronic device 750 in which the battery pack 703 is designated as a power supply. If the battery pack 703 is attached, the electronic device 750 reads the metadata from the memory 720, and displays the charging capacity by the natural energy power and the charging capacity by power other than the natural energy power based on the metadata.
The metadata is an example of charging data disclosed in the claims. The memory 720 is an example of a charging data storage section disclosed in the claims. The electronic device 750 is an example of a display section disclosed in the claims.
The metadata generation section 540 generates and outputs metadata. In detail, the metadata generation section 540 acquires a switching signal for controlling a switch 650 from a power transmission control section 630 via a signal line 831. In this switching signal, for example, a value of “1” is set when the switch 650 is caused to close the signal line and a value of “0” is set when the switch 650 is caused to open the signal line. In addition, the metadata generation section 540 acquires a control signal for controlling a switch 660 from a charging completion determination section 640 via a signal line 832. In this control signal, for example, a value of “1” is set when the switch 660 is caused to close the signal line and a value of “0” is set when the switch 660 is caused to open the signal line. Further, the metadata generation section 540 acquires a measured value of an output current Ig from an output current measurement section 510, and acquires a timer value Tc via a signal line 833. During charging with power from a solar battery 110, the metadata generation section 540 adds a value obtained by integrating the timer value Tc with the measured value of the output current Ig to a charging capacity by natural energy power. In addition, during charging with power from an AC power supply, the metadata generation section 540 adds a value obtained by integrating the timer value Tc with an output current of an AC adapter 330 to a charging capacity by power other than the natural energy power. The metadata generation section 540 generates metadata indicating each charging capacity and outputs the generated metadata to the memory 720.
The metadata generation section 540 is an example of a charging data generation section disclosed in the claims.
The integrating section 541 calculates a charge amount Cg, which is a value of a power amount into which the integral value of the output current Ig within a control cycle has been converted. An example of a unit of the charge amount Cg is mWh. The integrating section 541 outputs the charge amount Cg to the metadata generation/update section 542.
The metadata generation/update section 542 generates and updates the metadata. The case in which the switch 660 closes the signal line and the switch 650 opens the signal line (that is, when charging with only power from the solar battery 110 is in progress) will be described. In this case, the metadata generation/update section 542 adds the charge amount Cg to the charging capacity by the natural energy power. On the other hand, the case in which the switches 660 and 650 close all signal lines (that is, the case in which charging with power from the solar battery 110 and the AC power supply is in progress) will be described. In this case, the metadata generation/update section 542 adds the charge amount Cg to the charging capacity by the natural energy power, and adds a value obtained by integrating the output current of the AC adapter 330 within the control cycle to the charging capacity by power other than natural energy power. The metadata generation/update section 542 generates and outputs information indicating these charging capacities as metadata. After generating the metadata, the metadata generation/update section 542 updates each charging capacity in the metadata within the memory 720 according to an increase in the timer value Tc. When the switch 660 has opened the signal line (that is, when the charging has been completed), the metadata generation/update section 542 ends the update of the metadata.
The operation example of the charger 303 according to the fourth embodiment will be described with reference to
The charger 303 executes a power transmission control process (step S950), and generates and updates metadata (step S960). The charger 303 determines whether or not a constant time has elapsed (step S970).
As described above, according to the fourth embodiment of the present technology, the charging circuit 503 outputs metadata indicating the charging capacity by the natural energy power and the charging capacity by the power other than the natural energy power. Thereby, the electronic device 750 can display each charging capacity. The charging capacity is displayed for each power supply, so that the user can easily recognize how much of the natural energy power has been used in the charging.
In addition, the metadata is stored in the memory 720 within the battery pack 703. Thus, it is possible to acquire each charging capacity if the battery pack 703 is attachable even in a device outside the charger 303.
Although the electronic device 750 is configured to display the content representing the metadata, the charger 303 can be configured to further include a display section, which displays the content representing the metadata.
Next, the fifth embodiment of the present technology will be described with reference to
The conversion switching section 220 receives commercial power and natural energy power from a commercial power supply and a natural energy power supply, and supplies either power to a power outlet 210. An example of this natural energy power supply is an external solar power generation apparatus installed in a place different from that of the solar battery 110. In addition, the conversion switching section 220 superimposes a power supply identifier ID on an AC waveform of supplied AC power using a power line communication (PLC) module or the like. The power supply identifier ID is an identifier for identifying a supply source of the AC power. For example, a value of “0” is set in the power supply identifier ID when the AC power is supplied from the commercial power supply, and a value of “1” is set in the power supply identifier ID when the AC power is supplied from the natural energy power.
The charger 304 is different from the charger 303 of the fourth embodiment in that an AC adapter 340 and a charging circuit 504 are provided instead of the AC adapter 330 and the charging circuit 503.
The AC adapter 340 separates the power supply identifier ID from the AC waveform of the received AC power. The AC adapter 340 converts the AC power into DC power, supplies the DC power to the charging circuit 504 via a signal line 803, and outputs the power supply identifier ID to the charging circuit 504 via a signal line 807.
When charging is performed with the AC power, the charging circuit 504 updates a value of a charging capacity corresponding to a supply source indicated by the power supply identifier ID in the metadata.
The AC adapter 340 is an example of a separation section disclosed in the claims. The power supply identifier ID is an example of a power supply identification signal disclosed in the claims.
The inverter 221 converts DC power supplied from the natural energy power supply in AC power. The inverter 221 outputs the AC power after the conversion to the power supply identifier superimposition section 223.
The switch control section 222 controls switching of the supply source of the AC power. Specifically, the switch control section 222 monitors an amount of power generation of natural energy power, and controls the switch 226 based on the amount of power generation. For example, the switch control section 222 switches the supply source of the AC power to the natural energy power supply when the amount of power generation of the natural energy power is greater than or equal to a threshold value, and switches the supply source to the commercial power supply when the amount of power generation of the natural energy power is less than the threshold value.
The power supply identifier superimposition section 223 acquires the power supply identifier ID corresponding to the natural energy power supply from the power supply identifier storage section 225, and superimposes the power supply identifier ID on the AC waveform of AC power supplied from the inverter 221. The AC power in which the power supply identifier ID is superimposed on the AC waveform is output to an input terminal of the switch 226.
The power supply identifier superimposition section 224 acquires a power supply identifier ID corresponding to the commercial power supply from the power supply identifier storage section 225, and superimposes the power supply identifier ID on the AC waveform of the AC power supplied from the commercial power supply. The AC power in which the power supply identifier ID is superimposed on the AC waveform is output to an input terminal of the switch 226.
The power supply identifier storage section 225 stores the power supply identifier ID for each power supply. The switch 226 switches the supply source of the AC power according to control of the switch control section 222. The switch 226 includes the two input terminals and one output terminal. One input terminal is connected to the power supply identifier superimposition section 223, and the other input terminal is connected to the power supply identifier superimposition section 224. The output terminal is connected to the power outlet 210 via a converter or the like.
The metadata generation/update section 543 receives a power supply identifier ID from the AC adapter 340 in addition to a switching signal and a control signal from the power transmission control section 630 and the charging completion determination section 640. The metadata generation/update section 543 identifies a supply source of AC power by referring to the power supply identifier ID when a battery 710 is charged with power from the solar battery 110 and the AC power supply. When an external solar battery is a supply source of the AC power, the metadata generation/update section 543 adds a charging capacity by the power from the AC power supply and the domestic solar battery 110 to a charging capacity by the natural energy power. When the commercial power supply is the supply source of the AC power, the metadata generation/update section 543 adds the charging capacity by the solar battery 110 to the charging capacity by the natural energy power, and adds the charging capacity by the AC power supply to the charging capacity by the power other than the natural energy power.
The operation example of the charger 304 according to the fifth embodiment will be described with reference to
On the other hand, the case in which the values of both the switching signal and the control signal are “1” and the power supply identifier ID is “1” will be described. In this case, power from the domestic solar battery 110 and power from the external solar battery are supplied to the battery 710. Thus, the metadata generation/update section 543 adds the charging capacities by the domestic solar battery 110 and the AC power supply to the charging capacity by the natural energy power.
As described above, according to the fifth embodiment of the present technology, the charging circuit 504 acquires a power supply identifier ID, and generates metadata based on the power supply identifier ID. Thereby, it is possible to calculate a charging capacity for each supply source even when there are a plurality of supply sources of AC power.
Although the conversion switching section 220 superimposes a power supply identifier ID for identifying whether or not the supply source is a natural energy power supply, an identifier for identifying a type of the natural energy power supply may be superimposed. For example, the conversion switching section 220 may superimpose a power supply identifier for identifying each power supply such as a water power generation apparatus, a solar power generation apparatus, or a geothermal power generation apparatus.
In addition, although the charger 304 calculates the charging capacity by the natural energy power and the charging capacity by power other than the natural energy power, the charging capacity may be calculated for each supply source of natural energy power. For example, the charger 304 calculates each of the charging capacity by the domestic solar battery 110, the charging capacity of the external solar battery, and the charging capacity by the commercial power supply. The charger 304 generates metadata representing each charging capacity as illustrated in
In addition, although the conversion switching section 220 superimposes the power supply identifier ID on both the AC power from the commercial power supply and the AC power from the natural energy power supply, the power supply identifier ID may be superimposed on only one power supply.
Next, the sixth embodiment of the present technology will be described with reference to
The electronic device 751 is a device using a battery pack 703 as a power supply, and includes an electronic device control section 760 and a display section 770. The electronic device control section 760 controls the entire electronic device 751. The electronic device control section 760 receives DC power from a charger 304 via a signal line 804, and receives metadata via a signal line 806. The electronic device control section 760 outputs the received DC power to a battery 710 via a signal line 808, and outputs the metadata to a memory 720 via a signal line 809. In addition, the electronic device control section 760 reads the metadata from the memory 720, and causes the display section 770 to display content representing the metadata. The display section 770 displays the content representing the metadata.
The processor 761 controls the entire electronic device 751. The processor 761 outputs metadata received from a charger 304 to the battery pack 703. In addition, the processor 761 reads the metadata stored in the battery pack 703, generates data for displaying the content representing the metadata, and outputs the generated data to the display section 770 via a signal line 881.
The memory 762 is a main storage apparatus directly accessible by the processor 761. The bus 763 is a common path through which the processor 761 or the memory 762 transmits or receives data.
As described above, according to the sixth embodiment of the present technology, the charger 304 charges the battery pack 703 via the electronic device 751. Thereby, the charger 304 can charge the battery pack 703 while the battery pack 703 is attached to the electronic device 751, so that convenience of the user is improved.
Although the memory 720 is configured to be provided within the battery pack 703, the memory 720 can be configured to be provided within the electronic device 751 instead of within the battery pack 703. Thereby, it is not necessary to provide the memory 720 in the battery pack 703.
Next, the modified example of the present technology will be described with reference to
The switch 651 includes two input terminals and one output terminal. One input terminal of the switch 651 is connected to a diode 320, and the other input terminal is connected to an AC adapter 330. The output terminal of the switch 651 is connected to a switch 660. A power transmission control section 630 switches an input destination of the switch 651 to the diode 320 when a predicted time Tg is earlier than a completion time Ts, and switches the input destination of the switch 651 to the AC adapter 330 when the predicted time Tg is the completion time Ts or later. Thereby, a battery 710 is charged with only AC power when the predicted time Tg is the completion time Ts or later. According to this configuration, because only one of natural energy power and power from an AC power supply is supplied, overcharging is less likely to occur as compared to the charger system of the first embodiment in which both are supplied.
The above-described embodiments are examples for embodying the present technology, and matters in the embodiments each have a corresponding relationship with invention-specific matters in the claims. Likewise, the matters in the embodiments and the invention-specific matters in the claims denoted by the same names have a corresponding relationship with each other. However, the present technology is not limited to the embodiments, and various modifications of the embodiments may be embodied in the scope of the present technology without departing from the spirit of the present technology.
In addition, a processing procedure described in the above-described embodiments may be regarded as a method having a series of procedures or regarded as a program for allowing a computer to execute a series of procedures or a recording medium that stores the program. As the recording medium, for example, a compact disc (CD), a mini disc (MD), a digital versatile disc (DVD), a memory card, a Blu-ray disc (registered trade mark), or the like may be used.
The present technology can also have the following configurations.
[1] A charger including: a setting section for setting a completion time that is a time at which charging of a secondary battery is completed; an output value acquisition section for acquiring an output value of a voltage or a current from a natural energy power supply apparatus, which is a power supply apparatus that generates natural energy power from natural energy; a power amount acquisition section for acquiring an amount of power that is supplied until the charging of the secondary battery is completed; a predicted time calculation section for calculating a time at which the charging of the second battery is completed by only the natural energy power based on the output value and the power amount as a predicted time; and a control section for causing the secondary battery to be charged with only the natural energy power when the predicted time is earlier than the completion time.
[2] The charger described above in [1], wherein the control section causes the secondary battery to be charged with power generated by a power supply apparatus other than the natural energy power supply apparatus when the predicted time is the completion time or later.
[3] The charger described above in [2], wherein the control section causes the secondary battery to be charged by further supplying the natural energy power when the predicted time is the completion time or later.
[4] The charger described above in [3], wherein the setting section further sets weather forecast data indicating weather, the output value acquisition section predicts the output value for each weather based on the set weather forecast data, and the prediction time calculation section calculates the predicted time based on the output value predicted for each weather and the power amount.
[5] The charger described above in any one of [2] to [4] further including a charging data generation section for generating and outputting information indicating a charging capacity of the secondary battery by the natural energy power and a charging capacity of the secondary battery by power other than the natural energy power as charging data.
[6] The charger described above in [5], wherein the power supply apparatus other than the natural energy power supply apparatus receives alternating current (AC) power in which a power supply identification signal for identifying a supply source of power is superimposed on an AC waveform, the charger further comprises a separation section for separating the power supply identification signal from the AC waveform, and the charging data generation section generates the charging data based on the separated power supply identification signal.
[7] The charger described above in any one of [1] to [6], wherein the control section causes the secondary battery to be charged with only the natural energy power when a remaining time, which is a time from a current time to the completion time, is greater than or equal to a predetermined time.
[8] The charger described above in any one of [1] to [7], wherein the control section causes the secondary battery to be charged with only the natural energy power when a remaining capacity of the secondary battery is greater than or equal to a predetermined capacity.
[9] The charger described above in any one of [1] to [8], wherein the setting section further sets weather forecast data indicating weather, the output value acquisition section predicts the output value for each weather based on the set weather forecast data, and the predicted time calculation section for calculating the predicted time based on the output value predicted for each weather and the power amount.
[10] A charging system including: a charger; and a battery pack, wherein the charger includes: a setting section for setting a completion time that is a time at which charging of a secondary battery is completed; an output value acquisition section for acquiring an output value of a voltage or a current from a natural energy power supply apparatus, which is a power supply apparatus that generates natural energy power from natural energy; a power amount acquisition section for acquiring an amount of power that is supplied until the charging of the secondary battery is completed; a predicted time calculation section for calculating a time at which the charging of the second battery is completed by only the natural energy power based on the output value and the power amount as a predicted time; a control section for causing the secondary battery to be charged with only the natural energy power when the predicted time is earlier than the completion time and causing the secondary battery to be charged with power generated by a power supply apparatus other than the natural energy power supply apparatus when the predicted time is the completion time or later; and a charging data generation section for generating and outputting information indicating a charging capacity of the secondary battery by the natural energy power and a charging capacity of the secondary battery by power other than the natural energy power as charging data, and wherein the battery pack includes: a charging data storage section for storing the output charging data; and the secondary battery.
[11] The charging system described above in [10], wherein the power supply apparatus other than the natural energy power supply apparatus receives AC power in which a power supply identification signal for identifying a supply source of power is superimposed on an AC waveform, the charger further includes a separation section for separating the power supply identification signal from the AC waveform, and the charging data generation section generates the charging data based on the separated power supply identification signal.
[12] The charging system described above in [10] or [11], wherein the charging system further includes a display section for displaying the charging capacity of the secondary battery by the natural energy power and the charging capacity of the secondary battery by the power other than the natural energy power based on the charging data.
[13] A charging method including: setting a completion time that is a time at which charging of a secondary battery is completed; acquiring an output value of a voltage or a current from a natural energy power supply apparatus, which is a power supply apparatus that generates natural energy power from natural energy; acquiring an amount of power that is supplied until the charging of the secondary battery is completed; calculating a time at which the charging of the second battery is completed by only the natural energy power based on the output value and the power amount as a predicted time; and controlling the secondary battery to be charged with only the natural energy power when the predicted time is earlier than the completion time.