Screen assemblies are ubiquitous in the downhole drilling and completions industry for enabling solids or particulate to be filtered from a flow of fluid, e.g., hydrocarbons, while enabling production of the fluid. Production and stimulation rates through the screen assemblies can be generally increased by increasing the size of the screen assembly. Additionally, it is well established that certain radial clearances between the outer dimension of the screen assembly and the inner dimension of the casing (or other tubular string) in which the screen assembly is positioned must be maintained in order to support stimulation and/or production at appropriate rates. For example, if the radial gap is undesirably small, there is a severe risk of premature screen outs and/or the sand or particulate in a frac or gravel pack bridging off before filling the annulus about a screen assembly. For the above reasons, it is established practice in the industry to use screen assemblies having dimensions that are significantly smaller than the drift diameter of the casing in order to maintain the aforementioned radial clearance in the range of about at least 0.5 inches.
Although maintaining the radial clearance is necessary to support industry accepted production and stimulation rates, it also puts a limit on the maximum possible size of the screen assemblies, which negatively impacts these same rates. The simultaneous use of a larger screen assembly and maintenance of the radial clearance is only possible in these prior systems by using larger casing, but this requires greater material costs and potentially a larger borehole. In view hereof, it is clear that the industry would well receive a system that enables larger screen assemblies to be used within a given size of casing without negatively affecting production and stimulation rates, e.g., by reducing the size of the radial clearance between the screen assembly and the casing to an unacceptable level.
A method of completing a borehole, including selectively expanding a tubular string having a substantially continuous first dimension to form at least one expanded portion of the tubular string having a second dimension greater than the first dimension and at least one unexpanded portion of the tubular string having the first dimension; and positioning at least one screen assembly radially proximate to the at least one expanded portion for forming an enlarged radial gap between the at least one screen assembly and the expanded portion of the tubular string.
A completion system, including a tubular string having an internal drift dimension and including at least one expanded portion having an expanded internal dimension larger than the internal drift dimension, the tubular string having at least one opening therein formed at the at least one expanded portion; and at least one screen assembly having an outer dimension approximating the internal drift dimension, the at least one screen assembly positioned radially aligned with the at least one expanded portion, wherein the outer dimension and the expanded dimension form a radial clearance therebetween being at least about 0.5 inches.
A method of completing a borehole, including selectively expanding a tubular string having a substantially continuous first dimension to form at least one expanded portion of the tubular string having a second dimension greater than the first dimension and at least one unexpanded portion of the tubular string having the first dimension; and positioning at least one screen assembly radially proximate to the at least one expanded portion for forming an enlarged radial gap between the at least one screen assembly and the expanded portion of the tubular string.
The following descriptions should not be considered limiting in any way. With reference to the accompanying drawings, like elements are numbered alike:
A detailed description of one or more embodiments of the disclosed apparatus and method are presented herein by way of exemplification and not limitation with reference to the Figures.
Methods for deploying a downhole production system can be best appreciated in view of
After arranging the casing 12, e.g., hanging or anchoring the liner 14 from or to the casing string 16, the liner 14 is selectively radially expanded. By selectively expanded, it is meant that portions of the liner 14 are dimensionally enlarged, i.e., plastically deformed, in the radial direction in order to form at least one expanded portion 22 and at least one unexpanded portion 24. In the illustrated embodiment, a plurality of the expanded portions 22 is interspaced with the unexpanded portions 24. The liner 14 has an initial drift dimension (e.g., internal diameter) designated D1, which drift dimension D1 is maintained by the unexpanded portions 24. The expanded portions 22 are radially expanded to an expanded internal dimension (e.g., internal diameter) designated D2, which is greater than the internal drift dimension D1. The term drift dimension or drift diameter is used with its ordinary meaning in the art, namely, relating to the effective or minimum dimension of the liner 14, i.e., such that any component smaller than the drift dimension can be run through the tubular (liner, casing, etc.). In accordance with this understood definition, the drift diameter or dimension D1 may differ slightly from the actual diameter or dimension of the liner 14. In the illustrated embodiment, the internal dimension D2 of the expanded portions 22 is less than the diameter of the casing string 16, while in another embodiment the internal dimension D2 may exceed the internal diameter of the upper casing string 16 or another section of the casing 12.
For the purposes of discussion herein, the term expansion is generally interchangeable with swage, deform, enlarge, and other synonyms thereof. Accordingly, the selective expansion of the casing 12, more specifically of the liner 14 of the casing 12, can be accomplished by any suitable swage, wedge, cone, or other device that is actuatable or transitionable between a retracted or retractable configuration that enables the device to be run through the liner 14 without deforming the unexpanded portions 24 and a radially extended or supported configuration that enables the expanding device to expand the portions 22. The actuation or transition between these two configurations could be provided via any suitable mechanism in any suitable manner, e.g., mechanical, hydraulic, electrical, etc. U.S. Pat. No. 6,352,112 (Mills), which patent is incorporated herein by reference in its entirety, provides an example of a selectively supported swage device that could be adapted for selectively expanding the portions 22 of the liner 14 without expanded the unexpanded portions 24. Those of ordinary skill in the art will recognize that other devices are also suitable for the purpose of selective expansion as described herein. The swaging device could be run into the casing 12 in the same trip as the liner 14, or a separate trip. The swaging could be performed from bottom-up, from top-down, or combinations thereof for each section desired to be swaged.
It is noted that the timing of the swaging process could be different than that described above. For example, in one embodiment, the swaging or expansion of the liner 14 occurs at surface before, or simultaneously with, run-in of the liner 14 as opposed to after it is already set downhole. In one embodiment, the expanded portion is formed by removing wall thickness of the liner 14, such that the outer dimension remains consistent while the dimensions D1 and D2 still differ. Multiple sections of the liner 14 could be coupled together in such an embodiment, e.g., threadedly, to form multiple alternating ones of the portions 22 and 24. In one embodiment, the expanded and unexpanded portions 22 and 24 are each formed from separate components having different dimensions that are affixed together, e.g., threaded, in order to form the liner 14, which is then run-into and secured to the upper casing string 16.
The annulus 20 radially about the casing 12 may be cemented according to any suitable technique, e.g., pumping cement down through the interior of the casing 12 (or another tubular run therewith) and forcing it back up through the annulus 20, thereby filling the annulus 20. In one embodiment the cementation occurs after expanding the portions 22, while in another embodiment, the expansion occurs immediately after pumping the cement before it has a chance to cure and harden. In the illustrated embodiment, a liner lap 25 at the junction between the liner 14 and the casing string 16 is specifically not swaged and forms one of the unexpanded portions 24. Advantageously, not swaging the liner lap 25 during the selective swaging process improves the hydraulic performance of a cement pumping operation that may occur subsequent to the selective swaging process with respect to if the liner lap 25 were also swaged.
After cementation, a perforation gun or other assembly for forming openings in the liner 14 is positioned with respect to the expanded portions 22 in the liner 14 and triggered in order to form a plurality of perforations 26 through the liner 14 and the cement in the annulus 20. Any style of perforating gun could be used and delivered downhole in any desired manner, e.g., coiled tubing, wireline, etc. The perforations 26 provide fluid communication between a downhole formation 28 through which the borehole 18 is formed and an interior passageway 30 of the casing 12. This fluid communication enables fluid, such as hydrocarbons, to be produced from the downhole formation 28 and/or fluid to delivered to the downhole formation 28, e.g., in order to stimulate, fracture, or treat the formation to facilitate later production therefrom (generally, “stimulate”). It is noted that in other embodiments, particularly those in which cementation is not required, that the liner 14 or other portion of the casing 12 could be pre-arranged with perforations or other openings in order to save time and avoid an additional perforation trip.
Once fluid communication is established, an inner string 34, e.g., a production string, can be run including one or more screen assemblies 36. The string 34 and the screen assemblies 36 may resemble a traditional multi-zone frac system or any other system arranged for enabling the stimulation of and/or production from a downhole formation. In the illustrated embodiment, one of the screen assemblies 36 is provided for each of the expanded portions 22, which may in turn be associated individually with production zones. A packer 38 or other seal device is arranged on the inner string 34 and arranged to engage against each unexpanded portion 24 in order to isolate the screen assemblies 36 and/or their corresponding zones from each other. The screen assemblies 36 are arranged with a filter or mesh 40, e.g., wire wrap screen, narrow slots, permeable foam, etc., in order to impede the passage of solids, e.g., sand, therethrough while permitting fluid flow. The screen assemblies 36 can each be provided with a first valve 42 arranged for enabling selective fluid communication directly with the formation 28 (bypassing the filter or mesh 40), e.g., in order perform a treatment, stimulation, fracturing, or other operation on the formation 28, and a second valve 44 arranged for enabling selective fluid communication through the mesh or filter 40 of the screen assemblies 36, e.g., in order to produce fluid from the formation 28 as well as create a circulation flow path for a gravel or frac pack or other stimulation or treatment operation. The valves 42 and 44 can be opened and/or closed due to hydraulic pressure, engagement with a shifting tool, a dropped plug or ball, or in any other desired manner or combinations thereof.
As noted above, fluid production and stimulation rates of a downhole completion are limited by the size, e.g., diameter, of the screen assemblies used. That is, smaller screens are associated with smaller base pipes and/or production strings having relatively restricted internal flow passages therethrough, which restricts fluid flow for production and stimulation. Furthermore, a minimum radial clearance, as noted above, between the outside of the screen assembly and the inner drift dimension of the casing must be maintained in order to support acceptable stimulation and/or production rates. Advantageously, with specific reference to the system 10, the swaging of the portions 22 of the liner 14 at which the screen assemblies 36 are positioned, enables the outer dimension (e.g., outer diameter) of the screen assemblies, designated D3 in
An alternate embodiment, designated as a system 10′, is shown in
In view of the foregoing, it is to be appreciated that the current invention is particularly advantageous for gravel and frac pack systems, and other systems for which the industry mandates a sufficient radial clearance (e.g., about half an inch or larger) between the screen assemblies and the outer tubular or casing housing the screen assemblies. Even more particularly to systems similar to those illustrated in which screen assemblies are positioned in a relatively smaller dimensioned string, e.g., the liner 14, which is hung or suspended from a relatively larger dimensioned upper string, e.g., the upper casing 16. That is, the relatively smaller dimensioned string, e.g., the liner 14, in which the screen assemblies are placed would typically result in either the size of the screen assemblies to be reduced or that of the radial gap between the screen assemblies and the inner surface of the casing, but this issue is avoided by the current invention. It is also to be understood that although the current invention is particularly advantageous in such situations, the casing or other outer tubular string may not have a relatively smaller dimensioned string hung from a relatively larger outer dimensioned string. Even in this embodiment, the overall dimension of the casing or outer tubular can be reduced, thereby saving material costs, while still producing at the same rate as a traditional system having a larger outer dimension. That is, the size of the casing or outer tubular only needs to be set as just large enough for the screen assemblies to be located therein without need to accommodate for the radial gap between the screen assemblies and inner dimension of the casing, as the desired radial gap is achieved by the above-described swaging process.
While the invention has been described with reference to an exemplary embodiment or embodiments, it will be understood by those skilled in the art that various changes may be made and equivalents may be substituted for elements thereof without departing from the scope of the invention. In addition, many modifications may be made to adapt a particular situation or material to the teachings of the invention without departing from the essential scope thereof. Therefore, it is intended that the invention not be limited to the particular embodiment disclosed as the best mode contemplated for carrying out this invention, but that the invention will include all embodiments falling within the scope of the claims. Also, in the drawings and the description, there have been disclosed exemplary embodiments of the invention and, although specific terms may have been employed, they are unless otherwise stated used in a generic and descriptive sense only and not for purposes of limitation, the scope of the invention therefore not being so limited. Moreover, the use of the terms first, second, etc. do not denote any order or importance, but rather the terms first, second, etc. are used to distinguish one element from another. Furthermore, the use of the terms a, an, etc. do not denote a limitation of quantity, but rather denote the presence of at least one of the referenced item.
This application claims the benefit of an earlier filing date from U.S. Provisional Application Ser. No. 61/739,606 filed Dec. 19, 2012, the entire disclosure of which is incorporated herein by reference.
Number | Name | Date | Kind |
---|---|---|---|
4858691 | Ilfrey et al. | Aug 1989 | A |
5390742 | Dines et al. | Feb 1995 | A |
7055598 | Ross et al. | Jun 2006 | B2 |
7225523 | Metcalfe | Jun 2007 | B2 |
7543637 | Green et al. | Jun 2009 | B2 |
7681648 | Ring | Mar 2010 | B2 |
8215409 | Adam et al. | Jul 2012 | B2 |
8511380 | Guignard et al. | Aug 2013 | B2 |
20040055758 | Brezinski et al. | Mar 2004 | A1 |
20040149431 | Wylie et al. | Aug 2004 | A1 |
20040216889 | Fraser, III | Nov 2004 | A1 |
20040244979 | Adam et al. | Dec 2004 | A1 |
20040251033 | Cameron et al. | Dec 2004 | A1 |
20040261994 | Nguyen et al. | Dec 2004 | A1 |
20050045342 | Luke et al. | Mar 2005 | A1 |
20060090903 | Gano et al. | May 2006 | A1 |
20060272807 | Adam et al. | Dec 2006 | A1 |
20090166040 | Cavender et al. | Jul 2009 | A1 |
20100018305 | Maute et al. | Jan 2010 | A1 |
20110067890 | Themig | Mar 2011 | A1 |
20110114336 | Lehr et al. | May 2011 | A1 |
20120085549 | O'Connor et al. | Apr 2012 | A1 |
20120103607 | Fitzpatrick et al. | May 2012 | A1 |
20130048308 | Lehr et al. | Feb 2013 | A1 |
20130062055 | Tolman et al. | Mar 2013 | A1 |
20140083682 | Grigsby et al. | Mar 2014 | A1 |
20140166284 | Allen et al. | Jun 2014 | A1 |
Entry |
---|
International Search Report and Written Opinion, International Application No. PCT/US2013/069154, Mailed Feb. 17, 2014, Korean Intellectual Property Office; International Search Report and Written Opinion, 8 pages. |
Mohamed, et al., “One-Trip Installation of 4 ¾ in. Expandable Screen Assembly”, SPE/IADC 108262, 2007, 4 pages. |
Omar Y. Mohamed et al, “One-Trip Installation of 4 ¾ in. Expandable Screen Assembly”, SPE/IADC 108262, 2007, 4 pages. |
Number | Date | Country | |
---|---|---|---|
20140166284 A1 | Jun 2014 | US |
Number | Date | Country | |
---|---|---|---|
61739606 | Dec 2012 | US |