Elevated water storage tanks come in a variety of sizes, styles, materials, and designs depending primarily on factors such as tank size requirements, site location, site geotechnical conditions and limitations, desired construction materials for the tank and for the supports (based on, for example, cost, availability, and design requirements), desired construction method, overall economics of the project, and so forth. In general there are four primary categories of elevated storage tanks: multi-column tanks; pedesphere tanks; fluted column tanks; and composite elevated tanks (“CET”). Each type of storage tank has a unique design and unique properties that require the incorporation of specific structures to the tank and specific construction methods for both fabrication of the tank components and construction of the final overall tank. In many cases, for example, what might be needed to construct, e.g., a multi-column tank is either not needed or in some cases is not appropriate for, e.g., a composite elevated tank.
Tank capacity and economics often play the largest role in determining what style tank is needed for any particular project. Multi-column tanks generally comprise a steel tank supported by multiple steel legs around the tank circumference extending down to a foundation. These tanks, generally speaking, are one of the more economical type of all steel construction, and they generally range in capacities from approximately 50,000 gallons to approximately 2 million gallons or greater. Pedesphere tanks generally comprise a spherical or spheroidal steel tank perched atop a single slender steel support column supported on a foundation. Pedesphere tanks generally range in capacities from approximately 50,000 gallons to approximately 1,500,000 gallons or greater. Fluted column tanks generally comprise a large steel tank supported by a single, large-diameter corrugated (“fluted”) steel support column. Fluted column tanks generally range in capacities from approximately 250,000 gallons to approximately 3 million gallons or greater. Composite elevated tanks generally comprise a large steel tank placed atop a reinforced concrete pedestal support shaft. Composite elevated tanks generally range in capacities from approximately 500,000 gallons to approximately 3 million gallons or greater.
Material pricing and availability, site-related construction method options, and labor often are key factors in the overall economics of any given elevated storage tank project. For example, because of the extensive labor and cost involved in forming and constructing a reinforced concrete support shaft, composite elevated tanks are generally cost-effective in capacities of 500,000 gallons or more. This is due in part because the typical method of construction for such a tank size is to form and fully construct a reinforced concrete pedestal, followed by construction and placement of steel tank container on top of the final pedestal. It is currently not cost efficient to simultaneously construct the steel tank and the reinforced concrete pedestal.
However, composite elevated tanks offer important benefits over all-steel construction, such as, for example, requiring no coatings or painting of the concrete pedestal support. Given this and other benefits of composite elevated tanks, composite elevated tanks would be utilized to a much greater extent if their cost-efficiency for smaller tank sizes (non-limiting examples of approximately 300,000 gallons and less) could be improved. This requires a novel method of constructing composite elevated tanks, and also requires novel structures associated with the tank to facilitate proper connection between the steel tank and the concrete pedestal.
Accordingly, a need exists in the art for an alternative construction method for small composite elevated storage tanks. The need also exists in the art for a tank design that facilitates such a novel construction method.
The present disclosure relates to a small composite elevated storage tank and a method for constructing same. The embodiments described herein streamline and simplify the construction of composite elevated tanks for smaller capacities of, for example, 300,000 gallons or less. In some embodiments, the concrete pedestal and steel tank container may be built concurrently, with the steel tank being lifted, in part or in total, onto the concrete pedestal.
In an embodiment, a method of building a composite elevated storage tank is provided comprising the steps of: building a reinforced concrete pedestal on a foundation at a storage tank site; coupling a tank anchor assembly with a top of the reinforced concrete pedestal; preparing a temporary tank support; building a steel tank on the temporary tank support, the steel tank having a first cone section, one or more levels of tank shell side wall, a roof, and a base plate; lifting the steel tank onto the reinforced concrete pedestal such that the base plate is positioned adjacent the tank anchor; and coupling the base plate to the tank anchor.
In an embodiment, a method of building a composite elevated storage tank is provide comprising the steps of: building a reinforced concrete pedestal on a foundation at a storage tank site by beginning with a first section of formwork for the pedestal and placing steel reinforcement and wet concrete inside the formwork and then repeating to achieve, with additional sections or lifts, an increasing height for the reinforced concrete pedestal until a penultimate level has been achieved; preparing a temporary tank support; building a steel tank on the temporary tank support by fabricating an assembly comprising a first cone section, a skirt welded to a bottom of the first cone section, and a base plate welded to a bottom of the skirt; placing the assembly on the temporary tank support by setting the base plate on the temporary tank support; continuing to build the steel tank from the bottom upwards by welding additional cone sections above the first cone section until a desired number of additional cone sections has been achieved; welding plates of a first level of tank shell to a top level of an uppermost cone section of the additional cone sections; continuing to add levels to the tank shell by welding plates of additional levels to each successive lower level until a desired height of the tank shell has been achieved; in the ultimate lift of the reinforced concrete pedestal, placing a tank anchor assembly at the top of the formwork for the final lift; lifting the steel tank onto the reinforced concrete pedestal such that the base plate is positioned adjacent the tank anchor; and coupling the base plate to the tank anchor.
In an embodiment, a method of building a composite elevated storage tank is provided comprising the steps of: building a foundation at a storage tank site; building a temporary tank support near the foundation and at the storage tank site; building a reinforced concrete pedestal on the foundation; fastening a tank anchor assembly onto the reinforced concrete pedestal; building a steel tank on the temporary tank support, the steel tank having a first cone section, one or more levels of tank shell side wall, and a roof, wherein the first cone section further comprises a skirt depending therefrom, and the skirt further comprises a base plate welded to a bottom of the skirt; lifting the steel tank onto the reinforced concrete pedestal such that the base plate sits on the tank anchor; and coupling the base plate to the tank anchor.
In an embodiment, a composite elevated storage tank is provided comprising a reinforced concrete pedestal having a generally open cylindrical shape, the reinforced concrete pedestal further comprising one or more tank anchor assemblies, wherein the tank anchor assemblies are coupled to a top of the reinforced concrete; a steel tank of a predetermined capacity, the steel tank having a bottom, a first cone section, sidewall, roof, and a base plate coupled to both the steel tank and the tank anchor.
In an embodiment, a composite elevated storage tank is provided comprising a reinforced concrete pedestal having a ring wall of reinforced concrete, the ring wall further comprising one or more tank anchor assemblies coupled to a top of the ring wall; a geometrically closed steel tank of a predetermined capacity having a bottom, at least one sidewall, and top, wherein the bottom further comprises a subassembly further comprising a first cone section, a skirt welded to a bottom of the first cone section, and at least one base plate welded to a bottom of the skirt; wherein the one or more tank anchor assemblies is coupled to the at least one base plate to the steel tank to the reinforced concrete pedestal.
In an embodiment, a composite elevated storage tank is provided comprising a reinforced concrete pedestal having a tank anchor assembly coupled to a top of the reinforced concrete pedestal with an insulator separating the tank anchor assembly and the top surface; a steel tank having a first cone section, one or more additional cone sections, one or more levels of tank shell side wall, and a roof, wherein the first cone section further comprises a skirt depending therefrom, and the skirt further comprises a base plate welded to a bottom of the skirt; wherein the base plate is coupled to the tank anchor.
These and other advantages and features, which characterize the invention, are set forth in the claims annexed hereto. For a better understanding of the invention, and of the advantages and objectives attained through its use, reference should be made to the Drawings, and to the accompanying descriptive matter, in which there is described example embodiments of the invention. This summary is merely provided to introduce a selection of concepts that are further described below in the detailed description and is not intended to identify key or essential features of the claimed subject matter, nor is it intended to be used as an aid in limiting the scope of the claimed subject matter.
The embodiments discussed hereinafter are directed in part to a small capacity composite elevated storage tank and a method for constructing same. The functionality of the disclosed apparatus and method represents a significant improvement over known designs and methods. It is to be understood that neither the tank components described or shown herein, nor the method of constructing such an exemplary tank, is limited to the details of construction and the arrangement of components set forth in the following description or illustrated in the drawings, nor is the method of construction limited to the steps described or the order of steps described with reference to particular embodiments. Instead, exemplary methods to describe certain aspects of the preferred method of construction, and exemplary structures and features that enable such construction methods to be achieved are described herein. The described embodiments are exemplary in nature, and certain aspects of the structures may be capable of other embodiments and of being practiced or of being carried out in various ways. As will be described in detail below, the exemplary embodiments and descriptions serve to describe aspects and embodiments of the invention. To the extent that the embodiments described herein involve, in various stages, the use of known construction details and methods for aspects that are not directly relevant to the invention, a detailed discussion of such known details and methods will not be made herein. Also, it is to be understood that the phraseology and terminology used herein is for the purpose of description and should not be regarded as limiting.
Turning now to the drawings, wherein like numbers denote like parts throughout the several views,
As part of the novel aspects of the embodiments described herein, the pedestal 300 and the steel tank 200 may be constructed concurrently or consecutively, and in either case the construction of each can be, but need not be, performed at the site 10. This determination is based on many factors, including site 10 space availability, field personnel availability, equipment availability, project schedule, and overall operations schedule. In the figures, the site 10 is shown to comprise two portions in proximity to each other at the site 10: site pedestal location 11 and temporary tank location 12. In practice, site pedestal location 11 and temporary tank location 12 can be in close proximity to each other at the site 10, or can be a significant distance from each other at the site 10. Further, the temporary tank location 12 could also be located in a completely different location not appurtenant to the site 10 (e.g., at a steel tank manufacturing facility).
Reinforced Concrete Pedestal Construction
As is commonly understood, in the process for building the storage tank 100 (and indeed for all types of elevated storage tanks in common usage), the foundation work to excavate and build the foundation 310 generally occurs first. The storage tank 100, in particular, the pedestal 300, is placed on foundation 310. The design and construction details of foundation 310 are well-known to engineers tasked with designing and building composite elevated tanks like storage tank 100, and depend on many factors, including the capacity of the steel tank 200, the size and shape of the pedestal 300, site 10 space, site 10 location, soil bearing capacity, and other commonly understood engineering design parameters, and will not be described in detail here. Suffice to say that a properly designed and constructed foundation 310 at the site 10 is required to provide adequate support for the storage tank 100. Once the foundation 310 has been constructed, work begins on building the pedestal 300. Building a reinforced concrete pedestal per se is, in general, commonly understood in the industry to involve placement of formwork that will receive and contain the wet concrete for curing. The forms are assembled in segments. Reinforcing steel, which can be mesh or deformed bar (re-bar), is then placed within the formwork. Once all reinforcing steel has been placed, wet concrete is then placed inside the formwork according to required project parameters and standards, and according to various known methods of construction. For example, some methods of building a pedestal involve working in “lifts” around the entire ring (360 degrees) in a given lift (e.g., four feet of height at a time), and then, once that lift has sufficiently cured, moving formwork to a higher elevation in a second lift, again all the way around the entire ring, and then continuing this process at each successively higher elevation. Other building methods, however, involve working on sections of the ring at a given time, and forming and pouring concrete to a higher elevation (as compared to the “lift” method), but only in one segment of the ring at a time (e.g., approximately 90 degrees of the ring). Other methods might involve a mixture of these two methods. Regardless of how the formwork and concrete is placed during construction of the pedestal 300, in general, the process of building the formwork, adding reinforcing steel, and pouring concrete continues upward as the concreted pedestal 300 continues to be constructed. The final pour for the pedestal 300 involves structures and methods not included in the construction of known composite elevated tanks and that facilitate the novel aspects of the embodiments described herein. These details will be described below.
Steel Tank Construction
With continued reference to
From
Additional structures related to the steel tank 200 are optional and can be included, if desired. For example, some steel tanks 200 include therewithin an access tube 215. As is commonly understood in the steel tank industry, the access tube 215 serves as an access conduit within the tank section from the interior of the pedestal 300 to the tank roof 213. The figures depict an embodiment having an access tube 215, but an access tube is not required. The method of fabricating the steel tank 200 will now be described.
Temporary Tank Location
Referring to
In the embodiment shown in the figures, the assembly 23 can be fabricated off site and brought to the temporary tank location 12 as a whole, or the assembly 23 can be fabricated onsite at the temporary tank location, depending on preference. Preferably, the first cone section 210 is securely attached to the skirt 21 by double-sided fillet welding in the fabrication shop and then brought to the site 10 to be placed at the temporary tank location 12. Preferably the base plates 22, skirt 21, and first cone section 210 are fabricated at a fabrication facility and brought to the site 10 as a pre-fabricated assembly 23. This can ensure, among other things, that the assembly 23 is level and that necessary tolerances can be achieved. Once on site 10, the assembly 23 is placed atop the temporary tank construction supports 20. The assembly is then checked for level. As shown in
In
As discussed above, the figures depict an embodiment that includes as access tube 215, but such is not required. In
Anchorage of Tank to Pedestal
Referring again to
Prior to setting the steel tank 200 atop the pedestal 300, a portion of the anchorage assembly 110 described herein is preferably pre-fabricated at a fabrication shop and then brought to the site 10.
The top surface 312 of the tank anchor assemblies 311 in the embodiment shown in the figures should be flush with the top of the formwork so that the tank anchor assembly 311 extends neither above nor below the final top surface of the top of the concrete comprising the pedestal 300. This will ensure the tank anchor assemblies 311 will be level in relation to each other and to the top of the concrete surface. To facilitate this, one or more temporary anchor embedment wing plates 315 can be utilized to position and temporarily secure the tank anchor assemblies 311. In the embodiment shown, each temporary anchor embedment wing plate 315 comprises a generally “L” shape, having a first leg 315a and a second leg 315b disposed at a right angle to the first leg 315a. The temporary anchor embedment wing plates 315 are placed atop the final, uppermost formwork for the pedestal 300 such that first leg 315a resides atop the formwork and second leg 315b resides in contact with the side of the formwork. If desired, the temporary anchor embedment wing plates 315 may be temporarily secured to the formwork, e.g., by tack welding, nailing, screwing, adhesive, or other releasable means of attachment. The temporary anchor embedment wing plates 315 are removed as the formwork for the upper ring is removed.
During the stage of attaching (described below) the steel tank 200 to the pedestal 300, welding will be performed in close proximity to the concrete at the upper surface of the pedestal 300. In general, the welding of a steel member to another steel member that is embedded in concrete is not preferred practice. The heat of the welding process can cause concrete damage, which in turn can compromise strength and function. Therefore, prior to placing the tank anchor assemblies 311 for securement into the wet concrete, an insulator 316 is used to provide thermal insulation between the tank anchor assembly 311 and the upper surface of the concrete at the top of the pedestal 300. The insulator 316 can comprise one or more of several types and materials. For example, the insulator 316 can take the form of one or more solid pieces of discrete insulating material of any known material (e.g., cellulose; fiberglass; mineral wool; polymers; thermoplastics; natural materials; various other types of fibrous and non-fibrous, woven and non-woven, cross-linked and non-cross-linked materials; and the like having insulative properties) that can be cut to size and placed between the tank anchor assembly 311 and the upper surface of concrete. Alternatively, the insulator 316 can comprise one or more coatings, cementitious materials, fire-proofing materials, and the like that can be applied to the concrete, the tank anchor assemblies 311, the anchors 314, and/or any or all of these, that provide insulative properties. An example of a cementitious coating that can be applied to the concrete is a trowel-on material, such as a Portland cement based cementitious fireproofing material, available from Carboline and sold under the mark “Pyrocrete 241 HY”. Alternatively, the insulator 316 may comprise one or more additional plates (e.g., steel), separate or coupled to the tank anchor assembly 311, or even a thickened version or thickened area of tank anchor assembly 311. Any one or more of these insulators 316, in any combination, may be employed to provide the desired insulation to protect the concrete from the heat of welding. For ease of description,
After the pedestal 300 has been completed (with the embedment into the concrete of the anchors 314 of the tank anchor assemblies 311), the upper part of the pedestal 300 is now ready to receive the steel tank 200. With continuing reference to
As discussed previously, the anchorage assembly 110 (e.g., the tank anchor assemblies 311 and/or the assembly 23) can take on a variety of designs, it being the goal to provide a secure attachment of the steel tank 200 to the pedestal 300.
As has been described, the various structures described above and shown in the figures, enable a novel and non-obvious method for constructing a composite elevated tank. In general, the primary steps of the construction of such a composite elevated tank involve preparing a foundation 310 for a pedestal 300 at a site pedestal location 11 of water tank site 10. The pedestal 300 is constructed at the site pedestal location 11 by successively placing formwork into which steel reinforcement and wet concrete are placed. The pedestal 300 reaches higher elevations during the construction. Site 10 also can include (but is not mandatory) a temporary tank location 12. Steel tank 200 can (but need not) be built at the temporary tank location 12 concurrently with the construction of the pedestal 300. Temporary tank construction supports 20, on which the steel tank 200 will be constructed for later removal, are prepared at the temporary tank location 12. These steps in the construction method are not limited to the order described here, it being the intent to merely describe an embodiment for ease of description. Base plates 22 are welded to a skirt 21, which is welded to a first cone section 210. Additional cone sections 211 are welded to first cone section 210. For tanks having a suspended bottom 214, the plates making up the suspended bottom are welded to the underside of the first cone section 210. For tanks including an optional access tube 215, the access tube 215 is typically welded to the bottom. Consecutive plates of the tank shell 212 are welded to form the shell of the tank. For tanks having a roof geometry that requires an upper rim angle for support, the upper rim angle 216 is welded to the upper-most plate of tank shell 212. The tank roof 213 is then placed and welded to the upper rim angle 216 to complete the steel tank 200. For certain embodiments, as part of the final pour of the concrete pedestal 300, tank anchor assemblies 311 with anchors 314 are placed at the top of the final formwork. At least one insulator 316 is coupled between or within the bottom surface 313 of the tank anchor assemblies 311 and/or the top surface of the concrete. For certain embodiments using the type of tank anchor assemblies 311 shown in
While several embodiments have been described and illustrated herein, those of ordinary skill in the art will readily envision a variety of other means and/or structures for performing the function and/or obtaining the results and/or one or more of the advantages described herein, and each of such variations and/or modifications is deemed to be within the scope of the embodiments described herein. More generally, those skilled in the art will readily appreciate that all parameters, dimensions, materials, and configurations described herein are meant to be exemplary and that the actual parameters, dimensions, materials, and/or configurations will depend upon the specific application or applications for which the teachings is/are used. Those skilled in the art will recognize, or be able to ascertain using no more than routine experimentation, many equivalents to the specific embodiments described herein. It is, therefore, to be understood that the foregoing embodiments are presented by way of example only and that, within the scope of the appended claims and equivalents thereto, embodiments may be practiced otherwise than as specifically described and claimed. Embodiments of the present disclosure are directed to each individual feature, system, article, material, and/or method described herein. In addition, any combination of two or more such features, systems, articles, materials, and/or methods, if such features, systems, articles, materials, and/or methods are not mutually inconsistent, is included within the scope of the present disclosure.
All definitions, as defined and used herein, should be understood to control over dictionary definitions, definitions in documents incorporated by reference, and/or ordinary meanings of the defined terms.
The indefinite articles “a” and “an,” as used herein in the specification and in the claims, unless clearly indicated to the contrary, should be understood to mean “at least one.”
The phrase “and/or,” as used herein in the specification and in the claims, should be understood to mean “either or both” of the elements so conjoined, i.e., elements that are conjunctively present in some cases and disjunctively present in other cases. Multiple elements listed with “and/or” should be construed in the same fashion, i.e., “one or more” of the elements so conjoined. Other elements may optionally be present other than the elements specifically identified by the “and/or” clause, whether related or unrelated to those elements specifically identified. Thus, as a non-limiting example, a reference to “A and/or B”, when used in conjunction with open-ended language such as “comprising” can refer, in one embodiment, to A only (optionally including elements other than B); in another embodiment, to B only (optionally including elements other than A); in yet another embodiment, to both A and B (optionally including other elements); etc.
As used herein in the specification and in the claims, “or” should be understood to have the same meaning as “and/or” as defined above. For example, when separating items in a list, “or” or “and/or” shall be interpreted as being inclusive, i.e., the inclusion of at least one, but also including more than one, of a number or list of elements, and, optionally, additional unlisted items. Only terms clearly indicated to the contrary, such as “only one of” or “exactly one of,” or, when used in the claims, “consisting of,” will refer to the inclusion of exactly one element of a number or list of elements. In general, the term “or” as used herein shall only be interpreted as indicating exclusive alternatives (i.e. “one or the other but not both”) when preceded by terms of exclusivity, such as “either,” “one of,” “only one of,” or “exactly one of.” “Consisting essentially of,” when used in the claims, shall have its ordinary meaning as used in the field of patent law.
As used herein in the specification and in the claims, the phrase “at least one,” in reference to a list of one or more elements, should be understood to mean at least one element selected from any one or more of the elements in the list of elements, but not necessarily including at least one of each and every element specifically listed within the list of elements and not excluding any combinations of elements in the list of elements. This definition also allows that elements may optionally be present other than the elements specifically identified within the list of elements to which the phrase “at least one” refers, whether related or unrelated to those elements specifically identified. Thus, as a non-limiting example, “at least one of A and B” (or, equivalently, “at least one of A or B,” or, equivalently “at least one of A and/or B”) can refer, in one embodiment, to at least one, optionally including more than one, A, with no B present (and optionally including elements other than B); in another embodiment, to at least one, optionally including more than one, B, with no A present (and optionally including elements other than A); in yet another embodiment, to at least one, optionally including more than one, A, and at least one, optionally including more than one, B (and optionally including other elements); etc.
It should also be understood that, unless clearly indicated to the contrary, in any methods claimed herein that include more than one step or act, the order of the steps or acts of the method is not necessarily limited to the order in which the steps or acts of the method are recited.
In the claims, as well as in the specification above, all transitional phrases such as “comprising,” “including,” “carrying,” “having,” “containing,” “involving,” “holding,” “composed of,” and the like are to be understood to be open-ended, i.e., to mean including but not limited to. Only the transitional phrases “consisting of” and “consisting essentially of” shall be closed or semi-closed transitional phrases, respectively, as set forth in the United States Patent Office Manual of Patent Examining Procedures, Section 2111.03.
It is to be understood that the embodiments are not limited in its application to the details of construction and the arrangement of components set forth in the description or illustrated in the drawings. The invention is capable of other embodiments and of being practiced or of being carried out in various ways. Unless limited otherwise, the terms “connected,” “coupled,” “in communication with,” and “mounted,” and variations thereof herein are used broadly and encompass direct and indirect connections, couplings, and mountings. In addition, the terms “connected” and “coupled” and variations thereof are not restricted to physical or mechanical connections or couplings.
The foregoing description of several embodiments of the invention has been presented for purposes of illustration. It is not intended to be exhaustive or to limit the invention to the precise steps and/or forms disclosed, and obviously many modifications and variations are possible in light of the above teaching.
Number | Name | Date | Kind |
---|---|---|---|
2567958 | Mummert | Sep 1951 | A |
2679853 | Bryant | Jun 1954 | A |
2683550 | Mummert | Jul 1954 | A |
2741268 | Plunkett | Apr 1956 | A |
3073573 | Haskins | Jan 1963 | A |
3219224 | Anderson | Nov 1965 | A |
3235956 | Heathcote | Feb 1966 | A |
3300916 | Pritzker | Jan 1967 | A |
3805369 | Harper | Apr 1974 | A |
4312167 | Cazaly | Jan 1982 | A |
4327531 | Cazaly | May 1982 | A |
4403460 | Hills | Sep 1983 | A |
4486989 | Desrochers | Dec 1984 | A |
4494291 | Morrison | Jan 1985 | A |
4578921 | Cazaly | Apr 1986 | A |
4660336 | Cazaly | Apr 1987 | A |
5029426 | Larson | Jul 1991 | A |
5131201 | Larson | Jul 1992 | A |
6282863 | Christian | Sep 2001 | B1 |
6318034 | Zavitz | Nov 2001 | B1 |
7044072 | Converse | May 2006 | B2 |
7162844 | Morrison | Jan 2007 | B2 |
7188574 | Converse | Mar 2007 | B2 |
7500592 | Petricio Yaksic | Mar 2009 | B1 |
8261510 | Johnson | Sep 2012 | B2 |
8820009 | Johnson | Sep 2014 | B2 |
9217255 | Mork | Dec 2015 | B2 |
9556626 | Mork | Jan 2017 | B2 |
20130031854 | Johnson | Feb 2013 | A1 |
20150368038 | Oren | Dec 2015 | A1 |
20160168873 | Neighbors | Jun 2016 | A1 |
Number | Date | Country |
---|---|---|
2339703 | Sep 2001 | CA |
106697625 | May 2017 | CN |
1493697 | Sep 1967 | FR |
Entry |
---|
VSL International; Concrete Storage Structures Use of the VSL Special Construction Methods, 51 pages, dated May 1983. |