The invented ‘Composite RCC deck and prestressed parabolic bottom chord underslung open web steel girder bridge superstructure’ falls in the area of Bridge Engineering in Civil Engineering. The short (10 m) to long (200 m) span superstructures can be used for infrastructure projects related to single or multiple lane road, rail, metro rail, fly over and sea link.
In road, rail and metro rail like transportation systems, bridges are frequently required to cross rivers, as flyovers and sea links etc. For bridges high tensile strength (HTS) steel cables are very economical, using which long span suspension bridges, cable stayed bridges, and more recently stressed ribbon bridges are constructed. However, HTS cables are very flexible and this results in structural disadvantage in the bridge.
Using shear connectors, when RCC deck slab is made composite with the top chord of an under slung open web steel girder bridge superstructure, its buckling is prevented and strength and stiffness of the bridge significantly increase. Prestressing of the bottom chord, apart from inducing favourable pre-compression in the deck slab, counters its tension due to the applied loads, and it also exerts balancing upward thrust. This type of bridge using HTS cables in the bottom chord, is invented for its high strength. Bottom chord profile of the bridge, if made parabolic (polygon shaped), results in its uniform tension under uniformly distributed load due to self-weight or live load, which facilitates its prestress. Thus, ‘Composite RCC deck and prestressed parabolic bottom chord underslung open web steel girder bridge superstructure’, henceforth referred to as ‘the prestressed composite bridge’ is invented.
It was aimed to invent a robust prestressed composite bridge superstructure, which has high strength, low structural steel consumption, low cost, high reserve strength and easy erection, where substructure and superstructure constructions may be planned as parallel activities reducing the construction time and cost. It was also aimed to provide a bridge superstructure solution of this kind, which is suitable for short spans (10 m), as well as for long spans (200 m), for single or multiple lane road, rail, metro rail, fly over and projects like coastal links.
Typical design and approximate erection stage analysis examples of the prestressed composite bridge for 125 m span and 50 m span are given. While girder stresses under all erection stages are low and safe, member stresses under Serviceability Limit State (SLS) condition are also very safe, as the limiting deflection in SLS condition is governing.
Maximum deflections under SLS condition for 2-lanes of class-A IRC loading is 155.6 mm with 2.65 t/m average steel off take for 125 m span, and 57.6 mm with 1.77 t/m average steel off take for 50 m span bridges.
Due to low SLS condition stresses, conservative reserve strength of the bridge beyond SLS condition up to yield condition for the 125 m span bridge is 3.2 times the live load in SLS condition, and for the 50 m span it is 2.8 times. Therefore, design and construction methodology of this type of bridge supported with design guidelines as per existing codes of practice is invented.
Summary of design and erection stage analysis results for the 125 m and 50 m span bridges in terms of steel off take, member stresses, prestress applied and deflection under live load are given in table-1.
From the results it is seen that the prestressed composite bridge superstructures are economical, stiff, and have high reserve strength.
The above and still further features and advantages of embodiments of the present invention will become apparent upon consideration of the following detailed description of embodiments thereof, especially when taken in conjunction with the accompanying drawings, and wherein:
For better comprehension, figure titles and brief descriptions are also given in Table-2.
The headings used herein are for organizational purposes only, and are not meant to be used to limit the scope of the description or the claims. As used throughout this application, the word “may” is used in a permissive sense (i.e., meaning having the potential to), rather than the mandatory sense (i.e., meaning must). Similarly, the words “include”, “including”, and “includes” mean including but not limited to. To facilitate understanding, like reference numerals have been used, where possible, to designate like elements common to the Fig. s. Optional portions of the Figs. may be illustrated using dashed or dotted lines, unless the context of usage indicates otherwise.
A typical 125 m span and 9 m deep composite prestressed 2-lane open web steel girder bridge is designed for which 2-d line sketch is given in
Typical anchorage system at the supports of the under slung bridge superstructure is shown in
Using FEM software, the superstructure is analyzed as space frame with the composite deck modeled as plate elements, for which the model is shown in
Maximum deflection of the bridge under live load is 155.6 mm, which is within the prescribed limit of Span/800. Average steel off take of the bridge superstructure is 2.65 t/m, which is significantly lower than similar open web steel girder superstructure steel offtake. Parallel 125 m span 10 m deep and 12.5 m deep girder models are also analyzed and the results of the 9 m, 10 m and 12.5 m deep girders are compared.
The bridge girder panels may be fabricated in the workshop using welded or HSFG bolted connections. The panels are transported to the site where these are assembled and connected, and the individual girders are lifted to securely placed over the bearings using jacks or cranes or any other suitable device. The cross members for top and bottom chords may be then connected. Deck slab for the superstructure is cast in symmetrical parts using bonding agent and stage prestressing.
HTS prestressing cables are laid in the parabolic bottom chord. Prestressing of the strands is carried out in stages as per design. Results of the different construction stages for member stresses and maximum deflection are shown in
Typical example for stage prestressing is given below for the two number 27T15 cables in each bottom chord.
Stage 1: Launch the girder including cross members, cross girders and stringer beams and suitably apply a prestress of 2000 kN (
Stage 2: Apply additional 2000 kN prestress (
Stage 3: Cast deck slab in ⅕th spans from either end. This stage includes construction load of 5 kN/m2. Deflection at mid span of the girder in this stage is 3.5 mm (upward).
Stage 4: Apply additional 1000 kN prestress after 10 days of concreting in Stage 3 and cast next ⅕th spans (11). Deflection at mid span of the girder in this stage is 121.7 mm (downward).
Stage 5: Apply additional 1000 kN prestress after 10 days of concreting in Stage 4 and cast central ⅕th span (11). Deflection at mid span of the girder in this stage is 7.6 mm (downward).
Stage 6: Prestress by additional 3100 kN force after 28 days of applying SIDL on the deck (11). Deflection at mid span of the girder in this stage is 75.5 mm (upward).
As an alternative, two stage prestressing, first before deck casting, and second after its hardening may be better.
Live load is now applied on the bridge. Deflection at mid span of the girder in this stage is 80.5 mm (downward). Additional prestress can be applied in due course of time to make up for tine dependent losses etc., reflected in terms of sagging deflection.
Another typical 50 m span and 2.5 m deep composite prestressed 2-lane open web steel girder bridge is designed (
FEM model and axial stress diagram in service condition are given in
It is assumed that after application of prestress, the girders become horizontal and cables carry total permanent load and half the live load with impact. Finer prestress adjustment for losses etc. may be carried out as required for the final deck profile.
Taking parabolic bottom chord center as origin, equation for it is;
Provide 2 no. 19T15 (3870 kN) cables.
Taking 19T15 cable stressed after deck slab hardening, prestress applied along the two bottom chords;
Adding tensile strength of concrete say 1.4 N/mm2, and keeping cross girder spacing suitably, deck slab can be designed on no-crack basis, which is highly desirable for the composite deck.
The typical examples of 125 m span, 9 m deep and 50 m span 2.5 m deep, 2-lane highway superstructure girders are optimized to result in steel off take of 331.0 t and 88.5 t, respectively. The maximum deflections due to live load at mid span are 151.3 mm and 57.6 mm respectively for the 125 m and 50 m spans which are within the permissible deflection of Span/800.
For the 125 m span bridge, the axial member stresses during erection and concreting of the deck are checked with prestressing applied at different stages as per design to be safe. The limiting live load for elastic condition is found to be 3.2 times the SLS live load for the 125 m span, and 2.8 times for the 50 m span, confirming their robustness. In the case of the 125 m span, for parallel 10 m and 12.5 m deep girder examples, steel off takes are 310 t and 299 t, and corresponding live load deflections are 135.5 mm and 140.1 mm, respectively.
Concrete Grouting: Dead weight of the superstructure is fully supported by the prestress alone with favorable precompression in the RCC deck, and hence, expansive concrete grouting of the box sections is desirable. The Concrete Filled Steel Tube (CFST) now becomes composite, providing additional strength and stiffness to the bridge superstructure.
Number | Date | Country | Kind |
---|---|---|---|
202111043274 | Sep 2021 | IN | national |
PCT/IN2022/050200 | Mar 2022 | WO | international |