The invention relates to a construction arrangement of an elevator and to a method, and particularly to construction time protection of persons and/or components located in a lower portion of a hoistway of an elevator. The elevator is preferably an elevator for transporting passengers and/or goods.
When an elevator or a building surrounding it is under construction, there may be installation workers in the lower parts of the elevator hoistway carrying out construction work. Also, the lower parts of the hoistway may already be in construction-time transport use. During construction, there is an increased risk of objects falling into the lower parts of the hoistway. For example, tools or construction material may fall into the hoistway. Persons and components located in the lower parts of the hoistway must be protected from falling objects.
One known technique to improve construction process efficiency is a construction-time use CTU elevator with a temporary machine room that can be moved, in other words jumped, upwards as construction progresses. The CTU elevator, such as a jump-lift, enables a faster and safer construction process, earlier closing of the facade, reduced down-time, and safer transportation in all weather conditions. The construction-time elevator enables that construction of the elevator hoistway and elevator installations may continue at higher floors while the elevator is already operating in the same elevator hoistway at the lower floors, below a protection deck that may be called a crash deck in the midway of the hoistway.
The protection deck such as the crash deck above the elevator allows the use of the elevator during construction-time and protects the running elevator. A construction-time elevator system may comprise multiple crash decks on top of each other a distance from each other. When the structure of the building rises, the crash deck is moved a few floors up.
Prior art protection decks have been disclosed in documents EP2636629 B1 and EP3388379 A1, for example.
A drawback of known solutions has been that they have been relatively complicated, and a lot of rearranging has been needed during the process during progress of the construction.
The object of the invention is to introduce an improved construction time arrangement of an elevator and a method for constructing an elevator. An object is to introduce a solution by which one or more of the above defined problems of prior art and/or drawbacks discussed or implied elsewhere in the description can be solved.
It is brought forward a new construction arrangement of an elevator, comprising: a hoistway; a protection deck arranged within the hoistway for protecting the portion of the hoistway below it from falling objects; wherein the protection deck comprises: a frame mounted on stationary structure of the hoistway; a cover co-operating with the frame and extending across the hoistway, wherein the cover is adapted to protect the hoistway from falling objects and/or water from falling into the hoistway below it. The frame of the protection deck is, without dismantling it, configured to be increased and/or decreased in size, individually in at least one direction in relation to the corresponding adjacent stationary structure, such as a wall, of the hoistway.
It is also brought forward a new method for constructing an elevator comprising mounting a protection deck within a hoistway for protecting the portion of the hoistway below it from falling objects; wherein the protection deck comprises: a frame mounted on stationary structure of the hoistway; a cover co-operating with the frame and extending across the hoistway, wherein the cover is adapted to protect the hoistway from falling objects and/or water from falling into the hoistway below it. The frame of the protection deck is, without dismantling it, configured to be increased and/or decreased in size, individually in at least one direction in relation to the corresponding adjacent stationary structure, such as a wall, of the hoistway.
Advantageously the invention provides a non-parametric protection deck solution for variable hoistway dimensions. Thus, the protection deck is adjustable and re-usable and supports sustainability in construction.
Preferable further details of the invention are introduced in the following, which further details can be combined individually or in any combination.
According to some embodiments the frame is configured to be increased and/or decreased in size in width direction in relation to the corresponding adjacent stationary structure of the hoistway. According to some embodiments the frame is configured to be increased and/or decreased in size in length direction in relation to the corresponding adjacent stationary structure of the hoistway.
According to some embodiments the cover of the protection deck is, without dismantling it, together with the frame, configured to be increased and/or decreased in size, individually in at least one direction in relation to the corresponding adjacent stationary structure such as the wall of the hoistway.
Preferably the protection deck is individually size adjustable substantially in four directions at sides of four stationary structures of the hoistway, a first side wall, a second side wall opposite to the first side wall, a front wall, and a back wall opposite to the front wall.
The adjustability of the protection deck allows to move and install the protection deck in the hoistway in variable height positions where the width and/or the length of the hoistway may be larger or smaller than in a previous location of the protection deck, without substantially dismantling the protection deck. Advantageously the protection deck can be assembled from side wall to side wall and from front wall to back wall in the hoistway, and further lifted in the hoistway without dismantling.
In a preferred embodiment the protection deck frame is stretchable and contractable to form an outermost frame perimeter shape which differs from a rectangular shape. One advantage of this is that size anomalies and size deviations in a constructed hoistway or in a hoistway to be retrofitted do not harm the assembly of the protection deck.
According to some embodiments the frame comprises frame corners formed of two neighbouring frame beams connected to each other via a corner fixing element or directly, for example via a bolt or pinion fixing. Preferably the frame beams are adjustable in length. Preferably four frame beams form substantially the perimeter shape of the frame when assembled to each other.
Preferably the frame comprises joints between beams to allow an articulated movement of the beams in the frame in relation to each other. The frame may comprise joints between the frame beams and the support beams; and between neighbouring frame beams, to allow an articulated movement of said beams in relation to each other.
Preferably the frame comprises corner joints to allow an articulated movement of the frame beams in relation to each other. The corner fixing element may comprise the joint, and the frame beams may be assembled to the corner fixing element. The joint may be a bolt in a hole joint. The joint may be constituted of an auxiliary hinge. The hole may be oversized in comparison to the bolt to enable a play. A kind of swivel connection of the frame beams may be enabled by a predetermined movement gap in the assembly between two frame beams.
Preferably the frame comprises support beams between the frame beams such that the support beams are connected at their ends to two opposite frame beams. Preferably the support beams are adjustable in length. Preferably the frame comprises support beam joints to allow an articulated movement of the support beams in relation to the frame beams.
The length adjustability of the frame beams and the support beams, together with the articulating corner joints and support beam joints makes it possible to stretch and/or contract the frame in a shape deviating from a substantially rectangular shape. Preferably the adjusting operation can be done without dismantling the frame.
According to some embodiments the protection deck is suitable for hoistway layouts with dimensions ranging from 1600 mm×2000 mm to 3200 mm×3200 mm. According to some embodiments the arrangement comprises at least one elevator unit movable in the hoistway, including at least an elevator car. According to some embodiments the elevator arrangement covers elevator solutions ranging from 630 kg to 1600 kg.
Since the deck frame can be lifted upwards and/or downwards inside the shaft without dismantling the construction, the overall installation time shortens and thus the costs are lowered. According to some embodiments this is possible by using a suitable hoisting point tool. According to some embodiments lifting of the deck in the hoistway is performed with a dedicated light-weight tool on an upper landing or an upper landing sill from upper floors or hooks in the stationary structures of the hoisting point hoistway. The light weight of the hoisting point tool makes the installation easier, and the tool may be mounted on upper positions as the construction proceeds and the building rises.
According to some embodiments the protection deck frame is designed to co-operate with, among others, hoisting tools. Use of non-parametric frame co-operating with a related preferably non-parametric cover makes it possible to move the deck and/or change the size of the deck in variable hoistway dimensions and layouts without dismantling the protection deck.
According to some embodiments the arrangement comprises a first hoisting apparatus for hoisting construction material below the protection deck. According to some embodiments the first hoisting apparatus is supported by the protection deck, and the first hoisting apparatus comprises a first hoisting machine mounted on the protection deck, and a first flexible tension member movable with the first hoisting machine.
According to some embodiments the arrangement comprises a second hoisting apparatus for hoisting a load below the protection deck supported by the protection deck, said load preferably being an installation platform or a movable machine room of an elevator located below the protection deck or an elevator car below the protection deck. According to some embodiments the second hoisting apparatus comprises a second hoisting machine and a second flexible tension member movable with the second hoisting machine.
Said stationary structures may be opposite vertical wall faces of the hoistway. In a preferred embodiment the frame is mounted to the four hoistway corners formed of the two pairs of opposite vertical wall faces of the hoistway. In a preferred embodiment the arrangement comprises corner anchoring interfaces to be attached to hoistway corners. The hoistway corners are formed of two neighbouring stationary structures of the hoistway such as the walls of the hoistway. Preferably the protection deck frame comprises corner fixing elements to be attached to the anchoring interfaces. Preferably the corner fixing elements are designed to reduce drilled fixing elements and number of holes in the walls of the hoistway.
In a preferred embodiment the frame comprises at least in one frame corner a lifting connector, such as a hook or an eye or a gripper, allowing lifting of the deck, which connectors preferably are integrated with the corner fixing elements.
According to some embodiments the frame comprises at least one center support fixing element to be attached to the structure between two adjacent hoistway corners, and preferably to be used at least when the dimension between two adjacent hoistway corners exceeds above a predetermined value.
In a preferred embodiment, the arrangement comprises at least one further protection deck mounted within the hoistway for protecting the portion of the hoistway below it from falling objects. The at least one further protection deck may be a horizontal protection deck configured to be used as a crash deck. The at least one further protection deck may be a diagonally aligned or deflected protection deck configured to be used as top protection deck. Preferably the diagonally aligned or deflected protection deck is disposed at an upper/top height as the building rises or a top region of the hoistway constructed so far.
According to some embodiments the frame comprises retractable and contractable frame beams which preferably are angular adjustable. In a preferred embodiment two substantially parallel frame beams fixed together with a plurality of cross beams mainly form the frame. According to some embodiments the protection deck comprises engagement members to be engaged with a first side and second side of the hoistway, which first and second side are opposite sides of the hoistway. The first engagement member may be called sill fixture for engagement of the protection deck with the sill of a landing. Preferably the first engagement member is connected pivotally to the lower part of the frame and the second engagement member is connected pivotally to the upper part of the frame. In mounted state of the protection deck in the hoistway the first engagement member may rest again the sill of the landing and the second engagement member is engaged with the opposite wall. According to some embodiments the protection deck comprises at least one pivotable bridge safety balustrade on one side or both sides of the frame, the balustrade acting as a pivotable side frame of the protection deck when turned from the vertical position 90 degrees over the hoistway. Preferably the frame beams and support beams are retractable and contractable.
According to some embodiments the cover comprises several different shaped sections slightly overlapping each other. In a preferred embodiment the cover material comprises biomaterial. In a preferred embodiment the cover material comprises biocomposite such as polymer resin and biofiber. Preferably the cover material is recyclable. In a preferred embodiment the cover comprises a honeycomb structure comprising a biomaterial comb construction.
The invention provides a solution by which construction time protection and material hoisting can be provided safely and simply. Further the invention provides a non-parametric protection deck solution for variable hoistway dimensions. In a non-parametric design, the protection deck fits in various shaft/hoistway layouts and covers a large portion of volume elevator hoistway dimensions requirements. Also, the invention provides adjustable construction for different hoistway sizes. Further the invention allows reducing the number of anchoring bolts for the protection deck and related holes to the stationary structures such as walls of the hoistway. Further with the invention support cavities or pockets in the stationary structure of the hoistway are avoided. Further the protection deck may be adapted elevator platforms regardless the layout requirement or dimensions of elevator layout. Further the invention allows increasing re-usability and retro fitting of the protection deck and supports sustainability. Advantageously the protection deck as a whole and/or the protection deck frame can be moved upwards and downwards in the hoistway of the elevator without dismantling it, preferably by using suitable hoisting point tool. Further the invention allows reducing cost in material and installation. Installation time can be saved, and earlier commissioning of an elevator can be achieved.
Further with the invention working ergonomics can be enhanced.
In the following the present invention will be described in closer detail by means of preferred embodiments with reference to the attached drawings, in which:
In
Preferably the size of the frame 4 and the cover 3 can be increased and/or decreased substantially in a first and/or a second direction across the hoistway 1, and additionally the size of the frame 4 and the cover 3 can be increased and/or decreased substantially in a third and/or fourth direction, substantially orthogonal to the first and second directions, across the hoistway 1. The first and second directions may be called width direction W (forward and backward width direction) of the hoistway, and the third and fourth direction may be called length direction L (forward and backward length direction) of the hoistway.
The protection deck 2 comprises a first hoisting apparatus 5 for hoisting construction material below the protection deck 2. The first hoisting apparatus 5 is supported by the protection deck 2. The first hoisting apparatus 5 comprises: a first hoisting machine 5a mounted on the protection deck 2, preferably in particular on the frame 4 thereof; and a first flexible tension member 5b movable with the first hoisting machine 5a.
As illustrated in
The frame 4 is mounted to four hoistway corners 1a/1b, 1b/1c, 1c/1d and 1d/1a formed of the two pairs of opposite vertical wall faces 1a, 1c and 1b, 1d of the hoistway. The construction arrangement comprises corner anchoring interfaces 14 which are attached to said corners of the hoistway 1. The frame 4 comprises four corner fixing elements 11 (shown in
The frame 4 comprises frame corners, each formed of two neighbouring frame beams 40a, 40, 40b; 140a, 140, 140b; 40b′, 40′, 40a′; 140b′, 140′, 140a′ connected to each other via a corner fixing element 11 (
The frame 4 comprises first support beams 41a, 41, 41b and second support beams 42a, 42, 42b between the frame beams 140a, 140, 140b; 140b′, 140′, 140a′ such that the support beams are connected at their ends 15 to two opposite frame beams. The support beams are length adjustable. The support beam end 15 is constructed for example as a fork resting on the supporting frame beam to allow minor assembly work.
As shown in
The width and length of the frame 4 is preferably adjustable. Features facilitating adjustability have been disclosed in detail in
The frame 4 comprises at least one second support beam, preferably 2 to 10, such as four as illustrated in
The protection deck 2 comprises a supporting beam 7 connected pivotally to the frame 4, and a diverting wheel 71 mounted on said supporting beam 7. The flexible tension member 5b is guided to pass from the hoisting machine 5a to the diverting wheel 71, over it and from the diverting wheel 71 downwards in the hoistway 1. The supporting beam 7 is more specifically connected to the frame 4 preferably pivotally around a vertical axis x as well as around a horizontal axis x2 relative to the frame 4. Preferably the location of the diverting wheel 71 relative to the frame is adjustable by pivoting the supporting beam 7 around said axis x and/or said axis x2. The protection deck 2 comprises a second diverting wheel 72 for guiding the flexible tension member 5b to pass from the hoisting machine 5a to the diverting wheel 71.
The height adjustable protection deck 2 with auxiliary equipment is used as movable installation tool for hoisting of large loads such as: an installation platform or a movable machine room of an elevator located below the protection deck 2 or an elevator car 60 below the protection deck 2. For this purpose, the arrangement comprises a second hoisting apparatus 6 for hoisting a load 9, 10 below the protection deck 2 supported by the protection deck 2, said load preferably being an installation platform 9 or a movable machine room 10 of an elevator located below the protection deck 2, for example. The second hoisting apparatus 6 comprises a second hoisting machine 6a and a second flexible tension member 6b movable with the second hoisting machine 6a. A diverting wheel 6c has been mounted on the protection deck 2 for guiding and supporting the second flexible tension member 6b. This also enables mounting of the hoisting machine 6a separate from the protection deck 2. In the embodiment of
The frame 4 is constructed of preferably telescopic beams fixed to the wall with dedicated wall fixings which can locate on every wall, but the corners are preferred to reduce amount of anchor bolts 14′. Preferably the anchor bolts 14′ extend into holes of the wall of the hoistway 1, which hoistway wall preferably comprises concrete.
The first and second frame beams comprise a mid-section 40, 40′; 140, 140′, a first end section 40a, 40a′; 140a, 140a′ and a second end section 40b, 40b′; 140b, 140b′. Said frame beam end sections are longitudinally slidable within the frame beam mid-section to form a retractable and contractable frame beam. Correspondingly the first and second support beams comprise a mid-section 41; 42, a first end section 41a; 42a and a second end section 41b; 42b. Said support beam end sections are longitudinally slidable within the support beam mid-section to form a retractable and contractable support beam, in particular such that the ends 15 of the end sections extend out from the inner space of the mid-section. Naturally according to the concept of the invention at least one of the frame beams and support beams explained above and hereinafter may consist of two or three or four or more than four beam sections, to form a retractable and contractable beam, and is constructed longitudinally movable in direction of the beam, irrespective if any preceding section is arranged inside or outside or adjacent relative to the next section.
Preferably the first support beams 41a, 41, 41b are disposed in the center region of the frame area and are preferably designed heavier than the second support beams. The second support beams may be lighter for cover 3 load bearing. The first support beams 41a, 41, 41b are optimized for load bearing purpose. Preferably the first support beams are constructed for center bearing loads induced from hoisting equipment supported by the protection deck, such as installation platform support and lifting point interface support.
Optionally the arrangement comprises at least one center support fixing element 16, 16′ arranged to fix at least one frame beam to the supporting structure of the hoistway 1. In
A preferred preparatory or first installation of the frame comprises: drilling anchoring interfaces 14 to hoistway corners and/or walls; installing corner fixing elements 11 to the anchoring interfaces 14 and optional center support counter support parts; lifting frame beams to corner fixing elements 11; installing the load bearing first support beams 41a, 41, 41b in the center area to the frame beams and center support fixing elements 16, 16′; connecting the light weight second support beams 42a, 42, 42b to the frame beams; fixing the frame beams to corner fixing elements 11; and installing the lifting connectors such as hooks 17 to frame corners. After this first installation the frame may be lifted without dismantling to variable heights when the fixing elements 11 loosened from the anchoring interfaces 14.
The frame 4 is layered with protective cover 3 to prevent falling objects entering to the lower part of the shaft where a CTU elevator is operating.
Structure and materials of the sheet coverings 3 are designed to fit in different elevator shaft layout configurations and retain required strength to resist impacts of possible falling objects and projectiles from above during shaft mechanics and elevator etc. installation which proceeds to upper floors while elevator operates in shaft below, under the deck.
The cover 3 is designed to fit various layout configurations. The protective cover is installed on the frame 4 inside the elevator shaft.
The cover 3 comprises several different shaped sections slightly overlapping each other. The cover 3 comprises a base plate 3.1 on the middle between the frame beams and the cover can be size optimized in upcoming design rounds. Preferably the base plate comprises two neighboring wings cooperating with each other so that objects are avoided to fall below the cover. The base plate 3.1 may comprise an opening 3.1′ in the middle area of the cover to form installation base for equipment to be mounted on beams such as the first support beams. Further said opening may be used for the flexible tension member 5b which is guided downwards in the hoistway 1.
The cover 3 comprises adjustable first sections 3.2; 3.12 that are configured to move or slide in horizontal level to two separate degrees of freedom. The first sections are overlapping the base plate 3.1 and are disposed at the corner areas of the overall structure of the protection deck 2. In detail of the
The cover 3 comprises adjustable second sections 3.3, 3.4; 3.13, 3.14 that are configured to move or slide adjustably along the first sections 3.2; 3.12 such that they overlap the base plate 3.1. Generally, the first and second sections are adjustably and detachably interlocked by grooves or different forms of mechanical solutions. Preferably the cover is configured to fit for current volume platforms, from 630 kg to 1600 kg elevators.
In detail of
In prior art crash deck covers for example steel plates are used. Also, glass fiber mesh and polycarbonate on steel frame have found use. A known crash deck, the so-called builders deck is hand made of wood material. The cover will be bound to some wear and tear during the usage and will be replaced if damaged. This means with prior solutions unrecyclable waste or usage of heavy weight material.
According to some preferred embodiments the cover 3 material is recyclable, in particular recyclable biomaterial. Preferably the cover material is biodegradable. Crash deck cover sheet provides protection against possible falling projectiles in elevator shaft during shaft mechanic etc. installation. Such protective plates may be replaced after predetermined interval, instead steel frame has a very long shelf life.
According to some preferred embodiments the cover 3 material comprises biocomposite such as polymer resin and biofiber. A biocomposite is a composite material formed by a matrix (resin) and a reinforcement of natural fiber. Preferred biomaterials for the cover are listed hereinafter:
Advantages achieved with selecting biomaterial as cover material 3 are among others: recyclability, upcycling, downcycling, disposal by decomposition, disposal by burning, light weight and improved strength properties, such as impact resistance, easier installation due to reduced weight which leads to cost savings, waste reduction, renewability, and sustainability.
In more detail, flax and hemp reinforcements can be used to create composites, as a function of the process used. They provide: low density (1.5 vs. 2.54 for glass fiber), higher specific stiffness than for glass fiber, better vibration damping than for carbon or glass fiber, better thermal insulation than for carbon fiber, better acoustic insulation than for carbon or glass fiber, good impact response, good fatigue behavior, biodegradability, radio wave transparency, and good hybridization properties.
Preferably the cover 3 may be strengthened by weaving a metal wire mesh into the matrix, if needed also protective layer of gelcoat may be applied to surface for better life span.
In
Prior art topmost hoistway protection and weather proofing deck is mainly constructed on site by builder. Builders deck are usually various beam constructions or wooden beams with top layer composed of veneer or similar. The deck itself is handmade and built for purpose only just to be transformed into waste after dismantling it. Builders decks cannot be used for installation or as lifting interface.
Further, prior art protection deck or platform may be a steel construction of two separate decks placed on beams crossing from the door sill to separate pockets in back wall. Pockets are order bound and must be included in the construction plan of the building. Pockets are fabricated by builder. This type of solution requires planning and co-operation in advance between the elevator supplier frontline and the constructor. If a hoistway specific temporary ceiling or machine room is used to provide lifting interfaces for installation, it will delay the elevator installation work since it is finished last. In current situation different type of scaffolding might be needed in installing the temporary decks.
The frame 4′ comprises telescopic adjustable frame beams 20 which preferably are angular adjustable. In a preferred embodiment two substantially parallel frame beams 20 fixed together with a plurality of cross beams mainly form the frame 4′. The protection deck 2′ comprises engagement members 22, 23 to be engaged with a first side and second side of the hoistway 1, which first and second side are opposite sides of the hoistway. The first engagement member 22 may be called sill fixture for engagement of the protection deck 2′ with the sill of a landing 18. The first engagement member 22 is connected pivotally to the lower part of the frame 4′ and the second engagement member(s) 23 is connected pivotally to the upper part of the frame 4′. In mounted state of the protection deck 2′ in the hoistway 1 the first engagement member 22 rests again the sill of the landing 18 and the second engagement member(s) 23 is engaged with the opposite wall 1c.
The protection deck 2′ comprises at least one pivotable bridge safety balustrade 24 on one side or both sides of the frame 4′. The balustrade 24 is acting as a pivotable side frame of the protection deck when turned from the vertical position 90 (shown in
Using the arrangement explained along
Design solution of the arrangement explained along
Preferably the protection deck 2′ is used for staged installation of an elevator, for sectional installation of an elevator and for zoned and multi zoned installation of an elevator. The protection deck frame 4′ and the protection deck cover 3 are adjustable to suit variable dimensioned elevator hoistway 1. Preferably the adjustability allows to move and mount the protection deck 2′ in the hoistway in variable height positions where the width and/or the length of the hoistway may be larger or smaller than in a previous location of the protection deck, without substantially dismantling the protection deck. Advantageously the protection deck 2′ can be assembled from side wall to side wall and from front wall to back wall diagonally across the hoistway, and further lifted in the hoistway without dismantling. The diagonal assembly position allows to deflect falling objects away from the hoistway.
Advantageously the preparatory or first installation of the diagonal protection deck 2′ begins with sill fixture 22 installation and anchoring. The frame beams 20 are connected to the sill fixture and safety balustrade 24 is mounted. Optional wall brackets 23 may be positioned. The frame beams are turned diagonally across the shaft back wall 1c and wall brackets 23 are fixed, additional support may be provided from door frame with lifting hooks and shackles. The balustrade frame 24 is adjusted to suitable position and height and turned 90 degrees above the hoistway below. The covers 3 are fitted on the frame 4′, 24 and seams between the protection deck and the surrounding structure are sealed. Sealings are preferably attached to the top beam 27.
Along with
Preferably a specially constructed elevator installation tool package is transported to site and assembled when i.e., the building core structure 50 and hoistway 1 reaches for example mid height >3-4 floors, as shown in
Installation of the elevator 100 can be commenced several weeks or months before completion of the building construction and interior finalization. The method suggested here will shorten product handover time to end user drastically, though enabling CTU elevator for contractor.
In
Further the method may comprise mounting the protection deck 2, also called the first protection deck or crash deck 2 and described along
The second hoisting apparatus 6 may be configured to be used with the lifting interface 30 of the second protection deck 2′ in top of the hoistway or with the lifting equipment arranged in connection with the crash deck 2 disposed in the hoistway.
The elevator may be commissioned as soon as building has reached final height and hoistway roof is sealed permanently. Elevator installation is ready as soon as building reaches final height and can start serving material and people flow in unfinished building during the construction. This supports and improves over all internal logistics.
According to an embodiment there is provided a staged installation tool package including sufficient and dedicated equipment designed for the purpose of staged elevator installation, including at least one of the following: the non-parametric upper position and top position inclined/deflected/diagonal protection deck 2′ equipped with the lifting interface 30; the non-parametric mid hoistway horizontal protection deck called also crash deck 2, the hoisting point tool 80; necessary ad hoc equipment and tools and a suitable transport packaging. Such a tool package improves the installation, site logistics and internal people and material flow of the building, in addition to phased installation in multiple shafts concurrently. Such an installation tool package supports and improves sustainability of the elevator installation.
In the application, several details for the arrangement have been presented as preferred. This means that they are preferred, however they are not to be understood as necessary, because it may be that the arrangement can be implemented also without them.
It is to be understood that the above description and the accompanying figures are only intended to illustrate the present invention. It will be obvious to a person skilled in the art that the invention can be varied and modified without departing from the scope of the invention.
This application is a continuation of PCT International Application No. PCT/EP2021/073645 which has an International filing date of Aug. 26, 2021, the entire contents of which are incorporated herein by reference.
Number | Date | Country | |
---|---|---|---|
Parent | PCT/EP21/73645 | Aug 2021 | WO |
Child | 18434160 | US |