The present invention relates to a construction method for a new underground structure, and in particular to a construction method for a new underground structure by which a reduction in the load imposition of the new underground structure on an existing underground structure and a reduction in construction cost can be achieved.
When various structures, such as a building, are rebuilt, an existing structure is required to be dismantled, but, when the existing structure is equipped with an underground structure, such as a basement floor, the existing underground structure is also required to be dismantled. However, an underground exterior wall, a post, an underground beam, a foundation, and the like which constitute the existing underground structure bear soil pressure from surrounding soil, and therefore haphazard dismantlement may cause ground collapse, ground displacement, or the like, resulting in a considerable influence on neighboring areas.
Then, a method for newly building an underground structure without dismantling an existing underground structure is suggested in a patent document 1.
According to the construction method for an underground structure suggested in the patent document 1, first, a strut is set up to a floor-height middle portion of an existing underground exterior wall of the first basement floor, and floor beams are removed while pressure is applied to the strut in the direction of the exterior wall via by a jack. This series of operations are performed on each floor, a new wall is placed within the existing underground exterior wall so as to construct a combined wall with the existing underground exterior wall, and then the floor beams are removed. This series of operations are performed on each floor so that a new underground structure is constructed.
Patent Document 1: Japanese Patent Application Laid-open Publication No. 2005-201007
According to the construction method for an underground structure disclosed in the patent document 1, however, since the combined wall to be constructed is for integrating the existing underground exterior wall and a new wall with each other, the load imposition acting downstairs increases. Therefore, a larger supporting force is required to support this load, which causes the problem of increasing construction cost.
The present invention has been made in view of these circumstances, and an object thereof is to provide a construction method for a new underground structure, which can achieve reduction in the load imposition of a new underground concrete framework on an existing underground concrete framework, and reduction in construction cost for building the new underground concrete framework.
In order to achieve the above object, the present invention provides a construction method for a new underground structure by which a new underground concrete framework is constructed without entirely dismantling an existing underground concrete framework, wherein: a fluidized soil wall is constructed by filling an inner circumferential face of the existing underground concrete framework with fluidized soil, and a new underground concrete framework is constructed on the inner circumferential face of the fluidized soil wall.
Further, in order to achieve the above object, the present invention provides a construction method for a new underground structure by which an existing underground concrete framework is partially utilized to construct a new underground concrete framework without entirely dismantling and removing the existing underground concrete framework, the method including: vertically providing a first formwork body on an inner circumferential face of the existing underground concrete framework at a predetermined distance from the existing underground concrete framework; filling a space between the existing underground concrete framework and the first formwork body with fluidized soil to construct a fluidized soil wall; vertically providing a second formwork body on an inner circumferential face of the fluidized soil wall at a predetermined distance from the fluidized soil wall; and casting concrete in between the fluidized soil wall and the second formwork body to construct a new underground concrete framework.
In this case, it is desired that the first formwork body and the second formwork body are kept upright by separators, and further it is desired that the first formwork body and the second formwork body are formwork panels formed by bending and cutting a plate-like steel material into a substantially rectangular front shape and a substantially angular-wave-like cross-sectional shape.
According to the present invention, since the new underground concrete framework formed within the existing underground concrete framework is composed of the fluidized soil wall and the new underground concrete framework when a new underground structure is constructed, the usage of concrete can be reduced as compared with the case where the new underground concrete framework is composed of only the new underground concrete framework. Further, since fluidized soil has a lower specific gravity than concrete, the load imposition of the new underground concrete framework on the existing underground concrete framework can be reduced.
Hereinafter, a construction method for a new underground structure according to an embodiment of the present invention will be described with reference to the drawings.
As shown in
The underground pit in this underground structure is an underground space for housing piping equipment or the like, but it is unnecessary to provide the underground pit if the basement has a space for housing piping equipment or the like. Further, though the underground structure shown in
When an existing underground structure is dismantled, a post and the like which were used to construct the underground structure are dismantled, and only the existing underground concrete framework 200 composed of an existing beam 201, an existing load-bearing wall 202, and an existing foundation (foundation/underground beam) 203 remains.
Within this existing underground concrete framework 200, the fluidized soil wall 300 is constructed. This fluidized soil wall 300 is constructed by filling with fluidized soil (backfill material that is slurry backfill soil which has been preliminarily blended with cement in a controlled manner in a plant and which is fluidized so that it can be cast by a pump). Specifically, the fluidized soil wall 300 is constructed by driving formwork panels 500 within the existing underground concrete framework 200 at a predetermined distance therefrom, keeping the formwork panels 500 upright by separators 501, filling a space between the formwork panels 500 and the existing underground concrete framework 200 with the fluidized soil, and solidifying the fluidized soil.
Then, a new framework, that is, the new underground concrete framework 400, is constructed within the fluidized soil wall 300. The new underground concrete framework 400 is composed of a new slab 401 which constitutes the floor of the basement and the ceiling of the underground pit, a new beam 402, and a new wall 403. This new underground concrete framework 400 is constructed by driving formwork panels 600 within the fluidized soil wall 300 at a predetermined distance therefrom, coupling these formwork panels 600 with the formwork panels 500 of fluidized soil wall 300 described above by means of separators 601 to keep the formwork panels 600 upright, and casting concrete in between the formwork panels 500 of the fluidized soil wall 300 and the new formwork panels 600.
As shown in
It should be noted that, in the embodiment, a direction in which this ridges 11 are formed is defined as a longitudinal direction of the formwork panel 500, and a direction perpendicular to the longitudinal direction is defined as a lateral direction of the formwork panel 500.
As shown in
Further, in both ends of the ridge 11 in the panel lateral direction, that is, on boundary lines between the ribs 12 and the grooves 16 adjacent to the ribs 12, slits 13 each having a predetermined length are provided at predetermined distances like broken lines in parallel with the ridges 11. By bending the formwork panel 500 at a predetermined angle along this row of broken-line-like slits 13, a corner portion can be formed in the formwork. Further, by bending the formwork panel 500 along this row of broken-line-like slits 13 forward and backward alternately and repeatedly, the formwork panel 500 can easily be cut into a desired size.
This slit 13 is a slit having a very narrow width and a predetermined length and penetrating the formwork panel 500. This slit 13 is formed so as to have a width (clearance) and a length which allow discharge of excess water contained in concrete or fluidized soil but do not allow leakage of liquid concrete or fluidized soil from the slit 13 after casting of concrete or filling with fluidized soil.
The top face 31 of the ridge 11 is provided with a plurality of flap-like lids 14. By opening these lids 14, separator insertion holes are formed. By inserting the above-described separators 501 and 601 into these separator insertion holes and fastening the separators together by a predetermined method, the formwork panels 500 and 600 can be kept upright.
As shown in
In order to construct the fluidized soil wall 300, first, the formwork panels 500 are driven, then anchors 307 are driven into the existing underground concrete framework 200, then these driven anchors 307 are coupled with the separators 501, then the formwork panels 500 are kept upright by these separators 501, and then the space between the formwork panels 500 and the existing underground concrete framework 200 is filled with fluidized soil, resulting in construction.
Washers 301 and 302 each having its both ends bent are provided at connections between the formwork panels 500 and the separators 501. The washer 301 is provided on the back face of the formwork panel 500 (on the side of the existing underground concrete framework 200), and fastened to the formwork panel 500 by a nut 303. The washer 302 is provided on the front side of the formwork panel 500 (on the side of the new underground concrete framework 400). The washer 302 is a washer which is long in the longitudinal direction, and fastened, by a long nut 304, to a distal end of the separator 501 protruding from the formwork panel 500. Then, the fluidized soil wall 300 is constructed by filling the space between the existing underground concrete framework 200 and the formwork panels 500 with fluidized soil.
The new underground concrete framework 400, as described above, is constructed by driving the new formwork panels 600 within the fluidized soil wall 300 at a predetermined distance therefrom, coupling these formwork panels 600 with the formwork panels 500 for the fluidized soil wall 300 by means of the separators 601 so as to keep the formwork panels 600 upright, and casting concrete in between the formwork panels 500 of the fluidized soil wall 300 and the new formwork panels 600. At this time, the formwork panel 600 is kept upright by coupling one end of the separator 601 with the long nut 304 and coupling the other end thereof with the formwork panel 600, and a pipe 305 is provided on front faces of the formwork panels 600 and fixed thereto by form ties 306. In this state, by casting concrete in between the formwork panels 500 and the formwork panels 600, the new underground concrete framework 400 is constructed.
Hereinafter, the construction method for the underground structure will be described, based on the flowchart showing the construction procedure in
<Partial Removal of the Existing Underground Concrete Framework>
First, as shown in
Moreover, in the embodiment, the existing beam 201, the existing load-bearing wall 202, and the existing foundation 203 of the existing underground concrete framework 200 are considered as a continuous existing exterior wall, and utilized as a retaining wall for supporting underground soil pressure.
<Backfilling Work and Setting Up of a New Pile>
Next, the existing underground concrete framework 200 is backfilled with soil by carrying soil into the underground pit of the existing underground concrete framework 200, as shown in
In addition, the new pile 405a is not necessarily set up, depending on load-bearing performances of the existing foundation 203 and the existing pressure plate 208 of the existing underground concrete framework 200, and a bearing power that is the bearing capacity of the ground.
<Removal of Backfill Soil and Setting Up of a Strut and Wale for Land Retaining>
Next, as shown in
<Construction of a Fluidized Soil Wall in the Underground Pit>
Next, as shown in
Next, the fluidized soil wall 300 is constructed in the underground pit by filling a space between the existing foundation 203 and the formwork panels 500 with fluidized soil and solidifying the fluidized soil (step S108). The fluidized soil used here is slurry backfill soil which is preliminarily blended with cement in a controlled manner in a plant and which can be transported by a fresh concrete mixer vehicle and can be cast by a pump. And, by using the formwork panels 500 when constructing the fluidized soil wall 300, excess water can be discharged through the slits 13 created in these formwork panels 500, and therefore the time required to harden the fluidized soil can be shortened.
<Constructing of a New Underground Concrete Framework in the Underground Pit>
Next, as shown in
In the formwork panels 600 thus set up, in order to support lateral pressure applied to the formwork panels 600 when concrete is cast, the pipe 305 extending in the longitudinal direction of the formwork panels 600 is fixed on the side of surfaces of the formwork panels 600 by the form ties 306, as described above. Next, the new slab 401 and the new foundation 404 are constructed by casting concrete (step S113). In this manner, the new underground concrete framework 400 can be constructed in the underground pit.
Further, when the new underground concrete framework 400 is constructed, the slits 13 created in the formwork panels 600 can prevent leakage of concrete and can discharge excess water in the concrete when the concrete is cast.
<Building of a Fluidized Soil Wall in the Basement>
Next, as shown in
First, a plurality of anchors 307 are driven into the existing beam 201 and the existing load-bearing wall 202 of the existing underground concrete framework 200, and the respective anchors 307 are coupled with separators 501 (step S115). Next, formwork panels 500 are assembled so as to connect to the formwork panels 500 set up in the underground pit, and kept upright by the separators 501 (step S116). At this time, the formwork panels 500 and the separators 501 are fastened and fixed to each other by washers 301 and 302 and nuts 303.
Then, a fluidized soil wall 300 is constructed by filling a space between the existing underground concrete framework 200 and the formwork panels 500 with fluidized soil (step S117). Thus, the fluidized soil wall 300 constructed in the underground pit and the fluidized soil wall 300 constructed in the basement are constructed as a continuous single wall. And, the load of this fluidized soil wall 300 is supported by the existing beam 201, the existing load-bearing wall 202, and a part of the existing foundation 203 that constitute the existing underground concrete framework 200.
<Constructing of a New Underground Concrete Framework in the Basement>
Next, as shown in
It should be noted that the formwork panels 600 kept upright and the formwork panels 600 assembled into shapes of a slab and a beam are joined and assembled so as to obtain a continuous formwork panel 600.
Next, reinforcing bars for the new slab 401 are assembled (step S121), and concrete is cast into a space between the fluidized soil wall 300 and the formwork panels 600 (step S122). In this manner, the new underground concrete framework 400 for the basement can be constructed. Further, the new underground concrete framework 400 constructed in the underground pit and the new underground concrete framework 400 constructed in the basement form a continuous new concrete framework, the weight of which is supported by the new pile 405a.
As described above, in the construction method for an underground structure according to the embodiment, a new underground structure can be constructed, without dismantling the existing underground concrete framework, by utilizing this existing underground concrete framework as a retaining wall, and constructing the fluidized soil wall and the new underground concrete framework within the existing underground concrete framework.
And, since the fluidized soil wall and the new underground concrete framework which are constructed within the existing underground concrete framework are independent of each other via the formwork panel, the load of the fluidized soil wall can be supported by a portion contacting with the existing underground concrete framework, and the load of the new underground concrete framework can be supported by the new pile provided preliminarily and the foundation of the existing underground concrete framework.
Thus, since the loads of the fluidized soil wall and the new underground concrete framework can be distributed and supported by the existing underground concrete framework, the load supported by the existing underground concrete framework can be reduced.
Further, by providing the fluidized soil wall between the existing underground concrete framework and the new underground concrete framework, the fluidized soil wall makes it possible to reduce the thickness of the new underground concrete framework, as compared with the construction method in which the new underground concrete framework is directly provided in the existing underground concrete framework, and therefore the amount of concrete can be reduced.
Further, since the formwork panel according to the embodiment is formed by bending a panel steel plate into a substantially angular-wave-like cross sectional shape so as to have a plurality of ridges arranged in parallel at predetermined distances, the strength of the panel itself can be reinforced. This makes it possible for the formwork panel to sufficiently bear lateral pressure applied to the formwork panel even after filling with the fluidized soil or casting concrete. And, the slits with a predetermined length provided in this formwork panel make it easy to bend the formwork panel itself, and can promote discharge of excess water while preventing leakage of the fluidized soil or concrete. Thus, it becomes easy to bend the formwork panel at a corner, while constructing of the fluidized soil wall and the new underground concrete framework can be expedited.
11: Ridge
12: Rib
13: Slit
14: Lid
16: Groove
31: Top face
32: Side face
200: Existing underground concrete framework
201: Existing beam
202: Existing load-bearing wall
203: Existing foundation (foundation or underground beam)
204: Existing post
205, 206: Slab
208: Existing pressure plate
300: Fluidized soil wall
301, 302: Washer
303: Nut
304: Long nut
305: Pipe
306: Form tie
307: Anchor
400: New underground concrete framework
401: New slab
402: New beam
403: New wall
404: New foundation (foundation or underground beam)
405: New hole
405
a: New pile
406: Strut and wale for land retaining
407: New pressure plate
500, 600: Formwork panel
501, 601: Separator
Number | Date | Country | Kind |
---|---|---|---|
PCT/JP2010/054796 | Mar 2010 | JP | national |
Filing Document | Filing Date | Country | Kind | 371c Date |
---|---|---|---|---|
PCT/JP2010/054796 | 3/19/2010 | WO | 00 | 9/17/2012 |