This application claims priority of Application No. 201510615235.6 filed in China on Sep. 24, 2015, under 35 U.S.C. §119, the entire contents of which are hereby incorporated by reference.
The present invention relates to a construction method, and the technical field of producing a beam/slab on site utilizing compound concrete containing demolished concrete blocks, in particular, a construction method for producing a beam/slab made of compound concrete containing demolished concrete blocks.
Compound concrete is a mixture of coarsely-crushed concrete blocks and fresh concrete. The coarsely-crushed concrete blocks come from demolished buildings, and eventually have preferred size after a series of processing, e.g. breaking, screening and purifying process. This is a new technology in response to the environmental protection requirement in the country, developing green construction industry and realizing energy saving. However, it still faces difficulties as to how to use this technology effectively in practice.
In current engineering practice, a spacing between two adjacent stirrups in beams or two adjacent rebars in slabs is typically within 300 mm, but the demolished concrete block has a large size ranging from, say, 150 to 300 mm. These coarsely-crushed demolished concrete blocks thus cannot be placed into the rebar cage, particularly in regions with congested reinforcement. Owing to this, such technology has difficulty to be further applied. Alternatively, a conventional method can be used, that is, assembling bottom rebars into a cage first, then placing coarsely-crushed concrete blocks into the cage, followed by assembling top rebars eventually to close the cage. This construction method has a long construction period onsite, costing more time and labour.
Therefore, there is a need to have a construction method for producing beam/slab made of the compound concrete, the method can utilize the demolished concrete blocks, and is more simple, fast and reliable without any impact on the reinforcement configuration and force-carrying mechanism.
There will be providing a construction method for producing beam/slab made of compound concrete containing demolished concrete blocks, the method is safe, flexible and effective, and solves the current problems, e.g. difficulty of placing coarsely-crushed concrete blocks into the cage and long working period.
The invention is achieved by the following solution:
A construction method for producing a beam/slab made of compound concrete containing demolished concrete blocks, the method comprises the steps of
1) a lower rebar mesh and an upper rebar mesh for producing a beam are made respectively, wherein
According to the construction method for producing a beam/slab made of compound concrete containing demolished concrete blocks, in the step 1), the lower and upper rebar meshes of beam are manufactured respectively, and in the step 2), a connection portion among the lower rebar mesh and the upper rebar mesh is located at a top end of the vertical shorter segment of the lower L-shaped stirrup, after placing the coarsely-crushed concrete blocks or segment into the lower rebar mesh, the upper rebar mesh is lifted above the lower rebar mesh.
According to the construction method for producing a beam/slab made of compound concrete containing demolished concrete blocks, screw threads are configured on ends of vertical segments of the upper L-shaped stirrups and top ends of vertical shorter segment of the lower L-shaped stirrups respectively.
According to the construction method for producing a beam/slab made of compound concrete containing demolished concrete blocks, a threaded sleeve is screwed into the screw thread of each lower L-shaped stirrup, length of the screw thread of each upper L-shaped stirrup is twice a length of the threaded sleeve, and the lower L-shaped stirrups and the upper L-shaped stirrups are connected to each other by the threaded sleeves.
According to the construction method for producing a beam/slab made of compound concrete containing demolished concrete blocks, a length of the screw thread of each lower L-shaped stirrup is equal to or slightly larger than the length of the threaded sleeve.
According to the construction method for producing a beam/slab made of compound concrete containing demolished concrete blocks, an internal diameter of the threaded sleeve is equal to a diameter of the stirrups, preferably a reference diameter of an internal thread of the threaded sleeve is 10 mm.
According to the construction method for producing a beam/slab made of compound concrete containing demolished concrete blocks, in the step 2), when the lower rebar mesh of the beam is formed and placed into an open mould, placing the coarsely-crushed concrete blocks or segments into the lower rebar mesh, then the upper rebar mesh is lifted above the lower rebar mesh, and connected to the lower rebar mesh by threaded sleeves, and fresh concrete is poured into the beam rebar cage until full.
According to the construction method for producing a beam/slab made of compound concrete containing demolished concrete blocks, it further comprises steps of fixing bottom rebars of a slab onto the beam rebar cage, placing coarsely-crushed concrete blocks onto the bottom rebars of the slab, then lifting a top rebar mesh of the slab, made of a cold rolled rebar mesh, above the coarsely-crushed concrete blocks, and assembling the bottom rebars and the top rebar mesh of the slab together.
According to the construction method for producing a beam/slab made of compound concrete containing demolished concrete blocks, the cold rolled rebar mesh can be prefabricated based on a relevant blueprint.
By the abovementioned solution, the following benefits of the present invention can be achieved:
The invention will be described hereinafter with reference to two embodiments and figures, however those do not constitute any limitation to the invention.
In these embodiments, a dimension of a beam is 300 mm×700 mm, a thickness of a slab is 200 mm, wherein
With reference to
A connection portion among the upper L-shaped stirrup 1 and the lower L-shaped stirrup 2 is located at a top end of the vertical shorter segment of the lower L-shaped stirrup 2, wherein screw threads 3, 4 are provided on their connection ends of both stirrup 1 & 2 respectively, whereby the upper L-shaped stirrup 1 can be connected to the lower L-shaped stirrup 2 by a threaded sleeve 5 screwing both the screw threads 3 & 4 together, preferably the threaded sleeve 5 can be screwed on the screw thread 4, being ready for screwing the screw thread 3 when both stirrups 1 & 2 need to be joined together.
Length of the screw threads 3 can be ½ length of the threaded sleeve 5, and length of the screw thread 4 can be equal to or slightly greater than length of the threaded sleeve 5. An internal diameter of the threaded sleeve 5 is equal to a diameter of both the stirrups 1 & 2, preferably a reference diameter of an internal thread of the threaded sleeve 5 is 10 mm in this embodiment.
Furthermore, a cold rolled rebar mesh is applied to a top rebar mesh of the slab, and will be lifted over the open mould 10 for mounting. The cold rolled rebar mesh may be prefabricated based on a relevant blueprint.
After the beam rebar cage was formed and fresh concrete has been poured into the beam rebar cage fully, the bottom rebars 7 of the slab is positioned onto the mould 10, then the coarsely-crushed concrete blocks 9 are placed on the bottom rebars 7 of the slab, and the cold rolled rebar mesh, i.e. the top rebar mesh of the slab, is lifted over the open mould 10 for mounting.
During the construction, the process steps are as follows:
Please understand that the embodiments described hereinbefore are merely preferred embodiments of the present invention and not for purposes of any restrictions or limitations on the invention. It will be apparent that any non-substantive, obvious alterations or improvement by the technician of this technical field according to the present invention may be incorporated into ambit of claims of the present invention.
Number | Date | Country | Kind |
---|---|---|---|
2015 1 0615235 | Sep 2015 | CN | national |
Number | Name | Date | Kind |
---|---|---|---|
5317846 | Michlovic | Jun 1994 | A |
20080263978 | Abou-Saleh | Oct 2008 | A1 |
20110047928 | Aburto | Mar 2011 | A1 |
20120047816 | Zhong | Mar 2012 | A1 |
20120233936 | Zhong | Sep 2012 | A1 |
20130104492 | Hung | May 2013 | A1 |
20150075110 | Golledge | Mar 2015 | A1 |
20150354238 | Abbasi | Dec 2015 | A1 |
Number | Date | Country |
---|---|---|
101418629 | Apr 2009 | CN |
101671147 | Mar 2010 | CN |
102071740 | May 2011 | CN |
102677582 | Jan 2013 | CN |
10001839 | Apr 2001 | DE |
419620 | Jan 1911 | FR |
1498079 | Oct 1967 | FR |
100875488 | Dec 2008 | KR |