The present invention pertains to the field of construction methods and systems for grade separation structures and in particular, construction methods and systems which reduce or eliminate the need for long term traffic obstruction and temporary structures.
Traditional methods of constructing grade separations involve significant closures and/or detours (shoo-fly) of both of the existing thoroughfares. Closures usually lead to increased commute times, resulting in higher costs of travel and greater greenhouse gas emissions. Constructing detours typically requires a costly protection system (retaining wall) to be constructed along the edge of the work site, which involves temporary piles and/or caissons. The detour also causes a shift in ownership and/or liability for the right-of-way throughout the duration of the project. Detouring railways in particular is a costly measure, requiring large amounts of space and extensive coordination between multiple land owners, contractors and consultants. A current alternative to detouring railways involves temporarily supporting existing rail tracks during underpass construction. These existing rail track support systems are very costly, and also require a great amount of temporary works.
This background information is provided for the purpose of making known information believed by the applicant to be of possible relevance to the present invention. No admission is necessarily intended, nor should be construed, that any of the preceding information constitutes prior art against the present invention.
An object of the present invention is to provide construction methods and systems for grade separation structures. In accordance with an aspect of the present invention, there is provided a method for constructing a grade separation structure at intersection of two thoroughfares comprising installing pairs of caisson liners along a first thoroughfare; wherein the caisson liners are substantially centred on the intersection; providing pre-cast concrete segment with a first end and second end; connecting a modular trench box to the first end of the precast segment and connecting a second modular trench box to the second end of the precast segment to form a pre-cast assembly; excavating a trench across the thoroughfare and around a pair of caisson liners, wherein the trench is sized to accommodate the precast assembly; installing the precast assembly in the trench such that a first caisson liner is position in the first trench box and a second caisson liner is positioned in the second trench box; filling the trench with ballast material thereby burying the precast assembly; filling the first and second caisson liners with reinforced cast-in-place concrete; linking the precast segments to the caissons; installing bearings and finishing works on the caissons to complete bridge substructure; preparing the completed bridge substructure for bridge span installation; and installing bridge span; wherein following installation of the bridge span underpass is excavated and thoroughfares reinstated.
In accordance with another aspect of the invention, there is provided a method for constructing a grade separation structure at a thoroughfare comprising providing precast substructure elements with associated trench boxes; excavating a trench across the thoroughfare; installing the precast substructure elements with associate trench boxes in the trench; filling in at least part of the trench to reinstate the thoroughfare to live traffic; completing the substructure; and installing bridge span on the substructure.
In accordance with another aspect of the present invention, there is provided a method for constructing a grade separation structure comprising providing precast superstructure elements with formwork system, wherein the precast superstructure elements comprises a partial concrete deck; installing the precast superstructure elements with formwork system; extending the partial concrete deck with cast-in-place concrete; forming substructure elements; completing superstructure and attaching the substructure elements to the superstructure; and excavating beneath the superstructure to form an underpass.
In accordance with another aspect of the invention, there is provided a a method of protecting a vertical face excavation under a superstructure supported by caissons, the method comprising a) partially excavating a vertical face between two caissons under the superstructure, wherein an integral channel is provided between the two caissons proximal to the superstructure; and b) sliding a first steel waler horizontally along the integral channel guide; c) excavating under the installed first steel waler such that the first steel waler descends to the bottom of the excavation site; and d) sliding a second waler on top of the first steel waler.
These and other features of the invention will become more apparent in the following detailed description in which reference is made to the appended drawings.
Overview:
This invention provides methods for constructing a grade separation structure using precast substructure or superstructure elements with trench boxes and/or formwork systems to be partially buried under live traffic thereby minimizing the thoroughfare closure period. The trench boxes and/or formwork systems are optionally modular and/or configured to provide design flexibility. The method is amenable to different intersection configurations and can, in some embodiments, be used to realign a thoroughfare. The methods can also be used for the construction of new underpasses and the widening of existing thoroughfares. The size and dimensions of the system and the steps in the method can be modified to suit a wide range of geometries.
In some embodiments, where two or more rows of caissons are required, the trench boxes are optionally bolted to two precast elements simultaneously, for example at each end thereby allowing for the construction of multi-lane/multi-track bridges.
This cut and cover method can be repeated for each of the substructure/superstructure elements or could be performed for multiple segments simultaneously within the same closure period. In some embodiments, the method would minimize the closure periods to four to six hours.
Precast substructure or superstructure elements can be of a standard or generic design or configuration. Alternatively, the precast substructure or superstructure elements can be specifically designed for the specific grade separation structure. Optionally, conduits for cables, pipes or other infrastructure can be integrated. In some embodiments, the pre-cast elements include integral ballast walls. The pre-cast elements can be single pieces or can be multi-piece. The trench boxes are custom designed to suit this technology but optionally have standardized dimensions usable in most applications.
The precast substructure or superstructure elements may be cast on-site or cast elsewhere and delivered to the site.
The precast elements can be provided with pre-cast inserts to facilitate connection to the trench boxes. These inserts can optionally be configured as threaded sleeves.
In some embodiments, the method utilizes pre-assembled steel elements that include trench boxes/formwork and the steel bridge spans.
The method optionally utilizes elements to facilitate completion work including elements to facilitate construction of retaining walls. In one embodiment, the method provides channel guides extending between the caissons.
In one embodiment, the channel guides consist of three steel plates welded together into a āCā shape and are configured to house the first waler. The channel is tack welded to the caisson liners.
This invention provides methods and systems that facilitate the completion of a grade separation without significant closures or detours to route that will form the future overhead thoroughfare. In some embodiments, it allows for a minimization of the disruption of both thoroughfares.
In some embodiments, the method facilitates the completion of critical components of the grade separation structure without significant disruptions to public right-of-way by using precast concrete segments and/or pre-assembled steel elements provides for portions of the grade separation structure.
The construction work directly beneath the overhead thoroughfare, i.e. placing prefabricated elements, can be performed in short-term closure periods of approximately four to six hours. The remainder of the work (caissons, bearings, wingwalls, etc.) is then completed outside of the clearance envelope of the thoroughfare without significant closures and/or detours. The remainder of the construction will be completed using well adopted construction techniques and can be constructed by any competent heavy civil contractor using widely available equipment and without any additional training.
The equipment used to place the bridge spans may be case specific, and dependent on the weight of the segments. In most cases, the spans can be positioned in place using tandem mobile cranes. If the weight of the span exceeds the practical mobile crane lift capacity, a lateral slide could be utilized within a similar closure period of four to six hours.
This method is applicable to structures designed to support any type of traffic including railways in accordance with the regulatory design codes/manuals including CSA S6-14 Canadian Highway Bridge Design Code, AREMA Manual and, AASHTO LRFD Bridge Design Specifications.
Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention belongs.
To gain a better understanding of the invention described herein, the following examples are set forth. It will be understood that these examples are intended to describe illustrative embodiments of the invention and are not intended to limit the scope of the invention in any way.
Three Span Rail Crossing
During the precasting work, the right of way which is to be re-aligned under the overhead thoroughfare, is detoured around the work site as required. Once it is detoured, there would be no additional closures or disruptions to this thoroughfare required for construction operations. Once the precast segments have cured, modular trench boxes (5) can be connected to the precast segments, for example cast-in inserts (7) using bolts (6) (7) as shown in
The previously installed caisson liners (1), which are now enclosed by the trench boxes as seen in
The caissons are then be filled with reinforced cast-in-place concrete. If the exposed portion of the pier column is a smaller diameter than the buried caisson, a formwork collar is lowered into the liner prior to pouring the concrete. Then the precast segments are extended utilizing the trench boxes as formwork for the cast-in-place concrete (11) thereby linking the precast segment to the caissons (
The cast-in-place concrete is made integral with the precast segments using mechanical reinforcing steel couplers and/or post tensioning. Finally, the ballast walls (12), bearings (13) and finishing works on the substructure elements are completed. Prior to finishing the bridge substructure, the bridge spans (14) are cast/assembled including ballast and rail tracks as shown in
Once the substructure and superstructure elements are completed, the thoroughfare is temporarily closed for installation of the bridge spans. A portion of the rail track is disassembled and the filled trench is at least partially excavated to provide access to the partially buried precast assemblies (8) as shown in
Upon completion of each of the bridge spans, the overhead thoroughfare would be re-opened to live traffic. After completion of the structure, excavation of the underpass and final completion is begun. Once final excavation works are completed, the portions of caisson liners at the piers, which have been exposed, are optionally removed from the concrete columns. The sides of the excavation adjacent to the abutments are optionally completed with slope paving. An example of a completed structure is shown in
This three span system could also allow for future widening of both thoroughfares with only minor modifications. Widening of the lower thoroughfare would be completed by removing the slope paving and constructing an vertical abutment face. The overhead thoroughfare could be widened by installing an additional row of caissons parallel to the previously constructed spans. The abutments and piers would then be extended to join these additional caissons and new bridge spans placed on the extensions creating a new right-of-way for the overhead thoroughfare.
Single Span Rail Crossing with Vertical Abutment Faces
The construction sequence of a single span rail crossing with vertical abutment faces is illustrated in the example below.
Referring to
Referring to
The construction of the caissons, linking of the precast segments to the caissons, completion of ballast walls (12), bearings (13) and finishing works, as well as assembly and installation of the bridge span (14), is similar to that as set forth above and is as shown in
Referring to
Rigid Frame Design Roadway
This example details construction of new underpasses with integral abutments under multi-lane roadways with only single lane closure of the existing thoroughfare at a given time. A new rigid frame structure to be constructed under three lane roadway is illustrated. The prior construction conditions are shown in
Referring to
Lane 2 of the three lane road is excavated and a levelled granular base (24) is prepared in the excavation site and integral channels installed. Referring to
The entire segment is placed onto to the levelled granular base (24) within a trench on the overhead thoroughfare over the previously positioned integral channel guides (18) as shown in
Following re-opening of Lane 2, Lane 1 is temporarily closed and steel caisson liners (1) are installed as shown in
Although the invention has been described with reference to certain specific embodiments, various modifications thereof will be apparent to those skilled in the art without departing from the spirit and scope of the invention. All such modifications as would be apparent to one skilled in the art are intended to be included within the scope of the following claims.
Number | Date | Country | Kind |
---|---|---|---|
2920654 | Feb 2016 | CA | national |
Filing Document | Filing Date | Country | Kind |
---|---|---|---|
PCT/CA2017/000021 | 2/1/2017 | WO | 00 |
Publishing Document | Publishing Date | Country | Kind |
---|---|---|---|
WO2017/136918 | 8/17/2017 | WO | A |
Number | Name | Date | Kind |
---|---|---|---|
1970979 | Robb | Aug 1934 | A |
2658353 | Trexel | Nov 1953 | A |
2972234 | Suderow | Feb 1961 | A |
3843988 | Hirsch | Oct 1974 | A |
4075453 | Roberts | Feb 1978 | A |
5771518 | Roberts | Jun 1998 | A |
5839852 | Mattson | Nov 1998 | A |
20120159893 | Anderson | Jun 2012 | A1 |
Number | Date | Country |
---|---|---|
2005009309 | Jan 2005 | JP |
Number | Date | Country | |
---|---|---|---|
20190048540 A1 | Feb 2019 | US |