The present invention relates to a construction process of structures in situ, with or without prestressing, in particular, bridge decks, with a high component of ex situ prefabrication, including the assembling of empty segments, which precedes the activities in situ.
The present invention further relates to a construction system of structures comprising empty segments.
There are several documents on the prior art concerning the industrialization of building structures, including prefabrication and optimization of construction processes.
Document U.S. Pat. No. 3,299,191A discloses a method for sequential construction of works with many spans. Document U.S. Pat. No. 3,367,074 discloses a method for constructing prefabricated bridges. Documents U.S. Pat. Nos. 4,073,115 and 3,989,218A reveal methods to strengthen the construction by successive advances.
Documents DE-B-1101477 and GB2073296A disclose systems for controlling or reducing deformations of structures made in situ, and document PTE1639203 presents a system for constructing structures in situ.
Several prior art elements can also be found in Puentes I, II, III, by Javier Manterola, Prestressed Concrete Bridges, by Christian Menn, or Construction and design of prestressed concrete segmental bridges, by Jean Muller and Walter Poldony, among others.
In the methods of building structures with in situ concreting, in order to increase the industrialization of the process, it is possible to observe the partial pre-assembling of the steel reinforcement before being placed on the formwork as this process has been in common use for many years. However, in this process, the operations of assembling the steel reinforcement are not comprehensive and do not ensure the exact final geometry of the prefabricated elements. This last aspect is of great importance because it means that after placing portions of reinforcement elements (steel reinforcements) in the final position in the structure to be constructed, it is still necessary to reposition these steel reinforcements in the final position and mount the respective moulds; these activities have an important impact on the production cycles.
Additionally, the transport and handling of these pre-assembled steel reinforcement systems become increasingly complex with the increase in size of the prefabricated modules and, therefore, there are functional limitations to pre-assembled steel reinforcement systems of great size, or to pre-assembled steel reinforcement systems that include, for example, horizontal elements of some size. The prefabrication of pre-assembled steel reinforcement systems without relevant need for subsequent handling is reduced to elements whose smaller size in the plant view is around a few dozen centimeters.
In short, the in situ concreting processes have the advantages of requiring less means of transport and lifting, less means of support and less logistic means in the facilities and may, in some cases, lead to further optimization of materials, but they are less industrialized and require more manpower at the works front line (sometimes off shore) and could lead to extended construction deadlines. The traditional prefabrication processes are fairly industrialized, with significant reduction of construction deadlines, with more control in construction site fabrication, with a very significant reduction of work at the works front line (sometimes off shore). However, they have some disadvantages, in particular because they require load transport and lifting systems that are very powerful and expensive, as well as requiring additional resources and logistics means at the facilities and not ensuring the perfect continuity between all the structural elements, which may not allow for, in some cases, the most appropriate optimization of the material quantities or, according to some authors, may not ensure the best seismic performance (where this is relevant).
The construction process shown in the present invention may be a solution of high potential, an alternative to the precast segmental construction method, and that minimizes the main limitations or adversities of this method in accordance with the state of the art.
The objective of the present invention is to propose an industrialized construction process that provides substantial gains in productivity, minimizing the use of auxiliary equipment in the construction of structures or parts of structures.
This objective is accomplished by means of an industrialized construction process.
In particular, the construction process according to the present invention proposes to carry out all activity of prefabrication of construction elements ex situ, henceforth referred in the present document as empty segments, except the filling thereof, which is carried out in situ, without moving and transporting heavy loads, which is applicable to structures of various scales including smaller-sized structures and large structures.
In particular, the objective of the present invention is attained through a construction methodology or process that provides the prefabrication of the said empty segments—consisting of fixing elements and steel reinforcement elements and adapted to receive the filling material—allowing a process which simultaneously ensures a high degree of industrialization—ensuring tight deadlines and optimizing manpower at the works front line (similar to prefabrication construction) but without the need for heavy means for moving, lifting and transporting loads—reducing facilities requirements and logistic means—and, at the same time, ensuring the continuity of the structural elements, through the in situ application of the filling material, allowing an adequate level of material optimization.
The construction process of a so-called reference segment (corresponding to a construction segment of the structure or part of structure, to be constructed) is established in a systematic way and consists of the following steps:
According to preferred embodiments of the present invention, in the case of prestressed structures, there may also, in some cases, occur the placement of the prestressing ducts in the empty segments in situ (and the introduction of cables may be performed in situ or ex situ; in both cases the respective tensioning occurs in situ, after filling and consolidation of the filling material (post-tensioning solutions).
However, the proposed construction process according to the present invention allows both post-tensioning and pre-tensioning methods, and in the latter case, the process provides that the said step of prefabrication ex situ of said empty segments also includes the steps for introduction of the prestressing cables and the tensioning of these prestressing cables. It further includes the in situ step of transmitting the pre-tensioning of said fixing elements for the filling material.
It should be noted that, in these applications with prestressing, the goal is maintained for the most time consuming tasks to be performed ex situ and without moving and transporting heavy loads.
Another objective of this invention is to provide a construction system that supports the execution of an industrialized construction process of structures or parts of structure with substantial gains in productivity and a reduction in auxiliary means of construction.
Indeed, the construction process according to the present invention presupposes the existence of a construction system that features at least one empty segment provided with a general geometry corresponding to that of a respective reference segment and adapted so that it can be prefabricated and in order to receive the appropriate filling material. Said empty segments comprise at least steel reinforcement elements and fixing elements, the latter including at least a system of rigid elements and part of the moulds, and said fixing elements are designed to ensure the geometry and stability of said empty segments during transport and placement, and to ensure compatibility with the moulds that are not included in these fixing elements. Said system of rigid elements should at least have the structural capacity to support itself and to support the steel reinforcements and the moulds included in the fixing elements.
The resolution of the problem presented, and in particular the viability of said empty segments, requires the integration therein of a preponderant element: the hereinafter called ‘fixing element’, consisting of rigid elements and including at least part of the moulds, which generally provide the geometry and stability to the empty segments from their prefabrication to their placement in the final position in the structure, or part of structure, to be constructed, where the filling of the empty segments occurs, and these fixing elements are removed at the end of each cycle for reuse (if applicable). These fixing elements should also be compatible with the moulds needed for the construction of the structure that are not included therein.
Said fixing elements must have, at least, three properties:
It should be noted that the fixing systems, due to the previously mentioned structural capacity, allow the process to be applied to a wide range of scales, and can be applied to structures that have sections with widths of only dozens of centimeters to structures that have sections of dozens of meters.
With regard to the optional features of the fixing elements, which is a relevant part of the object of claim 15, each fixing element may be a retractable structure, may include a system of mechanically adjustable elements, may include mechanical devices to change position, may include gripping devices, may include sliding devices, may include fixing interfaces (which should be designed in a manner compatible with the corresponding interfaces of other elements, for example, in shoring systems or in the moulds outside the fixing elements), may be a separable parts system (comprising, for example, a rigid structure that supports the moulds and steel reinforcement elements), may be a system that includes insulating devices to trespass the filling material (without connection to concrete) and may be a system that includes concrete accelerating systems, for example, concrete accelerating systems by steam. These optional features can be combined in various ways in view of the construction characteristics and other existing equipment, for example shoring systems or moulds.
According to a preferred embodiment of the present invention, the said fixing elements, or one fixing element, may also optionally and depending on the design of the structure, or part of a structure, to be constructed, and the construction system, be provided so as to present an autonomous and sufficient structural capacity, and optionally configured so that they can support the load of the filling material, to ensure the stability of the said empty segment during the filling thereof with a filling material or may be provided so that they present a structural capacity to be pre-tensioned, including the capacity to sustain the pre-tensioning action of the cables, and wherein the said fixing element includes rigid reaction devices for tensioning so as to provide reaction in the said tensioning.
There are preferred embodiments that maximize the advantages resulting from the application of the proposed construction process and system, in particular the possibility to, in the prefabrication of the empty segments, include the assembling of interface elements and/or inserts, including profiles of metallic material, and/or carbon fibers, or prefabricated anchoring blocks or other prefabricated elements or elements to position the steel reinforcement, or elements to perform negatives in the filling material or a combination of, at least, part of the above elements, or include in that prefabrication the assembling of seals or other interface elements between moulds. It should also be possible to do variations of the process presented comprising additional activities in situ of placement of reinforcement elements or of placement of additional elements of moulds.
According to another preferred embodiment, the industrialized nature of the proposed process and construction system is greatly enhanced if the system is repetitive so as to include additional steps: in situ removal of fixing elements and, at least, part of the said moulds, transportation of the said fixing elements to ex situ prefabrication area, and beginning of the next cycle, which may justify the ex situ assembling of a plurality of sets of fixing elements in order to allow more than one front of empty segments prefabrication.
According to a preferred embodiment, according to claim 13, the construction process can be adopted in a hybrid manner, combining the proposed process and system with conventional construction methods, for example with in situ conventional construction or with prefabricated conventional construction. In other words, it is possible to carry out construction of, at least, part of the structure to be constructed with use of said empty segments and another part of the said structure to be executed, at least, partly simultaneously through the use of structure segments entirely prefabricated ex situ (that is, in accordance with a prefabrication process according to the state of the art) with correspondence to reference segments and/or special pier segments entirely prefabricated ex situ without the use of said empty segments and/or simultaneously, or alternatively, the proposed process occurring partly simultaneously with in situ construction of at least part of the structure without the use of the said empty segments (conventional construction in situ).
Very important is also the possibility of, in particular in the case of prestressed structures, the process enabling the full assembling of steel reinforcement elements in the empty segments, prefabricated ex situ, without any need of activities with steel reinforcement elements in situ. And, if there is more than one empty segment, this implies the inclusion of the previous step of structure design which includes checking the limit states and use in the existing interface sections between any two adjacent reference segments and that are not trespassed by steel reinforcement elements.
This preferred embodiment, is particularly useful for the construction of structures, such as bridge decks in prestressed concrete, and can enable faster production cycles than the prefabricated construction according to the state of the art, to the extent that the placement of the empty segments is faster than the placement of prefabricated segments with filling material already incorporated (prefabrication according to the state of the art).
Indeed, and as will be developed below, depending on design options used in the construction process in accordance with the present invention, the way of designing the structure to be built may be different from the current methods to design structures in situ and current methods to design prefabricated structures, due to the mechanical conditions of the interface sections between adjacent segments, in the final structure executed being different from those resulting from methods according to the state of the art.
The construction process and system according to the present invention can be applied to different types of structures, with different sections and with different materials, in particular presenting a construction system that includes one or more structures with a box girder section, a rectangular section, a square section, a Pi section, a T section, a double T section, a circular section, a triangular section, or any other form of mechanically feasible section for executing the said structure, including one or more structures which are, at least, a part of a bridge deck or overpass, a pier, an arc, a beam, a structural element with vertical walls, an inclined element or a complex structural element with another shape including one or more structures that are comprised of a filling material which can be, for example, a concrete, a hydraulic binder, a glass, a ceramic material, a plastic material, or an alloy.
In the design of a construction process the choice of types of construction equipment is of special relevance, in particular the selection and characteristics of shoring systems, which can be for example, self-launching scaffolding or ground scaffolding. The application of the proposed process and system may be enhanced if in the design or adaptation of the shoring system some solutions are adopted that should be evaluated case by case. In particular, the shoring system must be adapted so that it presents kinematic and geometrical compatibility with the said empty segments, including to ensure the possibility of the said empty segments passing in the support elements of the said shoring system (if applicable) and/or to ensure that the said shoring system or the moulds coupled therein include interface fixing devices to ensure the positioning of the said empty segments that may also have interface fixing devices, and/or that the shoring system features auxiliary means for moving loads to feed the empty segments at the front of the construction depending on the means of transport used in the logistics of the works, and/or shoring system having concrete accelerating system, for example, concrete accelerating system by steam.
It should be noted that the application of the presented process and the system presupposes that the structure to be constructed is configured so that it can be divisible into one or more so-called reference segments, which must have direct correspondence with the said empty segments.
The construction processes and construction system proposed according to the present invention, benefiting from prior art, in particular the method of precast segmental construction, sustain a variant solution of high potential that minimizes the main limitations or adversities of this conventional method.
In a systematic way, the process and the system according to the present invention provide the following advantages:
It becomes clear that there is room for the development of a new construction process and a new system that allows the combination of the main advantages of the in situ conventional construction processes and conventional prefabrication processes.
The invention will now be explained in greater detail based on preferred embodiments and the Figures that are attached.
The Figures show, in simplified schematic representations:
The present invention relates to a new construction process and a construction system of structural elements, for example, reinforced concrete, with several configurations, as shown in
In order to understand better, the reference segments (2) may coincide in terms of form and constitution with the conventional prefabricated concrete elements and may be segments that cover the span (corresponding to prefabricated beams) or segments with integral cross-section (corresponding to prefabricated segments), or to integral segments (corresponding to complete prefabricated segments), or segments of prefabricated piers, segments of other prefabricated elements, such as curved elements, sloped elements, concrete cores, etc.
Analyzing
Analyzing
In the case of, for example, reinforced concrete structures, the empty segment (3) comprises passive steel reinforcements (9) already with the final geometric configuration.
In the case of structures (1) of, for example, prestressed reinforced concrete, the empty segments (3) include prestressing ducts (10) and the prestressing cables (11) can be introduced after the assembling of one set of empty segments (3) that are concreted in one same operation, for example, corresponding to a span in the case of a bridge deck. The cables can be fully placed if their length is equal to or less than the empty segment (3).
If the structure (1) is composite or has interface elements or inserts incorporated (12) (for example, metallic elements) that become incorporated in the filling material (8), these elements can also be incorporated in the empty segments (3).
By means of the operation of pouring the filling material (8), and after consolidation of the filling material, the empty segment (3) becomes, therefore, the reference segment (2). In the case of structures (1) of reinforced concrete, this pouring operation is the concreting operation.
With reference to
If the fixing element (4) is dimensioned to have structural capacity to support the filling material (8), then the empty segment (3) can be placed without the use of shoring systems (6), as shown schematically in
With reference to
An important aspect in the application of the construction process in accordance with the present invention is the fixing element design (4). This element must comply with three requirements: i) ensure the final geometry, or close to the final one, of the elements that make up the empty segment (3) so that, by means of quick and simple operations, it is easy to ensure the desired geometry for the empty segment (3) after it is placed; ii) have the structural capacity to ensure the empty segment stability (3) in its transport and placement; and (iii) be compatible with the moulds (13) of the element to be constructed that are not included in the fixing element (4), or including those same moulds (13).
Additionally, it may also be advantageous, for the fixing element (4) to be previously prepared so as to be easily positioned, for example including fixing devices (16) that can be both positioners and fixing devices (16), or other devices which ensure the correct positioning of the empty segment (3).
In
The fixing elements (4) may, for example, include all the moulds from the outset (13), for example the formwork, as in the cases of
The fixing elements (4) include rigid elements (22) and may include, for example, adjusting devices (15) which may be useful not only to adjust the final geometry of the empty segment (3) but may also be useful to facilitate the removal of the fixing elements (4) after the empty segment (3) is filled by the material (8) and this is properly consolidated, or even to move or lift part or all of the fixing elements (4).
The adjusting elements (15) may consist of mechanical elements for manual adjustment, for example mechanical spindles, or other mechanical elements known in the state of the art, such as hydraulic jacks, manual spindles, retractable elements, or others with similar functions.
In
Next, and only by way of example, follows an explanation of the application of the construction process in accordance with the present invention to the construction of prestressed box girder decks concreted in situ using, for example, a shoring system (6) which is self-launching scaffolding. The necessary adjustments for the application of this process to other types of structures are explained later on.
This construction process, when applied to this example, comprises seven stages:
With reference to
It is possible that, for example, the deck (1), with a box girder cross-section indicated in cutaway A-A, for example, can be executed with several reference segments (2) per span. Each reference segment (2) to be constructed corresponds to an empty segment (3).
With reference to
Phase A—Prefabrication of Empty Segments (3), Including Assembling of Fixing Elements (4) in an Ex Situ Prefabrication Area (5);
This phase is explained based on
The fixing elements (4) could, in this example, have the configuration defined in
The fixing elements (4) to use in each cycle (except in the first cycle) are from the works front line, where they were used in a previous cycle. A preliminary operation, applicable to this example, consists in cleaning and painting with form release agents, or similar products, the modules, the inner formwork (13) that, in this example, are an integral part of the fixing element (4).
The empty segments (3) are prefabricated by assembling the steel reinforcements (9) in a manner compatible with the assembling of fixing elements (4) that integrate the empty segments (3), and part of the moulds (13) (inner formwork) which in this example is also part of the fixing element (4), and these three activities must be carried out in order to comply with the geometry of the reference segment (2) corresponding to the segment to be executed of the works, i.e. complying with the geometry of the final structure (1).
To increase productivity and quality control, steel reinforcement spacing elements can be used (23) i.e. ‘gabarits’ for positioning the steel reinforcements, for example, pierced steel sheets with strict position of each rod or cable, pieces of wood, pieces of concrete; in other applications these elements may also be an integral part of the (4) fixing elements, as shown for example, in
There may be an assembly line, for example, as schematically shown in
Depending on the structure (1) designed, the empty segments may include prestressing ducts (10), interface structures or inserts (12), or other elements that are part of the final structure (1) that can be incorporated in the prefabrication, as, for example, the prefabricated anchoring blocks (29), prefabricated elements (33) (see
The empty segments (3) must be made with the same or very similar geometry to that which ensures the correct execution of the final structure (1) and the fixing elements (4) must ensure the stability of the empty segments (3) during transport and placement. The fixing elements must be compatible with the moulds (13), in this case the formwork, which are not included in them, and, as is the case of this example, include the inner formwork (13) as shown in
If each empty segment (3) has a sole position for placement in the shoring (6), it may be appropriate to mark the empty segments (3), for example, by numbering them.
The fixing element segments (4) may also be provided with collective safety equipment, e.g. guards, platform, or safety belts fixing elements, which may be useful for carrying out the work safely.
In the case of the fixing elements (4) incorporating elements that trespass the filling material (8), in this case concrete, as it happens, for example, in the fixing element (4) in
In some cases, the empty segments (3) fabrication process can be more productive and with greater quality control, if the assembling of the empty segments (3) is carried out in the prefabrication area (5) on a platform, with an L1 extension, which can hold simultaneously and continuously all the empty segments (3) pertaining to the same execution phase.
Phase B—Transport, Placement and Fixing of the Empty Segments (3) in the Scaffolding (6);
This phase is explained based on
According to
Note that an empty segment (3) has dimensions and weight suitable for easy transport to the shoring system, for example a scaffolding, and for easy lifting and placement in the scaffolding (these elements may weigh several times less than an element of prefabricated concrete, (i.e. than the corresponding structure segment (1)).
As shown in
The design of the fixing elements (4) must take account the empty segments (3) type of supply to be carried out in the works. It may be appropriate, for example, to use more complete fixing elements (4), similar to those in
In the case of using overhead scaffolding (6), the plan view dimensions of the empty segments (3) must be made compatible with the support elements (20) of the scaffolding (6) (shown in
The placement of the empty segments (3) in the final position can be made by auxiliary means similar to the auxiliary means (7) of the prefabrication area, or it may be performed by auxiliary means (19) incorporated in the scaffolding (6).
As can be seen in
The fixing elements (4) may also include interface fixing devices (16) between them and seals (30) or other interface materials to ensure an airtight closing of the moulds (13) (as shown in
Depending on the design criteria, the empty segments (3) may, for example, have no connection between them (see
Empty segments (3) with steel reinforcement (9) which penetrate into the adjacent empty segment (as shown in view B-B of
It is also possible to adopt, for example, a solution, shown in
Alternatively, the overlapping reinforcement elements or overlaps (21) may travel with the empty segments (3) without being fixed, and it is possible to slide them when the empty segments (3) are already in their final position.
There may also be a design of fixing elements (4) and moulds (13) providing for the placement of closing moulds elements (24) in situ, schematically shown in
Depending on the design of the fixing elements (4), after placement of the empty segments (3) part of the moulds can be introduced (13), for example, the inner moulds, which in the case of the fixing elements having a design similar to that shown in
Finally, after all the empty segments have been placed (3) in the shoring system (6) and any additional works have been executed in situ as previously mentioned, in the case of the structure (1) being designed with prestressing, with the respective cables having an extension above the empty segments (3), then ducts (10) connecting elements must also be placed in situ, and the prestressing cables (11) must also be introduced in an in situ operation at the works front line, similarly to what happens in traditional construction with prefabricated segments.
The shoring system (6) may be prepared for the installation of lifting equipment (19) that allows the placement of prestressing coils under the deck. The installation of the prestressing cables is performed after the prestressing ducts sealing (10).
Phase C—Concreting of the Structural Element (1);
The operation of pouring the filling material (8), which in this example coincides with the concreting operation of the deck, may have very variable durations, and usually means several hours for the example being described. In this operation, a number of specialized operators will pour and vibrate the liquid concrete in all the empty segments (13) located between two consecutive construction joints (18), i.e. of a portion of the structure (1) to be constructed. Normally, as the extension to be executed in each cycle has, for example, dimension L (indicated in
The shoring system (6) which can be, for example and as already mentioned, self-launching scaffolding, can be equipped with elements that allow the creation of concreting circuits along the stretch to be constructed, for optimization of this process.
Note that the operation in question, in the example shown, is identical to the normal concreting operation of the in situ construction methodology, without any influence of ‘segmentation’ of the deck in that process, which is continuous and follows the normal rules of the state of the art for in situ concreting.
The same application principles apply if the filling material (8) is not concrete, but should also take into account the particularities of the material involved.
It should be noted that the filling of the empty segments (3), if there is more than one, does not imply the existence of the filling material discontinuities in the interface areas between empty segments (3).
If concrete accelerating admixtures (31) are incorporated in the fixing elements (4) or in the shoring systems (6) the curing periods may be shortened.
Phase D—Curing Period;
In the example shown, with structures in prestressed reinforced concrete, the curing period can mean dozens of hours and must be defined case by case, according to the rules of the state of the art for structures concreted in situ, and depending on the particular characteristics of the deck (or other structural member), for example, type of concrete, inclusion of prestressing or not, necessary resistance to the prestressing application and other common state of the art specifications that are applicable.
Depending on the conditions of the location of the works and the technical requirements, additional operations may be needed to ensure a proper curing, for example, watering the elements in consolidation.
In the case of filling material (8) is not concrete, the time of consolidation should be defined accordingly.
Phase E—Prestressing of the Structure (if any) and Removal of Scaffolding;
In the case where the structure (1) is, for example, prestressed, including elements of the prestressing type (10) and (11) or others, before the removal of the scaffolding takes place, the cables, or other prestressing elements, must be tensioned according to the tensioning plan provided for, and it can be a partial or total tensioning.
Then follows the removal of scaffolding of the structure (1), which is no more than disengaging the shoring system (6) from the weight of the part of the structure (1) being executed. This operation can be performed, for example, by manual or mechanical means, and can be done, for example, through a sequence of small localized operations, or through a single global operation with mechanical means designed for this purpose and known in the state of the art. This task may benefit from, for example, the use of an automatic control system of scaffolding deformations (6) depending on their structural response.
Normally, this operation is followed by the transposition of the shoring system (6) to the next portion of the structure (1), in this example to the next span of the structure (1) to be constructed. Where the shoring system (6) is self-launching scaffolding, this operation is the forward operation.
Phase F—Removal of the Fixing Elements (4) and Transport to Prefabrication Area (5).
At the same time, before or after the transposition of the shoring system (6) to a new position, a team of operators starts removing the fixing elements (4), which, for example, include the inner moulds (13).
If the fixing elements (4) have elements that trespass the filling material (8) as is the case of the fixing elements in Figurea 14a-14d, the fixing elements (4) must be separated into two or more parts.
Still based on
This removal will also be easier if, as shown in
In the case of the example shown, the construction of a prestressed reinforced concrete deck, carried out with empty segments (3) with fixing elements (4) including inner moulds (13) as, for example, retractable systems illustrated in
External auxiliary equipment (7), for example, or, also for example, auxiliary equipment (19) of the shoring system itself (6), may be used to facilitate the removal of the fixing elements (4) and placement in a means of transport (17) (with characteristics compatible with the type of supply previously defined) that will take them to the prefabrication area (5) where they will be used for the prefabrication of a new series of empty segments (3), thus starting a new cycle.
To increase productivity, it may be convenient to have a plurality of fixing elements sets (4) for each position. In such a way that, while a set of empty segments (3), including the respective fixing elements (4), is being used at the works front line, for the construction of the current stretch, another set (or more than one) of fixing elements (4) is in the prefabrication area (5) so that, at the same time, the next stretch is already being prefabricated, or several of the next stretches, if so defined.
In the case of using this process in overhead self-launching scaffolding, for example, a special pier segment (28) can be previously executed that, in addition to the components of an empty segment (3), can have incorporated, for example, a pre-slab and a frame of the shoring system (6). This special pier segment (28) may alternatively, and also for example, be a conventional prefabricated segment, already with filling material. In this case, this is the segment corresponding to ‘segment 0’.
In these special pier segments (28), the fixing element (4) can be different and need not have connections to the scaffolding, as can be seen in
The construction process in accordance with the present invention can be applied in various types of shoring systems (6) (lower self-launching scaffolding, ground scaffolding, or others) simply by making the adaptations resulting from the characteristics of the shoring systems, with impact on the choice of means of transport (17) and in the design of the fixing elements (4), and may also influence the design of auxiliary equipment (19) of shoring systems (6). It is good project practice to develop the project with a simultaneous selection of the type of shoring system (6) to be adopted.
The application of the construction process in accordance with the present invention to reinforced concrete structures without prestressing (10) and (11) is in everything identical to that presented in this text, without the tasks/actions and elements related to the prestressing.
In the construction of concrete structures, several structural systems, with several horizontal shapes can be executed by this method (see
Likewise, the construction process according to the present invention can be used in the construction of structures (1) of reinforced (and/or prestressed) concrete with different cross-sections, as for example the A-A cutaway section of
In some cases, as in the example of
This method without shoring system (6) can also be applied in elements such as shown in
The application of the construction process in accordance with the present invention to structures (1) executed with other materials, for example, glass, ceramic, plastic or with hydraulic binders other than those used in reinforced concrete, is also possible provided the structure (1) to be constructed is divisible into one or more structure segments (2) and can justify and reveal advantages if this structure (1) is composite, either including steel reinforcement materials (9) or interface structures or inserts (12), and may also include or not, active reinforcement elements (11) and active reinforcement ducts (10), if necessary, and in which there are advantages to pouring the filling material (8) in situ in a place other than the place of prefabrication of the empty segments.
For example, this type of solution can be used to construct library or warehouse shelving made of plastic, with steel reinforcements (11) and/or rigid inserts (12), in plastic reservoirs with steel reinforcements (9) and/or active reinforcement (11), or glass structures with a wide span to be executed in situ, and that include steel reinforcements (9) and/or inserts (12), or, more generally, composite structures in which it is advantageous to pour the filling material (8) in situ.
Number | Date | Country | Kind |
---|---|---|---|
107822 | Jul 2014 | PT | national |
Filing Document | Filing Date | Country | Kind |
---|---|---|---|
PCT/PT2015/050002 | 7/29/2015 | WO | 00 |
Publishing Document | Publishing Date | Country | Kind |
---|---|---|---|
WO2016/018166 | 2/4/2016 | WO | A |
Number | Name | Date | Kind |
---|---|---|---|
1299729 | Hubbell | Apr 1919 | A |
1888181 | Riesbol | Nov 1932 | A |
2708780 | Burkhalter | May 1955 | A |
3049786 | Jones | Aug 1962 | A |
3571835 | Buechler | Mar 1971 | A |
3882564 | Muller | May 1975 | A |
3999735 | Brownlee | Dec 1976 | A |
4104844 | Brownlee | Aug 1978 | A |
4426949 | Knutsen | Jan 1984 | A |
4573303 | Figari | Mar 1986 | A |
4604841 | Barnoff | Aug 1986 | A |
5425152 | Teron | Jun 1995 | A |
5577284 | Muller | Nov 1996 | A |
6101779 | Davenport | Aug 2000 | A |
6345403 | Nagle | Feb 2002 | B1 |
7197854 | Bettigole | Apr 2007 | B2 |
8109691 | Clark | Feb 2012 | B2 |
8375676 | Takakura | Feb 2013 | B2 |
8640292 | Sorkin | Feb 2014 | B1 |
8671641 | Takakura | Mar 2014 | B2 |
9604416 | Sorkin | Mar 2017 | B2 |
9751236 | Daul | Sep 2017 | B2 |
9982434 | Crigler | May 2018 | B1 |
20050102951 | Bennett | May 2005 | A1 |
20050115195 | Bettigole | Jun 2005 | A1 |
20070028552 | DeLoach, Sr. | Feb 2007 | A1 |
20100088985 | Mellier | Apr 2010 | A1 |
20100275545 | Kumpf | Nov 2010 | A1 |
20110041433 | He | Feb 2011 | A1 |
20110194897 | Clark | Aug 2011 | A1 |
20120282025 | French | Nov 2012 | A1 |
20150252558 | Chin | Sep 2015 | A1 |
20150330079 | Sorkin | Nov 2015 | A1 |
20160305077 | Shamsai | Oct 2016 | A1 |
20160319541 | Sanabra | Nov 2016 | A1 |
20170037624 | Sorkin | Feb 2017 | A1 |
20170152660 | Sorkin | Jun 2017 | A1 |
20170275881 | Sorkin | Sep 2017 | A1 |
20180050467 | Kloet | Feb 2018 | A1 |
20190010695 | Zavitz | Jan 2019 | A1 |
Number | Date | Country |
---|---|---|
25 20 105 | Nov 1976 | DE |
2 088 244 | Aug 2009 | EP |
2008274637 | Nov 2008 | JP |
Entry |
---|
International Search Report for PCT/PT2015/050002 dated Dec. 3, 2015 [PCT/ISA/210]. |
Written Opinion for PCT/PT2015/050002 dated Dec. 3, 2015 [PCT/ISA/210]. |
Number | Date | Country | |
---|---|---|---|
20170275901 A1 | Sep 2017 | US |