1. Field of the Invention
The present invention relates to a furnace system, and more particularly to a high temperature and continuous furnace system including a pre-heating device for pre-heating the work piece to the required temperature, a furnace facility including a heating zone and a carburizing zone for heating the work piece to a higher temperature, and a diffusing zone and a cooling zone for suitably cooling the work piece to the required structure or strength.
2. Description of the Prior Art
Typical steel materials, such as the high chromium steel materials or plates comprise a number of slits or slots or gaps formed or provided therein while subjected with various heating processes or procedures with various kinds of furnace facilities, such that the strengths of the typical high chromium steel materials are low or are not good enough to make products and may become defective products.
For solving such problems, the skilled technicians use or employ a high temperature to heat the typical high chromium steel materials and to have the slits or slots or gaps formed or provided in the typical high chromium steel materials filled with the steel materials and to have a compact and solid structure such that the strengths of the typical high chromium steel materials may be suitably increased and may be used and made into various kinds of products.
For the typical high chromium steel material heating furnaces, the high chromium steel materials or plates are required to be disposed or engaged into the typical steel furnaces for heating the high chromium steel materials or plates to the required higher temperature and for allowing the slits or slots or gaps formed or provided in the typical high chromium steel materials or plates to be filled with the steel materials and to have a compact and solid structure.
However, after the heating operations, the heated high chromium steel materials or plates should be removed from the typical steel furnaces for cooling purposes, and a number of skilled technicians and man working hours are required to move the typical high chromium steel materials or plates into and out of the typical steel furnaces such that manufacturing procedures and cost will be greatly increased.
U.S. Pat. No. 4,227,874 to Nugent, U.S. Pat. No. 4,582,301 to Wunning, U.S. Pat. No. 4,767,320 to Sasaki et al., U.S. Pat. No. 5,848,890 to McCormick, and U.S. Pat. No. 7,520,746 to Johnston et al. disclose several of the typical furnace product supporting or transporting devices for supporting or transporting the typical high chromium steel materials or plates into and out of the typical steel furnaces.
However, the typical furnace product supporting or transporting devices may only be used to support or to transport the typical high chromium steel materials or plates into and out of the typical steel furnaces, but may not be used to move or to transport the typical high chromium steel materials or plates between heating zones and/or cooling zones.
In addition, without pre-heating processes or procedures, the typical high chromium steel materials or plates will be quickly heated to a very high temperature and may have a good chance to be distorted or twisted and will become a defect product. Furthermore, the heat energy generated during the heating processes or procedures may not be recycled or reused such that a number of heat energy will be wasted.
For improving or overcoming the afore-described disadvantages of the conventional steel furnace systems, the applicant had developed another typical high temperature and continuous furnace system and issued as U.S. Pat. No. 8,298,475 to Tseng which includes a heating zone and one or more cooling zones for suitably heating the high chromium steel and for allowing the high chromium steel to have a compact and solid structure, and includes a heat energy recycling or reusing system to recycle or reuse the heat energy and to economize the heat energy, and includes a pre-heating zone for pre-heating the high chromium steel before the high chromium steel is heated to a required or predetermined high temperature and for preventing the high chromium steel from being distorted or twisted.
However, the metal products made or manufactured with the typical high temperature and continuous furnace system may also have a cracking problem; i.e., a number of slits or slots may still be formed within the metal products such that the defective products may have a good chance to be formed.
The present invention has arisen to mitigate and/or obviate the afore-described disadvantages of the conventional steel furnace systems.
The primary objective of the present invention is to provide a high temperature and continuous furnace system including a pre-heating device for pre-heating the work piece to the required temperature, a furnace facility including a heating zone and a carburizing zone for heating the work piece to a higher temperature, and a diffusing zone and a cooling zone for suitably cooling the work piece to the required structure or strength.
In accordance with one aspect of the invention, there is provided a furnace system comprising a conveyer device for supporting and transporting a work piece, a pre-heating device supported on the conveyer device and located at an entrance portion of the conveyer device for receiving the work piece and for pre-heating the work piece, the pre-heating device including a front door and a rear door for confining the work piece within the pre-heating device, a heating member disposed in the pre-heating device for pre-heating the work piece, a furnace facility disposed on the conveyer device and located behind the pre-heating device, the furnace facility including a longitudinal chamber formed therein for receiving the work piece, and including a heating zone for further heating the work piece to a higher temperature, a carburizing zone located behind the heating zone for further heating the work piece and for carburizing the work piece, a diffusing zone located behind the carburizing zone for lowering the temperature of the work piece, a temperature decreasing zone located behind the diffusing zone for decreasing the temperature of the work piece, and a cooling zone located behind the temperature decreasing zone for lowering the work piece to a room temperature, the furnace facility including a front door and a rear door and at least one intermediate door for confining the work piece within the furnace facility, the conveyer device being provided for transporting and moving the work piece from the pre-heating device through the heating zone and the carburizing zone and the diffusing zone and the temperature decreasing zone and the cooling zone of the furnace facility, and a heating element disposed in the furnace facility for pre-heating the work piece.
The pre-heating device includes a safety valve and a discharging port provided in the pre-heating device for preventing the pre-heating device from being over-pressurized. The pre-heating device includes a fan device for air circulating purposes. The pre-heating device includes a thermometer for detecting a temperature in the pre-heating device.
The furnace facility includes a safety valve and a discharging port provided in the furnace facility for preventing the furnace facility from being over-pressurized. The furnace facility includes a fan device for air circulating purposes.
The furnace facility includes an oxygen detector for detecting an oxygen quantity in the furnace facility. The furnace facility includes a nitrogen supplying port for supplying a nitrogen to the furnace facility.
The furnace facility includes a methyl alcohol supplying mouth disposed in the heating zone, the carburizing zone or the diffusing zone for supplying a methyl alcohol to the heating zone, the carburizing zone or the diffusing zone of the furnace facility.
A receptacle may further be provided and disposed below a rear end portion of the conveyer device for collecting the work piece.
Further objectives and advantages of the present invention will become apparent from a careful reading of the detailed description provided hereinbelow, with appropriate reference to the accompanying drawings.
Referring to the drawings, and initially to
A furnace facility 30 is also disposed or attached or mounted or supported on top of the conveyer device 10 and disposed or arranged or located behind the pre-heating device 20, and includes a heating zone 31 disposed or located or arranged behind the pre-heating device 20 and disengaged or separated from the pre-heating device 20 for further heating and increasing the temperature of the work piece 90 to the required or predetermined higher temperature (about 500˜750° C.), and a carburizing zone 32 disposed or located or arranged behind the heating zone 31 for further heating and increasing the temperature of the work piece 90 to the required or predetermined higher temperature (about 750˜930° C.), and for carburizing the work piece 90, and an annealing or diffusing zone 33 disposed or located or arranged behind the carburizing zone 32 for slightly lowering or decreasing the temperature of the work piece 90 to the required or predetermined less or lower temperature (about 930˜860° C.) and for diffusing the work piece 90.
The furnace facility 30 further includes an ageing or temperature decreasing zone 34 disposed or located or arranged behind the diffusing zone 33 for further gradually lowering or decreasing the temperature of the work piece 90 to the required or predetermined less or lower temperature (about 860˜830° C.), and a cooling zone 35 disposed or located or arranged behind the ageing or temperature decreasing zone 34 for further quickly lowering or decreasing the temperature of the work piece 90 to the required or predetermined less or lower or room temperature (about 20° C.). The furnace facility 30 includes a front door 36 and a rear door 37 and one or more middle or intermediate door 38 (
The furnace facility 30 also includes one or more heating devices or members or elements 40 disposed or attached or mounted or engaged in the furnace facility 30 and located or arranged in at least the heating zone 31 and the carburizing zone 32 for suitably heating and increasing the temperature of the work pieces 90 to the required or predetermined higher temperature. The heating elements 40 and the heating member 23 may be selected from the gaseous heating devices or materials, electrical heating devices or materials or the like for suitably heating the work pieces 90. The temperature of the work pieces 90 will be lowered or decreased in at least the diffusing zone 33 and the temperature decreasing zone 34 and the cooling zone 35 such that no heating devices or members or elements are required to be provided or disposed or located or arranged in the furnace facility 30. The furnace facility 30 may include a cooling device or material or member or element (not illustrated), such as selected from a gaseous, or water or oil or other fluid cooling device or material or member or element for suitably cooling the work pieces 90.
The conveyer device 10 is provided for transporting or moving the work pieces 90 from the pre-heating device 20 through the heating zone 31 of the furnace facility 30, and then toward and through the carburizing zone 32 and the diffusing zone 33 and the temperature decreasing zone 34 and the cooling zone 35 of the furnace facility 30. The furnace system may further include a container or receptacle 70 disposed or located or arranged below the other end or rear end portion 12 of the conveyer device 10 (
As shown in
As shown in
In operation, as shown in
The work piece 90 is then transported or moved or sent into the carburizing zone 32 of the furnace facility 30 and further heated to the required or predetermined higher temperature (about 750˜930° C.) and preferably stayed or retained in the carburizing zone 32 for about one hundred and twenty (120) minutes, and for allowing the slits or slots or gaps formed or provided in the work piece 90 to be further filled with the steel materials and to have a further compact and solid structure. The work piece 90 is then transported or moved or sent into the diffusing zone 33 of the furnace facility 30 and slightly or gradually lowered or decreased to the required or predetermined less or lower temperature (about 930˜860° C.) and for diffusing the work piece 90. It is preferable that the work piece 90 is stayed or retained in the diffusing zone 33 of the furnace facility 30 for about forty to sixty (40-60) minutes, and for allowing the slits or slots or gaps formed or provided in the work piece 90 to be further completely filled with the steel materials.
The work piece 90 is then transported or moved or sent into the temperature decreasing zone 34 of the furnace facility 30 and slightly or gradually lowered or decreased to the required or predetermined less or lower temperature (about 860˜830° C.), and stayed or retained in the temperature decreasing zone 34 of the furnace facility 30 for about thirty (30) minutes and for slightly or gradually lowering or decreasing the temperature of the work piece 90 and for preventing the work piece 90 from being distorted or twisted, and the work piece 90 is then transported or moved or sent into the cooling zone 35 of the furnace facility 30 and lowered or decreased to the less or lower or room temperature, and thus for forming the required work piece 90.
Accordingly, the high temperature and continuous furnace system in accordance with the present invention includes a pre-heating device for pre-heating the work piece to the required temperature, a furnace facility including a heating zone and a carburizing zone for heating the work piece to a higher temperature, and a diffusing zone and a cooling zone for suitably cooling the work piece to the required structure or strength.
Although this invention has been described with a certain degree of particularity, it is to be understood that the present disclosure has been made by way of example only and that numerous changes in the detailed construction and the combination and arrangement of parts may be resorted to without departing from the spirit and scope of the invention as hereinafter claimed.
Number | Name | Date | Kind |
---|---|---|---|
2091172 | Wilson | Aug 1937 | A |
4227874 | Nugent | Oct 1980 | A |
4582301 | Wunning | Apr 1986 | A |
4627814 | Hattori | Dec 1986 | A |
4767320 | Sasaki | Aug 1988 | A |
5273585 | Shoga | Dec 1993 | A |
5749978 | Colombani | May 1998 | A |
5848890 | McCormick | Dec 1998 | A |
7018584 | Serafini, Jr. | Mar 2006 | B2 |
7029625 | Shimosato | Apr 2006 | B2 |
7520746 | Johnston et al. | Apr 2009 | B1 |
8298475 | Tseng | Oct 2012 | B2 |
Number | Date | Country | |
---|---|---|---|
20150275325 A1 | Oct 2015 | US |