The technique for the excavation and preparation of tunnels or of underground excavations of any type whatsoever for roads, railways, for canals or underground waterways etc., generally makes use of peripheral consolidation techniques in such way as to create a resistant surrounding for the thrust of the earth during the internal excavation and the final realisation of the work.
Nowadays such known consolidation interventions envisage multiple perforations created around all or part of the external circumference of the tunnel, within which metal, fibreglass or other suitable material reinforcements or inserts are introduced, which are filled with a jet of concrete or other means of consolidation, such as cement mixtures, gel or resins, injected at low or high pressure. These consolidating materials mix with the material present around the periphery of the tunnel being built.
With these known systems crown or umbrella stretches of the consolidated terrain are created, which allow the carrying out in safety of a smooth stretch of excavation of the tunnel. Such a system of execution takes place for further courses of consolidation that are obviously quite short (for example 15-20 m. in length) with resistant veins off axis compared to the tunnel axis, in such way as to be able to act for later stretches of consolidation and relative successive excavation stretches.
The main inconveniences of this known system of proceeding are the following:
In cases in which the consolidation should have to be performed from above on a surface over the tunnel (tunnels with little cover) the difficulties of consolidation, at the current state of the art, are the following:
Guided perforation systems are also known for tunnels or underground channels of limited cross-section such as sewers, water ducts, channels for electric and telephone cables etc., where said guided perforation takes place by means of equipment with rotating pipes fitted with special perforating heads, such flute shaped heads or hole bottom with asymmetric headed hammers or alternatively with mud turbines, which allow performance of piloted perforations even of considerable length, such as for instance more than 800 m depending on the terrain to cross, with direction that is constantly checked with systems of directional command, such as radio, magnetic, radar, radioactive, with reference to GPS systems or with optical and electronic references, so as to allow at any time the exact location and orientation of the head in the perforation phase.
Perforation may take place with the use of air or fluids under pressure, with destruction or coring bits, with the use of hole bottom hammers, with milling cutters, tricone bits, chisels, mud turbines etc. suitable for correction of the direction of perforation.
The material that results from the perforation discharges between the walls of the drill hole and the drill rod or between the rods and the possible casing, as commonly happens with perforation equipment for wells. The perforation rods that step by step advance within the excavation are then recovered together with the perforation head and during such recovery the possible boring of the hole and the placing of casing takes place with an internal liner in case of drainage or service pipes.
As mentioned, such guided perforation equipment as known nowadays, allows only the perforation of holes or channels of limited cross-section and does not yet permit the excavation of tunnels of considerable or large dimensions, which require consolidation before the excavation operations.
The purpose of this invention is that of eliminating the inconveniences complained of in regard to the technique used today for the preparation of tunnels or of similar underground works of considerable dimensions and lengths and practically to eliminate the need for successive, intermittent and alternative interventions (consolidation and excavations of limited length) and the consequent purpose of this invention is that of obtaining a method of execution that allows consolidation of the whole length of the tunnel or consolidation for stretches of considerable length, consolidation followed by the corresponding excavation.
According to this invention, this purpose is satisfied, performing the works of consolidation by means of an adequate number of guided peripheral perforations and possibly to the nucleus or in another position of the tunnel being built and later consolidation with the introduction in each perforation of opportune products, commonly known as reinforcements or inserts (metallic, in fibreglass or in other suitable materials) aimed at receiving the consolidation jet at high or low pressure or allowing consolidation using the jet-grouting technology with pressure jets of cement mixtures, gel or resins.
During the works of consolidation works of drainage may also be made, making use of one or more of the guided perforations, obviously covered and left free to discharge the drainage waters.
In the case in which the perforation reaches the other extremity of the work on the tunnel or the excavation, it is possible to replace the perforation bits either with reamers to pull the reinforcements or with nozzles for the treatment of jet-grouting type; and it is also possible to use the perforation rods as jet rods; in case the perforations terminate, instead, in the terrain the jet-grouting equipment will be mounted behind the perforation bits or, just as the inserts, reintroduced in the hole following extraction of the perforation rods also with the use of coatings to prevent the caving in of the hole itself.
Having performed the works of consolidation on the periphery of the tunnel being built, one arranges, after the setting time for the cement mixtures and/or other materials used for the consolidation, to excavate the core of the tunnel for the whole of its length or for relatively long stretches of the same.
After excavation the works of plugging of the bottom and walls are carried out according to known techniques for finishing of the tunnel.
This way of proceeding according to the invention, has considerable executive and economic advantages. The executive advantages are substantially:
The economic advantages obtained with the method in question are:
The invention in question is clarified in its practical and exemplary realisations of a tunnel in the attached drawings, where:
With reference to said figures, with
In
This guided perforation equipment is constantly monitored and controlled by radio, magnetic, radar, optic or electronic reference systems etc. in such way as to define the precise position of the perforation bit and its orientation. The guided perforation 3 is the first phase of the consolidation operations.
In
The next phase three of the consolidation operations, envisages numerous guided and consolidated peripheral perforations 3 practically with parallel axes, created around the tunnel being built 1 with crown arrangement according to
The next phase four concerns, after setting of the consolidations, start of excavation 7, which takes place along the whole length of the tunnel 1 or for successive long stretches of the same.
The last phase five regards treatment of the finishing of the walls and floor as well as all the successive works inherent with the definitive functional arrangement of the tunnel.
Particular interest is paid in this invention, to phase two of consolidation, which uses the numerous guided perforations 3 as described above, and the works of consolidation that may be made with columnar jet-grouting treatment or by means of systems with reinforcements or still again with the two systems mixed. Furthermore, one or more of the guided perforations 3 may be used for drainage of the tunnel.
Consolidation through columnar jet-grouting treatment envisages, during withdrawal or advancing of the guided perforation equipment 3, injection within the perforation of aggregating substances, such as cement compounds, gel, resins, etc., which on mixing with the terrain create resistant cores along the whole length of the tunnel or part of it.
Instead, consolidation through a reinforcement system envisages, either during the perforation or during withdrawal of the guided perforation equipment 3, the introduction into the perforation of metal or other material inserts and successive injection at low or high pressure, of aggregating materials (cement compounds, resins, etc.). This reinforcement improves the resistance of the internal core 6 that is forming with the expansion of the aggregating products in the terrain adjacent to the guided perforation.
The mentioned systems of jet-grouting consolidation or by means of reinforcements, may also be used one with the other according to the type of excavation to be carried out and the type of tunnel to be created.
In case of use of a guided perforation 3 for drainage of the tunnel, one arranges to replace the excavation head with a bore reamer that drags, during recovery of the rotating tubular rods of the perforation equipment, a metal pipe or one of other suitable material, that is laid inside the excavation with the function of casing for the drainage duct.
The placement of inserts and drainage even after the extraction of the perforation rods from the same part of the start of perforations is envisaged with a simple thrusting of the reinforcements or drainage pipes into the free hole protected in the perforation phase by casing pipes (to be recovered later) that prevent caving in.
It is therefore evident, according to the aims of this invention, that use of the guided perforation system, to carry out the external consolidation of the tunnel before excavation, allows to obtain functional and economic advantages of great value compared to the current consolidation technique with extremely short stretches (15−20 m.) permitting consolidation over the entire length of the tunnel or on a few relatively long stretches of the tunnel itself (stretches of tunnel up to 800 m and more are possible). Even the preparation of tunnels with routes with little cover realisable with consolidation to be obtained with jet-grouting techniques from above (from the surface), according to this invention shows advantages that are evident in that most of the empty perforations before reaching the consolidation zone are eliminated.
The advantage should also be noted that consolidation through guided perforation, according to this invention, allows to obtain a resistant work according to precise static conditions in that guided perforations are traced exactly as in the project, even following curved routes though orientation of the guided perforating heads. The invention is also advantageous for the realisation of consolidation of underground elements, even horizontal, of separation of contiguous terrain with hydraulic and hydro-geological aims, to separate phreatic or artesian surfaces or for the impermeabilisation of lakes, troughs, canals or to restore impermeability to tanks used for discharge. These underground elements may have consolidation works through guided perforations done in simple or multiple series, where each guided perforation receives the aggregating materials by means of a system with inserts or with the jet-grouting system. These consolidation works of the task may be independent of possible excavations or remodelling of the terrain.
Number | Date | Country | Kind |
---|---|---|---|
GE2003A0005 | Jan 2003 | IT | national |
Number | Name | Date | Kind |
---|---|---|---|
3498674 | Matthews | Mar 1970 | A |
5845720 | Borjeson et al. | Dec 1998 | A |
6234716 | Chiaves | May 2001 | B1 |
6241426 | Schellhorn | Jun 2001 | B1 |
Number | Date | Country |
---|---|---|
2 320 366 | Nov 1974 | DE |
34 47 872 | Jul 1986 | DE |
199 40 774 | Apr 2001 | DE |
0 291 193 | Nov 1988 | EP |
0 774 566 | May 1997 | EP |
0 833 011 | Apr 1998 | EP |
08060976 | Mar 1996 | JP |
2001082074 | Mar 2001 | JP |
WO 9425688 | Nov 1994 | WO |
Number | Date | Country | |
---|---|---|---|
20040144003 A1 | Jul 2004 | US |