This disclosure is generally related to the modular construction of process facilities, with particular examples given with respect to modular steam cracker processing facilities (although the modular construction described herein may apply to other types of processing facilities).
In the engineering industry, a petrochemical plant that uses energy to break apart (e.g., crack) molecules to form new molecules is called a cracker. Generally, the cracker process may widely differ depending on the type of feedstock used (e.g., natural gas liquids (NGLs) such as ethane, propane, and butane; naphtha, light gas oil, etc.). In recent years, due to technological advancements such as shale development, several petrochemical manufacturers have discovered an abundance of NGLs in shale plays like the Marcellus, Bakken, Utica, and Eagle Ford. Since ethane is a major component of NGLs, the cost of ethane due to a significant increase in availability has decreased. With this newfound low cost of energy and ethane, manufacturers seek to expand steam cracking abilities to form ethylene from ethane feedstock.
Steam cracking may be used to convert ethane to ethylene and, additionally, propylene. The worldwide demand for ethylene is ever-increasing. Ethylene serves as a building block in producing a variety of other chemicals (e.g., polyvinylchloride (PVC), ethylbenzene, ethylene oxide, ethylene glycol, polyethylene terephthalate, etc.) used to manufacture products such as construction materials (e.g., piping for plumbing, siding for houses, decking, etc.), Styrofoam, automobile tires, surfactants, detergents, antifreeze, polyester, and beverage bottles. Thus, ethylene is typically seen as a basic commodity similar to electricity or water because it may be used to form various finished goods and consumer products. However, conventional steam cracking facilities can be extraordinarily challenging to build especially in remote locations or under adverse conditions. Additionally, conventional steam cracking facilities may require up to millions of hours of work on-site leading to higher labor risks and higher set-up costs.
Given the difficulties of building a facility entirely on-site, there has been considerable interest in 2nd Generation Modular Construction. In that technology, a facility is logically segmented into modules. The modules are constructed in an established industrial area, trucked or airlifted to the plant site, and then coupled together at the plant site (typically via a piperack (external piping) interconnecting the 2nd Gen modules (“2nd Gen”)). Typically such 2nd Gen modules are not process based, but rather are equipment based, meaning that each of the modules in a 2nd Gen Construction typically relates to a specific equipment type (e.g., pumps, compressors, heat exchangers, cooling towers, etc.). Several 2nd Gen Modular Construction facilities are in place in the tar sands of Alberta, Canada, and they have been proved to provide numerous advantages in terms of speed of deployment, construction work quality, reduction in safety risks, and overall project cost.
2nd Gen Modular facilities have also been described in patent literatures. An example of a large capacity oil refinery composed of multiple, self-contained, interconnected, and modular refining units is described in WO 03/031012 to Shumway. A generic 2nd Gen Modular facility is described in US 2008/0127662 to Stanfield.
Unless otherwise expressly indicated herein, WO 03/031012, US 2008/0127662, and all other extrinsic materials discussed herein, and in the priority specification and attachments, are incorporated by reference in their entirety. Where a definition or use of a term in an incorporated reference is inconsistent with or contrary to the definition and/or usage of that term provided herein, the definition or usage of that term provided herein applies, and the definition of that term in the reference does not apply.
In some embodiments, a modular processing facility comprises at least 3 process blocks. The at least 3 process blocks are non-identical process blocks, and the at least 3 process blocks each comprise one or more modules. Each process block of the at least 3 process blocks is interconnected to one or more of the other at least 3 process blocks, and the at least 3 process blocks comprise the following: an ethane cracking furnace, a steam generation process, a water stripper, a water quench, a compression, a caustic scrubber, a drier, a deethanizer, an acetylene conversion, a demethanizer, a refrigerator, or a splitter.
In some embodiments, a method of constructing a modular facility comprises arranging a plurality of process blocks with respect to one another, directly interconnecting each process block to one or more adjacent process blocks, and configuring each process block to accomplish a corresponding process. The plurality of process blocks are non-identical process blocks, and the plurality of process blocks each comprise one or more modules. The plurality of process blocks comprise at least 3 of: an ethane cracking furnace process block, a water quench process block, a water stripper process block, a cracked gas compression process block, a caustic treatment process block, a drying process block, a deethanizer process block, an acetylene conversion process block, a demethanizer process block, a refrigeration process block, or a C2 splitter process block.
In some embodiments, a facility comprises a first process block, a second process block, and a third process block. The first process block, the second process block, and the third process block are coupled together, and at least 3 transportable modules are used to collectively compose the first process block, the second process block, and the third process block. Each of the first process block, the second process block, and the third process block is fluidly and electrically coupled to at least one other of the first process block, the second process block, and the third process block using direct-module-to-module connections, and no external piperack interconnects the first process block, the second process block, and the third process block. The first process block is positioned adjacent to each of the second process block and the third process block, and the first process block is configured to carry out a first process and the second process block is configured to carry out a second process different from the first process.
These and other features will be more clearly understood from the following detailed description taken in conjunction with the accompanying drawings and claims.
For a more complete understanding of the present disclosure, reference is now made to the following brief description, taken in connection with the accompanying drawings and detailed description, wherein like reference numerals represent like parts.
It should be understood at the outset that although illustrative implementations of one or more embodiments are illustrated below, the disclosed systems and methods may be implemented using any number of techniques, whether currently known or not yet in existence. The disclosure should in no way be limited to the illustrative implementations, drawings, and techniques illustrated below, but may be modified within the scope of the appended claims along with their full scope of equivalents.
The following brief definition of terms shall apply throughout the application:
The term “comprising” means including but not limited to, and should be interpreted in the manner it is typically used in the patent context;
The phrases “in one embodiment,” “according to one embodiment,” and the like generally mean that the particular feature, structure, or characteristic following the phrase may be included in at least one embodiment of the present invention, and may be included in more than one embodiment (importantly, such phrases do not necessarily refer to the same embodiment);
If the specification describes something as “exemplary” or an “example,” it should be understood that refers to a non-exclusive example;
The terms “about” or “approximately” or the like, when used with a number, may mean that specific number, or alternatively, a range in proximity to the specific number, as understood by persons of skill in the art field (for example, +/−10%); and
If the specification states a component or feature “may,” “can,” “could,” “should,” “would,” “preferably,” “possibly,” “typically,” “optionally,” “for example,” “often,” or “might” (or other such language) be included or have a characteristic, that particular component or feature is not required to be included or to have the characteristic. Such component or feature may be optionally included in some embodiments, or it may be excluded.
The terms “commissioning” and “pre-commissioning” refer to processes and procedures for bringing a system, component, module, process block, piece(s) of equipment, etc. in to working condition. These terms may include testing to verify the function of a given system, component, module, process block, piece(s) of equipment, according to the design specifications and objectives.
The term “process” is used herein in the manner that one of ordinary skill (i.e., a process engineer) would use the term for individual processes in a process block layout of a processing facility. In addition, a process carried out within a process block may include one or more “unit operations” which include a physical change and/or chemical transformation in a given process flow (e.g., fluid or solid flow).
Unless the context dictates the contrary, all ranges set forth herein should be interpreted as being inclusive of their endpoints, and open-ended ranges should be interpreted to include only commercially practical values. Similarly, all lists of values should be considered as inclusive of intermediate values unless the context indicates the contrary.
There have been significant cost savings in using 2nd Gen Modular approaches. It is contemplated, for example, that building of a process module costs $4 (US) in the field for every $1 (US) spent building an equivalent module in a construction facility. Nevertheless, despite the many advantages of 2nd Gen Modular, there are still problems. Serious problems may arise from the ways in which the various modules are inter-connected. In 2nd Gen Modular units, the fluid, power, and control lines between modules are carried by external piperacks. This can be seen clearly in FIGS. 1 and 2 of WO 03/031012, for example. In facilities using multiple, self-contained, substantially identical production units, it is logically simple to operate those units in parallel, and to provide feed (inflow) and product (outflow) lines along an external piperack. However, where small production units are impractical or uneconomical, the use of external piperacks can be a hindrance. For example, not only does the 2nd Gen usage of one or more external piperacks typically result in the utilization of more piping and additional work in the field to interconnect modules, external piperacks interconnecting modules (and/or the use of equipment-based modules) may also typically severely limit the amount of pre-commissioning, check out, and/or commissioning of modules individually and/or before they are installed at the ultimate site of the facility (e.g., at a construction facility in an industrial area remote from the ultimate site of the entire process facility). This limitation typically arises due to the equipment-based nature of 2nd Gen modules as described above, which does not lend itself to stand-alone pre-commissioning, check-out, and/or commissioning (because in order for a process to be performed using such equipment-based 2nd Gen modules, the modules would have to be interconnected with other modules in a way that forms a process which can be evaluated effectively as a whole). This may also especially be true since typical 2nd Gen modules do not have integrated electrical and instrumentation (E+I) systems in each module, but instead, typically are connected to a centralized E+I system (for example via home run interconnecting cabling through traditional interconnecting racks).
What is needed is a new modular paradigm, in which the various processes of a cracker plant are segmented into process blocks, where each process block comprises one or more (typically multiple) modules. Each such process block typically has a plurality of different types of equipment relating to different engineering disciplines, all working together to jointly perform an overarching process. And typically, the process blocks are configured to allow for off-site (e.g., stand-alone pre-commissioning, check-out and/or commissioning, for example at a site away from the ultimate site and/or away from the site of other process blocks). Also, in forming a 3rd Gen facility, the process blocks are typically interconnected without external piperacks (and most typically without any external piping therebetween, rather having direct connections which are typically located within the envelope (opening) of the relevant process blocks). This document refers to such designs and implementations as 3rd Generation (“3rd Gen”) Modular Construction or as 3rd Gen processing facilities, as further discussed below.
The disclosed subject matter provides apparatus, systems, and methods in which the various processes of a cracker plant are segmented into process blocks, each process block comprising one or more (typically multiple) modules, wherein at least some of the modules within at least some of the process blocks are fluidly and electrically coupled to at least another of the modules using direct-module-to-module connections (e.g., without external piping).
Typically, embodiments of a 3rd Gen processing facility would be constructed (for example modularly) by coupling together at least two process blocks. In preferred embodiments, a processing facility might be constructed at least in part by coupling together three or more process blocks. In some embodiments, each of at least two of the blocks comprises at least two truckable modules, and more preferably three, four, five, or even more such modules. Contemplated embodiments can be rather large, and can have four, five, ten, or even twenty or more process blocks, which collectively might comprise up to a hundred, two hundred, or even a higher number of truckable modules in some embodiments. Other embodiments may have process blocks comprising one or more transportable modules. All manner of industrial processing facilities are contemplated, including nuclear, gas-fired, coal-fired, or other energy producing facilities, chemical plants, petrochemical plants, and mechanical plants. And while 3rd Gen techniques might be used for some off-shore modular construction, more often 3rd Gen modules and construction techniques would be used to construct on-shore processing facilities.
As used herein the term “process block” means a part of a processing facility that has several process systems within a distinct geographical boundary. Typically, each process block is configured to achieve a single (stand-alone) process, for example of the sort that a process engineer might use in a process block layout. Thus, the term “process” in this context is utilized in the manner that one of ordinary skill (e.g., a process engineer) would use the term for individual processes in a process block layout of a processing facility. A process carried out within a process block may include one or more unit operations (e.g., a physical change and/or chemical transformation), and typically a process block might comprise two or more unit operations. So in at least some embodiments, a process block includes multiple pieces and types of equipment (e.g., pumps, compressors, vessels, heat exchangers, vessels, coolers, blowers, reactors, etc., for example) for carrying out a plurality of unit operations within a contiguous, defined geographical area (i.e., the geographical area defined by the corresponding process block). In addition, in at least some embodiments the process blocks (e.g., the multiple pieces and types of equipment as well as the multiple unit operations) would be arranged and designed to support or relate to at least one common, overarching process, for example relating to the primary process flow of the production facility as a whole. Typically, each process block would have its own self-supporting (e.g., independent) E+I. Due to such features, each process block may be operable or configured for independent pre-commissioning, check-out, and/or commissioning (for example, with respect to E+I of the relevant process block). Thus, each process block may be independently pre-commissioned, checked-out, and/or commissioned with respect to E+I, for example at a site remote from the ultimate/final site of the overall facility and/or without interconnection with any other process block and/or module and/or equipment. Each process block typically accepts specific feed(s) and processes such feed(s) into one or more products (e.g., outputs). In some instances, one or more of the feed(s) for a specific process block may be provided from other process blocks(s) (e.g., the products from one or more other interconnected process blocks) in the facility, and in some instances the products from a specific process block might serve as inputs or feeds into one or more other process blocks of a facility.
In the hydrocarbon and chemical business, a process block can comprise equipment, such as processing columns, reactors, vessels, drums, tanks, filters, as well as pumps or compressors to move fluid(s) through the processing equipment including heat exchangers and heaters for heat transfer to or from the fluid(s). The type and arrangement of equipment within the defined geographic area of a given process block is designed to carry out the specific process(es) with the feed for that process block (i.e., the equipment arranged within the process block is chosen and arranged to facilitate the designed process(es) of the process block and is not simply grouped by equipment type such as would be found in a 2nd Gen modular construction). A process block typically might inherently have a series of piping systems and controls to interconnect the equipment within the process block. By eliminating the traditional interconnecting piperack (e.g., external piping of 2nd Gen), the 3rd Gen approach may facilitate an efficient systems-based layout resulting in the reduction of piping quantities. For solid material processing facilities, such as mineral processing, the piping systems described above would typically be replaced with material handling equipment (e.g., conveyors, belts, elevators, etc.). In the 3rd Gen approach, a process block may include, for example, 20 to 30 pieces of equipment, but there could be more or less pieces of equipment in some process block embodiments. Typically, all equipment for a specific process may be located within a single (for example, contiguous) geographic footprint and/or envelope. Thus, the inputs/feeds for a specific process block may typically be the inputs needed for the process (as a whole), and the outputs for the process block may typically be the outputs resulting from the process (as a whole). Thus, the actual process may be self-contained within the corresponding process block. And typically, each such process block is configured to achieve a distinct/different process (which may include one or more unit operations as previously described). While some process facilities might comprise only two process blocks, more typical process facilities may comprise at least 2 process blocks (and in some embodiments, at least 3, at least 5, at least 7, at least 10, or at least 15 process blocks), with each of the at least 2 process blocks being non-identical (e.g., each of the at least 2 process blocks may be configured for a different process) (e.g., not simply multiple, substantially identical modules, for example in parallel). So while there may be some amount of duplication of process blocks (for example, for scaling purposes) in 3rd Gen, it is typically true of 3rd Gen processing facilities that they include at least 2 different modular process blocks, which may be interconnected (for example via piping and/or electrical lines) in forming the entire facility. By way of example, a facility might have one or more process blocks for: generation of steam, distillation, scrubbing, separating one material from another, crushing, grinding, and/or performing other mechanical operations, performing chemical reactions with or without the use of catalysts, cooling, and the like. More specifically, a steam cracker facility may include one or more process blocks for steam generation, ethane cracking (e.g., via furnaces), quenching, compressing cracked gas, dilution, stripping water, caustic treatment, drying, demethanizing, deethanizing, converting acetylene, cooling, splitting ethylene, and the like.
As used herein, the term “truckable module” means a section of a process block that includes multiple pieces of equipment and has a transportation weight between 20,000 kilograms (Kg) and 200,000 Kg. The concept is that a commercially viable subset of truckable modules would be large enough to practically carry the needed equipment and support structures, but would also be suitable for transportation on commercially-used roadways in a relevant geographic area, for a particular time of year. It is contemplated that a typical truckable module for Western Canada tar sands areas would be between 30,000 Kg and 180,000 Kg, and more preferably between 40,000 Kg and 160,000 Kg. From a dimensions perspective, such modules would typically measure between 15 and 30 meters long, and at least 3 meters high and 3 meters wide, but no more than 35 meters long, 8 meters wide, and 8 meters high. While some embodiments may employ one or more truckable modules, other embodiments may employ one or more transportable modules. Transportable modules are modules (e.g., sections of a process block or an entire process block including multiple pieces of equipment) operable to be transported using one or more means for transport. “Transportable module” is intended to be a broader term than “truckable module,” such that the term typically includes truckable modules, for example, but also includes larger modules that would not be considered truckable. So for example, a transportable module might be at least 30,000 Kg or at least 40,000 Kg. In some embodiments, a transportable module might be up to 6,000,000 Kg, or even more (for example, for very large modules). In some embodiments, a transportable module might be between 30,000 Kg and 6,000,000 Kg, between 30,000 Kg and 500,000 Kg or between 40,000 Kg and 350,000 Kg. From a dimensions perspective, such transportable modules would typically measure at least 15 meters long, at least 3 meters wide, and at least 3 meters high, or in other embodiments at least 15 meters long, at least 4 meters wide, and at least 4 meters high.
Truckable and/or transportable modules may be closed on all sides, and on the top and bottom, but more typically such modules would have at least one open side, and possibly all four open sides, as well as an open top. The open sides allow modules to be positioned adjacent to one another at the open sides, thus creating a large open space, comprising 2, 3, 4, 5 or even more modules, through which an engineer operator, or other personnel could walk from one module to another, for example within a process block.
A typical truckable and/or transportable module may include equipment from multiple disciplines, as for example, process and staging equipment, platforms, wiring, instrumentation, and lighting.
One significant advantage of 3rd Gen Modular Construction is that process blocks are designed to have only a relatively small number of external couplings. In some embodiments, for example, there are at least two process blocks that are fluidly coupled by no more than three (3), four (4), or five (5) fluid lines, excluding utility lines. However, there could be two or more process blocks that are coupled by six (6), seven (7), eight (8), nine (9), ten (10), or more fluid lines, excluding utility lines. Each process block may include its own integrated E+I system such that E+I lines (e.g., cables, wires, etc.), for each process block, are routed through the modules of that process block. Fluid, power, and control lines coming into a process block may “fan out” (extend into different directions from a single point) to various modules within the process block. The term “fan out” is not meant in a narrow literal sense, but in a broader sense to include situations where, for example, a given fluid line splits into smaller lines that carry a fluid to different parts of the process block through orthogonal, parallel, and other line orientations. As used herein, “utility lines” refers to lines (e.g., pipes, conduits, tubes, hoses, etc.) for carrying fluids (i.e., liquids and gases) that facilitate the chemical and/or physical processes within one or more process blocks. For example, the fluid carried by a utility line may include air, nitrogen (N2), oxygen (O2), water (H2O), steam, etc. The term “utility line” does not include electrical or instrumentation cables, lines, wires, etc. (e.g., such as would be associated within the E+I system).
Process blocks can be assembled in any suitable manner. The arrangement of the process blocks may change depending on the site plan available, but, generally, the process block arrangement may be similar in order to optimize flow through the facility. For example, in some embodiments, 3rd Gen process blocks are arranged and interconnected with one another without an external piperack (so for example, the process blocks would not be laid out with a piperack backbone connecting the process modules, as may be fairly typical in 2nd Gen modular design, for example). Instead, in these embodiments, the 3rd Gen process blocks typically are directly interconnected with one another in accordance with a 3rd Gen Construction block layout, for example. In other words, each of the process blocks typically would be arranged/positioned in proximity (for example, oftentimes abutting) with one or more process blocks with which it interacts (e.g., with inputs and outputs directly interconnecting the process blocks), without intervening external interconnecting piperack(s) and/or process blocks there between. In some embodiments all of the process blocks might be positioned and/or interconnected in this manner (e.g., in proximity with and directly interconnected with the other process blocks with which it interacts). In other embodiments, only some of the process blocks (e.g., 3 or more, 5 or more, 8 or more, or 10 or more process blocks) may be so arranged and/or interconnected (and other process blocks might be arranged and/or interconnected differently). For example, in some embodiments, the process blocks for the primary process flow may all be positioned and/or interconnected, even though one or more other process blocks may be positioned in such a way as to require interconnection through an unrelated process block. This direct connection between interconnected process blocks may allow for close coupling of the process blocks, for example, with each process block abutting one or more other process blocks such that the interconnections therebetween are located within the envelope of those process blocks. The process blocks can be positioned end-to-end and/or side-to-side and/or above-below one another. Contemplated facilities include those arranged in a matrix of x by y blocks, in which x is at least 2 and y is at least 3. As another example, in other embodiments, the inputs and outputs of at least some of the 3rd Gen process blocks may be coupled via an internal piping spine that runs through at least a portion of the processing facility (and particularly through (e.g., internally within) the corresponding process blocks). The utility lines associated with the 3rd Gen process blocks may also route along the piping spine so as to feed each of the process blocks. In these embodiments (as well as in other embodiments) the E+I lines and the fluid lines interconnecting the equipment within each process block are not routed through the piping spine and are instead routed independently of the piping spine within the process block (i.e., within the area defined by the corresponding process block).
Within each process block, the modules can also be arranged in any suitable manner. Often times the arrangement of the modules may depend on the transportation constraints for that specific location. Typically, since modules are likely much longer than they are wide (in some embodiments), preferred process blocks have 3 or 4 modules arranged in a side-by-side fashion, and abutted at one or both of their collective ends by the sides of one or more other modules. Individual process blocks can certainly have different numbers of modules, and for example, a first process block may have five (5) modules, another process block may have two (2) modules, and a third process block may have another two (2) modules. In other embodiments, a first process block may have at least five (5) modules, another process block may have at least another five (5) modules, and a third process block may have at least another five (5) modules. Generally, all modules within a process block may abut next to a module within that process block, either horizontally or vertically.
In some embodiments, 3rd Gen Modular Construction facilities are those in which the process blocks collectively include equipment configured to extract oil from oil sands or equipment configured to produce ethylene and/or polypropylene from ethane. Facilities are also contemplated in which at least one of the process blocks produces power used by at least another one of the process blocks, and independently wherein at least one of the process blocks produces steam used by at least another one of the process blocks, and independently wherein at least one of the process blocks includes an at least two story cooling tower. It is also contemplated that at least one of the process blocks includes a personnel control area, which is controllably coupled to the equipment within the at least one process block (e.g., via electrical conductors, fiber optics cables, etc.). In general, but not necessarily in all cases, the process blocks of a 3rd Gen Modular facility may collectively include at least one of a vessel, a compressor, a heat exchanger, a pump, and/or a filter.
Although a 3rd Gen Modular facility might have one or more piperacks to interconnect modules within a process block, it is not necessary to do so. Thus, it is contemplated that a modular building system could comprise A, B, and C modules juxtaposed in a side-to-side fashion, each of the modules having (i) a height greater than 4 meters and a width greater than 4 meters, and (ii) at least one open side; and a first fluid line coupling the A and B modules; a second fluid line coupling the B and C modules; and wherein the first and second fluid lines do not pass through a common interconnecting piperack.
In some embodiments, the modular building system would further comprise a first command line coupling the A and B modules; a second command line coupling the B and C modules; and wherein the first and second command lines do not pass through the common piperack. In more preferred embodiments, the A, B, and C modules may comprise at least, 5, at least 8, at least 12, or at least 15 modules. Preferably, at least two of the A, B and C process blocks may be fluidly coupled by no more than five fluid lines, excluding utility lines. In still other preferred embodiments, a D module could be stacked upon the C module, and a third fluid line could directly couple C and D modules.
Methods of laying out a 2nd Gen Modular facility are different in many respects from those used for laying out a 3rd Gen Modular facility. Whereas the former generally merely involves dividing up equipment for a given process or unit operation among various modules (e.g., an equipment-based approach), the latter preferably takes place in a (process-based) five-step process as described below.
For example, in a typical 2nd Gen Modular facility, equipment is grouped and arranged by type (e.g., pumps for servicing various different processes are arranged within one or more pumping modules and lines connecting the pumps to the various other pieces of equipment related to the various processes and process blocks are routed through one or more external piperacks). While traditional 2nd Gen Modular Construction can be used to prefabricate (prefab) about 50-60% of a complex, multi-process facility; 3rd Gen Modular Construction can be used to prefab up to about 90-95% of the facility. 3rd Gen modular construction can also reduce interconnecting piping and/or cabling, (for example, due to the more direct nature of the interconnections and/or the reduced number of inputs/outputs for each process block) as well as reducing time in the field needed to interconnect modules. The reduction in the length/amount of piping and/or cabling (lines) may result in lower total installed costs (TIC) and/or lower operating hydraulic power demand (with respect to piping) and/or lower operating power demand (with respect to electrical cabling).
Furthermore, the process-based nature of 3rd Gen may allow for much more substantial pre-commissioning, check-out, and/or commissioning (for example at the fabrication or module yard, at a location/site away (e.g., remote) from the ultimate site of the facility—e.g., off-site), thereby reducing effort and time in the field to complete any additional pre-commissioning, check-out, and/or commissioning of process blocks and their systems. By way of example, each process block of a facility might be fully pre-commissioned, checked-out, and/or commissioned off-site, such that the only pre-commissioning, check-out, and/or commissioning left for the field would be interconnections between process blocks and/or the process facility as a whole. So for example, each process block of a 3rd Gen facility (e.g., a 3rd Gen Cracker Facility) might be fully pre-commissioned, checked-out, and/or commissioned off-site (e.g., remotely) with respect to E+I (due to each process block having its own integral/independent/stand-alone E+I system), such that the only E+I pre-commissioning, check-out, and/or commissioning left for the field might be E+I interconnections between process blocks and/or the process facility as a whole (e.g., to ensure that the facility as a whole is up and running properly with respect to E+I once the entire 3rd Gen facility is complete (e.g., with all or substantially all of the process blocks interconnected)). In such embodiments, E+I pre-commissioning, check-out, and/or commissioning could take place at a site remote from the ultimate site of the completed facility and/or without interconnection with any other process blocks and/or modules and/or equipment (e.g., outside of the process block at issue) (for example, with no other process blocks present at that remote site). This also might mean that different process blocks may be constructed as different remote sites, providing efficiency with respect to scheduling and/or resource allocation.
Also, in at least some embodiments, each process block in a 3rd Gen process facility disclosed herein includes its own independent (e.g., self-supporting) power and control (i.e., E+I) systems such that the various process blocks in the 3rd Gen facility do not share E+I systems. As a result, each process block may be independently installed and operated without needing to install other process blocks making up the processing facility. In addition, the independent E+I systems for each process block allow for the avoidance of routing E+I lines through an external piperack extending through the processing facility. Typically speaking, in a 2nd Gen facility, a single E+I system is shared and distributed among all modules such that a relatively large amount of E+I lines (e.g., cabling) must be routed between the control station, room, etc. and the various pieces of equipment within each module. Thus, such a typical 2nd Gen arrangement typically requires running the shared E+I lines through one or more external piperacks extending throughout the facility, which is distinct from 3rd Gen modules.
Step 102 is to allocate a plot space for each 3rd Gen Construction process block. The plot space allocation can rely on a piping layout specialist to distribute the relevant equipment within each 3rd Gen Construction process block. At this phase of the project, estimated sizes and weights of equipment may be used to prepare each “block”. A 3rd Gen Construction process block equipment layout requires attention to location to ensure effective integration with piping, and electrical and control distributions. In order to provide guidance to the piping layout specialist, the following steps can be followed:
Step 102A is to obtain necessary equipment types, sizes and weights. It is important that equipment be sized so that it can fit onto a module. Any equipment that has been sized and that cannot fit onto a module envelope may need to be evaluated by a process lead for possible resizing for module installation.
Step 102B is to establish an overall footprint or geometric area for the process block using a combination of transportable module dimensions. A first and second level of the process block may be identified using a grid layout where the grid identifies each module boundary within the process block.
Step 102C is to allocate space for the electrical and control distribution panels on the first level.
Step 102D is to group the equipment and instruments by primary systems using process block process flow diagrams (PFDs).
Step 102E is to lay out each grouping of equipment by system (rather than by equipment type) onto the process block layout assuring that equipment does not cross module boundaries. The layout may focus on keeping the pumps located on the same module grid and level as the E+I distribution panels. This may assist with keeping the electrical power cables together. If it is not practical, a secondary option can include having the pumps or any other motor close to the module with the E+I distribution panels. In addition, equipment should be spaced to assure effective operability, maintainability, and safe access and egress.
The use of OptiPlant and/or Fluor's Optimeyes™ may be an effective tool at this stage of the project to assist with process block layouts.
Step 103 is to prepare a detailed equipment layout within process blocks to produce an integrated 3rd Gen facility. Each process block identified from step 102 is laid out onto a plot space assuring interconnects required between blocks are minimized. The primary interconnects are identified from the process flow block diagram. Traditional (external) interconnecting piperacks may no longer be needed or used. A simple, typical 3rd Gen “block” layout 300 is illustrated in
Step 104 is to develop a 3rd Gen Module Configuration Table and power and control distribution plan, which combines process blocks for the overall facility to eliminate traditional interconnecting piperacks and reduce the number of interconnects. A 3rd Gen module configuration table is developed using the above data. Templates can be used, and for example, a 3rd Gen power and control distribution plan can advantageously be prepared using the 3rd Gen power and control distribution architectural template.
Step 105 is to develop a 3rd Gen Modular Construction plan, which includes fully detailed process block modules on an integrated multi-discipline basis. The final step for this phase of a project is to prepare an overall modular 3rd Gen Modular Execution plan, which can be used for setting the baseline to proceed to the next phase. It is contemplated that a 3rd Gen Modular Execution will require a different schedule than traditionally executed modular projects.
Many of the differences between the traditional 1st Generation and 2nd Gen Modular Construction and the 3rd Gen Modular Construction are set forth in Table 1 below, with references to the 3rd Gen Modular Execution Design Guide, which was filed in U.S. Provisional application No. 61/287,956, the entire contents of which being previously incorporated by reference above:
A typical 3rd Gen modular processing facility/system may include at least 3 (typically modular, such as being formed of one or more transportable modules) process blocks (although other embodiments may comprise at least 2, at least 5, at least 7, or at least 10 process blocks). The at least 3 process blocks typically may be non-identical process blocks (e.g., each process block configured for a different process and/or having different structure and/or equipment and/or layout). In this way, 3rd Gen modular construction may be quite different from typical 2nd Gen construction approaches, since the 3rd Gen facility typically may not simply be multiple, substantially identical modules, for example, in parallel (as may be typical of 2nd Gen modular construction, for example).
Typically, the at least 3 process blocks of an exemplary 3rd Gen facility may each comprise one or more transportable modules (which typically would be configured to jointly achieve the process of the corresponding process block, if the corresponding process block is made up of multiple modules). A 3rd Gen modular facility may employ a different layout (of modular elements) than conventional 2nd Gen facilities. For example, the at least 3 process blocks of an exemplary 3rd Gen modular facility may not be laid out on an (external) piperack backbone for interconnecting process blocks (or modules). In other words, in at least some embodiments there typically would be no external interconnecting piperack between/linking/interconnecting the at least 3 process blocks of such a 3rd Gen facility (for at least the process blocks associated with the primary process fluid flow through the production facility). Instead, the 3rd Gen process blocks may be adjacent to one another and directly interconnected (for example, without intervening external piperack or other equipment therebetween). This may mean that in some 3rd Gen embodiments, for example, the interconnections between process blocks would be disposed entirely within an envelope of the process blocks. Thus, interconnections between a first and a second of the at least 3 process blocks of an exemplary 3rd Gen modular facility may be located entirely within the envelopes of the first and second process blocks. Oftentimes, such process blocks may be coupled to minimize interconnects and/or to reduce overall footprint of the facility (for example, with interconnecting process blocks abutting one another). While there may not be interconnecting external piperack(s) in typical 3rd Gen modular construction, each of the process blocks may comprise integral pipeways for fluid/electrical/optical (e.g., fiber optics) distribution within the process block (and in some instances for process block interconnects).
Typically, each of the at least 3 process blocks of a 3rd Gen facility may be configured based on a process-based approach or layout. For example, each process block can be configured to achieve a specific stand-alone process, which may be operable to run without accessing equipment from other modules outside the process block (e.g., other than inputs and outputs from the process block as a whole—such that a process block merely takes its inputs, for example, from one or more other process blocks, performs an integral process or unit operation using those inputs, and then provides or emits the outputs from the integral process (for example, to one or more other process blocks). Each process block typically accepts specific feed(s) and processes such feed(s) into one or more products (e.g., outputs). In some instances, one or more of the feed(s) for a specific process block may be provided from other process blocks(s) (e.g., the products from one or more other interconnected process blocks) in the facility, and in some instances, the products from a specific process block may serve as inputs or feeds into one or more other process blocks of a facility. In the hydrocarbon and chemical business, a process block can comprise equipment, such as processing columns, reactors, vessels, drums, tanks, filters, as well as pumps or compressors to move the fluids through the processing equipment and heat exchangers and heaters for heat transfer to or from the fluids. A process block may include a series of piping systems and controls to interconnect the equipment within the block. By eliminating the traditional interconnecting piperack (e.g., an external piperack), the 3rd Gen approach may facilitate an efficient systems-based layout resulting in the reduction of piping quantities. For solid material processing facilities, such as mineral processing, the piping systems described above may be replaced with material handling equipment (e.g., conveyors, belts, etc.). A process block may include between about 20 to 30 pieces of equipment, but there could be more or less equipment in some process block embodiments. Typically, all equipment for a specific process would be located within a single (for example, contiguous) footprint or geographic area and/or envelope. Thus, the inputs/feeds for a specific process block would typically be the inputs needed for the process (as a whole), and the outputs for the process block would typically be the outputs resulting from the process (as a whole). Thus, the actual process would basically be self-contained (physically) within the corresponding process block. This may differ from conventional 2nd Gen approaches, which may use an equipment-based approach (such that 2nd Gen modules may be required to interact with equipment from several modules being needed to perform a specific process). In other words, 3rd Gen process block embodiments may not have an equipment-based approach or layout.
In at least some embodiments of a 3rd Gen modular processing facility, each process block includes multiple pieces and types of equipment for carrying out one or more unit operations within the contiguous area or region defined by the process block. The unit operations and associated equipment may be arranged to carry out, or relate to one or more common, overarching processes within the 3rd Gen modular processing facility.
In at least some of these embodiments, the equipment disposed within the process block may be grouped by type within a given process block. For example, within a given process block, each of the units or pieces of equipment of one type (e.g., each of the pumps within the process block) may be disposed together within a first defined envelope or space within the overall boundary of the process block and each of the units or pieces of equipment of another type (e.g., each of the heat exchangers within the process block) may be disposed together within a second defined envelope or space within the overall boundary of the process block. Within this example, the first defined region may be separate (e.g., not overlapping) with the second defined region with the given process block. In some embodiments, such grouping of a specific type of equipment may only occur for one type of equipment within the process block (such as E+I equipment, which may all be grouped or located together within a process block), or it may occur for multiple (or even all) types of equipment within the process block.
In a typical exemplary 3rd Gen modular processing facility, each of the at least 3 process blocks may comprise its own integral E+I system and distribution (e.g., electrical control and instrument system). As a result, each process block in a 3rd Gen modular processing facility disclosed herein may include its own integral (e.g., self-supporting) power supply and/or distribution and control systems for operating that process block (and the equipment disposed therein). This may eliminate home run interconnecting cabling through traditional interconnecting racks (of the sort which may be used in conventional 2nd Gen modular approaches). In addition, this may be beneficial for allowing each process block to operate as a stand-alone process (as described above, for example), and may provide commissioning benefits (for example, as discussed above). So, for example, each of the at least 3 process blocks may be configured to allow for independent pre-commissioning, check-out, and/or commissioning of its corresponding process system and/or E+I (for example, without connection to any other of the at least 3 process blocks). This may allow for separate/independent pre-commissioning, check-out, and/or commissioning of its corresponding process system and/or E+I, for example, at a location separate and apart (e.g., geographically distant) from the ultimate site of the facility (such as a fabrication facility or module yard). The ability to perform separate/independent pre-commissioning, check-out, and/or commissioning for each 3rd Gen process block may be due to integral E+I within each process block, the process block design approach, and/or lack of external interconnecting piperack, which, for example, may allow for fewer connections which can be more easily connected for simulation and/or testing. Moreover, because of the independent, integral E+I system and distribution within each process block, as each process block can be installed at the production facility, it may be independently operated for its intended function or process while other process blocks are either not yet operational or are not yet even installed (assuming that the operating process block's feed is available and other necessary utility services to the operating process block have been connected and are operating). Such independent operation of process blocks was not available in a 2nd Gen production facility since operation of any one process required the installation of the shared E+I system and distribution to the entire production facility. As a result, the total time to production from a 3rd Gen production facility may be greatly shortened from that typically experienced in a 2nd Gen production facility.
The arrangement/layout of process blocks in exemplary 3rd Gen modular facilities may also be distinct. For example, each of the at least 3 process blocks may be located/arranged in proximity to one or more other of the at least 3 process blocks (e.g., without intervening process blocks, modules, and/or piperacks therebetween). Typically, each of the at least 3 process blocks may be interconnected to one or more other of the at least 3 process blocks (and, for example, the interconnects might include fluid (e.g., piping), solids (e.g., conveyors), etc.). Typically, each of the at least 3 process blocks would be positioned/arranged in proximity to the other of the at least 3 process blocks to which it directly interconnects, for example, without intervening external piperacks and/or process blocks therebetween. While not required in all 3rd Gen embodiments, often the at least 3 process blocks would abut at least one other of the at least 3 process blocks (for example, interconnected process blocks might typically abut one another—for example, forming a contiguous geographic footprint and/or envelope). For such abutting process blocks, interconnections between such process blocks might typically be disposed entirely within the envelope (internal lines) of abutting process blocks. And in some 3rd Gen embodiments, all process blocks may abut the other process blocks to which they interconnect (or at least might directly abut the other process blocks with which it interacts with respect to the primary process flow), such that the facility as a whole may have a contiguous geographic footprint and/or envelope (in which case, all interconnections between process blocks might be within the contiguous envelope of the facility process blocks as a whole (e.g., jointly), such that no external piperacks would be necessary).
The process blocks may each have feed input piping (or solid material transfer), product output piping (or solid material transfer), and utility support inputs and outputs. Utility support inputs and outputs may include one or more inputs for fluid lines (e.g., pipes, conduits, hoses, etc.) that carry fluids (e.g., liquids and/or gases) to support the systems operation within a process block. For example, such liquids and gases carried by the utility pipes include, steam, water, N2, O2, air, etc. Process blocks may be arranged to efficiently interconnect to each other based on the process flow through the facility. Utilities may also be interconnected between process blocks in a similar design for efficient flow.
Each process block may be formed of one or more transportable modules (thereby allowing construction of such modules off-site at locations distant from the final site for the process facility). Each of the transportable modules for the process blocks may be sized, as discussed above, with respect to transportable modules. And in some embodiments, one or more of the modules may be sized to be truckable, as described above. So, a process block can be formed of (e.g., comprise) one to several modules, for example, depending on the maximum module size and/or weight the local site infrastructure will allow for transport. The use of smaller truckable modules might result in several modules per process block, while the use of VLMs (very large modules) may allow for one module per process block. The modules making up each process block may be configured with equipment so that, when interconnected, the modules may jointly perform the process of the corresponding process block (for example, with the equipment in a plurality of related modules for a corresponding process block working together (e.g., interlinked) to accomplish the overall process of the process block). In laying out modules (in forming a corresponding process block), each module may be arranged in proximity (abutting) with the one or more modules with which it interconnects (e.g., without any intervening external piperack and/or module). So typically, the modules for a process block may not interconnect via an external piperack (a piperack located external to the modules), but may rather be directly connected internally via an envelope of each module. The modules associated with a specific (corresponding) process block may abut to form a contiguous footprint and/or envelope for the process block as a whole. As otherwise described herein, such abutment of modules and/or process blocks may be side-by-side, end-to-end, and/or stacked, for example.
Such 3rd Gen modular process facilities may be constructed uniquely, due to the 3rd Gen nature of the process blocks and/or modules and/or the process-based approach. For example, a typical exemplary 3rd Gen modular method of constructing a processing facility (for example, of the sort described above) might comprise arranging a plurality of process blocks (e.g., at least 3 process blocks) with respect to one another, wherein the at least 3 process blocks are non-identical process blocks (e.g., each configured for a different process) (e.g., not simply multiple, substantially identical modules, for example in parallel), wherein the at least 3 process blocks each comprise one or more transportable modules (which are configured to jointly achieve the process of the corresponding process block); and wherein the at least 3 process blocks are not laid out on an external piperack backbone for interconnecting process blocks (or modules) (e.g., no external interconnecting piperack between/linking/interconnecting the 3 process blocks) (e.g., process blocks are directly interconnected (without intervening piperack therebetween, for example, such that the interconnections between process blocks are disposed entirely within an envelope of the process blocks—for example, with interconnections between a first and a second of the at least 3 process blocks being located entirely within the envelopes of the first and second process blocks)). Such a method might also and/or further comprise constructing one or more (e.g., each or all) of the at least 3 process blocks at one or more location different (remote/away) from the ultimate site of the processing facility (e.g., a fab or mod yard); and pre-commissioning, check-out, and/or commissioning of a corresponding process system for the one or more process blocks constructed away from the ultimate facility site (e.g., at the fabrication site or module yard) (e.g., without connection to any other of the at least 3 process blocks—instead using an input stream source, e.g., emulating the output stream from the process module which is to be interconnected) (e.g., at a location separate and apart from the ultimate site of the facility, such as a module yard) (e.g., due to integral E+I, process block design approach, and/or lack of external interconnecting piperack). In some embodiments, such methods may further comprise directly interconnecting (e.g., without an external interconnecting piperack) each process block (which might be pre-commissioned, checked out, or commissioned previously) to one or more adjacent process blocks (e.g., without intervening external piperacks and/or other process blocks therebetween). In some such methods, the arrangement of process blocks may also include close coupling one or more (e.g., all) of the at least 3 process blocks (e.g., to reduce overall footprint of the facility and/or reduce/minimize interconnects). Some method embodiments may further comprise designing/configuring each process block to accomplish a corresponding process, which in some embodiments may include laying out equipment in the modules making up each process block accordingly. Also, some method embodiments may further comprise the step of providing integral E+I distribution for each of the at least 3 process blocks (e.g., to eliminate home run interconnecting cabling). The modular nature of 3rd Gen construction may also allow for more efficient construction and/or implementation, for example, using integrated execution to support the modular implementation with reduced scheduling versus traditional/conventional stick build or 2nd Gen (e.g., equipment only modules).
In some embodiments, two or more of the process blocks to be interconnected may not be able to be placed adjacent to one another such that one or more fluid lines interconnecting the inputs and outputs of the two or more process blocks may be routed through an intervening process block or other equipment. In at least some embodiments, such a routing of the one or more fluid lines does not occur. Design efforts (regarding placement of process blocks and/or interconnections between process blocks) may seek to minimize this type of indirect routing or interconnection as much as possible (e.g., most process blocks should preferably be directly interconnected and located adjacent to the other process blocks with which it interacts, especially with respect to the primary process flow). So for at least some embodiments, the primary flow (i.e., the primary process flow through the 3rd Gen production facility) may flow between adjacent and directly interconnected process blocks. Stated another way, the process blocks in a 3rd Gen production facility that are associated with the main or primary process flow are typically positioned adjacent one another such that each of these process blocks is directly interconnected with no intervening piperacks or other equipment or modules therebetween. So while there may be process blocks in a 3rd Gen facility that are not adjacent and/or interconnected with one or more other process blocks with which it interacts, in a 3rd Gen facility typically at least 3, at least 5, at least 8, or at least 10 process blocks (for example, relating to the main or primary process flow) would be adjacent (or abutting) and/or directly interconnected with the other such of the at least 3, at least 5, at least 9 or at least 10 process blocks with which it interacts.
In addition, in some embodiments, one or more of the fluid lines interconnecting the inputs and outputs of the 3rd Gen process blocks are routed through a central piping spine that runs through at least a portion of the (and in some instances, through the entire) processing facility (and particularly through at least some of the process blocks, with the spine located internally within at least some of the process blocks). In addition, in at least some of these embodiments, the utility lines (e.g., carrying steam, water, air, N2, O2, etc.) associated with the process blocks may also route along the piping spine so as to access each of the process blocks. In these embodiments (as well as in other embodiments) the E+I lines and the fluid lines interconnecting the equipment within each process block are not routed through the piping spine and are instead routed within each individual process block (i.e., within the geographic area defined by the corresponding process block) as described above. Such an optional spine might serve to line up inputs and outputs for multiple process blocks (for example regarding the primary process flow and/or utilities), thereby optimizing layout of a facility. So, typically such a spine would not be used for equipment connections within process blocks, but would instead typically be focused on inputs and outputs between interconnected process blocks.
While 3rd Gen modular construction may be used for any number of different types of process facilities, one specific example would be a (steam) ethylene cracker application (e.g., for processing an ethane feed into ethylene (and possibly additional output streams)) as discussed below with respect to
The modular construction techniques described herein can be used for a variety of processes including cracker processes.
Generally, the caustic treatment towers 410 may be located between compressor stages (compressors 412 and 414) as shown in
Having described the production of ethylene, pygas, and propylene in
In the exemplary embodiment of
In
In
e.g., And as discussed above, the distributed (e.g., stand-alone/independent) E+I for each process block of a 3rd Gen facility may allow for independent pre-commissioning, check-out, and/or commissioning of that process block (e.g., with respect to E+I). For example, each process block may be pre-commissioned, checked-out, and/or commissioned at a site remote from the ultimate facility site and/or without the need for interconnection to any other process block and/or module and/or equipment. By way of example, one or more of the exemplary pre-commissioning, check-out and/or commissioning steps set forth in Tables 2-5 below may be performed independently for each process block of a 3rd Gen facility (e.g., at a remote site and/or without interconnection with other process blocks, modules, and/or other equipment):
It should be understood that one or more of these Tables 2-5 steps (e.g., relating to E+I systems pre-commissioning, check-out and/or commissioning) may be performed remotely (e.g., at a site remote from the ultimate facility site) and/or independently (e.g., without interconnection to any other process block, for example) for each process block of a 3rd Gen facility (for example for a 3rd Gen cracker facility of the type described above).
Still further,
Also in
Having described above various system/facility and method embodiments, various additional embodiments may include, but are not limited to the following:
In a first embodiment, a modular processing facility/system, comprising: a plurality (for example, at least 3) (modular) process blocks; wherein the plurality of (e.g., at least 3) process blocks are non-identical process blocks (e.g., each configured for a different process) (e.g., not simply multiple, substantially identical modules, for example in parallel); wherein the plurality of (e.g., at least 3) process blocks each comprise one or more transportable modules (which are configured to jointly achieve the process of the corresponding process block); and wherein the plurality of (e.g., at least 3) process blocks are not laid out on a (common) (external) piperack backbone for interconnecting process blocks (or modules) (e.g., no external interconnecting piperack between/linking/interconnecting the process blocks) (e.g., the process blocks are directly interconnected (without intervening piperack therebetween, for example, such that the interconnections between process blocks are disposed entirely within an envelope of the process blocks—for example, with interconnections between a first and a second of the at least 3 process blocks being located entirely within envelopes of the first and second process blocks). In a second embodiment, the system/facility of the first embodiment, wherein each of the plurality of (e.g., at least 3) process blocks is configured based on a process-based approach (e.g., to achieve a specific stand-alone process) (e.g., not equipment-based). In a third embodiment, the system/facility of embodiments 1-2, wherein the process blocks are close coupled to minimize interconnects and/or to reduce overall footprint of the facility. In a fourth embodiment, the system/facility of embodiments 1-3, wherein each of the plurality of (e.g., at least 3) process blocks comprises its own integral E+I Distribution (for example, thereby eliminating home run interconnecting cabling through traditional interconnecting racks). In a fifth embodiment, the system/facility of embodiments 1-4, wherein each of the plurality of (e.g., at least 3) process blocks is configured to allow for independent pre-commissioning, check-out, and/or commissioning (e.g., with respect to E+I) of a corresponding process system (for example, without connection to any other of the at least 3 process blocks) (for example, at a location separate and apart from the ultimate site of the facility, such as a mod yard) (for example, due to integral E+I, process block design approach, and/or lack of external interconnecting piperack). In a sixth embodiment, the system/facility of embodiments 1-5, wherein each of the plurality of (e.g., at least 3) process blocks comprises integral pipeways for utility distribution (and process block interconnects). In a seventh embodiment, the system/facility of embodiments 1-6, wherein each of the plurality of (e.g., at least 3) process blocks is located/arranged in proximity to (e.g., without intervening process blocks, modules, and/or piperacks therebetween) one or more other of the at least 3 process blocks (for example, with all process blocks forming a contiguous geographic footprint for the facility as a whole based on abutting process blocks). In an eighth embodiment, the system/facility of embodiments 1-7, wherein each of the plurality of (e.g., at least 3) process blocks is interconnected to one or more other of the at least 3 process blocks, and wherein the interconnects include fluid (e.g., piping). In a ninth embodiment, the system/facility of embodiments 1-8, wherein each of the plurality of (e.g., at least 3) process blocks is positioned/arranged in proximity to the other of the plurality of (e.g., at least 3) process blocks to which it directly interconnects, without intervening external piperacks and/or process blocks therebetween. In a tenth embodiment, the system/facility of embodiments 1-9, wherein each of the plurality of (e.g., at least 3) process blocks abuts at least one other of the process blocks. In an eleventh embodiment, the system/facility of embodiments 1-10, wherein the interconnections between process blocks are disposed entirely within the envelope of abutting process blocks. In a twelfth embodiment, the system/facility of embodiments 1-11, wherein each (or alternatively, some) of the transportable modules for the process blocks is sized as a truckable module. In a thirteenth embodiment, the system/facility of embodiments 1-12, wherein each of the plurality of process blocks comprises a plurality of transportable or truckable modules, which jointly may be configured to achieve the process for the corresponding process block. In a fourteenth embodiment, the system/facility of embodiments 1-13, wherein each process block is configured to allow for independent pre-commissioning, check-out, and/or commissioning (e.g., without being connected to another one or more of the process blocks) (e.g., at a site separate and apart from the ultimate facility site). In an additional embodiment, the system/facility of embodiments 1-14 might have all adjacent process blocks abut one another. In yet another embodiment, the system/facility of any of the embodiments above might be configured for a cracker facility, for example including any one or more of the following: the process blocks comprising seven or more (or alternatively two or more, three or more, five or more, ten or more, or all) of the following—an ethane cracking furnace process block, a steam generation process block, a water quench process block, a water stripper/dilution stream process block, a cracked gas compression process block, a caustic treatment process block, a drying process block, a deethanizer process block, an acetylene conversion process block, a demethanizer process block, a refrigeration process block, and/or a C2 splitter process block; in which such process blocks are laid-out/arranged in one or more of the following: the ethane cracker furnace process block being (side-to-side) adjacent to (or abutting) the water quench process block; the water quench process block being (side-to-side) adjacent to (or abutting) the cracked gas compression process block; the caustic treatment process block being (side-to-side) adjacent to (or abutting) the drying process block; the drying process block being (side-to-side) adjacent to (or abutting) the deethanizer process block; the deethanizer process block being (side-to-side) adjacent to (or abutting) the acetylene conversion process block; the acetylene conversion process block being (side-to-side) adjacent to (or abutting) the demethanizer process block; the demethanizer process block being (side-to-side) adjacent to (or abutting) the refrigeration process block; the refrigeration process block being (side-to-side) adjacent to (or abutting) the C2 splitter process block; in which the process blocks are interconnected (in flow, for example) in one or more of the following ways: the output stream from the cracked gas compression process block flowing into the caustic treatment process block; two-way flow between the cracked gas compression process block and the caustic treatment process block (so compression occurs before and after caustic treatment, prior to flow into the drying process block); the cracked gas compression process block being adjacent to (or abutting) the caustic treatment process block (wherein the adjacency/abutment could be side-to-side or diagonal in different embodiments); the ethane feed (into the facility) being heated by the ethane cracking furnace process block; the output stream from the ethane cracking furnace process block being sent to the water quench process block for cooling; the water quench process block possibly interacting with the water stripper process block to form a dilution stream which interacts with the ethane cracking furnace process block; the cooled output stream from the water quench process block sent to the cracked gas compression process block; the output steam from the cracked gas compression process block being sent to the caustic treatment process block; the caustic treatment process block interacting with the cracked gas compressor process block in a two-way manner (such that the stream is compressed before and after caustic treatment); the (final) outlet stream from the caustic treatment process block being sent to the drying process block to be dried (and oftentimes cooled); the output stream from the drying process block being sent to the deethanizer process block; the (overhead) output stream from the deethanizer process block being sent to the acetylene converter process block; the output stream from the acetylene converter process block being sent to the demethanizer process block, the refrigeration process block providing refrigerant to the cold box for the demethanizer process block; the output stream from the demethanizer process block sent to the C2 splitter process block; the ethylene from the C2 splitter process block being sent to the refrigeration process block; the process/facility output stream from the C2 splitter block being ethylene (along with ethane that is recycled back to the ethane feed into the ethane cracking furnace); the process/facility output stream also including light pygas and/propylene; all process blocks adjacent or abutting side-to-side (with respect to the flow between process blocks, for example such that the flow between process blocks passes from a side of one process block into a side of a second interconnected process block); and/or no more than one (or two or three alternatively) process blocks diagonally adjacent or abutting with respect to the flow between process blocks (for example, no more than one, two, or three process blocks interconnected via flow in a diagonally adjacent/abutting manner). Any or all variants/steps described with respect to
In a fifteenth embodiment, a modular method of constructing a processing facility (for example, for forming any one of the modular processing facilities/systems described above), comprising: arranging a plurality of process blocks (e.g., at least 3 process blocks) with respect to one another; wherein the plurality of (e.g., at least 3) process blocks are non-identical process blocks (e.g., each configured for a different process) (e.g., not simply multiple, substantially identical modules, for example in parallel); wherein the plurality of (at least 3) process blocks each comprise one or more transportable modules (e.g., typically a plurality of transportable or truckable modules for each process block) (e.g., which are configured to jointly achieve the process of the corresponding process block); and wherein the plurality of (e.g., at least 3) process blocks are not laid out on an (external) piperack backbone for interconnecting process blocks (or modules) (e.g., no external interconnecting piperack between/linking/interconnecting the 3 process blocks) (e.g., process blocks are directly interconnected (without intervening piperack there between, for example such that the interconnections between process blocks are disposed entirely within an envelope of the process blocks—for example, with the interconnections between a first and a second of the at least 3 process blocks being located entirely within the envelopes of the first and second process blocks)). In a sixteenth embodiment, the method of embodiment 15, further comprising: constructing one or more (for example, each or all) of the plurality of (e.g., at least 3) process blocks at one or more location different (remote/away) from the ultimate site of the processing facility (for example, a fab or mod yard); and pre-commissioning, check-out, and/or commissioning (for example of E+I) of a corresponding process system for the one or more process block(s) constructed away from the ultimate facility site (e.g., at the site of construction for such one or more process blocks) (for example, at the fab or mod yard) (for example, without connection to any other of the at least 3 process blocks) (for example at a location separate and apart from the ultimate site of the facility, such as a mod yard) (for example, due to integral E+I, process block design approach, and/or lack of the external interconnecting piperack). In a seventeenth embodiment, the method of embodiments 15-16, further comprising directly interconnecting (e.g., without the external interconnecting piperack) each process block to one or more adjacent process blocks (e.g., without intervening external piperacks and/or other process blocks there between). In an eighteenth embodiment, the method of embodiments 15-17, further comprising, close coupling one or more (for example, all) of the at least 3 process blocks (for example, to reduce overall footprint of the facility and/or reduce/minimize interconnects). In a nineteenth embodiment, the method of embodiments 15-18, further comprising designing/configuring each process block to accomplish a corresponding process (and laying out equipment in the modules making up each process block accordingly). In a twentieth embodiment, the method of embodiments 1-19, the method further comprising providing (e.g., at the one or more location different (remote/away) from the ultimate site of the processing facility (for example, a fab or mod yard)) integral E+I distribution for each of the at least 3 process blocks (e.g., to eliminate home run interconnecting cabling). In a twenty-first embodiment, wherein each of the process blocks comprises its own integral E+I Distribution/System. In a twenty-second embodiment, the method of embodiments 15-21, wherein arranging a plurality of process blocks (e.g., at least 3 process blocks) with respect to one another comprises positioning each process block so that it abuts any of the other process blocks to which it is connected (e.g., to form a contiguous geographic footprint for the facility based on abutting process blocks). In a twenty-third embodiment, the method of embodiments 15-22 wherein each of the plurality of (e.g., at least 3) process blocks is configured to allow for independent pre-commissioning, check-out, or commissioning of a corresponding process system (for example, with respect to E+I and/or with each such process block being configured with multiple types of equipment in order to allow for the corresponding process system to run independently of the other process blocks (e.g., without interacting with other, outside equipment in the midst of performing the process) to perform its process, for example using only feeds into the process (e.g., process block) for the process block to perform its corresponding process system (e.g., with no interaction with equipment or process blocks outside the process block to perform any portion of the process (e.g., within the internal system flow of the process—so that the only external interaction is for feeds to the entire process of the process block, and from there the process of the process block is self-contained))). In a twenty-fourth embodiment, the method of embodiments 15-23 further comprising beginning partial operation of the facility before all of the process blocks for the full facility are provided at the ultimate facility site and/or are interconnected (for example, operating a first process block independently while awaiting installation of a second process block; or operating a first and second (interconnected) process block while awaiting installation of a third process block; or operating a first, second, and third (interconnected) process block while awaiting installation of a fourth process block; etc.). In a twenty-fifth embodiment, the method of embodiments 1-24, for a cracker facility/system (for example comprising an ethane cracking furnace process block, a water quench process block, a water stripper process block, a cracked gas compression process block, a caustic treatment process block, a drying process block, a deethanizer process block, an acetylene conversion process block, a demethanizer process block, a refrigeration process block, and/or a C2 splitter process block), wherein arranging (and or interconnecting) the process blocks with respect to one another comprises one or more of the following: the ethane cracker furnace process block being arranged, located, or placed (side-to-side) adjacent to (or abutting) the water quench process block; the water quench process block being arranged, located, or placed (side-to-side) adjacent to (or abutting) the cracked gas compression process block; the caustic treatment process block being arranged, located, or placed (side-to-side) adjacent to (or abutting) the drying process block; the drying process block being arranged, located, or placed (side-to-side) adjacent to (or abutting) the deethanizer process block; the deethanizer process block being arranged, located, or placed (side-to-side) adjacent to (or abutting) the acetylene conversion process block; the acetylene conversion process block being arranged, located, or placed (side-to-side) adjacent to (or abutting) the demethanizer process block; the demethanizer process block being arranged, located, or placed (side-to-side) adjacent to (or abutting) the refrigeration process block; the refrigeration process block being arranged, located, or placed (side-to-side) adjacent to (or abutting) the C2 splitter process block; the output stream from the cracked gas compression process block being interconnected to flow into the caustic treatment process block; the cracked gas compression process block and the caustic treatment process block being interconnected for two-way flow between the cracked gas compression process block and the caustic treatment process block (so compression occurs before and after caustic treatment, prior to flow into the drying process block); the cracked gas compression process block being arranged, located, or placed adjacent to (or abutting) the caustic treatment process block (wherein the adjacency/abutment could be side-to-side or diagonal in different embodiments); the ethane feed (into the facility) being heated by the ethane cracking furnace process block; the output stream from the ethane cracking furnace process block being sent to the water quench process block for cooling; the water quench process block possibly interacting with the water stripper process block to form a dilution stream which interacts with the ethane cracking furnace process block; the cooled output stream from the water quench process block sent to the cracked gas compression process block; the output steam from the cracked gas compression process being sent to the caustic treatment process block; the caustic treatment process block interacting with the cracked gas compressor process block in a two-way manner (such that the stream is compressed before and after caustic treatment); the (final) outlet stream from the caustic treatment process block being sent to the drying process block to be dried (and oftentimes cooled); the output stream from the drying process block being sent to the deethanizer process block; the (overhead) output stream from the deethanizer process block being sent to the acetylene converter process block; the output stream from the acetylene converter process block being sent to the demethanizer process block, the refrigeration process block providing refrigerant to the cold box for the demethanizer process block; the output stream from the demethanizer process block sent to the C2 splitter process block; the ethylene from the C2 splitter process block being sent to the refrigeration process block; the process/facility output stream from the C2 splitter being ethylene (along with ethane that is recycled back to the ethane feed into the ethane cracking furnace); the process/facility output stream also including light pygas and/propylene; all process blocks adjacent or abutting side-to-side (with respect to the flow between process blocks, for example such that the flow between process blocks passes from a side of one process block into a side of a second interconnected process block); and/or no more than one (or two or three alternatively) process block diagonally adjacent or abutting with respect to the flow between process blocks (for example, no more than one, two, or three process blocks interconnected via flow in a diagonally adjacent/abutting manner). In a twenty-sixth embodiment, the method of embodiments 1-25, for a cracker facility/system (for example comprising an ethane cracking furnace process block, a water quench process block, a water stripper process block, a cracked gas compression process block, a caustic treatment process block, a drying process block, a deethanizer process block, an acetylene conversion process block, a demethanizer process block, a refrigeration process block, and a C2 splitter process block), wherein pre-commissioning, check-out and/or commissioning of the ethane cracking furnace process block comprises providing an ethane feed stream (input/feed stream source) to the ethane cracker furnace process block (when the process block is not interconnected with any other process blocks and/or is not part of an entire/functional facility and/or is not located at the ultimate site of the facility, but is located at the one or more location different (remote/away) from the ultimate site of the processing facility) and/or evaluating the performance of the ethane cracker furnace process block (for example, by evaluating the output stream (e.g., to ensure that the process block is performing within specification and/or regulations), for example, by measuring one or more characteristics of the output stream from the cracker furnace process block and comparing to a lookup table); wherein pre-commissioning, check-out and/or commissioning of the water quench process block comprises providing an input/feed stream source, e.g., emulating the ethane feed coming from the ethane cracker furnace, to the water quench process block (when the process block is not interconnected with any other process blocks and/or is not part of an entire/functional facility and/or is not located at the ultimate site of the facility, but is located at the one or more location different (remote/away) from the ultimate site of the processing facility) and/or evaluating the performance of the water quench process block (for example, by evaluating the output stream (e.g., to ensure that the process block is performing within specification and/or regulations), for example, by measuring one or more characteristics of the output stream of the water quench process block and comparing to a lookup table); wherein pre-commissioning, check-out and/or commissioning of the water stripper process block comprises providing an input/feed stream source, e.g., emulating the stream from the water quench interacting with the water stripper, to the water stripper process block (when the process block is not interconnected with any other process blocks and/or is not part of an entire/functional facility and/or is not located at the ultimate site of the facility, but is located at the one or more location different (remote/away) from the ultimate site of the processing facility) and/or evaluating the performance of the water stripper process block (for example, by evaluating the output stream (e.g., to ensure that the process block is performing within specification and/or regulations), for example, by measuring one or more characteristics of the output stream of the water stripper process block and comparing to a lookup table) wherein pre-commissioning, check-out and/or commissioning of the cracker gas compression process block comprises providing an input/feed stream source, e.g., emulating the input stream from the water quench, to the cracker gas compression process block (when the process block is not interconnected with any other process blocks and/or is not part of an entire/functional facility and/or is not located at the ultimate site of the facility, but is located at the one or more location different (remote/away) from the ultimate site of the processing facility) and/or evaluating the performance of the cracked gas compression process block (for example, by evaluating the output stream (e.g., to ensure that the process block is performing within specification and/or regulations), for example, by measuring one or more characteristics of the output stream of the cracked gas compression process block and comparing to a lookup table); wherein pre-commissioning, check-out and/or commissioning of the caustic treatment process block comprises providing an input/feed stream source, e.g., emulating the stream from the cracked gas compression, to the caustic treatment process block (when the process block is not interconnected with any other process blocks and/or is not part of an entire/functional facility and/or is not located at the ultimate site of the facility, but is located at the one or more location different (remote/away) from the ultimate site of the processing facility) and/or evaluating the performance of the caustic treatment process block (for example, by evaluating the output stream (e.g., to ensure that the process block is performing within specification and/or regulations), for example, by measuring one or more characteristics of the output stream of the caustic treatment process block and comparing to a lookup table); wherein pre-commissioning, check-out and/or commissioning of the drying process block comprises providing an input/feed stream source, e.g., emulating stream from caustic treatment, to the drying process block (when the process block is not interconnected with any other process blocks and/or is not part of an entire/functional facility and/or is not located at the ultimate site of the facility, but is located at the one or more location different (remote/away) from the ultimate site of the processing facility) and/or evaluating the performance of the drying process block (for example, by evaluating the output stream (e.g., to ensure that the process block is performing within specification and/or regulations), for example, by measuring one or more characteristics of the output stream of the drying process block and comparing to a lookup table); wherein pre-commissioning, check-out and/or commissioning of the deethanizer process block comprises providing an input/feed stream source, e.g., emulating the stream from drying, to the deethanizer process block (when the process block is not interconnected with any other process blocks and/or is not part of an entire/functional facility and/or is not located at the ultimate site of the facility, but is located at the one or more location different (remote/away) from the ultimate site of the processing facility) and/or evaluating the performance of the deethanizer process block (for example, by evaluating the output stream (e.g., to ensure that the process block is performing within specification and/or regulations), for example, by measuring one or more characteristics of the output stream of the deethanizer process block and comparing to a lookup table); wherein pre-commissioning, check-out and/or commissioning of the acetylene conversion process block comprises providing an input/feed stream source, e.g., emulating the stream from the deethanizer, to the acetylene conversion process block (when the process block is not interconnected with any other process blocks and/or is not part of an entire/functional facility and/or is not located at the ultimate site of the facility, but is located at the one or more location different (remote/away) from the ultimate site of the processing facility) and/or evaluating the performance of the acetylene conversion process block (for example, by evaluating the output stream (e.g., to ensure that the process block is performing within specification and/or regulations), for example, by measuring one or more characteristics of the output stream of the acetylene conversion process block and comparing to a lookup table); wherein pre-commissioning, check-out and/or commissioning of the demethanizer process block comprises providing an input/feed stream source, e.g., emulating the stream from the acetylene conversion, to the demethanizer process block (when the process block is not interconnected with any other process blocks and/or is not part of an entire/functional facility and/or is not located at the ultimate site of the facility, but is located at the one or more location different (remote/away) from the ultimate site of the processing facility) and/or evaluating the performance of the demethanizer process block (for example, by evaluating the output stream (e.g., to ensure that the process block is performing within specification and/or regulations), for example, by measuring one or more characteristics of the output stream of the demethanizer process block and comparing to a lookup table); wherein pre-commissioning, check-out and/or commissioning of the refrigeration process block comprises providing an input/feed stream source. e.g., emulating the stream from the C2 splitter, to the refrigeration process block (when the process block is not interconnected with any other process blocks and/or is not part of an entire/functional facility and/or is not located at the ultimate site of the facility, but is located at the one or more location different (remote/away) from the ultimate site of the processing facility) and/or evaluating the performance of the refrigeration process block (for example, by evaluating the output stream (e.g., to ensure that the process block is performing within specification and/or regulations), for example, by measuring one or more characteristics of the output stream of the refrigeration process block and comparing to a lookup table); and/or wherein pre-commissioning, check-out and/or commissioning of the C2 splitter process block comprises providing an input/feed stream source, e.g., emulating the stream from the demethanizer, to the C2 splitter process block (when the process block is not interconnected with any other process blocks and/or is not part of an entire/functional facility and/or is not located at the ultimate site of the facility, but is located at the one or more location different (remote/away) from the ultimate site of the processing facility) and/or evaluating the performance of the C2 splitter process block (for example, by evaluating the output stream (e.g., to ensure that the process block is performing within specification and/or regulations), for example, by measuring one or more characteristics of the output stream of the C2 splitter process block and comparing to a lookup table). In a twenty-seventh embodiment, the method of embodiment 26 wherein the input/feed stream is provided to the process block being pre-commissioned, checked-out, and/or commissioned by an independent, stand-alone source (such as a tank and/or additional equipment to place the stream in proper condition to mimic the input when the process block is connected to the other process blocks in a functional facility that is running in operational mode) and/or is not provided by another process block and/or is located at the one or more location different (remote/away) from the ultimate site of the processing facility. In another embodiment, the method of any of the embodiments above, wherein the pre-commissioning, check-out and/or commissioning of each process block (e.g., for the cracker facility) with respect to E+I may take place remotely (e.g., at a location separate and apart (e.g., distant) from the ultimate site of the facility and/or from one or more (or all) of the other process blocks for the facility) and/or without connection to any other process blocks and/or modules and/or equipment for the facility and/or using the independent E+I corresponding to each process block and/or may involve one or more of the exemplary steps shown in Table 2 above.
It should be apparent to those skilled in the art that many more modifications besides those already described are possible without departing from the inventive concepts herein. The inventive subject matter, therefore, is not to be restricted except in the spirit of the appended claims. Moreover, in interpreting both the specification and the claims, all terms should be interpreted in the broadest possible manner consistent with the context. In particular, the terms “comprises” and “comprising” should be interpreted as referring to elements, components, or steps in a non-exclusive manner, indicating that the referenced elements, components, or steps may be present, utilized, or combined with other elements, components, or steps that are not expressly referenced. Where the specification claims refer to at least one of something selected from the group consisting of A, B, C . . . and N, the text should be interpreted as requiring only one element from the group, not A plus N, or B plus N, etc.
Accordingly, the scope of protection is not limited by the description set out above, but is defined by the claims which follow that scope including all equivalents of the subject matter of the claims. In the claims, any designation of a claim as depending from a range of claims (for example #-##) would indicate that the claim is a multiple dependent claim based on any claim in the range (e.g., dependent on claim # or claim ## or any claim therebetween). Each and every claim is incorporated as further disclosure into the specification, and the claims are embodiment(s) of the present invention(s). Furthermore, any advantages and features described above may relate to specific embodiments, but shall not limit the application of such issued claims to processes and structures accomplishing any or all of the above advantages or having any or all of the above features.
Additionally, the section headings used herein are provided for consistency with the suggestions under 37 C.F.R. 1.77 or to otherwise provide organizational cues. These headings shall not limit or characterize the invention(s) set out in any claims that may issue from this disclosure. Specifically and by way of example, although the headings might refer to a “Field,” the claims should not be limited by the language chosen under this heading to describe the so-called field. Further, a description of a technology in the “Background” is not to be construed as an admission that certain technology is prior art to any invention(s) in this disclosure. Neither is the “Summary” to be considered as a limiting characterization of the invention(s) set forth in issued claims. Furthermore, any reference in this disclosure to “invention” in the singular should not be used to argue that there is only a single point of novelty in this disclosure. Multiple inventions may be set forth according to the limitations of the multiple claims issuing from this disclosure, and such claims accordingly define the invention(s), and their equivalents, that are protected thereby. In all instances, the scope of the claims shall be considered on their own merits in light of this disclosure, but should not be constrained by the headings set forth herein.
Use of broader terms such as “comprises”, “includes”, and “having” should be understood to provide support for narrower terms such as “consisting of”, “consisting essentially of”, and “comprised substantially of”. Use of the terms “optionally,” “may,” “might,” “possibly,” and the like with respect to any element of an embodiment means that the element is not required, or alternatively, the element is required, both alternatives being within the scope of the embodiment(s). Also, references to examples are merely provided for illustrative purposes, and are not intended to be exclusive.
Also, techniques, systems, subsystems, and methods described and illustrated in the various embodiments as discrete or separate may be combined or integrated with other systems, modules, techniques, or methods without departing from the scope of the present disclosure. Other items shown or discussed as directly coupled or communicating with each other may be indirectly coupled or communicating through some interface, device, or intermediate component, whether electrically, mechanically, or otherwise. Other examples of changes, substitutions, and alterations are ascertainable by one skilled in the art and could be made without departing from the spirit and scope disclosed herein.
This application claims priority to U.S. Provisional Patent Application Ser. No. 62/579,560 entitled “Cracker Modular Processing Facility” filed Oct. 31, 2017, which is incorporated herein by reference in its entirety.
Filing Document | Filing Date | Country | Kind |
---|---|---|---|
PCT/US2018/058358 | 10/31/2018 | WO | 00 |
Number | Date | Country | |
---|---|---|---|
62579560 | Oct 2017 | US |