Claims
- 1. A method of constructing a building structure, characterized by:
- a. precasting supporting modules, each having transverse guideways;
- b. positioning the supporting modules in predetermined spaced and coplanar relation;
- c. stacking similarly positioned supporting modules thereon to form a multiple level structure;
- d. extending tendons through the guideways and between the supporting modules of an upper level;
- e. placing a casting form to extend between spaced supporting modules at said upper level;
- f. casting a supported slab in the form and around the portions of tendons extending between the supporting modules;
- g. lowering the casting form to a lower position at the level of a lower pair of spaced supporting modules while having said cast slab supported at said upper level;
- h. extending tendons through the guideways and between the supporting modules at the lower level;
- i. casting a further supported slab, in said casting form and repeating said step of lowering said casting form and repeating said step of lowering said casting form;
- j. and after completion of each level tensioning, the tendons exert transverse compression loads in the supporting and supported modules.
- 2. A method as defined in claim 1, wherein said casting form is suspended by cables and the supported slabs are cast about the cables, characterized by:
- a. sliding the cables through any previously cast supported slab as the form is lowered to a lower casting position.
Parent Case Info
This is a division of application Ser. No. 93,097, filed Nov. 27, 1970 and now abandoned.
US Referenced Citations (10)
Foreign Referenced Citations (5)
Number |
Date |
Country |
290,175 |
Dec 1965 |
AU |
1,010,724 |
Jun 1957 |
DT |
1,434,793 |
Oct 1968 |
DT |
988,114 |
Apr 1965 |
UK |
893,974 |
Apr 1962 |
UK |
Divisions (1)
|
Number |
Date |
Country |
Parent |
93097 |
Nov 1970 |
|