The present invention relates to a design and rapid construction method for the flush assembly of prefabricated beams and floor slabs used in construction engineering structures. The present invention is especially applicable to construction projects when field welding is not convenient to be implemented as well as there is a quite high demand for space height.
In the construction engineering structures, the connection method between prefabricated steel beam and floor slab is quite essential, which directly relates to space utilization, construction progress and project cost. At present, the main connecting methods of the assembly beam-slab in our country are putting the floor slab at the top of the beam through different ways to complete the further construction of floor system, which results in a certain reduction of space utilization. Therefore, a construction project in Shanghai foreshore has put forward the requirement of setting the floor slab flush with the upper surface of steel beam. In addition, the existing assembly floor connection methods require a lot of field welding, field formwork and scaffold construction, which will affect the construction quality and progress.
Therefore, there is a need for a new type flush design and rapid construction method of prefabricated steel beam and floor slab to improve space utilization and reduce construction periods. Based on the discussion above, the present invention proposes a new type of prefabricated steel beam and floor slab flush design and its rapid construction method, which can make the top surface of floor slab to be flush with steel beam, avoid field welding, and has the advantages of high space utilization rate as well as more controllable construction quality. When prefabricated concrete slabs or steel plate concrete composite slabs are adopted, there is no requirement for the field formwork and scaffolding, which owns the advantages to improve the construction speed.
The present invention provides a design and rapid construction method for the flush assembly of prefabricated steel beams and floor slabs; the beam-slab system has the advantages of high space utilization rate, fast construction speed, no field welding, convenient installation, etc.
The technical solution of the invention:
A flush assembly design method of prefabricated steel beams and floor slabs is presented, which mainly aims at the design of prefabricated beam-slab substructures. The prefabricated assembly beam-slab substructure comprises reinforced concrete floor slab 1, prefabricated steel beam 2 and cast-in-place concrete 3 between beams and slabs.
The prefabricated rebar ring 4 is arranged at the end of the reinforced concrete floor slab 1, which is used to connect the vertical pre-welded studs 5 of the prefabricated steel beam 2.
The upper flange of the prefabricated steel beam 2 is “” shaped and consists of horizontal flange 6, vertical flange 7 and top flange 8. The height of the vertical flange 7 is the same as the thickness of the reinforced concrete floor slab 1. Beam stiffener 9 is arranged on horizontal flange 6 to improve the stiffness and bearing capacity of horizontal flange 6 and prevent horizontal flange 6 from local deformation. At the same time, the vertical pre-welded studs 5 are welded on the horizontal flange 6. The position of the vertical pre-welded studs 5 corresponds to the prefabricated rebar ring 4 at the end of the reinforced concrete floor slab 1. The inner space composed of vertical flange 7 and top flange 8 is filled with beam flange inner side concrete 10 to prevent the flange from deformation under compression. Horizontal pre-welded studs 11 are set inside the vertical flange 7 to fix the beam flange inner side concrete 10 to prevent its falling off.
A fast construction method for the flush assembly of prefabricated steel beams and floor slabs, when the floor slab is a reinforced concrete floor slab, the steps are shown as follows:
1) Prefabricate the reinforced concrete floor slab 1 in the factory and set the prefabricated rebar ring 4 at the end of the reinforced concrete floor slab.
2) Prefabricate steel beam 2 in the factory; set vertical pre-welded studs 5 and stiffener 9 on horizontal flange 6; the position of vertical pre-welded studs 5 corresponds to the prefabricated rebar ring 4 at the end of reinforced concrete floor slab 1; set horizontal pre-welded studs 11 inside vertical flange 7.
3) Invert prefabricated steel beam 2 and taking its vertical flange 7 and top flange 8 as formwork, then complete pouring the beam flange inner side concrete 10 in the factory, and the horizontal pre-welded bolt 11 is set to fix beam flange inner side concrete 10.
4) On-site assembling; put the reinforced concrete floor slab 1 on the horizontal flange 6 of prefabricated steel beam 2 and hitch the prefabricated rebar ring 4 of the reinforced concrete floor slab 1 to the vertical pre-welded bolt 5 one by one.
5) Taking the horizontal flange 6, vertical flange 7 of prefabricated steel beam 2 and the side of reinforced concrete floor slab 1 as the formwork, pour concrete 3 in the gap between prefabricated steel beam 2 and reinforced concrete floor slab 1 to complete the construction of beam-slab substructure on site.
The floor stated above is not limited to prefabricated reinforced concrete floor slab 1; when the floor slab is the cast-in-place slab, and if scaffolding and supporting formwork are allowed to be used on site, then hitch the prefabricated rebar ring 4 at the end of the floor slab to the vertical pre-welded bolt 5 one by one after finishing supporting formwork, and then pour the concrete on site; if there is no scaffolding on site, use steel plate concrete composite floor slab; pre-welding prefabricated rebar ring 4 at the end of the steel plate or profiled steel plate in the factory, and connecting prefabricated rebar ring 4 of steel plate with vertical pre-welded bolt 5 of prefabricated steel beam 2 during on-site assembly, then pouring concrete on site with steel plate as formwork.
The beneficial effect of the invention is summarized as follows: compared with the existing technology, the prefabricated steel beam and floor flush assembly method proposed by the invention 1) can not only satisfy the bearing capacity requirements of the beam and slab, but also improve the space utilization rate of the construction structure; 2) both of beams and slabs of the invention can be prefabricated in the factory, then construction can be accomplished just by assembling beam and floor slab and pouring a small amount of concrete on site, more than that, scaffolding and formwork can be omitted during the process to realize rapid construction and reduce construction period greatly; 3) the invention avoids field welding and can guarantee construction quality better.
Where: 1 reinforced concrete floor slab; 2 prefabricated steel beam; 3 concrete; 4 prefabricated rebar rings; 5 vertical pre-welded stud; 6 horizontal flange; 7 vertical flange; 8 top flange; 9 beam stiffener; 10 beam flange inner side concrete; 11 horizontal pre-welded stud; 12 bottom steel plate when the floor slab is steel plate concrete composite slab.
In order to make the above features and advantages of the invention more understandable, in conjunction with the attached drawings, the technical solution of the invention is described in detail below through taking the prefabricated reinforced concrete floor as an example.
As shown in
The construction is carried out as follows:
1) Prefabricate the reinforced concrete floor slab 1 in the factory and set the prefabricated rebar ring 4 at the end of the reinforced concrete floor slab.
2) Prefabricate steel beam 2 in the factory: Set vertical pre-welded studs 5 and stiffener 9 on horizontal flange 6; the position of vertical pre-welded studs 5 corresponds to the prefabricated rebar ring 4 at the end of reinforced concrete floor slab 1; set horizontal pre-welded studs 11 inside vertical flange 7.
3) Invert prefabricated steel beam 2 and taking its vertical flange 7 and top flange 8 as formwork, then complete pouring the beam flange inner side concrete 10 in the factory, and the horizontal pre-welded bolt 11 is set to fix beam flange inner side concrete 10.
4) On-site assembling: Put the reinforced concrete floor slab 1 on the horizontal flange 6 of prefabricated steel beam 2 and hitch the prefabricated rebar ring 4 of the reinforced concrete floor slab 1 to the vertical pre-welded bolt 5 one by one.
5) Taking the horizontal flange 6, vertical flange 7 of prefabricated steel beam 2 and the side of reinforced concrete floor slab 1 as the formwork, pour concrete 3 in the gap between prefabricated steel beam 2 and reinforced concrete floor slab 1 to complete the construction of beam-slab substructure on site.
Filing Document | Filing Date | Country | Kind |
---|---|---|---|
PCT/CN2018/120633 | 12/12/2018 | WO | 00 |