Claims
- 1. A process for excavating and backfilling soil (44) particularly for laying pipes (46) in ditches comprising the steps of excavating soil (44) to form a ditch, removing the excavated material, preparing a supporting layer for pipes (46) in the soil (44), placing and embedding the pipes (46) in one of a grit and gravel layer (48), backfilling the ditch with filler (50), packing the filler (50), applying a top layer (54, 58), characterized by digging a first ditch section (52), removing the excavated material, preparing a supporting layer in the first ditch section (52) and placing and embedding (46) in the grit and gravel layer (48) in the first ditch section (52), milling subsequent ditch sections (56) in several layers (40) at a given milling depth, simultaneously loosening and mixing the milled material with binder being added, excavating the previously milled and treated layer (40), using the treated material as filler (50) in the previous ditch section (56), the ditch section (56) to be dug upstream of the pipes (46) being first milled at a given milling depth, loosened, comminuted and mixed, with at least one of liquid and solid binders being added by means of a milling/mixing rotor (22) integrated in an excavator bucket (16), and the treated material capable of being packed is subsequently excavated by the excavator bucket (16) and placed as filler (50) onto the pipes (46) located upstream of the ditch section (56) in the working direction.
- 2. The process according to claim 1 characterized in that excavation of the soil (44), milling, loosening and mixing, excavation of the material previously prepared in the first ditch section (52) and backfilling the treated material as filler (50) in the following ditch sections (56) are carried out by an excavator bucket (16) having an integrated milling/mixing rotor (22).
- 3. A process for excavating and backfilling soil (44) particularly for laying pipes (46) in ditches comprising the steps of excavating soil (44) to form a ditch, removing the excavated material, preparing a supporting layer for pipes (46) in the soil (44), placing and embedding the pipes (46) in one of a grit and gravel layer (48), backfilling the ditch with filler (50), packing the filler (50), applying a top layer (54, 58), characterized by digging a first ditch section (52), removing the excavated material, preparing a supporting layer in the first ditch section (52) and placing and embedding (46) in the grit and gravel layer (48) in the first ditch section (52), milling subsequent ditch sections (56) in several layers (40) at a given milling depth, simultaneously loosening and mixing the milled material with binder being added, excavating the previously milled and treated layer (40), using the treated material as filler (50) in the previous ditch section (56), and the excavation of the soil (44), milling, loosening and mixing, excavation of the material previously prepared in the first ditch section (52) and backfilling the treated material as filler (50) in the following ditch sections (56) are carried out by an excavator bucket (16) having an integrated milling/mixing rotor (22).
- 4. A process for excavating and backfilling soil (44) particularly for laying pipes (46) in ditches comprising the steps of excavating soil (44) to form a ditch, removing the excavated material, preparing a supporting layer for pipes (46) in the soil (44), placing and embedding the pipes (46) in one of a grit and gravel layer (48), backfilling the ditch with filler (50), packing the filler (50), applying a top layer (54, 58), characterized by digging a first ditch section (52), removing the excavated material, preparing a supporting layer in the first ditch section (52) and placing and embedding (46) in the grit and gravel layer (48) in the first ditch section (52), milling subsequent ditch sections (56) in several layers (40) at a given milling depth, simultaneously loosening and mixing the milled material with binder being added, excavating the previously milled and treated layer (40), using the treated material as filler (50) in the previous ditch section (56), and an excavator bucket (16) travels along one and the same path reproducibly preset by a control unit and applies one and the same working depth during milling, loosening, mixing and excavating the milled material.
- 5. A process for excavating and backfilling soil (44) particularly for laying pipes (46) in ditches comprising the steps of excavating soil (44) to form a ditch, removing the excavated material, preparing a supporting layer for pipes (46) in the soil (44), placing and embedding the pipes (46) in one of a grit and gravel layer (48), backfilling the ditch with filler (50), packing the filler (50), applying a top layer (54, 58), characterized by digging a first ditch section (52), removing the excavated material, preparing a supporting layer in the first ditch section (52) and placing and embedding (46) in the grit and gravel layer (48) in the first ditch section (52), milling subsequent ditch sections (56) in several layers (40) at a given milling depth, simultaneously loosening and mixing the milled material with binder being added, excavating the previously milled and treated layer (40), using the treated material as filler (50) in the previous ditch section (56), the at least one of liquid and powdered binder is continuously supplied to an excavator bucket (16) during milling the following ditch layers (56).
Priority Claims (1)
Number |
Date |
Country |
Kind |
197 27 549 |
Jun 1997 |
DE |
|
CROSS-REFERENCE TO RELATED APPLICATION
This application is a divisional application of Ser. No. 09/446,612 filed on Dec. 27, 1999, and now U.S. Pat. No. 6,312,194.
US Referenced Citations (2)
Number |
Name |
Date |
Kind |
4812078 |
Rivard |
Mar 1989 |
A |
6158925 |
Schleining et al. |
Dec 2000 |
A |