The descriptive report hereof refers to a patent of invention request to an item set whose assembly creates a new device to be installed in the coating column used on cementing of probing, gas/oil and/or mineral shaft walls.
After inserting this coating tubular column in the shaft (in the cementing phase), if obstruction prevents it from reaching the bottom, the device object of the patent request hereof, allows the coating column to be coupled to the probing equipment rolling chuck that injects the fluid simultaneously in torque for the wall thinning until it is clear, so the said coating may reach the shaft bottom.
After the coating column surpasses the clear point and reaches the shaft bottom, it automatically applies the cement paste injection to coat the shaft wall, then avoiding intervals to replace equipment and slowness in the shaft cementing phase.
As it is known by technicians in this mineral and/or gas/oil probing segment, as long as the soil is drilled by the chaplet drill, the shaft wall must be coated with steel tubes and cemented with a cement paste to isolate intermediary rock zones and keep normal upside and downside movements of the drilling column, without obstruction.
In this cementing phase, through the lifting equipment, the drilling column is removed and a so-called coating tubular column is inserted in place of it, which in its terminal (shoe), along with the shaft bottom, injects the cement paste, rising due to the huge pressure and adheres itself to the gap between the shaft wall and the coating column, then proceeding with the cementing operation (with the cement paste). Then the surface equipment are demobilized and the drilling column is once again inserted to proceed with the chaplet drill operation, activated by the probing equipment chuck, thinning the waste cement forged on the shaft bottom and penetrating the soil normally.
It happens that due to its own aggressive drilling features, shaft wall landslides create “holes” or obstructions that obstruct the full coating column lowering until the bottom, in the said cement paste injection phase. If it is forced by its own weight against the obstruction found, the said coating column may be damaged. In such cases, a fluid is injected instead of the cement paste through the coating column terminal, which goes upward from the shaft bottom through the void gap, until it reaches the obstruction in order to “soften it”, “thin it” or “erode it” in a continuous flow and strong pressure applied. Therefore, this procedure is needed so the coating column may reach the shaft bottom and the wall cementing may be carried out successfully.
However, this coating operation may become even more complex in case the clearing operation is not made successfully at its beginning (even though the fluid is injected). It might happen due to the material hardness (obstruction) found, then with a probing equipment column lifting system, the coating column must be removed, and the drilling column coupled to a chuck shall be inserted once again to conclude the thinning procedure on the obstruction through the chaplet drill. Only this way, after removing the drilling column with the opened chuck and with the probing lifting system, the coating column may be inserted again to eventually inject the cement paste between the coating and shaft wall. Then, with the help of the probing equipment column lifting system, the drilling column is inserted once again within the shaft and the next drilling phase is restarted (if there is such new drilling phase).
As it is noted, the clearing operation inside the shaft during the coating column lowering phase might become expensive, considering such handling and additional equipment replacement, slowing down the shaft drilling system for mineral and oil/gas probing.
The device hereof, object of this patent request, shall enable the coating column spin simultaneously to the fluid injection if there is an obstruction in the drilling shaft wall. Thus the coating column may be operated in low torque (without damage) in combination with the fluid injection to erode or thin the obstruction inside the shaft, proceeding with cement paste injections without removing and reinserting alternatively the drilling column in this phase (as it usually occurs).
In a superficial explanation, the device, assembly system and their related operation may be better detailed in the attached drawings, in which we see:
According to the attached drawings the “ASSEMBLY AND INSTALLATION SYSTEM DEVICE IN A COATING COLUMN COUPLED TO A CHUCK FOR A PROBING SHAFT CLEARING”, object of the patent of invention request hereof, is comprised of a lower retainer box (1) with a cylindrical body, with an edge (2) vented by a radial hole (3), as it delimits the setback throat (4), and the said box (1) contains retainer rings (5), as shown in 1B, thus assembled to have its body surpassed (1), from a vented axle (6). This vented axle (6) has an externally threaded lower end (7) and, after its lowering, it creates a lower throat (8) delimited by a central stopper (9). After the said central stopper (9), the vented axle (6) extends an upper tower (10), spread in a diameter gradual reduction per degrees, forming a lower part (11), an intermediary part (12) and an upper part (13), incorporating a nearby ledge (14) from which the upper end extends itself (15), as shown in 2A and 2B.
The lower retainer box (1), along with its retainer rings (5) is surpassed by the threaded lower end (7) of the vented axle (6) and places its edge (2) in parallel to the central stopper (9) of the latter. Then from the upper end (15), the axle (6) accommodates the lower bearing (16) that is placed over the central stopper (9), as shown in 3A and 3B, followed by a mounting (17) with a threaded upper end (18), externally forming an inner upper housing (19), in addition to a nearby lower valance (20) with a radial hole (21), which forms an inner lower housing (22). By introducing the mounting (17), the housing (22) envelopes the lower bearing (16) and the mounting's nearby edge aligns its holes to the retainer box (1) edge (2) holes (3), which are locked by bolts (23) around the central stopper (9) of the vented axle (6), as shown in 4A and 4B.
In the housing (19), inserted by the axle (6) loose end (15) and enveloping the intermediary part (12) of its tower (10), it contains an upper bearing (24) of a lower edge coupling (25), stressed from a cylindrical bracket (26), which is vented by a hole (27) into its wall, as shown in 5A and 5B. Through its hole (27), a thrust bolt (27a) is placed over the upper part (13) of the vented axle (6), followed by the insertion of a span ring (28), supported in setback on the mounting (17) threaded upper edge (18), as shown in 6A and 6B. As shown in 7A and 7B, an upper retainer box (29) with a stressed lower edge (30) contains retainer rings (31) inside it, and in its external nearby flats (32), o'rings (33) are also placed, as they go through the loose of the axle (6) end as well, (15) enveloping and sealing it by its retainer rings (33) and by its said stressed edge (30) placed on the span ring (28), as shown in 8A and 8B.
As shown in
According to the assembling explained above, with the bolt (27a) locking with the cylindrical support (26), placed over the upper bearing (24) on a mounting (17), the vented axle (6) is kept loose, i.e., may be able to spin over the upper head (34). In turn, the lower bearing (14) placed on the stopper (9) keeps the vented axle (6) always aligned to the inner connecting route with the fluid input (40) of the upper head (34). Now the retainer rings (5) and (31) of the corresponding lower and upper retainer boxes (1) and (29) keep the vented axle (6) sealed. Thus, through its fluid input (40) the device shall have an oversleeve (M) connection to a liquid cement reservoir (not shown) and, in its lower threaded end (7), it shall be threaded in the coating column (R) used in oil/gas drilling shaft (P) cementing operations.
In the eyelet (41) of the upper head (34), the coating column (R) couples the probing equipment column lifting system grip (not shown), as it is directed and coupled to the platform chuck (MA), whose clamping jaws relieve the pressure, opening itself and making it able to lower it inside the shaft (P), as shown in
Due to fact the axle (6) is assembled in a “loose” spin in the upper head (34) (in turn, it is static, fixed by the crane), such movement allows all the coating column (R) to have a continuous torque by chuck (MA) action, receiving the fluid (F) simultaneously from the input (40) and threaded end (7) of the device, in a great pressure, as it is injected through the said column terminal. Thus the spin combined to the injection will thin or erode the hindrance (O) in a quick and effective manner. With the thinning, as shown in
A sequence of procedures is listed below for the coating column lowering. The indicated technical specifications in English are used in all national territory and, therefore, are kept in this patent request.
Operational Procedure for Production Coating Lowering 1. QHSE
15.1 Wear the complete PPE for operations within the area;
15.2 Make a work risk evaluation, when necessary;
15.3 Open a work permit (PT), when necessary;
15.4 Wear a safety belt while working at high heights;
15.5 While checking unsafe operations or conditions, suspend the work;
1.6 Isolate the area while moving loads, carrying out hot working. Pressure tests etc.;
1.7 If you have any doubts about such works, call a safety technician or consult a supervisor.
2. Initial Inspection
2.1 Ensure the wear bushing is recovered while concluding the drilling operation, after removing the column from the shaft (“SDS-PROC-PI-002—Wear Bushing Installation and Uninstalling”). Remember the blind compartment shall be closed between operations in order to keep the shaft safety;
2.2 Ensure 4½″ tube compartment is replaced by 3½″ tube compartments, and after replacing it, carry out BOP full or partial test, depending on the last test date, following the procedure “SDS-PROC-PI-001—BOP Test”;
2.3 Have a tally promptly, prepared by Operator's Company Man, assuring the coating is duly jigged before lowering it in the shaft;
2.4 Provide the platform with all equipment and procedures needed to lower the coating.
3. Tools needed for lowering 3.1 Bucking machine;
3.2 Monkey wrench;
3.3 Spinning wrench with Torque wrench; 3.4
Still with a probe hoist, lower the coating smoothly inside the bucking machine, place the tube male thread FJL within the female thread, starting the first manual screw or with the help of a monkey wrench.
Filing Document | Filing Date | Country | Kind |
---|---|---|---|
PCT/BR2013/000581 | 12/18/2013 | WO | 00 |
Publishing Document | Publishing Date | Country | Kind |
---|---|---|---|
WO2015/089597 | 6/25/2015 | WO | A |
Number | Name | Date | Kind |
---|---|---|---|
1861485 | Tremolada | Jun 1932 | A |
2029598 | Timbs | Feb 1936 | A |
2127312 | Seamark | Aug 1938 | A |
8567511 | Mackenzie | Oct 2013 | B2 |
20060185841 | Swagerty | Aug 2006 | A1 |
20080271884 | Robichaux | Nov 2008 | A1 |
20110162852 | Nguyen | Jul 2011 | A1 |
20120285743 | Gosselin | Nov 2012 | A1 |
20120292046 | Klimack | Nov 2012 | A1 |
20130025850 | Eriksen | Jan 2013 | A1 |
20160090816 | Gosselin | Mar 2016 | A1 |
Number | Date | Country |
---|---|---|
2 164 374 | Mar 1986 | GB |
2013104069 | Jul 2013 | WO |
Entry |
---|
International Search Report, PCT/BR2013/000581, dated Aug. 28, 2014. |
Number | Date | Country | |
---|---|---|---|
20170218718 A1 | Aug 2017 | US |