The present invention relates generally to the field of electric power management and, more specifically, to a system and methods for managing an aggregation of electric power consumers to participate in energy markets.
In the United States, electric power utility companies are highly regulated by both federal and state governments. In general, the retail rates charged by such companies for the power they supply are not set by an open market. Instead, the retail rates are set by a commission or other regulatory tribunal through a formal, administrative process which takes into account present and predicted future demand, costs incurred to build or gain access to new sources of supply, and a variety of other factors. Wholesale rates are often based on the independent system operator (ISO) market, but not in all areas.
Within the regulated market for electric power, there are power generating facilities known as “base load power plants,” “load following power plants” and “peaking power plants.” Base load power plants are typically large, lower cost facilities which operate continuously to meet the base demand for power in a given service area. Load following power plants, as the name implies, are generally intended to operate when demand (loads) are high, but limit or curtail operation when demand is low. Peaking is power plants, which often is used to refer to 10 minute and 30 minute reserves which are part of the ancillary services market, are generally intended to operate only intermittently to meet peak demand in the service area, or to meet demand in the event of a contingency such as a power plant failure. Thus, the need for a peaking power plant to actually operate may arise on only a few days each year and may last for only a few hours.
To participate in energy markets, a facility is by regulation required to generate a minimum output power level (e.g., 100 kW), be capable of bringing that power online within a predetermined time period following a request from a grid operator, and remain online for a predetermined minimum time period. In accordance with prevailing regulations, peaking power plants are paid a premium rate for the power they supply. This is justifiable given the extremely intermittent operation of such plants, the state of readiness that they must maintain, and the importance of ensuring that peak demand is satisfied without interruption.
Recently, a court considered the question of whether, under prevailing regulations, a market participant could consist of a facility which reduces electrical loads in a given service area, thereby reducing power consumption as opposed to generating additional power. The court answered the question in the affirmative, thus creating an opportunity to develop new facilities which are eligible to participate in all of the established energy markets including, but not limited to, ancillary services (10 and 30 minute reserves, frequency control, and regulation), real-time market, day-ahead market, and forward capacity market, but which operate on a model of reduced consumption and not increased production.
Another problem of interest manifests in solar (photovoltaic or pv) panel-equipped homes, businesses or other premises. The vast majority of such installations are grid-tie systems, which means that excess power generated by the solar pv panels is sent back to the power grid, and any additional power needed by the premises is supplied by the grid. Because of anti-islanding laws, all grid-tie systems no longer operate when the power grid goes down, even though the solar pv panels could be generating power that could be used on the premises. In recent years, islanding inverters have made it possible to continue using solar pv panels while still complying with anti-islanding laws. These is secondary inverters work in conjunction with batteries and a critical load panel to supply homes, businesses or premises with limited power to critical loads. However, the critical loads are “fixed” because they must be selected in advance and wired into the critical load panel which is separate from the main circuit breaker panel.
In accordance with one aspect of the invention, a group of homes, businesses, or other electric power consuming premises are aggregated and commonly controlled to dynamically reduce loads in sufficient quantities, and with sufficient rapidity and duration, to participate as a market participant in the energy markets including participating as a peaking power plant. While the amount of reduced power consumption for a single premises is typically quite small, the total reduced consumption of an aggregation of just a few thousand homes or businesses may be on the order of hundreds of kilowatts. By electing to participate in the aggregation, each home, business or other premises contributes to a substantial, ongoing conservation effort, and may share in the revenue which is received from the provider. Similarly, when power costs are low, loads inactive during peak periods may be activated saving cost over operating those loads during the peak period.
Each home, business or other premises which participates in the aggregation is provided with a premises power controller and intelligent circuit breakers which augment conventional circuit breakers or fuses. The premises power controller and intelligent circuit breakers may be installed during construction or as a retrofit. The premises power controller may include a processor, memory, a display which may function to provide a user interface, interfaces for the intelligent circuit breakers, major appliances, heating, ventilating and air conditioning (HVAC) systems, water heaters, as well as interfaces for solar, geothermal, micro-hydro, or wind generation and inverters, storage batteries, generators, other renewable power sources, home automation systems, schedulers or user control devices. The premises power controller may also include interfaces for environmental sensors (e.g., temperature, barometric pressure, voltage, current, motion is detectors) and other sensors of interest. The premises power controller may also include wide area network (WAN) connectivity or other suitable network connectivity for communicating with an aggregation server or other systems that may be remotely located.
Each intelligent circuit breaker is electrically capable of being actuated and interfaces with a conventional circuit breaker which is manually capable of being actuated. Each intelligent circuit breaker includes a power meter, a wireless transceiver for communicating with other intelligent circuit breakers and the premises power controller, a breaker controller, memory, and a display. For lighting circuits, the intelligent circuit breaker also includes a dimmer. The memory may be used to temporarily store data of interest regarding the intelligent circuit breaker's status, power consumption, operating history, and the like. The intelligent circuit breakers may advantageously be constructed in a form factor which is compatible with (i.e., adapted to fit) circuit breaker panels offered by major manufacturers of electrical equipment (e.g., Square D by Schneider Electric, General Electric Company, Siemens AG, Murray by Siemens AG, Thomas & Betts of ASEA Brown Boveri, and Crouse-Hinds by Eaton).
Because the intelligent circuit breakers are normally installed inside a metal breaker panel, there is typically considerable interference with wireless communication to and from the breakers. To overcome such interference, a wireless mesh network may be established among the wireless transceivers that are associated with the intelligent circuit breakers. The wireless mesh network enables messages received by a designated gatekeeper wireless transceiver to propagate across all of the other wireless transceivers while reducing congestion in communication with the premises power controller. The gatekeeper wireless transceiver is responsible for transmitting messages originating from any of the other wireless transceivers to the premises power controller, as well as relaying messages received from the premises power controller to one or more of the other wireless transceivers. To further reduce interference, the gatekeeper wireless transceiver may be located in proximity to an aperture in the breaker panel. The aperture alone, or possibly in combination with wire runs which pass through the aperture, may enable satisfactory wireless communication between the gatekeeper wireless transceiver and is premises power controller. Alternatively, the aperture may accommodate a small antenna which is coupled to the gatekeeper wireless transceiver.
Through its own wireless transceiver, wireless mesh network, and gatekeeper wireless transceiver, each intelligent circuit breaker may send messages to the premises power controller. Such messages may report the amount of power being consumed instantaneously, the average power consumed over a given time period, a change in the amount of power consumed, status information, or other data of interest. Such data may be temporarily stored by the premises power controller before it is passed along to the aggregation server or other system.
Each intelligent circuit breaker may also receive messages from the premises power controller. One type of message causes the circuit breaker to actuate, thereby opening the circuit and disconnecting the associated load, or closing the circuit and connecting the load to a line (power grid) source, a renewable power source, backup generator, or an energy storage device, such as a differential pressure cell, an electro-chemical battery, and a chemical energy storage system (hereinafter after battery) on the premises. Thus, one advantage provided by the present invention is that critical loads within the premises need not be wired to a separate, dedicated circuit breaker panel in order to maintain power to those loads when the power grid is down.
A premises may also include an AC-DC converter whose output is coupled to a DC-AC inverter with power factor control, which in turn is coupled to dimmable loads. The output (DC) of the converter is coupled to the inverter, at which a power factor may be altered in conjunction with an inversion to AC. The altered power factor causes a reduction of the amount of real power absorbed by the dimmable loads, thereby providing further improvement to overall efficiency as well as contributing to a reduction in consumption as part of an aggregation's performance as a market participant.
Another advantage provided by the present invention is that when the power grid is up and a renewable source is generating “surplus” power on the premises, the intelligent circuit breakers may be dynamically managed to connect additional loads (e.g., charge available batteries and electric vehicles first, followed by a swimming pool heater, auxiliary water heater, and the like) to consume the available “surplus” power as opposed is to selling such power to the utility company, if possible and advantageous given the prevailing circumstances.
Yet another advantage provided by the present invention is that each individual load may be dynamically managed by the premises power controller to both improve overall efficiency of the premises, and enable the premises to function as part of an aggregation that participates in the energy markets.
Yet another advantage provided by the present invention is that user-oriented functions such as lighting control, including dimming, may be performed without the need for separate, conventional lighting control equipment.
Yet another advantage provided by the present invention is that a premises, when dynamically managed by a premises power controller in conjunction with intelligent circuit breakers, maintains a higher level of functionality and acts as its own nano-grid when the power grid is down. Conversely, when the power grid is up, the present invention may capitalize on time-of-use pricing by managing loads based on need and pricing structure.
In general, each premises power controller is programmed to dynamically manage power consumption within the premises in accordance with a plurality of predetermined scenarios. Such power management scenarios may include, for example, a “normal” scenario when the power grid is up, an “emergency” scenario when the power grid is down, a “renewable favorable” scenario when environmental conditions are favorable for a renewable power source that is associated with the premises, a “renewable unfavorable” scenario when environmental conditions are unfavorable for a renewable power source, and a “market trading” scenario when the premises must function within an aggregation that is participating in the independent system operator market including providing ancillary services (e.g., performing as a peaking power plant), and the like.
When a regional grid controller or other authority signals the aggregation server that a market participant is needed to meet demand, the aggregation server uses the WAN to direct the premises power controllers within the aggregation to initiate their “market trading” or similar power management scenarios. In response, each premises power controller, subject to an overriding command issued by the premises owner or other authority, proceeds to dynamically disconnect individual loads by sending appropriate messages wirelessly to the intelligent circuit breakers. The disconnected loads may remain disconnected for the entire time that the aggregation is functioning as a market participant or, alternatively, may be reconnected by an authorized override. Once the aggregation server receives a signal that the aggregation no longer needs to function as a market participant, the server issues a message to the premises power controllers directing them to resume their “normal” power management scenarios or another appropriate scenario.
The premises power controller may also issue notifications to users regarding power management-related events. For example, if the premises is equipped with solar panels and the premises power controller receives a weather forecast for sunshine, a notification may be sent to a user's email address, mobile phone, or other device to remind the user to plug in an electric vehicle to charge, turn on an auxiliary water heater, or take other action to fully use the power which is expected to be generated by the solar panels. Additionally, during periods of abnormally high energy costs, or very low expected production, notifications may be issued to users reminding them to take measures to limit use, such as ensuring that windows and doors are closed, lighting demands are reduced, or other loads are minimized.
The invention description below refers to the accompanying drawings, of which:
The premises which form aggregation 118 may be classified in one of three classes. Class 1 premises are those which do not include any solar or other renewable is source of power (collectively, “renewable source”) nor any battery capable of storing a significant amount of power, but may include a backup generator which may serve to power some or all of the premises when power grid 100 is unavailable. When power gird 100 is available, Class 1 premises normally only draw power (unidirectionally) from power grid 100.
Class 2 premises are those which include at least one renewable source and possibly a backup generator, but do not include a battery of significant capacity. Class 2 premises draw power from power grid 100 when the renewable source is offline or insufficient to meet the demand of the premises, but may deliver power to power grid 100 when there is a surplus. Thus, Class 2 premises are characterized by bidirectional power flow.
Class 3 premises are those which include at least one renewable source as well as one or more batteries of significant capacity, and possibly a backup generator. Like Class 2 premises, Class 3 premises may draw power from or deliver power to power grid 100 depending upon environmental conditions, the demand of the premises and other factors. As described in detail below, aggregation 118, which represents a mix of Class 1, 2 and 3 premises, may be managed as single entity which performs as an energy market participant based on a model of reduced consumption of power possibly in combination with production from battery storage.
Wireless communication links 216 may be implemented with Bluetooth®, Wi-Fi, or any of a number of other commercially available wireless technologies. Such wireless communication links greatly reduce the cost of and time required for installation of premises power controller 202. Alternatively, if the design of or materials used in a particular premises is not conducive to wireless communication, wired communication links (e.g., Ethernet) may be used by the addition of appropriate interfaces on premises power controller 202 as well as the other devices shown in
Backup generator 228 is coupled to a transfer switch 232 by a conductor 230. Transfer switch 232 is coupled by a conductor 234 to circuit breaker panel 206. Transfer switch 232 is also coupled to a utility company meter (not shown) by a conductor 218. When power grid 100 is down, transfer switch 232 moves to the position shown in
In general, premises power controller 202 is responsible for managing power consumption in premises 200. Among other features and capabilities, premises power controller 202 is responsible for dynamically actuating individual intelligent circuit breakers 222, 226 to disconnect individual loads, thereby reducing power consumption of premises 200 and contributing to an aggregation which is performing as an energy market participant. As described in detail below, more than one premises power controller 202 may be present in a given premises for purposes of redundancy, load sharing, or the like.
All other elements are substantially similar to those shown in
Transfer switch 232 operates to disconnect panel 206 from power grid 100 (
Also shown is an AC-DC converter 410 whose output is coupled to a DC-AC inverter with power factor control 412, which in turn is coupled to dimmable loads 414. AC-DC converter 410 and DC-AC inverter with power factor control 412 communicate with premises power controller 202 through wireless communication links 216. As described in detail below, converter 410, in combination with inverter 412, may be used to advantageously alter the power factor so as to reduce the amount of real power absorbed by dimmable loads 414.
As described above in connection with
An LCD 602 and a 16 GB microSD card are coupled to embedded graphics controller 604. A pair of relays 630 is coupled, respectively, between a pair of screw terminals 620 and a pair of Hall Effect sensors 618. Each of a pair of screw terminals 620 serves as a connection point to a conventional 15 A/120 VAC circuit breaker (not shown), such as an arc fault breaker, which is manually capable of being actuated. In the alternative, the relays may be embodied as an actuated mechanical switch to obviate the need of the conventional circuit breaker while providing for adequate safety. Each of a pair of screw terminals 622 serves as a connection point to a desired load (not shown). An AC-to-DC power supply 624 outputs +12 VDC and +3.3 VDC to power intelligent circuit breaker 226. As an alternative to using power measurement DSP 608 to output pulses when the sensed voltage and current are near zero, a zero cross detection circuit 628 may be used to generate a square wave output signal which is coupled to breaker controller 600.
Breaker controller 600, using its onboard Bluetooth® connectivity, communicates with other breaker controllers to establish a wireless mesh network among all of the breaker controllers. The presence of a mesh network advantageously enables a single breaker controller within a breaker panel or, alternatively, a designated gatekeeper transceiver, to conduct communications with a premises power controller (
LCD 602 may be used to display a variety of information (e.g., the current state of the circuit breaker, a configuration of the circuit breaker, instantaneous power consumption, identifier, such as a zone, of the circuit breaker, and diagnostic codes). MicroSD card 606 may be used to store power consumption data and other data of interest until a scheduled time when such data is forward to a premises power controller 202 or discarded as stale.
Power measurement DSP 608 is capable of calculating, among other values, instantaneous power consumption separately for each load connected to screw terminals 622, as well as average power consumption over a specified period of time, and peak power consumption. Power measurement DSP 608 may also be configured to output pulses (on dedicated pins ZX0, ZX1, which are coupled to breaker controller 600) when the current and voltage are near zero.
By knowing when zero crossings of current and voltage are occurring, breaker controller 600 ensures that relays 630 are only switched (i.e., intelligent circuit breaker 222 is opened or closed) contemporaneously with the occurrence of a zero crossing. This advantageously reduces arcing and tends to prolong the service lives of relays 630.
An intelligent circuit breaker suitable for a single 30 A/220 VAC circuit may be implemented using the components shown in
A dimming function may be implemented using a traditional cut phase dimming technique, as illustrated in
Turning now to
Due to interference with wireless communication typically caused by (metal) circuit breaker panel 706, gatekeeper transceiver 712 may be assigned exclusive responsibility for communicating with premises power controller 202 (
Gatekeeper transceiver 712 may also include power monitoring functionality for measuring total power consumption (or surplus) at main conductors 218. A current transformer 710 is coupled to each main conductor 218, and to gatekeeper transceiver 712. As may be seen best in
In general, each wireless lighting control keypad 722 typically includes a processor, microcontroller or the like which is capable of running some or all of the same software run by premises power controller 202 as described herein. In addition, each wireless lighting control keypad 722 typically includes wireless network connectivity such as Wi-Fi or Bluetooth®. With such network connectivity, keypads 722 may establish wireless communication links 730 with intelligent circuit breakers 222 or intelligent circuit breakers with dimmers 226. Thus, any of wireless lighting control keypads 722 may be used as an alternative to, or in conjunction with, premises power controller 202 to turn lamps 724 (or other lighting loads) on or off as well as dimming such lamps.
Next, at step 906, aggregation server 112 transmits a message to each premises is power controller 202 within aggregation 118 to run its “market trading” power management scenario. In general, when a given premises power controller 202 run its “market trading” scenario, this will cause particular loads in the premises to be “shed” or disconnected (by actuating the associated intelligent circuit breakers) and, for class 3 premises that include batteries with significant storage capacity, may also result in the connection of such batteries to supply power to the power grid. Next, at step 908, aggregation server 112 follows an ISO market rule to implement a demand response reduction curve.
Alternatively, at step 1008, if the determination indicates that no control command was received, then intelligent circuit breaker 222, 226 checks its power reading status at step 1014. If that status has changed compared to a last known status, as determined at step 1016, then intelligent circuit breaker 222, 226 sends its power reading to premises power controller 1018, and subsequently waits for an acknowledgement from the premises power controller at step 1020. If, at step 1016, no change in power reading is status was found, then at step 1022 intelligent circuit breaker 222, 226 sends an indication of no change to premises power controller 1022, and subsequently waits for an acknowledgement from the premises power controller at step 1024.
If, at step 1110, a determination is made that the premises is not a Class 3 premises, control flow advances to step 1109 at which a query of premises power controller 202 is made for a current virtual energy price. The term “virtual energy price” is used in this specification to refer to a value that serves as a proxy for the relative scarcity or abundance of energy. Each action relating to a load or source within a given premises is associated with either a threshold or scaling factor against the virtual energy price. In its simplest formulation, a system based on a virtual energy price may implement a priority list of loads or sources capable of both discrete and smooth transitions (i.e., capable of smoothly transitioning and discretely transitioning power consumption or generation) as well as selection of the loads based on temporal use (e.g., a recency of use). In a more sophisticated implementation, such a system could model the full dynamism of an energy market.
By choosing a quantity with the same units and order of magnitude as is typical on the public energy market, it is possible for a user to specify his or her priorities once, is and in terms of real dollars. In cases where the premises pays market rates for energy, the power grid is available, and market rates are provided by aggregation server 112, this will be especially meaningful to the user. In other cases, the virtual energy price will be computed to perform the actions necessary for the effective management of system resources and will not have any relationship to energy costs on the public market.
As an alternative to calculating a virtual energy price, a state machine could be implemented which accesses a lookup table or other data structure to obtain a value which is a suitable reference or proxy for the purposes described herein.
Next, at step 1111, a determination is made whether the virtual energy price is above a notification threshold. If not, control flow loops to step 1102. If so, meaning that a user notification should be sent, control flow advances to step 1113 (
Referring again to step 1105, if a (second) broadcasting premises power controller 202 was discovered, control flow advances to step 1115 in which wireless communication is established between the discovered (master) premises power controller 202 and the (subordinate) premises power controller 202 performing this step. Next, at step 1117, the subordinate premises power controller 202 takes measurements from any sensors attached to it. This is followed, at step 1119, by the subordinate premises power controller 202 collecting user input. Next, at step 1121, the subordinate premises power controller 202 attempts to transmit its sensor measurements and user actions to master premises power controller 202.
At step 1123, a determination is made whether the attempted transmission to the master premises power controller failed. If so, control flow loops to step 1101. If not (meaning transmission was successful), control flow advances to step 1125 at which subordinate premises power controller 202 attempts to read system state and pending commands from master premises power controller 202. Next, at step 1127, a determination is made whether the attempted read failed. If so, control flow loops to step 1101. If not (meaning the read was successful), control flow advances to step 1129 at which subordinate premises power controller 202 updates its user interface according to the previously read system state, and executes new commands. If either the transmission failed at step 1121, or reception failed at step 1125, it is assumed that master premises is power controller 202 has been removed, powered down, or failed, and an election for a new controller is performed at step 1101. In this fashion, multiple, redundant premises power controllers 202 may be operated within a given premises.
Referring now to
If, at step 1114, premises power controller 202 determines that public power grid 100 is available, control flow advances to a determination at step 1116 whether energy price data is available. Energy price data may be supplied to premises power controller 202 by aggregation server 112 or other external source via WAN 116. If energy price data is available, control flow advances to step 1124 (
If, at determination step 1118, no explicit command was received from aggregation server 112 (meaning aggregation 118 is not currently required to perform as a market participant), then control flow advances to step 1122 at which a virtual energy price is set to a default value, and then to step 1124 (
Turning now to
If, at step 1138, the calculated virtual energy price was less than or equal to the backup generator on threshold value, or at step 1140 the backup generator's minimum off time has not yet elapsed, then control flow advances to step 1144 where premises power controller 202 determines whether the calculated virtual energy price is less than the generator off threshold value. It should be noted that the backup generator on and off threshold values are different to add hysteresis and avoid a condition where the backup generator is cycling on and off. If the calculated virtual energy price is less than the generator off threshold value, premises power controller 202 next determines at step 1146 whether a generator minimum on time has elapsed and, if so, proceeds at step 1148 to turn the generator off. If, at step 1144, the calculated virtual energy price is not less than the generator off threshold value (i.e., they are equal within the hysteresis band) or, at step 1146, the generator minimum on time has not yet elapsed, the control flow advances to step 1124.
Referring again to step 1133, if public power grid 100 is available, then control flow advances to step 1150 where a determination is made whether the utility company which serves the premises pays for net production of power. If not, then control flow advances to step 1152 where premises power controller 202 makes a forecast of the current day's on-premises power production, followed by step 1154 at which the virtual energy price is set to the rate charged by the utility company.
Next, at step 1156, premises power controller 202 simulates premises power consumption using the virtual energy price and forecast. If, based on the simulation, no net production of power is expected for the next 24 hours (i.e., all on-premises power production will be consumed), control flow advances to step 1124 (
Referring again to step 1150, if the utility company which serves the premises pays for net power production, control flow advances to step 1164 at which a determination is made whether energy price data is available. If so, control flow advances to step 1124. If not, a determination is made step 1166 whether an explicit command (message) was received from aggregation server 112. If not, meaning aggregation 118 is not currently required to perform as a market participant, then control flow advances to step 1170 at which a virtual energy price is set to the default value, and then to step 1124. If, at step 1166, a command was received from aggregation server 112 (meaning aggregation 118 is required to perform as a market participant and premises power controller 202 needs to reduce loads), then at step 1168 premises power controller 202 simulates premises power consumption to find a virtual price that satisfies the requirements of aggregation 118 performing as a market participant.
Referring now to
If battery exhaustion will occur within the next 24 hours, control flow advances to step 1178 at which the virtual energy price is increased (i.e., the virtual energy price is increased because a power scarcity is forecast for the premises). Next, at step 1180, a determination is made whether the (increased) virtual energy price is greater than a generator on threshold value. If not, control flow advances to step 1124. If so, control flow advances to step 1182 and the (non-renewable source) generator is turned on, provided it was off and a minimum off time has elapsed, followed by an advance to step 1124.
Referring again to step 1176, if battery exhaustion is not expected within the next 24 hours, then control flow advances to step 1184 at which a determination is made whether battery overrun is predicted within the next 24 hours. If not, control flow advances to step 1124. If so, control flow advances to step 1186 and the virtual energy price is decreased, again representing an expected power surplus for the premises. Next, at step 1188, a determination is made whether the virtual energy price is less than a generator off threshold value. If not, control flow advances to step 1124. If so, at step 1190, premises power controller 202 turns off the generator, assuming it was on and a minimum run time had elapsed.
Referring again to step 1172, if the public power grid 100 is available, control flow advances to step 1192 where premises power controller 202 performs a look ahead on an expected time-cost curve. Next, at step 1194, a determination is made whether the next peak on the expected time-cost curve is positive or negative. If a negative peak is expected, control flow advances to step 1196 at which a determination made whether if charging begins now will minimum cost be incurred during the charge cycle. If not, control flow advances to step 1124. If so, control flow advances to step 1198 where premises power controller 202 enables the battery to start charging, followed by an advance to step 1124.
If, at step 1194, a positive peak is expected, control flow advances to step 1200 at which a determination is made whether if battery discharge begins now, is the product of the sale revenue minus buy costs and the battery efficiency greater than the minimum cycle gain (i.e., will discharging yield a minimum gain to justify wear on equipment). If so, control flow advances to step 1205 where a determination is made whether if battery discharge begins now is a sell-buy efficiency greater than minimum cycle gain. If so, control flow advances to step 1204 and battery discharge begins. If not, control flow advances to step 1202 where a determination is made whether an explicit command (message) was received from aggregation server 112 to perform as a market participant. If so, control flow advances to step 1204 to begin battery discharge. If not, control flow advances to step 1124.
If the load is not dimmable, then at step 1211 a determination is made whether the load is of type for which a power factor (PF) may be controlled to reduce the amount of real power absorbed by the load. If so, control flow advances to step 1213 (
If, on the other hand, at step 1236 the point is determined to be below the cost-temperature curve D (e.g., either of the points indicated by reference letters E or H in
If the minimum run time of the HVAC system will not cause the zone temperature to cross the user-defined set point, then at step 1242 a determination is made whether a minimum off time for the HVAC system has elapsed. If not, meaning it is too soon to run the HVAC system again, control flow again returns to
If, at step 1402, the global virtual energy price is not above the user-set threshold, the control flow advances to step 1408 at which a determination is made whether the global virtual energy price is below the user-set threshold. If not, control flow returns to
With reference again to step 1501, if the load is determined to be currently connected, control flow advances to step 1502 at which a determination is made whether the virtual energy price is above a user-set threshold. If so, a determination is made at step 1504 whether the diversion load's minimum on time has elapsed. If the minimum on time has not elapsed, control flow returns to
If, at step 1502, the virtual energy price is not above the user-set threshold, control flow advances to step 1508 at which a determination is made whether the virtual energy price is below the user-set threshold. If not, control flow returns to
If, at step 1599, it is determined that the load is correctly connected to the system, then control flow advances to step 1600 for a determination whether a user has requested a charge cycle. If so, control flow advances to step 1610 where the electric vehicle begins charging, followed by a return to
If, at step 1804, the user's mobile phone is not accessible, then control flow advances to step 1806 in which a determination is made whether a user requested mobile push notifications. If so, control flow advances to step 1814 at which a request for a push notification event is sent to aggregation server 112. If not, control flow advances to step 1808 at which a determination is made the user has provided an email address at which to receive notifications. If so, control flow advances to step 1816 at which a request for an email notification event is sent to aggregation server 112, followed by step 1810 at which a message is displayed on display 526 (
The foregoing description has been directed to specific embodiments of this invention. It will be apparent, however, that other variations and modifications may be made to the described embodiments, with the attainment of some or all of their advantages. For example, it is expressly contemplated that the teachings of this invention can be implemented as software, including a computer-readable medium having program instructions executing on a computer, hardware, firmware, or a combination thereof. Accordingly this description is to be taken only by way of example and not to otherwise limit the scope of the invention. It is thus the object of the appended claims to cover all such variations and modifications as come within the true spirit and scope of the invention.
The present application is a continuation of U.S. patent application Ser. No. 15/966,798, entitled DYNAMIC MANAGEMENT OF CRITICAL LOADS, filed on Apr. 30, 2018 by Robert P. Madonna et al., and issued on Nov. 8, 2022 as U.S. Pat. No. 11,494,852, which is a continuation of U.S. patent application Ser. No. 15/706,145, entitled SYSTEM AND METHODS FOR CREATING DYNAMIC NANO GRIDS AND FOR AGGREGATING ELECTRIC POWER CONSUMERS TO PARTICIPATE IN ENERGY MARKETS, filed on Sep. 15, 2017 by Robert P. Madonna et al., and issued on Mar. 23, 2021 as U.S. Pat. No. 10,956,992, which application claims priority from commonly owned Provisional Patent Application No. 62/395,230, entitled SYSTEM AND METHODS FOR CREATING DYNAMIC NANO GRIDS AND FOR AGGREGATING ELECTRIC POWER CONSUMERS TO PARTICIPATE IN ENERGY MARKETS, filed on Sep. 15, 2016 and from commonly owned Provisional Patent Application No. 62/406,481, entitled SYSTEM AND METHODS FOR CREATING DYNAMIC NANO GRIDS AND FOR AGGREGATING ELECTRIC POWER CONSUMERS TO PARTICIPATE IN ENERGY MARKETS, filed on Oct. 11, 2016 which applications are hereby incorporated by reference.
Number | Name | Date | Kind |
---|---|---|---|
4001646 | Howell | Jan 1977 | A |
5185705 | Farrington | Feb 1993 | A |
7043380 | Rodenberg, III | May 2006 | B2 |
9300141 | Marhoefer | Mar 2016 | B2 |
20040007534 | Liao et al. | Jan 2004 | A1 |
20040163073 | Krzyzanowski et al. | Aug 2004 | A1 |
20050102544 | Brewer | May 2005 | A1 |
20050216131 | Sodemann et al. | Sep 2005 | A1 |
20070222295 | Wareham et al. | Sep 2007 | A1 |
20080143305 | Drugge et al. | Jun 2008 | A1 |
20100152910 | Taft | Jun 2010 | A1 |
20100161146 | Boss et al. | Jun 2010 | A1 |
20100314940 | Palmer et al. | Dec 2010 | A1 |
20110210712 | Tagare | Sep 2011 | A1 |
20110313587 | Lin | Dec 2011 | A1 |
20120104847 | Roscoe et al. | May 2012 | A1 |
20120239218 | Forbes, Jr. | Sep 2012 | A1 |
20120265459 | Sfaelos et al. | Oct 2012 | A1 |
20120324271 | Nigam | Dec 2012 | A1 |
20120330473 | Meredith et al. | Dec 2012 | A1 |
20140067144 | Chen et al. | Mar 2014 | A1 |
20140088780 | Chen | Mar 2014 | A1 |
20140139023 | Hwang et al. | May 2014 | A1 |
20140277800 | Hughes | Sep 2014 | A1 |
20140336837 | Kiuchi et al. | Nov 2014 | A1 |
20140379161 | Busser | Dec 2014 | A1 |
20150012145 | Kiko | Jan 2015 | A1 |
20150042286 | Lu et al. | Feb 2015 | A1 |
20150214759 | Wootton | Jul 2015 | A1 |
20150214768 | Matsuyama et al. | Jul 2015 | A1 |
20150256665 | Pera et al. | Sep 2015 | A1 |
20150276253 | Montalvo | Oct 2015 | A1 |
20150280436 | Weckx et al. | Oct 2015 | A1 |
20160226235 | Lathrop | Aug 2016 | A1 |
20160350778 | Levine et al. | Dec 2016 | A1 |
20160358722 | Lakshmanan et al. | Dec 2016 | A1 |
20160363949 | Zimmanck | Dec 2016 | A1 |
20170140602 | Curt | May 2017 | A1 |
20170236676 | Bartonek | Aug 2017 | A1 |
20170288599 | Chapman | Oct 2017 | A1 |
20170344045 | Forbes, Jr. | Nov 2017 | A1 |
20180075548 | Madonna | Mar 2018 | A1 |
20180082816 | Herrmann | Mar 2018 | A1 |
20180299160 | Inuga et al. | Oct 2018 | A1 |
20180342870 | Zeng et al. | Nov 2018 | A1 |
20190261493 | Dolan et al. | Aug 2019 | A1 |
Number | Date | Country |
---|---|---|
2353667 | Feb 2002 | CA |
102084569 | Jun 2011 | CN |
102323472 | Jan 2012 | CN |
202939450 | May 2013 | CN |
103326381 | Sep 2013 | CN |
204230176 | Mar 2015 | CN |
104537505 | Apr 2015 | CN |
105848389 | Aug 2016 | CN |
2002-95152 | Mar 2002 | JP |
2002320327 | Oct 2002 | JP |
2003092844 | Mar 2003 | JP |
2003-111311 | Apr 2003 | JP |
2005110218 | Apr 2005 | JP |
2007510394 | Apr 2007 | JP |
2007236023 | Sep 2007 | JP |
2008310972 | Dec 2008 | JP |
2010531129 | Sep 2010 | JP |
2010-537622 | Dec 2010 | JP |
2011-120323 | Jun 2011 | JP |
201222706 | Feb 2012 | JP |
2012-511300 | May 2012 | JP |
2012-514963 | Jun 2012 | JP |
2012-235615 | Nov 2012 | JP |
2013115885 | Jun 2013 | JP |
2014-03726 | Jan 2014 | JP |
2014036465 | Feb 2014 | JP |
2014108003 | Jun 2014 | JP |
2014165998 | Sep 2014 | JP |
2015-215879 | Dec 2015 | JP |
2016100917 | May 2016 | JP |
2016-134939 | Jul 2016 | JP |
2016-158479 | Sep 2016 | JP |
2016226141 | Dec 2016 | JP |
2017511098 | Apr 2017 | JP |
2017216789 | Dec 2017 | JP |
2009-507340 | Feb 2024 | JP |
1014404920000 | Sep 2014 | KR |
WO-2004023624 | Mar 2004 | WO |
WO-2005065148 | Jul 2005 | WO |
WO-2007027063 | Mar 2007 | WO |
WO-2010065197 | Jun 2010 | WO |
WO-2011073020 | Jun 2011 | WO |
WO-2015094518 | Jun 2015 | WO |
WO-2015134987 | Sep 2015 | WO |
WO-201609492 | Jan 2016 | WO |
WO-2016036419 | Mar 2016 | WO |
Entry |
---|
Demeo, Anna, et al. “Community smart grid utilizing dynamic demand response and tidal power for grid stabilization.” Smart Grid and Renewable Energy 4.07 (2013): 465-472. |
EP Office Action mailed Jun. 7, 21, EP Application No. 17 777 715.8-1202, 4 pages. |
Husen et al. “Lighting Systems Control for Demand Response,” IEEE 2011, 6 pages. |
Kempton, Willett et al. “Vehicle-to-grid power implementation: From stabilizing the grid to supporting large-scale renewable energy.” Journal of power sources 144.1 (2005): 280-294. |
PCT Invitation to Pay Additional Fees and, Where Applicable, Protest Fee, International Application No. PCT/US2017/051808, mailed Dec. 1, 2017, 14 pages. |
PCT Notification of Transmittal of the International Search Report and the Written Opinion of the International Searching Authority, or the Declaration, International Searching Authority, International Application No. PCT/US2017/051808, mailed May 14, 2018, 24 pages. |
Park, Sung Min. “Control and Integration Strategies for Bidirectional and Unidirectional Converters in Residential Distributed Power Systems.” (2015). |
Xu, et al. “A generic user interface for energy management in smart homes.” Energy Informatics 1 (2018): 1-63. |
Number | Date | Country | |
---|---|---|---|
20230033596 A1 | Feb 2023 | US |
Number | Date | Country | |
---|---|---|---|
62406481 | Oct 2016 | US | |
62395230 | Sep 2016 | US |
Number | Date | Country | |
---|---|---|---|
Parent | 15966798 | Apr 2018 | US |
Child | 17963868 | US | |
Parent | 15706145 | Sep 2017 | US |
Child | 15966798 | US |