The present application claims priority from Japanese Patent Application No. 2022-023747 filed on Feb. 18, 2022, which is incorporated by reference herein in its entirety.
The present invention relates to an electric power trade supporting device.
JP 2021-108525 A discloses an electric power operation system. The system disclosed in the publication includes a power storage facility that stores electric power generated by a renewable energy power generation facility, a user site having a management facility that controls the power storage facility, and an information processing unit that communicates with the management facility and electricity consumers and performs information processing.
The management facility sends, to the information processing unit, user site information and electricity storage information including the amount of electric energy that can be supplied. The information processing unit performs identification and authentication of the user site information and the electricity storage information and accepts an electric power demand request sent from electricity consumers. It also performs matching of the electric power demand request with the user site information and the electricity storage information, generates a discharge instruction as a result of the matching, and sends the discharge instruction to the management facility. Based on the discharge instruction, the management facility causes the electricity storage facility to discharge electric power so as to transfer the electric power to a predetermined electric power transmission and distribution grid.
The present inventors intend that an electricity trade with a higher degree of freedom be achieved.
An electric power trade supporting device according to the present disclosure includes a memory storage unit recording profiles of users respectively. The electric power trade supporting device is configured to execute the following processes:
This electric power trade supporting device enables the users who are electric power receivers (i.e., purchasers) to be provided with the electric power profiles of the electric power capable of being supplied by the users who are electric power suppliers (i.e., sellers). The users who are electric power receivers (i.e., purchasers) are able to find a type of electric power that the users wish to be supplied and to apply for receipt of the electric power. This enables the users who wish to receive supply of electric power to select a type of electric power when receiving electric power.
The electric power profile may include at least one of amount of the electric energy that the user is able to supply, power source information of the electric power to be supplied, and a supply condition.
The amount of electric energy that the user is able to supply may include an amount of electric energy stored in the smart grid, an amount of electric energy that is scheduled to be generated in the smart grid, and an amount of electric energy that is scheduled to be stored in the smart grid.
The amount of electric energy stored in the smart grid may be recorded in association with the user.
The electric power trade supporting device may also be configured to execute the following processes:
These processes make it possible to provide the electric power demand profiles from the users who are electric power receivers (i.e., purchasers) to the users who are electric power suppliers (i.e., sellers). The users who are electric power suppliers (i.e., sellers) are able to find a counterparty to which they want to supply electric power and to make an application to supply electric power. This enables the users who wish to supply electric power to select a destination to supply the electric power. In addition, the users who are electric power receivers (i.e., purchasers) are also able to limit the electric power to be supplied according to the electric power demand profile and to select the quality (i.e., means of power generation) of the electric power to be used.
The electric power demand profile may include at least one of date and time when the user desires to receive supply of electric power, an amount of electric energy that the user desires to be supplied with, power source information of electric power that the user desires to be supplied with, a supply condition, and an intended use of electric power.
The electric power trade supporting device may be configured to record transaction data in a blockchain, the transaction data including information of the process of making the application, information of the process of approving, and information of the electric power supplied in the process of supplying the electric power.
Embodiments of the present disclosure will be described hereinbelow. It should be noted, however, that the embodiments illustrated herein are, of course, not intended to limit the disclosure. The present disclosure is not limited to the following embodiments described herein unless specifically stated otherwise. The drawings are depicted schematically and do not necessarily accurately depict actual objects. The features and components that exhibit the same effects are designated by the same reference symbols as appropriate, and the description thereof will not be repeated.
Herein, electric vehicles that are connectable to the transmission grid 20 include various types of electric vehicles that are connected to the transmission grid 20 and are capable of charging and discharging, such as plug-in hybrid electric vehicles (PHEVs), plug-in range extender electric vehicles (RexEVs), fuel cell electric vehicles (FCEVs), and battery electric vehicles (BEVs). The electric vehicles may also include hybrid electric vehicles (HEVs), range extender electric vehicles, and fuel cell electric vehicles, each provided with the function to be connected to the transmission grid 20 and supply electric power generated by the vehicles to the transmission grid 20. The hybrid electric vehicles and the range extender type electric vehicles may include not only ones that generate electric power using gasoline or diesel fuel but also ones that generate electric power with a hydrogen engine.
The electricity consumers are those who consume electric power, such as households and factories. The electricity consumers receive supply of electricity while purchasing electricity when appropriate. The power generation operators that make use of natural energy such as solar power generation and wind power generation sell the generated electric power. The business operators installed with a solar power generation equipment on their own factories or buildings, the electricity consumers that perform home power generation, and the like sell electricity when surplus electric power arises in the solar power generation equipment and purchase the electric power that cannot be covered by the solar power generation equipment.
Among them, a management system 28a within a household is referred to as a home energy management system (HEMS). A management system 30a within a factory is referred to as a factory energy management system (FEMS). A management system 32a within a building is referred to as a building energy management system (BEMS). An energy management system 35a of the microgrid 35 that manages the electric power demand in a region and the amount of electric power supply supplied by regional power plants such as solar power generation plants, wind power generation plants, and biomass power generation plants is referred to as cluster/community energy management system (CEMS). CEMS is a vital system of the smart grid, which manages the overall energy of the region including HEMS, BEMS, and FEMS. The smart grid 10 is installed with an information processing apparatus 100 that collects information from these elements. The smart grid 10 is configured to be able to control and optimize the flow of electric power in the transmission grid 20 from both supply side and demand side by utilizing information technology through the communication network 40.
As illustrated in
As illustrated in
In the example shown in
The electricity storage devices 61 to 65 may include various types of electricity storage devices, such as stationary-type electricity storage devices and on-board batteries of electric vehicles that are connectable to the smart grid 10. The stationary-type electricity storage devices may also include home-use stationary-type electricity storage devices and large-scale electricity storage devices, for example.
In the example shown in
A factory A3 is equipped with a power generation device 52 that utilizes renewable energy, such as a solar panel, and a stationary-type electricity storage device 63. In the example shown in
For example, the resident of a residential house A1 may be an employee of the factory A3. In this case, it is possible that the resident of the residential house A1 commutes to the factory A3 by an electric vehicle 71. The electric vehicle 71 may be connected to the smart grid 10 at the residential house A1 and at the factory A3 as appropriate. For this reason, even on weekdays, the electric vehicle 71 is connected to the smart grid 10 most of the time during the time slot in which it is parked. The electric vehicles 71 to 73 may be connected to the smart grid 10 via a charging station 81 of charging spots A6 that are provided not only at residential houses and the workplaces but also at commercial facilities, tourist spots, and regional areas. Also, the charging spot A6 and the electric vehicles 71 to 73 may be configured to have a function of controlling charging from the smart grid 10 and discharging to the smart grid 10 appropriately. The charging from the smart grid 10 and the discharging to the smart grid 10 may be controlled by, for example, the resource aggregator 13.
A power generation operator A4 is equipped with a power generation device 54 installed with a large number of solar panels. The power generation operator A4 allows the electric power generated by the solar panels to be discharged to the smart grid 10. The power generation device of the power generation operator A4 is not limited to the solar power generation device but may be various types of power generation devices, such as wind power generation devices, biomass power generation devices, and small-sized hydroelectric power generation devices. The power generation operator A4 may be provided with an appropriate stationary-type electricity storage device 64. An electricity storage operator A5 is a business operator that prepares a large-scale electricity storage equipment 65 installed with a large number of electricity storage devices. In the embodiment shown in
The higher the total capacity of all the electrical storage devices connected to the smart grid 10 is, the higher the degree of flexibility in electricity storage. The total capacity of all the electrical storage devices connected to the smart grid 10 may be, for example, higher than or equal to an electricity storage capacity corresponding to the electric power required by the microgrid in half a day, more preferably higher than or equal to an electricity storage capacity required in two or three days, and still more preferably higher than or equal to an electricity storage capacity required in a week. Moreover, all the electrical storage devices may desirably be charged sufficiently. Furthermore, all the electrical storage devices connected to the smart grid 10 as a whole may have a sufficient available capacity relative to the amount of power that can be generated within the region of the microgrid. This increases the degree of flexibility in electricity storage and power transfer in the smart grid 10 and thereby improves user convenience. The smart grid 10 managed by the information processing apparatus 100 disclosed herein allows, for example, an electricity storage operator A5 as illustrated in
The information processing apparatus 100 for the smart grid 10 is an apparatus that processes information of the smart grid 10. The information processing apparatus 100 may be implemented by, for example, a computer that executes predetermined processes according to an embedded program. In the embodiment shown in
In addition to being used for self-consumption, the electric power generated by the power generation devices 51 to 55 connected to the smart grid 10 is stored in their own storage batteries and their own electric vehicles. When surplus electric power arises, the surplus electric power is supplied to the smart grid 10. The information processing apparatus 100 may be configured to execute an electricity selling process each time when this occurs. When a shortfall of electric power occurs, the electric power surplus electric power is supplied to the smart grid 10. The information processing apparatus 100 may be configured to execute an electricity purchasing process each time when this occurs.
For example, the user of the residential house A1 may store the electric power generated by the user's own power generation device 51 into an electricity storage device 61. It is also possible to supply the electric power generated by the user's own power generation device 51 to the smart grid 10. Each time when electric power is supplied to the smart grid 10, the electric power is sold to an electric power utility operator. The electric power supplied to the smart grid 10 is consumed through the smart grid 10 by a consumer connected to the smart grid 10. Each time when the consumer receives electric power from the smart grid 10, the consumer purchases electricity from the electric power utility operator.
On the other hand, the smart grid 10 is connected to the plurality of electricity storage devices 61 to 65. The plurality of electricity storage devices 61 to 65 may be configured so that the charging and discharging can be controlled, for example, according to an instruction from the resource aggregator 13. The present inventors believe that, in this type of smart grid 10, the user of the residential house A1 is able to store surplus electric power that occurs at the user's own house through the smart grid 10. For example, the surplus electric power of the user of the residential house A1 may be controlled so that the surplus electric power of the smart grid 10 can be stored through the smart grid 10 into the plurality of electricity storage devices 61 to 65 connected to the smart grid 10. In this case, when the electric power generated by the user's own power generation device 51 of the user of the residential house A1 is supplied to the smart grid 10, it is also possible to store the electric power into the plurality of electricity storage devices 61 to 65 connected to the smart grid 10 through the control by the resource aggregator 13.
This allows the user of the residential house A1 to store the electric power into the plurality of electricity storage devices 61 to 65 connected to the smart grid 10 when the electric power generated by the user's own power generation device 51 is supplied to the smart grid 10. Through the smart grid 10, the user can receive the electric power stored in the plurality of electricity storage devices 61 to 65 connected to the smart grid 10 at any time the user wishes. Such a control is made possible by the smart grid 10, which includes the transmission grid 20 and the communication network 40 and is controlled by information technology. In this case, the user is allowed to choose to store the surplus electric power into the smart grid 10 each time instead of being processed as a sale of electricity.
From such a viewpoint, the present inventors have conceived that the information processing apparatus 100 for the smart grid 10 is allowed to store a virtual electrical storage capacity that is defined as an amount of electric energy corresponding to the amount of electric energy in which a user is allowed to receive electric power from the smart grid 10, in association with the user. This allows the electric power discharged from the user to the smart grid 10 to be recorded as the electric power that is stored in the smart grid 10 or as the electric power that the user is allowed to receive from the smart grid 10. This means that the user is able to store surplus electric power through the smart grid 10. The stored electric power is recorded as a virtual electrical storage capacity corresponding to the amount of electric energy that the user is allowed to receive from the smart grid 10. Thus, by recording the virtual electrical storage capacity in association with the user in the information processing apparatus 100 for the smart grid 10, the information processing apparatus 100 is able to control the smart grid 10 so that the user can receive the corresponding amount of electric power according to the virtual electrical storage capacity stored in association with the user. This enables the user to store the electric power generated at the user's own house through the smart grid 10 and to use the stored electric power at any time, so that the user does not need to sell electricity each time.
In this embodiment, the processes executed by the information processing apparatus 100 include a first recording process m1, a depositing process m2, a withdrawal process m3, a transferring process m4, a purchasing process m5, a selling process m6, a price setting process m7, an exchange process m8, an exchange setting process m9, a capacity-data transmission process m10, a second recording process m11, and a sharing setting process m12. Each of the processes m1 to m12 is implemented by a process according to a program embedded in the information processing apparatus 100. It is to be understood that this description merely illustrates examples of the processes executed by the information processing apparatus 100, and that the processes executed by the information processing apparatus 100 are not limited to the examples illustrated herein.
The first recording process m1 is a process of recording virtual electrical storage capacities in association with respective users, each virtual electrical storage capacity corresponding to the amount of electric energy in which a corresponding user is allowed to receive from the smart grid 10. The virtual electrical storage capacity is a datum that can be handled by the information processing apparatus 100. The virtual electrical storage capacity is the amount of electric energy corresponding to the amount of electric energy in which a user is allowed to receive from the smart grid 10, which is recorded in the information processing apparatus 100 in association with the user. The virtual electrical storage capacity may also be considered as the right to receive the corresponding amount of electric energy from the smart grid 10. The virtual electrical storage capacity may also be considered as the amount of electric energy that the user has stored in the smart grid 10. The virtual electrical storage capacity may be considered as the amount of electric energy that the user has stored in the smart grid 10 and also considered as the right to receive the corresponding amount of electric energy through the smart grid 10. Note that it does not matter whether the amount of electric energy that is actually stored by the user through the smart grid 10 into the electricity storage devices 61 to 65 connected to the smart grid 10 matches the virtual electrical storage capacity that is recorded in the information processing apparatus 100 as information.
The information processing apparatus 100 may include a memory storage unit that stores virtual electrical storage capacities in association with users. Each of the users may be assigned an ID for identifying the user. Since the virtual electrical storage capacities are stored in association with the respective users in the information processing apparatus 100, the information processing apparatus 100 can handle each of the virtual electrical storage capacities as the amount of electric energy that a user can freely dispose of. In other words, in reality, the virtual electrical storage capacities may be data that can be handled by a computer.
Also in this embodiment, as illustrated in
Specifically, in the embodiment shown in
The information processing apparatus 100 may include a memory storage unit that stores information indicative of the power generation devices 51 to 55 connected to the smart grid 10 in association with the users.
The information processing apparatus 100 may include a memory storage unit that stores information indicative of the electricity storage devices 61 to 65 connectable to the smart grid 10 in association with the users.
The depositing process m2 is a process of increasing the virtual electrical storage capacity of a user according to the amount of electric energy that is output to the transmission grid 20 from an electrical equipment unit associated with the user. The electrical equipment units associated with the users may include, for example, the power generation devices 51 to 55, the electricity storage devices 61 to 65, the electric vehicles 71 to 73, and the like. It is possible to use a smart meter, for example, to measure the amount of electric energy that is output to the transmission grid 20 from the power generation devices 51 to 55, the electricity storage devices 61 to 65, and the electric vehicles 71 to 73, which serve as the electrical equipment units.
For example, in the depositing process m2, when electric power is output from one of the power generation devices 51 to 55 to the transmission grid 20, the power generation device from which electric power is output and the user thereof are identified. Then, the virtual electrical storage capacity of the corresponding user recorded in the first recording process m1 is increased according to the amount of electric energy that is output to the transmission grid 20 from the one of the power generation devices 51 to 55 (see
For example, as illustrated in
In this case, in the depositing process m2, the virtual electrical storage capacity is updated according to the following equation (f1).
Virtual Electrical Storage Capacity=Virtual Electrical Storage Capacity (0)+Discharged Electric Energy (f1)
Here, virtual electrical storage capacity (0) is the virtual electrical storage capacity before the depositing process m2, and discharged electric energy is the amount of electric energy that is discharged from the residential house A1 to the transmission grid 20 of the smart grid 10. For example, the depositing process m2 may be configured to increase the virtual electrical storage capacity of the user of the residential house A1 by 1 kWh when 1 kWh of electric power is discharged from the residential house A1 to the smart grid 10.
How much virtual electrical storage capacity should be increased according to the amount of electric energy in the depositing process m2 may be determined by simply adding the discharged electric energy, as in the foregoing equation (f1). The amount of the virtual electrical storage capacity to be increased in the depositing process m2 is not limited to being determined by the equation (f1) but may be set to a predetermined amount. For example, the depositing process m2 may be configured to increase the virtual electrical storage capacity by increasing or decreasing a predetermined proportion of the amount of electric energy that is output to the transmission grid 20 from one of the power generation devices 51 to 55 associated with a user. In other words, there may be a difference between the amount of electric energy that is output to the smart grid 10 and the amount of the virtual electrical storage capacity to be increased. For example, taking power transmission loss into account, the virtual electrical storage capacity to be increased may be reduced relative to the amount of electric energy that is output from a user to the smart grid 10.
For example, in the case where electric power supply and demand are tight, the tightness of electric power supply in the smart grid 10 is alleviated when electric power stored in an electricity storage device 61 or the like in the residential house A1 is discharged to the smart grid 10. Accordingly, the depositing process m2 may be configured to increase the virtual electrical storage capacity by adding a predetermined amount to the amount of electric energy that is output from the electricity storage device 61 to the smart grid 10. In this case, for example, in the case of adding 5% of the amount of electric energy that is output from the electricity storage device 61 to the smart grid 10, the depositing process m2 may be configured to increase the virtual electrical storage capacity by 1.05 kWh when 1 kWh of electric power is output from the electricity storage device 61 to the smart grid 10. This serves to alleviate the tightness of electric power supply in the smart grid 10 and also provides the user with an advantage of storing the virtual electrical storage capacity more efficiently. In addition, in the case where the smart grid 10 has a surplus of electric power, for example, the tightness of electric power supply is alleviated when the electric power stored in an electricity storage device or the like in the residential house A1 is discharged to the smart grid 10. In this way, adjusting the amount of the virtual electrical storage capacity to be increased in the depositing process m2 may be used to adjust the supply and demand of electric power.
In addition, the depositing process m2 may be configured to deduct a predetermined amount corresponding to a commission fee from the virtual electrical storage capacity. The amount corresponding to the commission fee may be set freely, and may be predetermined in the information processing apparatus 100. For example, a predetermined proportion of the amount of electric energy that is output from an electrical equipment unit of the user to the smart grid 10 may be deducted, as the amount corresponding to the commission fee, from the virtual electrical storage capacity to be added. As a specific example, in the case of deducting 5% of the amount of electric energy that is output from the power generation device 51 to the smart grid 10, the depositing process m2 may be configured to increase the virtual electrical storage capacity by 0.95 kWh when 1 kWh of electric power is output from the power generation device 51 to the smart grid 10. Thus, by deducting the amount corresponding to the commission fee for the service of using the virtual electrical storage capacity from the virtual electrical storage capacity, the commission fee for the service of using the virtual electrical storage capacity can be cleared off by the virtual electrical storage capacity. This makes it possible to eliminate or reduce the process of clearing off the commission fee for the service of using the virtual electrical storage capacity with the use of money or points.
The withdrawal process m3 is a process of reducing the virtual electrical storage capacity of a user according to the amount of electric energy received by the user from the transmission grid 20.
In the withdrawal process m3, when a user receives electric power from the transmission grid 20, the user is identified from the device with which the user receives electric power. For example, when electric power is received and consumed from the transmission grid 20 at the residential house A1, the user is identified from a smart meter installed on the residential house A1. Likewise, when an electric vehicle is charged at a charging spot A6 in a city, the user is identified by acquiring an electric vehicle ID from the electric vehicle. Then, the virtual electrical storage capacity of the user recorded in the first recording process m1 is reduced according to the amount of electric energy that received by the user from the transmission grid 20 (see
For example, as illustrated in
The withdrawal process m3 may predetermine how much virtual electrical storage capacity should be reduced according to the amount of electric energy that is received by a user. For example, the withdrawal process m3 may be configured to reduce the virtual electrical storage capacity by the same amount as the amount of electric energy received by the user from the smart grid 10.
In this case, the withdrawal process m3 updates the virtual electrical storage capacity, for example, according to the following equation (12).
Virtual Electrical Storage Capacity=Virtual Electrical Storage Capacity (0)−Received Electric Energy (f2)
Here, virtual electrical storage capacity (0) is the virtual electrical storage capacity before the withdrawal process m3, and received electric energy is the amount of electric energy received by the user from the smart grid 10. For example, when a user receives 1 kWh of electric power from the smart grid 10 through a charging station at a charging spot A6 in a city, the withdrawal process m3 may be configured to reduce the virtual electrical storage capacity of the corresponding user by 1 kWh. Thus, an equivalent amount of virtual electrical storage capacity is reduced by the withdrawal process m3 for the virtual electrical storage capacity when electric power is received from the smart grid 10, but the cash asset of the user is not directly reduced.
How much virtual electrical storage capacity should be reduced according to the amount of electric energy in the withdrawal process m3 may be determined by simply subtracting the received electric energy, as specified by the foregoing equation (f2). The amount of the virtual electrical storage capacity to be reduced in the withdrawal process m3 is not limited to being determined by the equation (f2) but may be set to a predetermined amount. For example, the withdrawal process m3 may be configured to reduce the virtual electrical storage capacity by increasing or decreasing a predetermined proportion of the amount of electric energy that is output to the transmission grid 20 from one of the power generation devices 51 to 55 associated with a user. In other words, there may be a difference between the amount of electric energy that is supplied from the smart grid 10 and the amount of the virtual electrical storage capacity to be reduced. For example, taking power transmission loss into account, the virtual electrical storage capacity to be reduced may be increased relative to the amount of electric energy supplied from the smart grid 10 to the user.
In the case where electric power supply and demand are tight, the tightness of electric power supply in the smart grid 10 is alleviated by reducing the amount of discharging from the smart grid 10. In this case, it is desired to reduce the amount of discharging from the smart grid 10. For this reason, in the case where the electric power supply and demand are tight, the withdrawal process m3 may be configured to reduce the virtual electrical storage capacity by adding an extra amount of electric power corresponding to the tightness of electric power supply and demand to the amount of electric energy received from the smart grid 10. In this case, for example, in the case of adding 5% of the amount of electric energy that has been received from the smart grid 10, the withdrawal process m3 may be configured to reduce the virtual electrical storage capacity by 1.05 kWh when 1 kWh of electric power is received from the smart grid 10. This allows the user to be prompted to reduce electric power consumption and enables the smart grid 10 to alleviate the tightness in electric power supply. In addition, in such a case where the smart grid 10 has a surplus of electric power and the electricity storage devices 61 to 65 connected to the smart grid 10 have a low available capacity, it is possible to reduce the amount of electric energy for reducing the virtual electrical storage capacity relative to the amount of electric energy received from the smart grid 10. This allows the user to be prompted to increase electric power consumption. In this way, adjusting the amount of the virtual electrical storage capacity to be reduced in the withdrawal process m3 may be used to adjust the supply and demand of electric power.
In addition, the withdrawal process m3 may be configured to deduct a predetermined amount corresponding to a commission fee from the virtual electrical storage capacity. It is possible to set the amount corresponding to the commission fee freely. For example, a predetermined proportion of the amount of electric energy that has been received by a user from the smart grid 10 may be added, as the amount corresponding to the commission fee, to the amount of the virtual electrical storage capacity to be reduced. As a specific example, in the case where the amount corresponding to the commission fee is set to 5% of the amount of electric energy that the user has received from the smart grid 10, the withdrawal process m3 may be configured to reduce the virtual electrical storage capacity by 1.05 kWh when the user receives 1 kWh of electric power from the smart grid 10. In this case as well, by deducting the amount corresponding to the commission fee for the service of using the virtual electrical storage capacity from the virtual electrical storage capacity, the commission fee for the service of using the virtual electrical storage capacity can be cleared off by the virtual electrical storage capacity. This makes it possible to eliminate or reduce the process of clearing off the commission fee for the service of using the virtual electrical storage capacity with the use of money or points.
The system of using the virtual electrical storage capacity provided by this information processing apparatus 100 may be operated by, for example, an electric power utility operator or a resource aggregator as the operator. The commission fee for using the system and service of using the virtual electrical storage capacity may be billed monthly or yearly at a flat rate from the operator to the user who uses the system of using the virtual electrical storage capacity provided by this information processing apparatus 100. In this case, it is unnecessary to set the amount of commission fee every time the depositing process m2 or the withdrawal process m3 is performed. The system of using the virtual electrical storage capacity provided by this information processing apparatus 100 may be offered to users without charging fees. The system of using the virtual electrical storage capacity serves to reduce the processes and administrative burden that involves monetary exchange resulting from the sales and purchases of electricity by the users. Accordingly, it is expected that the system of using the virtual electrical storage capacity will become widely available if the system is offered to users without charging fees corresponding to such an administrative burden, for example, for free.
As described above, the information processing apparatus 100 disclosed herein executes a first recording process m1 of recording a virtual electrical storage capacity in association with a user, a depositing process m2, and a withdrawal process m3. The first recording process m1 involves recording a virtual electrical storage capacity in association with a user. The depositing process m2 involves increasing the virtual electrical storage capacity of the corresponding user according to the amount of electric energy that is output to the transmission grid 20 from an electrical equipment unit associated with the user. The withdrawal process m3 involves reducing the virtual electrical storage capacity of the corresponding user according to the amount of electric energy that has been used by the user from the transmission grid 20. This allows the user to store generated electric power in the smart grid 10 in the form of virtual electrical storage capacity and to receive electric power through the smart grid 10 using the virtual electrical storage capacity.
The virtual electrical storage capacity recorded in the first recording process m1 may also be treated as the amount of electric energy that is actually stored in the electricity storage devices 61 to 65 connected to the smart grid 10. The user is allowed to receive electric power through the smart grid 10 according to the amount of electric energy of the virtual electrical storage capacity. In addition, the virtual electrical storage capacity is the amount of electric energy that is considered as the electric power that can be virtually disposed of freely by the user. Also, the virtual electrical storage capacity may be the electric power that can be virtually disposed of freely by the user.
In the depositing process m2, the user is, for example, allowed to virtually store the electric power generated in the residential house A1 as the virtual electrical storage capacity in the smart grid 10, without selling the electric power as surplus electric power. In the withdrawal process m3, the user is allowed to use the electric power stored as the virtual electrical storage capacity through the smart grid 10 at any desired location and at any desired time. Therefore, the user does not need to purchase electricity each time when the user receives electric power from the smart grid 10, as long as a sufficient virtual electrical storage capacity has been stored.
As a result, for example, as long as sufficient electricity storage devices are connected to the smart grid 10 so as to be able to accept surplus electric power from the residential house A1, surplus electric power can be stored in the smart grid 10 as a virtual electrical storage capacity even when the residential house A1 is not provided with a stationary-type electricity storage device. This means that, by storing surplus electric power as the virtual electrical storage capacity in the smart grid 10, it is possible to obtain a condition similar to that in which there is a stationary-type electricity storage device in the residential house A1 even when the residential house A1 is not provided with a stationary-type electricity storage device. As a result, the user of the residential house A1 can reduce the capacity of the stationary-type electricity storage device or altogether eliminate the installation of the stationary-type electricity storage device, for example, to reduce the cost to be spent on the stationary-type electricity storage device.
Moreover, when the user possesses an electric vehicle that is connectable to the smart grid 10, the user is able to use the virtual electrical storage capacity to feed electric power to the electric vehicle at any desired location through the smart grid 10. In this case, as illustrated in
Thus, by using the virtual electrical storage capacity achieved by the information processing apparatus 100 proposed herein, the user is able to virtually store the electric power generated at his/her own house in the smart grid 10. The user is allowed to receive the electric power that is virtually stored in the smart grid 10 in the form of virtual electrical storage capacity through the smart grid 10 when a shortage of electric power occurs in the residential house A1. The user is also allowed to receive electric power from the smart grid 10 to an electric vehicle using the virtual electrical storage capacity even at a travel destination.
Thus, the virtual electrical storage capacity may also be considered as the right to receive a corresponding amount of electric energy from the smart grid 10. In other words, the virtual electrical storage capacity may be considered as the amount of electric energy that the user has stored in the smart grid 10 and also considered as the right to receive the corresponding amount of electric energy through the smart grid 10. For example, when the user is a resident of the residential house A1 equipped with solar panels and goes out for a trip to a distant location on a weekend using the electric vehicle 71, the electric power generated by the solar panels is stored as a virtual electrical storage capacity through the smart grid 10. Since the virtual electrical storage capacity is the right to receive a corresponding amount of electric power through the smart grid 10, the user is allowed to receive electric power from the smart grid 10 using the stored virtual electrical storage capacity when the user connects the electric vehicle to the smart grid 10 at a charging spot at the travel destination. At that time, a process is performed to reduce the virtual electrical storage capacity of the user according to the amount of electric energy that has been received by the user. In such a way, the user is able to virtually store the electric power generated at the user's own house into the smart grid 10 and to receive electric power at any desired time and at any desired location. As a result, by storing the electric power generated at the residential house A1 into the smart grid 10 as a virtual electrical storage capacity, the user of the residential house A1 is allowed to maximally use the electric power generated at the user's own house without leaving a surplus of electric power.
The user is not limited to the level of individual person. For example, a solar panel power generation operator may be able to store a virtual electrical storage capacity by using the virtual electrical storage capacity when discharging electric power to the smart grid 10. When the solar panel power generation operator needs to use electric power for another business operation, the power generation operator is able to receive electric power from the smart grid 10 using the virtual electrical storage capacity that has been stored by the solar panel power generation. Thus, the user may be at the level of juristic person. Accordingly, large-scale consumers that also conduct a power generation business or the like may also be employed as users, and the virtual electrical storage capacity is managed in a centralized manner so that the amount of electric power used can be cleared off by the virtual electrical storage capacity. A juristic person user may store the electric power generated by a power generation business into the smart grid 10 and consume the electric power for another business operation. Thus, the user is not limited to the level of individual person. When, as described above, electric power is received from the smart grid 10 through the withdrawal process m3 using the virtual electrical storage capacity, not through sales of electricity or purchases of electricity, for example, the information processing apparatus 100 may be configured to communicate with a control terminal of the user and execute a predetermined process in cooperation with the control terminal of the user. When this is the case, the electric power utility operator also uses electric power through the virtual electrical storage capacity, which reduces the processes of paying money to users according to the sales of electricity by the users and receiving money according to the purchases of electricity by the users. This reduces administrative burden that accompanies monetary exchange in comparison with the cases where interchange of electric power is processed each time by sales of electricity and purchases of electricity.
The information processing apparatus 100 may be configured to be able to perform various processes, such as transferring, purchasing, and selling processes of the virtual electrical storage capacity. In these processes, the information processing apparatus 100 may be configured to communicate with a control terminal of the user and execute a predetermined process in cooperation with the control terminal of the user. The control terminal of the user may be a personal computer, a smartphone, or the like, for example. The control terminal of the user may be a control terminal for HEMS or the like installed for monitoring the interchange of electric power with a smart meter. The information processing apparatus 100 may be configured to be provided with a dedicated web site so that predetermined information can be input through the web site. Alternatively, the information processing apparatus 100 may be configured to include dedicated software embedded in a personal computer or a smartphone so that predetermined information can be input through the processes of the software. For example, the information processing apparatus 100 may be configured to communicate with a personal computer or a smartphone and cause a control terminal of the user to display a control screen panel for executing various processes so that necessary information can be input therein. The information processing apparatus 100 may be configured to be able to obtain information necessary for the processes of transferring, purchasing, and selling of the virtual electrical storage capacity through these control terminals of users.
The transferring process m4 is a process of transferring the virtual electrical storage capacity between users. For example, as illustrated in
In this case, the virtual electrical storage capacity of the transferor user A4 may be reduced by an amount corresponding to the transfer capacity, and the virtual electrical storage capacity of the transferee user A3 may be increased by the amount corresponding to the transfer capacity. As described above, the virtual electrical storage capacity can be transferred between users. This allows electric power to be interchanged between the users by the process of transferring the virtual electrical storage capacity, not by the sales or purchases of electricity. That is, the user who has received the transfer of the virtual electrical storage capacity can receive an amount of electric power corresponding to the transferred virtual electrical storage capacity through the smart grid 10. The transferring process m4 enables transferring and leasing of the virtual electrical storage capacity without transferring money between the users. Although the virtual electrical storage capacity is transferred in this case, the actual electric power is interchanged through the smart grid 10. For this reason, it is unnecessary to actually transfer the electric power corresponding to the transferred amount between the electricity storage devices of the users.
The purchasing process m5 is a process of purchasing the virtual electrical storage capacity of a user. The purchasing process m5 includes an embodiment in which the user purchases the virtual electrical storage capacity from an electric power utility operator, for example, and an embodiment in which the user purchases the virtual electrical storage capacity from another user. Note that, if the electric power utility operator is considered as one of the users, both embodiments may be implemented by the same process.
Here, the monetary balances managed by the information processing apparatus 100 may be managed as the record of monetary values each time. For example, the operator that offers the system or service of using the virtual electrical storage capacity does not need to produce monetary exchange between the users each time. The purchasing process m5 may also be configured to exchange the monetary balance as appropriate for commercially usable points that are given to the user. The purchasing process m5 may also be configured to allow the user to check the monetary balance as necessary and allow the user to request a money transfer into a bank account actually owned by the user or request an exchange process for points. The purchasing process m5 may be configured to allow the operator that offers the system and service of using the virtual electrical storage capacity to execute a money transfer process or an exchange for points through a payment handling operator such as a bank or a credit card company. When the purchasing process m5 is configured to allow the operator to execute a money transfer process or an exchange for points through a payment handling operator, the operator does not need to directly hold or manage the information of bank accounts and credit cards of the users.
In the purchasing process m52, the user A3 purchases the virtual electrical storage capacity from the user A4. In this case, the information processing apparatus 100 determines the seller to be the user A4 and identifies a purchaser user A3, a purchase amount g3, and a purchase price g4. The information necessary for the purchasing process may be obtained through, for example, the control terminal of the user A3. In the purchasing process m52, the virtual electrical storage capacity of the user A3 may be increased and the virtual electrical storage capacity of the user A4 may be reduced according to the purchase amount g3. On the other hand, the monetary balance of the user A3 may be reduced and the monetary balance of the user A4 may be increased according to the purchase price g4. In this way, the purchasing process m5 may transfer the virtual electrical storage capacity between the vendor and the purchaser according to the purchase amount and also transfer the monetary balance between the vendor and the purchaser according to the purchase price. The information necessary for such a purchasing process m5 may be processed according to the input from, for example, the control terminal of the user that is a purchaser. For example, the information necessary for the selling process m51 may be obtained through the control terminal of the user A1 that is a purchaser. For example, the information necessary for the selling process m52 may be obtained through the control terminal of the user A3 that is a purchaser.
The selling process m6 is a process of selling the virtual electrical storage capacity of a user.
For example, as illustrated in
The price setting process m7 is a process of setting a price per unit amount of the virtual electrical storage capacity. The price setting process m7 sets, for example, a distribution price applied when the virtual electrical storage capacity is traded between users.
For example, the service provider of the smart grid 10 may also serve as an electricity storage operator A5 equipped with a large-scale electricity storage equipment 65 that has sufficient capability of storing electric power discharged to the smart grid 10. In addition, according to contract agreements with users, the service provider of the smart grid 10 may be configured to make use of the available capacity of the electricity storage devices 61 to 65 of the users. In this case as well, the service provider of the smart grid 10 may also have sufficient capability of storing electric power discharged to the smart grid 10. In this case, the service provider of the smart grid 10 may adjust the amount of electric energy supplied to smart grid 10 by the electricity storage device 65 appropriately. The service provider of the smart grid 10 can set the price per unit amount of the virtual electrical storage capacity that serves as the reference appropriately in the information processing apparatus 100. The price set here may serve as the reference price per unit amount of the virtual electrical storage capacity because it may be widely made available to users. The resource aggregator 13 can control the smart grid 10 to adjust the electric power supply and demand. Accordingly, the resource aggregator 13 may serve the role of such a service provider of the smart grid 10.
Moreover, by means of the price setting process m7, for example, the electric power utility operator A0 can set the price per unit amount of the virtual electrical storage capacity that is applied when trading the virtual electrical storage capacity between users. The power generation operator A4 with solar panels can set the price per unit amount for selling of the virtual electrical storage capacity. The factory operator A3 can set the price per unit amount for purchasing of the virtual electrical storage capacity. These prices may be made public on a web site that is open to users that are allowed to trade (sell and buy) the virtual electrical storage capacity, or on a closed web site between specific users. This is expected to promote trading of the virtual electrical storage capacity between users.
In this case, a restrictive condition under which a user is allowed to receive electric power from the smart grid may be specified for the virtual electrical storage capacity. When it is possible to specify restrictive conditions under which a user is allowed to receive electric power from the smart grid, the solar panel power generation operator A4 is able to sell a virtual electrical storage capacity provided with a restrictive condition under which electric power can be received from the smart grid. For example, the solar panel power generation operator A4 generates a large amount of power on a sunny day. However, if there is no business operator that uses the electric power, the power generation operator A4 may in some cases be forced to stop the power generation due to demand response. In such a circumstance, the solar panel power generation operator A4 may sell, at a low price, a virtual electrical storage capacity with a restrictive condition under which electric power is allowed to be received from the smart grid according to a peak time slot of the electric power generated by the solar panel power generation operator A4.
The electricity storage operator A5 may purchase such a low-price virtual electrical storage capacity to prompt the solar panel power generation operator to generate power, and may store the electric power into the electricity storage device 65 through the smart grid 10. The factory operator A3 is allowed to procure electric power at low cost, for example, when the factory is desired to increase the production. It is also possible to set the price of the virtual electrical storage capacity to be purchased concurrently with the time when the factory is desired to increase the production, to invite a power generation operator selling the virtual electrical storage capacity that is usable at that time, and to purchase the virtual electrical storage capacity that is usable at that time in advance. This means that, even in such cases where electric power supply becomes tight at a time when the factory needs to increase the production but the amount of electric energy to be used should be reduced due to a request from demand response, it is possible to obtain a virtual electrical storage capacity that can be used at that time and to thereby control the smart grid 10 to receive sufficient electric power preferentially.
From such a viewpoint, the virtual electrical storage capacity may be provided with a restrictive condition under which a user is allowed to receive electric power from the smart grid.
Thus, the price setting process m7 may be configured to, for example, store prices per unit amount of the virtual electrical storage capacity within a predetermined memory storage area of the information processing apparatus 100. The price setting process m7 may also be provided with the function of making the prices public between users that are able to trade (buy and sell) the virtual electrical storage capacity. Where the prices are made public may be a web site that is widely open to users or a closed web site that is made public between specific users.
In this case, for example, the price of the virtual electrical storage capacity may vary in association with the tightness of electric power supply and demand of the smart grid 10 that is managed by the resource aggregator 13. The price setting may be carried out in response to an electric power supply instruction from the aggregation coordinator 11. In the case of trading between users, the price per unit amount of the virtual electrical storage capacity may be set differently from, for example, the prices for sales of electricity or the purchases of electricity. Although the virtual electrical storage capacity is the right to receive electric power from the smart grid 10, it is possible to place a restriction on when to enforce the right. For example, the price of the virtual electrical storage capacity may be set for each of the restrictive conditions so that the price of the virtual electrical storage capacity varies depending on different time periods, such as time slots, times and dates, and days of the week, in which the user is allowed to receive electric power from the smart grid 10.
The exchange process m8 is a process of exchanging the virtual electrical storage capacity for a predetermined commercially usable point. The exchange setting process m9 is a process of setting a number of points to be exchanged per unit of the virtual electrical storage capacity. Such an exchange process allows the virtual electrical storage capacity to be exchanged for commercially usable points. The exchange setting process m9 is a process of setting a number of points to be exchanged per unit of the virtual electrical storage capacity. In the exchanging for points as well, it is possible to set a reference exchange rate and to set an exchange rate for user-to-user trading, similar to the price setting for the virtual electrical storage capacity. In addition, the virtual electrical storage capacity to be exchanged may be provided with a restrictive condition under which a user is allowed to receive electric power from the smart grid 10. In the first recording process m1, point balances may be recorded in association with user IDs, as shown in
The capacity-data transmission process m10 is a process of transmitting the virtual electrical storage capacity of a user to a predetermined terminal of the user. This allows the user to know the virtual electrical storage capacity. The information processing apparatus 100 may allow the user to check the virtual electrical storage capacity of the user, for example, through a web site to which the user can access with a terminal. The information processing apparatus 100 may periodically transmit information of the virtual electrical storage capacity to a pre-registered mail address of the user.
As described above, the virtual electrical storage capacity may be increased not only by outputting electric power to the transmission grid 20 of the smart grid 10 but also by transferring or purchasing of the virtual electrical storage capacity. For this reason, the depositing process m2 may not always be performed. Basically, the virtual electrical storage capacity reduces when electric power is received from the transmission grid 20 of the smartgrid 10. However, power generation operators, individuals installed with a large number of solar panels, and the like output electric power to the transmission grid 20 of the smart grid 10 in many cases, so they tend to obtain virtual electrical storage capacity through the depositing process m2 more easily. These kinds of users may dispose of the virtual electrical storage capacity by selling the virtual electrical storage capacity or exchanging it for points. Thus, because the virtual electrical storage capacity corresponding to the amount of electric energy in which a user is allowed to receive from the smart grid is set in association with the user, it is possible to achieve electricity trading with a higher degree of freedom and to improve user convenience in utilizing electric power.
The smart grid 10 is, as illustrated in
In this case, as illustrated in
For example, in the embodiment shown in
The sharing setting process m12 is a process of setting a portion of an electricity storage capacity of an electricity storage device connected to the smart grid to be available for sharing with a user connected to the smart grid. When employing such a sharing setting process m12, the sharing setting process m12 allows a portion of the electricity storage capacity of the electricity storage device to be used by an arbitrary user participating in the smart grid 10.
The information processing apparatus 100 may disclose the information of electricity storage capacities that are made available to participants of the smart grid 10 through the smart grid 10, on a dedicated web site or the like to the users participating the smart grid 10. Based on the disclosed information, the user participating the smart grid 10 may execute a process of storing generated electric power into the electricity storage capacity that is set for sharing. In such a process, the information processing apparatus 100 identifies the user ID in response to a control operation of the user and also causes an electrical equipment unit of the corresponding user identified by the user ID to discharge electric power to the smart grid 10. Then, the corresponding amount of electric power may be stored into the electricity storage capacity that is made available for sharing through the smart grid 10. Taking power transmission loss or the like into account, the amount of electric energy that is stored in the electricity storage capacity made available for sharing may be smaller than the amount of electric energy discharged from the electrical equipment unit of the user to the smart grid 10.
In the embodiment shown in
In the example shown in
In addition, blockchain technology, for example, may be used for the trade records of the depositing process m2, the withdrawal process m3, the transferring process m4, the purchasing process m5, the exchange process m8, and so forth of the virtual electrical storage capacity, the allocated capacity allocated to users, the monetary balance, the point balance, and the like in the information processing apparatus 100.
The system utilizing the virtual electrical storage capacity as described above records the amount of electric energy that each of the users can receive from the transmission grid 20 of the smart grid 10 in the information processing apparatus 100 as the virtual electrical storage capacity. In this case, a surplus of the electric power generated by the power generation devices 51 to 55 connected to the smart grid 10 is output to the smart grid 10 and is also recorded as the electric power that each of the users is allowed to receive from the transmission grid 20 of the smart grid 10 in association with the corresponding users. Irrespective of time and location, the user is allowed to receive electric power according to the virtual electrical storage capacity from the smart grid 10 at any desired time and at any desired location. When such a system of virtual electrical storage capacity is used by all the users participating in the smart grid 10, generated electric power are interchanged or rented between users in the user community connected by the smart grid 10. Moreover, the second recording process m11 and the sharing setting process m12 allow interchange of the electricity storage functions of the electricity storage devices 61 to 65 connected to the smart grid 10 between users. This makes it possible to fully utilize the functions of the power generation devices 51 to 55 and the electricity storage devices 61 to 65 connected to the smart grid 10. This is expected to allow the electric power generated in the user community to be consumed within the community more efficiently. It is possible to maximize self-generation and self-consumption.
Currently, in such a smart grid 10, electric power is purchased through the smart grid 10 each time when there is a shortfall of electric power. On the other hand, electric power is sold through the smart grid 10 each time when there is a surplus of electric power. In cases where storage batteries are provided, it is also possible that electric power may be stored in the storage battery when there is a surplus of electric power. The present inventors believe that, for such a smart grid 10, the electric power that is stored as surplus electric power can be made available as the electric power that is usable by other parties through the transmission grid 20 in addition to being used for self-consumption. With this in mind, it is possible to make available the electric power that is stored as surplus electric power to other parties through the transmission grid 20 after further identifying the provider and the receiver within the smart grid 10.
The electric power trade supporting device 120 includes a memory storage unit 120a.
The memory storage unit 120a records each of user profiles. The memory storage unit 120a is provided, for example, in the information processing apparatus 100. Respective user IDs may be assigned to a plurality of users of the smart grid 10. The users may be individuals, corporations, or organizations. Herein, each of the user IDs is computer-readable information for identifying a user. Each of user profiles is information on features of a user. The information to be included in the user profile may be determined in advance. The user profile may include, for example, name, affiliation, address (location if the user is a corporation), bank account, and so forth of the user. The user profile may be associated with user IDs assigned to the user and stored in the memory storage unit 120a of the electric power trade supporting device 120. The user profile may be recorded, for example, when the user uses a service provided by the electric power trade supporting device 120 for the first time. The process in which the user profile is recorded in the memory storage unit 120a of the electric power trade supporting device 120 is referred to as user registration. Table 1 relates to the memory storage unit 120a and shows an example of a table that records data. Note that the electric power trade supporting device 120 includes a memory storage unit that stores other information, not just the memory storage unit 120a. Examples of the other information stored by the electric power trade supporting device 120 include user communication records as well as electric power profiles and electric power demand profile, which will be discussed later.
The electric power trade support device 120 is configured to execute the following processes S1a to S1g.
The electric power profile is the profile of the electric power that can be supplied by the user U1. Herein, the electric power that can be supplied by the user U1 may be the electric power that can be supplied to the smart grid 10 by the user U1. For example, the electric power that can be supplied by the user U1 may be electric power that is generated by a power generating facility owned by user U1, stored in a storage battery, and is suppliable to the smart grid 10. The electric power that can be supplied by the user U1 is not limited to the electric power that is generated by a power generating facility owned by user U1 and stored in a storage battery. For example, the electric power that can be supplied by the user U1 may include electric power that is purchased through the smart grid 10 by the user U1 and is stored in an electricity storage facility exclusively owned by the user U1 through the smart grid 10. In this respect, the amount of electric energy that can be supplied by the user U1 may be the above-described virtual electrical storage capacity. The electricity storage facility exclusively owned by the user U1 is, for example, an electricity storage facility owned by the user U1. The electricity storage facility is not limited to the electricity storage facility exclusively owned by the user U1 but may include an electricity storage facility that is available to the smart grid 10 through the smart grid 10. For example, when a large-scale electricity storage facility of the smart grid 10 includes electricity storage facilities that are available to the participants of the smart grid 10 through the smart grid 10, a portion of the electricity storage facilities that is allocated to the user U1 may be regarded as the electricity storage facility exclusively owned by the user U1.
On the other hand, users G to J do not possess their own electricity storage devices. However, the users G to J are provided with dedicated allocated capacities g3 to j3 in the electricity storage device 65 of the electricity storage operator A5. Therefore, although the users G to J do not possess their own electricity storage devices, the users G to J are able to store a surplus of electric power generated at their homes in the electricity storage device 65 of the electricity storage operator A5. This enables the electric power of the users G to J that is stored in the electricity storage device 65 of the electricity storage operator A5 to serve as the electric power that can be supplied by the users A to F.
Thus, a plurality of users A to J exemplified in
The electric power profile is information that records the characteristics of electric power that the user U1 is able to supply. The electric power profile may be information that identifies, for example, the user U1 who supplies electric power, the means of power generation generating the electric power that the user U1 is able to supply, the location of power generation generating the electric power that the user U1 is able to supply, and the like. The smart grid 10 may include a memory storage unit that records an electric power profile of the electric power that the user U1 is able to supply. Table 2 is an example of a table for storing the electric power profile. The table shown as Table 2 is configured to be able to record, for each electric power profile, an electric power profile ID, an amount of electric energy, a user ID, a means of power generation, a location of power generation, a power generating facility ID, date and time of supply, a price, a region, and affiliation (attribute). The types of information to be contained in the electric power profile are not limited to those listed in Table 2.
Herein, the electric power profile IDs are identifiers that are assigned to distinguish various types of electric power that the users are able to supply. The user IDs are identifiers that are assigned to distinguish various users. The power generating facility IDs are identifiers that are assigned to distinguish various power generating facilities.
The electric power profile may be stored, for example, in a computer connected to the communication network 40 of the smart grid 10 such that each electric power that the user U1 is able to supply is associated with such information as an amount of electric energy, a means of power generation, and a location of power generation. In the case of the above-described virtual electrical storage capacity, the electric power profile may be stored in association with such information as a means of power generation and a location of power generation, for each of the amounts of electric energy. For example, the following describes a case in which a user owns a solar power generation facility and a wind power generation facility, each of which stores electricity in a common electricity storage facility. In this case, the amount of electric energy stored in the electricity storage facility is stored in association with such information as means of power generation and location of power generation. Therefore, with the electric power profile associated with the amount of stored electric energy in the electricity storage facility, it is possible to distinguish between the amount of electric energy generated by a solar power generation facility and the amount of electric energy generated by a wind power generation facility.
For example, in the example shown in
The electric power profile may be, for example, information associated with such information as means of power generation and location of power generation for each of predetermined unit amounts of electric energy. It is also possible that the amount of electric energy to be recorded in the electric power profile may be calculated from the proportion thereof relative to the electric power capable of being supplied by the user A.
For example, referring to
For example, it is possible that the recorded information may be as follows: an electric power of 100 kW h is stored in the electricity storage device 61; 60% thereof (60 kW·h) is the electric power generated by the solar power generation, 20% thereof (20 kW·h) is the electric power generated by the wind power generation, and 20% thereof (20 kW·h) is the electric power stored by the fuel cell. Although the details are discussed later, there is a case in which electric power generated by solar power generation is requested and output to the smart grid 10 as the electric power generated by solar power generation. In this case, calculation may be made such that the proportion of the electric power generated by solar power generation is reduced according to the amount of the electric energy that has been output. For example, assume that, of the electric power stored in the electricity storage device 61, an electric power of 20 kW·h is output to the solar power generation as the electricity storage device 61 as electric power generated by solar power generation. In this case, it follows that, of the remaining electric power 80 kW·h stored in the electricity storage device 61, 50% (40 kW·h) is the electric power generated by the solar power generation, 25% (20 kW h) is the electric power generated by the wind power generation, and 25% (20 kW h) is the electric power generated by the fuel cell. Thus, the proportions of the electric power generated by a means of power generation and a location of power generation out of the electric power that is suppliable by the user A may be recorded in association with such information as the means of power generation and the location of power generation. Then, the just-mentioned proportions of the electric power may be used as a basis to derive the amounts of the electric energy associated with such information as the means of power generation and the location of power generation out of the electric power that can be supplied by the user A.
Although an example of the electric power profile has been illustrated herein, the electric power profile is not limited to such an example. The electric power profile may include, for example, at least one of an amount of the electric energy that the user is able to supply, power source information of the electric power to be supplied, and a supply condition. Herein, the power source information of the electric power to be supplied may be information concerning the power generating facility. The supply condition is a condition that is applied when the user supplies suppliable electric power.
The supply condition may include, for example, the date and time of supply, the price, the region to be supplied with electric power, and the affiliation or attribute of the recipient of electric power. The region to be supplied with electric power may be limited to a region or distribution grid, for example, within the microgrid to which the user belongs or within the microgrid provided by the resource aggregator 13. The price may be varied by the region or the date and time. For example, it is possible to increase the price step by step as the power transmission path becomes longer. As for the date and time at which electric power is to be supplied, the compensation rate may be set higher when the electric power demand is higher while the compensation rate may be set lower when the amount of power generated is higher. Also, if the conditions are met, it is possible to set such a condition that electric power can be supplied free of charge.
For the affiliation or attribute of the recipient of the electric power, it is possible to record, for example, such information that indicates what kind of entity the recipient of the electric power is. When the recipient is a business operator, such information that can identify the types of business or the contents of business may be recorded for the affiliation or attribute. Thus, as the conditions required for supplying the electric power that can be supplied by the user, it is possible to set conditions concerning the recipient of supply of electric power. That is, the conditions required for the counterparty to which electric power is to be supplied are recorded in the electric power profile so that the recipient of supply of the electric power can be limited. For example, when the user wishes to supply the suppliable electric power to a rice producer, the electric power profile may record that the affiliation or attribute of the recipient of supply is to be a rice producer. This enables the user to limit the recipient of supply of the electric power to rice producers. The affiliation or attribute is not limited to rice producers but may be other affiliations or attributes, such as farming, factory, school, and hospital. It is also possible that a plurality of types of business may be registered in the affiliation or attribute. When it is unnecessary to limit the affiliation or attribute of the recipient of supply, it is possible to select “None”.
Herein, the electric power profile may be recorded in a computer connected to the smart grid 10. The electric power profile may be recorded, for example, so as to be acquirable by the electric power trade supporting device 120. Accordingly, the electric power profile may be recorded in a computer on the user U1 side that is accessible through the smart grid 10 or recorded in a computer of the resource aggregator 13. As for the power generating facilities, respective IDs preassigned to the power generating facilities may be recorded so that, for example, each power generating facility can be identified.
The process S1a involves, as illustrated in
The process S1b provides the electric power profile to another user U2 through the communication network 40. For example, the other user U2 may be a user who receives a service provided through the electric power trade supporting device 120, and the other user U2 may be preregistered in the electric power trade supporting device 120. The electric power profile may be configured to be provided to the other user U2 through the communication network 40. The services provided through the electric power trade supporting device 120 may be constructed so as to provide the electric power profile of the electric power suppliable by the user U1, who is the electric power supplier and to allow browsing of the electric power profile of the electric power that is suppliable by the user U1, in response to a request from the user U2 that is to receive supply of electric power trade supporting device 120. The services provided through the electric power trade supporting device 120 may also be configured to allow the user U2, who wishes to receive supply of electric power, to search the information of the electric power profile of the electric power that is suppliable by the user U1 to select, based the electric power profile, the electric power that satisfies the desired condition.
The process S1c is a process in which the user U2 who wishes to receive supply of electric power makes an application to the user U1 having suppliable electric power to receive supply of the electric power. Such a process S1c is executed electronically through a communication network such as the Internet. In this embodiment, the electric power trade supporting device 120 is constructed to allow the user U2 who wishes to receive supply of electric power to be provided with information about the electric power profile of the electric power receivable by the user U2 and to browse the electric power profile of the receivable electric power. The electric power trade supporting device 120 may also be configured to, for example, search the supply conditions that are set by the user U1 having suppliable electric power to extract the electric power receivable by the other user. Based on such provision of information, browsing of the electric power profile, searching of the supply conditions, and the results of extracting, the user U2 who wishes to receive supply of electric power may make an application to the user U1, who is an electric power supplier, to receive supply of electric power.
The process S1d involves sending a profile of the user who has made an application in the step S1c of making the application, to the user having received the application. In the embodiment shown in
In the process S1e, the user U1 who has received an application for receipt of supply of electric power approves the application made by the user U2 who has applied for receipt of supply of electric power. In this embodiment, the electric power trade supporting device 120 is configured to allow the user U1, who has received the application for receipt of supply of electric power, to be able to select whether or not to approve the application made by the user U2, who has applied for receipt of supply of electric power. It is also possible that the electric power trade supporting device 120 may be configured to automatically execute the process of approving without necessitating user operation if the user U2 satisfies a predetermined supply condition based on the profile of the user U2 who has applied for receipt of supply of electric power. The process of automatically approving can reduce the burden on the user U1 required for the approving process and also allows the processes from the application to the approval to be performed smoothly. The electric power trade supporting device 120 may be configured to send a notification of the result of approving to the user U2 who has applied for receipt of supply of electric power (S1e1). For example, when the electric power trade supporting device 120 is configured to automatically execute the process of approving, the electric power trade supporting device 120 may be configured to send a notification of disapproval to the user U2 who has made the application if the user U2 who has made the application does not satisfy the predetermined supply condition.
In the process S1f, it may be possible to execute a process of supplying, in response to the process of approving, the electric power of the user U1 having received the application to the user U2 having made the application through the smart grid 10. The process of supplying electric power can be performed as appropriate by controlling the electricity storage devices 61 to 65 through the transmission grid 20 and the communication network 40 of the smart grid 10. Such control may be configured to be executed, for example, through communication with the electric power trade supporting device 120. In this case, it may also be possible to execute, in response to the process of approving, the process of supplying the electric power of the user U1 having received the application to the smart grid 10. Furthermore, it is also possible to execute the process of supplying electric power from the smart grid 10 to the user U2 having made the application. At that time, it is also possible to simultaneously execute the process of supplying electric power from the user U1 having received the application to the smart grid 10 and the process of supplying electric power from the smart grid 10 to the user U2 having made the application.
It is also possible to execute the process of supplying electric power from the user U1 having received the application to the smart grid 10 and the process of supplying electric power from the smart grid 10 to the user U2 having made the application at different times. For example, the electric power of the user U1 having received the application is supplied to the smart grid 10 and stored into a predetermined electricity storage device 65 connected to the smart grid 10. Thereafter, the just-mentioned stored electric power may be supplied from the smart grid 10 at the time when the user U2 having made the application requires electric power. Alternatively, it is also possible that the electric power in a predetermined amount of electric energy may be supplied from the electricity storage device 65 to the user U2 having made the application through the smart grid 10 at the time when the user U2 having made the application requires electric power, and thereafter, electric power of the user U1 having received the application may be supplied to the smart grid 10. Thus, the electric power of the user U1 having received the application may be supplied to the user U2 having made the application through the smart grid 10, and the time of supply and the amount of electric energy supplied do not necessarily need to match each time.
In the process S1g, a compensation is paid from the user U2 who received supply of electric power to the user U1 who supplied the electric power. The compensation is determined according to the supply condition set out by the user U1 who supplied the electric power.
With this electric power trade supporting device 120, the electric power profile is provided from the user U1 who is an electric power supplier (i.e., seller) (S1b), and the user U2 who is an electric power receiver (i.e., purchaser) is able to find a type of electric power that the user U2 wishes to be supplied with and to make an application for receipt of the electric power (S1c). For example, when the user who is an electric power receiver (purchaser) wants to procure electric power with green energy, such as solar power, wind power, hydraulic power, geothermal energy, and biomass, the user is able to find the electric power generated by such means of power generation based on the electric power profile and apply for receipt of electric power. Alternatively, when the user who is an electric power receiver (purchaser) wants to support the power generation in a specific region, such as regional small-sized hydroelectric power generation and regional biomass power generation, the user is able to find the electric power that is generated in that area and make an application. Thus, the user U2 who wishes to receive supply of electric power is allowed to select a type of electric power and to receive the electric power. In addition, this electric power trade supporting device 120 allows the user U1 who is an electric power supplier (seller) to determine a supply destination user to which the electric power is to be supplied based on the user profile. Thus, the electric power of the user U1 who is an electric power supplier (seller) is made widely available to other users who use the service of the electric power trade supporting device 120, the user U2 who is an electric power receiver (purchaser) is allowed to select a type of electric power to be supplied with, and the user U1 who is the electric power supplier (seller) is allowed to select a recipient that uses the user U1's electric power.
For example, the user who is an electric power supplier (seller) is able to support a specific business operator by suppling electric power. Moreover, the supply condition may be set to be free of charge. In this case, it is also possible that the user who is an electric power supplier (seller) may supply electric power free of charge when the user can sympathize with the business of the supply destination user to whom electric power is to be supplied based the user profile. For example, when the user wants to donate electric power to farmers, schools, or tourist facilities in rural areas where shortage of electric power is likely to occur, the user is able to identify another user who is to be an electric power receiver (purchaser) to supply electric power and moreover make the compensation free of charge. The user can allow the users that the user wants to support, such as farmers, schools, or tourist facilities in rural areas where shortage of electric power is likely to occur, to use surplus electric power generated at the user's own home. This enables the surplus electric power generated at the user's own home to be used effectively for such purposes as community support and regional development.
The electric power trade supporting device 120 may be configured to record transaction data in a blockchain, the transaction data including information of the process of making the application, information of the process of approving, and information of the electric power supplied from the user having received the application to the smart grid and information of the electric power supplied from the smart grid to the user having made the application in the process of supplying the electric power. This enables a series of transaction records in the electric power trade supporting device 120 to be recorded as verifiable information by the blockchain. When the transaction data are recorded in the blockchain, the information recording a series of processes S1a to S1g may be put together as one transaction and recorded in the blockchain.
Here, the user U1 who is an electric power supplier (seller) may set a supply condition in the electric power profile. The electric power profile may include at least one of an amount of the electric energy that the user is able to supply, power source information of the electric power to be supplied, and a supply condition. By setting an appropriate supply condition in the electric power profile, the user U1 can limit the user U2 who is an electric power receiver (purchaser) according to the intention of the user U1. Various conditions may be set for the supply condition, such as the date and time of supply, the price, the region to be supplied with electric power, and the affiliation or attribute of the recipient of electric power, for example. This allows the user U1 who is an electric power supplier (seller) to supply electric power to a recipient according to the user's intention.
The electric power trade support device 120 may also be configured to execute the following processes S2a to S2f.
S2a: A process of acquiring an electric power demand profile relating to an electric power demand of one of the users.
S2b: A process of providing the electric power demand profile to another user through a communication network.
S2c: A process of making an application for supplying electric power to meet the electric power demand, the application made by the other user.
S2d: A process of sending, to a user having received the application, an electric power profile of electric power that is suppliable by the user having made the application in the process of making the application.
S2e: A process of approving, by the user having received the application, the application made by the user having made the application.
S2f: A process of supplying, in response to the process of approving, the electric power of the user having received the application to the user who has made the application through the smart grid.
S2g: A process of paying a compensation from the user U2 who received the electric power to the user U1 who supplied the electric power.
Each of electric power demand profiles is information on the electric power demand of a user. The electric power demand profile may be information that identifies, for example, the user who wishes to receive supply of electric power, the amount of electric energy the user wishes to receive, the means of power generation generating the electric power that the user wishes to receive, and the like. The smart grid 10 may include a memory storage unit that records an electric power demand profile of the electric power that the user wants to receive. Table 3 is an example of a table for storing the electric power demand profile. The table shown as Table 3 is configured to be able to record, for each electric power demand profile, an electric power demand profile ID, an amount of electric energy, a user ID, a means of power generation, date and time of supply, a price, a region, affiliation (attribute), and a gift in return. The types of information to be contained in the electric power demand profile are not limited to those listed in Table 3.
Herein, the electric power demand profile IDs are identifiers that are assigned to distinguish various types of electric power that the users are able to supply. The user IDs are identifiers that are assigned to distinguish various users. The date and time of supply record the date and time when the user wishes to receive electric power. The amount of electric energy records the amount of electric energy the user wishes to receive. The means of power generation records the power source information of the electric power from which the user wishes to receive supply. The price records the price of electric power. For example, it records the unit price per unit amount of electric energy. The region records the suppliable region. The price and the region may serve as one of the supply conditions. The affiliation (attribute) may record, for example, the use of electric power and the like.
Thus, the electric power profile may include at least one of date and time when the user U2, who is an electric power receiver, desires to receive supply of electric power, an amount of electric energy that the user desires to be supplied with, power source information of electric power that the user desires to be supplied with, a supply condition, and an intended use of electric power. The supply condition may include, for example, conditions such as a compensation. The compensation may be set as free of charge. That is, this electric power trade supporting device 120 enables the user U2, who is an electric power receiver, to recruit a partner that can support the business operation of the user U2 in the form of supply of electric power. The intended use of electric power may include information about the intended uses for which electric power is used, such as farmer, school, or tourist facility. Such information about the intended use of electric power may serve as motivation of the user U1 who is an electric power supplier to make an offer to supply electric power. The electric power demand profile may also include information of, for example, the gift in return. For example, when the user U2 who is an electric power receiver is a strawberry producer, it is possible to send produced strawberries to the user U1 who is the electric power supplier as the gift in return for receipt of supply of electric power. The information of the gift in return contained in the electric power demand profile may serve as motivation of the user U1 who is an electric power supplier to make an offer to supply electric power.
The process S2a involves acquiring an electric power demand profile relating to an electric power demand of one of the users. The electric power trade supporting device 120 may acquire the electric power demand profile relating to the electric power demand of the user and store the acquired electric power demand profile into a predetermined memory storage unit.
The process S2b provides the electric power demand profile to another user through a communication network. For example, the other user may be a user who receives a service provided through the electric power trade supporting device 120, and the other user may be preregistered in the electric power trade supporting device 120. The process S2b provides the electric power demand profile to the other user through the communication network 40. This allows, as illustrated in
In the process S2c, the other user makes an application for supplying electric power to meet the electric power demand of one of the users. Because the electric power demand profile is provided in the process S2b, the user U1 having suppliable electric power is allowed to check the electric power demand profile and to offer supply of electric power to a counterparty to which the user U1 wants to supply the electric power. For example, in the example shown in
In this embodiment, the electric power trade supporting device 120 may be configured to provide the user U1 who is an electric power supplier with information about the electric power demand profile, and to allow the user U1 who is an electric power supplier to browse the electric power demand profile acquired from the user who is an electric power receiver. The electric power trade supporting device 120 may also be configured to, for example, allow the user U1 having suppliable electric power to search some pieces of information contained in the electric power demand profile and to extract the other user U2 to be supplied with electric power. The electric power trade supporting device 120 may be configured to allow the user U1 who is an electric power supplier to make an application for supplying of electric power to the user U2 who wishes to receive supply of electric power, based on such provision of information and the results of browsing, searching, and extracting of the electric power demand profile. In addition, the electric power demand profile may include power source information of the desired electric power. In this case, the electric power trade supporting device 120 may be configured to prohibit the user U2 from making the application when the electric power supplied by the user U1 who is an electric power supplier is not the desired type of electric power, in cases where, for example, power source information such as solar power generation is recorded in the power source information of the desired electric power. Thus, the user U1 who is an electric power supplier is able to set an appropriate condition for the electric power demand profile and to thereby limit the application for supplying of electric power to meet the electric power demand of the user U2. This enables the user U2 who is an electric power receiver to collect the electric power generated by desired power sources.
The process S2d involves sending, to the user U2 having received the application, the electric power profile of the electric power that is suppliable by the user U1 having made the application in the process S2c of making the application. This process enables the user U2 who is an electric power receiver to acquire such information about the user U1 who is an electric power supplier and the power source information of the electric power supplied by the user U1. When the user U2 who is an electric power receiver wants to receive the required electric power with green energy, the user U2 is able to check the power source information of the electric power supplied by the user U1 based on the electric power profile.
In the process S2e, the user U2 who has received the application approves the application made by the user U1 having made the application. In this embodiment, the electric power trade supporting device 120 is configured to allow the user U2, who has received the application for supplying of electric power, to be able to select whether or not to approve the application made by the user U1, who has made the application for supplying of electric power. It is also possible that the electric power trade supporting device 120 may be configured to allow the user U1, who received the application for supply of electric power, to automatically execute the process of approving without necessitating user operation, if the electric power profile of the user U1, who has applied for supply of electric power, satisfies a predetermined supply condition based on the electric power profile of the user U1, who has applied for supply of electric power. The process of automatically approving can reduce the burden on the user U2 required for the approving process and also allows the processes from the application to the approval to be performed smoothly. The electric power trade supporting device 120 may be configured to send a notification of the result of approving to the user U1 who has applied for supplying of electric power (S2e1). For example, when the electric power trade supporting device 120 is configured to automatically execute the process of approving, the electric power trade supporting device 120 may be configured to send a notification of disapproval to the user U1 who has made the application if the user U1 who has made the application does not satisfy the predetermined supply condition.
The process S2f causes, in response to the process S2e of approving, the electric power of the user U1 having made the application to be supplied to the user U2 having received the application through the smart grid 10. For example, it is possible to execute, in response to the process S2e of approving, the process of supplying the electric power of the user U1 having made the application to the smart grid 10. Furthermore, it is also possible to execute the process of supplying electric power from the smart grid 10 to the user U2 having received the application. At that time, it is also possible to simultaneously execute the process of supplying electric power from the user U1 having received the application to the smart grid 10 and the process of supplying electric power from the smart grid 10 to the user U2 having made the application. It is also possible to execute the process of supplying electric power from the user U1 having made the application to the smart grid 10 and the process of supplying electric power from the smart grid 10 to the user U2 having received the application at different times. Thus, the electric power of the user U1 having made the application may be supplied through the smart grid 10 to the user U2 having received the application, and the time of supply and the amount of electric energy supplied do not necessarily need to match each time.
In the process S2g, a compensation is paid from the user U2 who received supply of electric power to the user U1 who supplied the electric power. The compensation is determined according to the supply condition set out by the user U2 who received supply of electric power in the electric power demand profile. The compensation may not necessarily be paid by money but may be paid by the gift in return or the like that is specified in the electric power demand profile.
In this case as well, the electric power trade supporting device 120 may be configured to record transaction data in a blockchain, the transaction data including information of the process S2c of making the application, information of the process S2e of approving, and information of the electric power supplied in the process S2f of supplying the electric power. This enables a series of transaction records in the electric power trade supporting device 120 to be recorded as verifiable information by the blockchain. When the transaction data are recorded in the blockchain, the information recording a series of processes S2a to S2g may be put together as one transaction and recorded in the blockchain.
According to the flow illustrated in
It is also possible that the electric power trade supporting device 120 may also be configured to execute both processes shown by the flow in
Various embodiments of the invention have been described hereinabove according to the present disclosure. Unless specifically stated otherwise, the embodiments described herein do not limit the scope of the present invention. It should be noted that various other modifications and alterations may be possible in the embodiments of the invention disclosed herein. In addition, the features, structures, or steps described herein may be omitted as appropriate, or may be combined in any suitable combinations, unless specifically stated otherwise.
Number | Date | Country | Kind |
---|---|---|---|
2022-023747 | Feb 2022 | JP | national |