Claims
- 1. Apparatus for use in a two-stage concrete pouring construction process such as pouring floors or ceilings for buildings, comprising:
- a horizontal shuttering;
- an element moulding for use as a sunken shuttering comprising a rigid profile metal mesh on said horizontal shuttering, said mesh having two longitudinal edges;
- a plank liner arranged between the metal mesh and the horizontal shuttering for spacing the mesh from the horizontal shuttering, said plank liner being removable before the concrete pouring of the second stage;
- a plurality of horizontally oriented reinforcing bars;
- perforation means in said element moulding for introducing the plurality of horizontally oriented reinforcing bars, said perforation means being disposed in two parallel lines, each line laying near one of the two longitudinal edges of the element moulding; and
- support means for laterally buttressing the element moulding metal mesh on one side and to be fixed to said horizontal shuttering before the introduction of the concrete pouring of a first stage, and removable before the concrete pouring of the second stage.
- 2. Apparatus of claim 1, wherein several sections of element mouldings are stacked vertically.
- 3. Element moulding of claim 2, wherein several sections of element mouldings are attached to the support means by fastening means.
- 4. Element moulding of claim 1, wherein several sections of element mouldings are laid end to end longitudinally.
- 5. Element moulding of claim 4, wherein several sections of moulding are attached to the support element means by fastening means.
- 6. Element moulding of claim 1, wherein:
- said metal mesh is castellated in a U-form with a connecting bridge.
- 7. Element moulding according to claim 1, wherein several sections of the element moulding are stacked vertically and unilaterally buttressed by said removable support means before the introduction of the concrete pouring of the first stage.
- 8. Apparatus of claim 6, wherein said U-form metal mesh includes a leg portion which is parallel to said shuttering and said plank liner, said leg portion bearing upon said plank liner and supporting the metal mesh prior to the pouring of the concrete of the first sage.
- 9. Apparatus for use in a two-stage concrete pouring construction process such as pouring floors or ceilings for buildings, comprising:
- a shuttering;
- an element moulding comprising a rigid profile metal mesh mounted on said shuttering;
- a plank liner arranged between the metal mesh and the shuttering for spacing the metal mesh from the shuttering;
- perforation means in said metal mesh;
- a plurality of reinforcing bars extending through said perforation means transversely to said metal mesh; and
- support means for laterally buttressing the element moulding metal mesh on one side, said support means being adapted to be fixed to said shuttering before the introduction of the concrete pouring of a first stage, and removable before the concrete pouring of the second stage.
- 10. Element moulding of claim 9, wherein several sections of element mouldings are stacked vertically.
- 11. Element moulding of claim 9, wherein several sections of element mouldings are attached to the support means by fastening means.
- 12. Element moulding of claim 9, wherein several sections of element mouldings are laid end to end longitudinally.
- 13. Element moulding of claim 9, wherein several sections of element moulding are attached to the support element means by fastening means.
- 14. Element moulding of claim 9, wherein said metal mesh is castellated in a U-form with a connecting bridge.
- 15. Apparatus of claim 14, wherein said U-form metal mesh includes a leg portion which is parallel to said shuttering and said plank liner, said leg portion bearing upon said plank liner and supporting the metal mesh prior to the pouring of the concrete of the first stage.
Priority Claims (1)
Number |
Date |
Country |
Kind |
3384/80 |
May 1980 |
CHX |
|
Parent Case Info
This application is a continuation of application Ser. No. 255,504, filed Apr. 20, 1981.
US Referenced Citations (15)
Foreign Referenced Citations (5)
Number |
Date |
Country |
3013710 |
Nov 1980 |
DEX |
581480 |
Nov 1924 |
FRX |
846222 |
Dec 1939 |
FRX |
1495550 |
Aug 1967 |
FRX |
1500731 |
Feb 1978 |
GBX |
Non-Patent Literature Citations (1)
Entry |
Sweet's Catalog, 1977, vol. 1, 3.6/He, p. A-1. |
Continuations (1)
|
Number |
Date |
Country |
Parent |
255504 |
Apr 1981 |
|