The invention relates to the optimization of the power usage of elevators.
The electrical energy requirement of elevators varies at different times. During a run the power requirement is essentially greater than during a standstill of the elevator. The load of the elevator car as well as, inter alia, the magnitude of the counterweight of the elevator car affect the power consumption during a run.
The fuses of a rising main in a building as well as the cables are usually dimensioned according to a greater required power. Generally the costs of a mains electricity connection of a building increase when the dimensioning of the fuses/the power requirement of the building increases.
From the viewpoint of the electricity provider, a wide-ranging power variation can be a problem, because it might cause, among other things, oscillation in the frequency of the electricity network.
The aim of the invention is consequently to smooth the load caused in the electricity supply of a building by the operation of elevators without this causing any detriment to the users of the elevators.
To achieve this aim the invention discloses an elevator installation as defined in claim 1, an elevator system as defined in claim 17 and a method as defined in claim 19.
One aim of the invention is to smooth the load caused in the main supply of a building by the operation of elevators without this causing any detriment to the users of the elevators. To achieve this aim the invention discloses an elevator installation as defined in claim 13 and also a method as defined in claim 29.
One aim of the invention is to smooth the load caused in the public electricity network by the operation of elevators without this causing any detriment to the users of the elevators. To achieve this aim the invention discloses an elevator installation as defined in claim 14 and also a method as defined in claim 30.
One aim of the invention is to smooth the load caused in the reserve power device of a building by the operation of elevators without this causing any detriment to the users of the elevators. To achieve this aim the invention discloses an elevator installation as defined in claim 15 and also a method as defined in claim 31.
The preferred embodiments of the invention are described in the dependent claims. Some inventive embodiments and inventive combinations of the various embodiments are also presented in the descriptive section and in the drawings of the present application.
Elevator installation in a building in which there is an electricity distribution network that is connected to the electricity supply of the building. The elevator installation comprises a plurality of elevator cars as well as a control, which is configured to form a run plan for driving the elevator cars on the basis of service requests. The elevator installation further comprises a plurality of hoisting machines as well as a plurality of power supply devices for a hoisting machine that are connected to the electricity distribution network of the building, each of which power supply devices is configured to drive an elevator car according to a run plan with a hoisting machine, by supplying electric power via the electricity distribution network to a hoisting machine driving an elevator car as well as by supplying electric power back to the electricity distribution network from a hoisting machine braking an elevator car. The aforementioned control is configured to form alternatives for a run plan for driving elevator cars on the basis of service requests, to determine the electric power which the hoisting machines need for implementing the aforementioned alternatives, and also to select for use from the plurality of different alternatives a run plan, which when implemented causes the electric powers of the hoisting machines, when summed together, to smooth the power variation occurring in the electricity supply of the building. When smoothing the momentary power variation the load, i.e. the maximum current, exerted on the electricity supply of the building by operation of the elevators decreases. At the same time, however, power is received evenly via the electricity distribution network of the building, so that the elevators or other electrical devices do not need to be removed from use owing to overload. Consequently the operation of the elevator installation and of the other electrical devices of the building can continue without causing extra detriment to users. The advantages to be achieved with the solution further increase in large buildings as the number of elevators driving simultaneously increases, in which case the momentary power variation in the electricity supply of the building decreases even more.
The electricity supply of a building is generally dimensioned according to the maximum power requirement. Although the energy consumption of elevators is, in fact, only approx. 5 percent of the total energy consumption of a building, the momentary peak power requirement of elevators usually corresponds to approx. 50 percent of the power consumption of the whole building. Consequently by means of the solution according to the description—by reducing the power variation caused by elevators—the dimensioning of the electricity supply of a building can be significantly reduced. This is also economically important to the owners of a building, because the investment costs for the electricity supply of a building increase by approx. 300 euros per each kilowatt needed (contract charge approx. 100 euros/KW, transformers approx. 100 euros/KW, reserve power systems approx. 100 euros/KW).
In some embodiments the aforementioned electricity supply of a building is the main supply of the building. This means that electric power can be received via the main supply more evenly than is known in the art. In some embodiments also the fuse size of the main supply can at the same time be reduced.
In some embodiments the aforementioned electricity supply of a building is a reserve power device. This means that electric power can be received from a reserve power device more evenly than is known in the art. At the same time the load exerted on the reserve power device usually also decreases at the same time. Consequently the dimensioning of the reserve power device needed can be reduced or the transport capacity of the elevator installation being supplied with the reserve power device can be increased.
In some embodiments the control is connected with a data transfer bus to the building automation apparatus, with which the electricity consumption of devices external to the elevator installation is controlled, and that the building automation apparatus is configured to change the electricity consumption of the devices external to the elevator installation in a manner specified by the control on the basis of a change command to be received from the control. The control is further configured to form a change command for changing the electricity consumption of the devices external to the elevator installation and also to select for use from the plurality of different alternatives a run plan, which when implemented causes the electric powers of the hoisting machines, when summed together with the changed electricity consumption of the devices external to the elevator installation, to smooth the power variation occurring in the electricity supply of the building. This means that the control can affect the power variation occurring in the electricity supply of the building very efficiently by optimizing at the same time both the power consumption of the hoisting machines and also the power consumption of the devices external to the elevator installation. The aforementioned devices external to the elevator installation in a building can be e.g. the heating apparatus for household water, air-conditioning apparatus, a heating system and lighting.
In some embodiments the control is connected to a data transfer bus that is external to the building for adjusting the power limit of the main supply, and the control is configured to change the power limit of the main supply on the basis of a control signal to be received from the data transfer bus external to the building. This means that the power limit of the main supply can be changed on the basis of a control signal received from the electricity provider via the data transfer bus external to the building. In this case the operation of the elevator installation can still continue with sufficient transport capacity in a situation in which the electric power available for operating the elevators from the public electricity network has decreased.
The control preferably comprises a processor and also a memory, in which is recorded an optimization program to be executed with the microprocessor. In the optimization program the control is configured to function in the manner disclosed in the description. An optimization program means a computer program in which a calculation relating to the operating parameters of the elevator installation, such as to elevator waiting times, energy consumption, power consumption and/or transport capacity, can be performed. In some preferred embodiments the optimization program also comprises one or more optimization algorithms, by using which a run plan that best corresponds to the set objectives can be selected from a plurality of alternatives, said objectives being such as a set limit value for the power of the electricity supply of the building, an objective for minimizing the power variation of the electricity distribution network of the building, an objective for reducing the power variation of the public electricity network, et cetera. In some embodiments a genetic algorithm is used as an optimization algorithm.
According to one aspect, in the method for controlling elevators a run plan is formed for driving elevator cars on the basis of service requests and also the elevator cars are driven according to the run plan, by supplying electric power via the electricity distribution network of the building to each hoisting machine driving an elevator car, as well as by supplying electric power back to the electricity distribution network of the building from a hoisting machine braking an elevator car. Further, in the method alternatives for a run plan are formed for driving elevator cars on the basis of service requests, the electric power which the hoisting machines need for implementing the aforementioned alternatives is determined, and also a run plan is selected for use from the plurality of different alternatives, when implementing which run plan the electric powers of the hoisting machines, when summed together, smooth the power variation occurring in the electricity supply of the building.
MORE DETAILED DESCRIPTION OF PREFERRED EMBODIMENTS OF THE INVENTION
The group controller 6 divides the service requests between the elevator cars, and each elevator car is driven on the basis of service requests in such a way that the elevator car stops at floors according to the service requests.
The elevator installation of
Each elevator of an elevator group comprises drive unit 8, which comprises an elevator control unit and also a frequency converter. The input of the frequency converter is connected to the electricity distribution network 1 of the building and the output is connected to the stator windings of the electric motor 5 of the hoisting machine 5. In this embodiment of the invention a permanent-magnet synchronous motor is used as an electric motor, but also e.g. a DC motor, induction motor or reluctance motor could be used as an electric motor instead of a permanent-magnet synchronous motor. An elevator car 4 is driven by supplying with a frequency converter electric power via the electricity distribution network 1 to the permanent-magnet synchronous motor of a hoisting machine 5 driving an elevator car, as well as by supplying electric power back to the electricity distribution network from a permanent-magnet synchronous motor braking an elevator car.
The group controller 6 is configured to form alternatives for a run plan for driving elevator cars on the basis of service requests. The software is also configured to estimate the electric power which the hoisting machines need for implementing the aforementioned alternatives, and also to select for use from the plurality of different alternatives a run plan, which when implemented causes the electric powers of the hoisting machines, when summed together, to smooth the power variation occurring in the electricity supply of the building, i.e. in the main supply 11 of the building or in connection with a reserve power device 12. For this reason the group controller 6 estimates the load of the different elevator cars 4 by estimating the number of passengers from the number of service requests for the elevator car 4. In addition the group controller 6 receives information from the sensor of the load-weighing device of each elevator car 4 about the load of the elevator car 4 in question. On the basis of the estimated and the measured load data the group controller calculates for each hoisting machine 5 an estimate for the power consumption during a run and also the sum PΣ of the power consumptions of the hoisting machines 5 from the viewpoint of the electricity supply of the building.
The group controller 6 also calculates the waiting time of an elevator, i.e. the time elevator passengers must wait for elevator service, for the different alternatives. A maximum waiting time, i.e. the longest permissible waiting time for an elevator, is also entered into the group controller 6. The maximum waiting time is consequently a performance indicator, which guarantees a certain level of elevator service. The group controller 6 removes those alternatives in which the waiting time of an elevator would exceed the aforementioned maximum waiting time and selects from a plurality of permitted alternatives for use a run plan, which when implemented the power variation in the electricity supply of the building is the smallest possible within the scope of the maximum waiting time. Consequently the power variation in the electricity supply of a building can be reduced without the level of elevator service falling if a maximum waiting time were to be exceeded.
The group controller 6 forms a number of alternatives for a run plan by dividing the service requests in alternative ways between the different elevator cars and also calculates the electric power needed by the hoisting machines 5 in the different alternatives as well as the sum PΣ of electric powers in a corresponding manner. In some embodiments the service requests are distributed in a coordinated manner between the different elevator cars 4 in such a way that the purpose of each elevator car 4 is to stop at floors according to service requests given to it. In some embodiments also the starting moment of an elevator car 4 leaving to serve one or more service requests is also altered in some alternatives. In some embodiments also the acceleration during the final part of the acceleration phase and/or the deceleration during the initial part of the deceleration phase of one or more elevator cars is adjusted in the alternatives. In some embodiments also the maximum speed of one or more elevator cars is adjusted in the alternatives. Described in more detail in connection with the description of
The selection between alternative run plans can be made using optimization algorithms known in the art. One generally used algorithm is a genetic algorithm, the operation of which is described in international patent publication WO 01/65231 A2. Selections can be made in this way e.g. for minimizing the waiting times of an elevator, but here a genetic algorithm is utilized by minimizing the magnitude of the variation in the sum PΣ of the power consumptions of the hoisting machines from the viewpoint of the electricity supply of the building, in addition to, or instead of, minimizing waiting times. In some embodiments this is implemented by calculating the statistical dispersion index for the sum PΣ of power consumptions in each alternative run plan. In some embodiments the power consumption caused in the electricity supply of the building by loads external to the elevator installation are added to the sum PΣ of power consumptions, which addition is also taken into account when calculating the dispersion index. Most preferably the average deviation or variance of the sum PΣ of the power consumptions is used as the dispersion index. By means of a genetic algorithm a run plan is selected for use from a plurality of alternatives, with which run plan the aforementioned average deviation or variance of the sum PΣ of the power consumptions is the smallest. In some embodiments the selection is carried out by setting a penalty term for those run plans in which greatest instantaneous value of the sum PΣ exceeds the set threshold limit and also by favoring in the selection the run plans for which no penalty term is set, i.e. the run plans which do not exceed the aforementioned power limit.
In some embodiments a power limit is recorded in the memory of the group controller 6, which power limit the load in the electricity supply of the building may not exceed and the software of the group controller 6 is configured to select a run plan for use in the first instance, when implementing which run plan the electric powers of the hoisting machines, when summed together, smooth the power variation occurring in the electricity supply of the building in such a way that the maximum power in the electricity supply of the building does not exceed the aforementioned power limit. This means that, in addition to the dispersion index, a peak value for the sum PΣ of the power consumptions of the hoisting machines 5 is determined, which peak value is compared to the aforementioned power limit for the electricity supply of the building. Those alternatives in which the peak value would exceed the aforementioned power limit are then totally eliminated from the plurality of run plan alternatives. In some embodiments the selection of the run plan is carried out by setting a penalty term for those run plans in which greatest instantaneous value of the sum PΣ exceeds the power limit for the electricity supply of the building and also by favoring in the selection the run plans for which no penalty term is set.
The group controller 6 is also connected to a data transfer bus 17, which extends to outside the building. The data transfer bus 17 can be e.g. an internet connection, a wireless link or corresponding. In some embodiments the group controller 6 is configured to receive via the data transfer bus 17 control commands from outside the building from an electricity provider, on the basis of which the aforementioned power limit for the electricity supply is adjusted. Consequently the power limit can be increased or decreased in such a way that load of the generators of a power plant and at the same time the frequency of the electricity network would remain as stable as possible. In some embodiments the group controller 6 is configured to receive via the data transfer bus 17 from outside the building, from an electricity provider or e.g. from an electronic electricity exchange, information about momentary fluctuations in the price of electricity, in which case the power limit can e.g. be raised when electricity is momentarily cheap and the power limit can be lowered when the price of electricity momentarily increases. In this way the electricity bill for the building can be reduced at the same time, however, maintaining the level of the elevator service needed.
The solution of the description enables more efficient utilization of the existing infrastructure e.g. in areas in which the capacity of the public electricity network would otherwise start to run out. This is the type of situation e.g. in a part of Germany and also in the Manhattan district in New York, U.S.A., where society already offers financial incentives for reducing electricity consumption.
In
The building automation apparatus 19 is connected with a network switch (not presented in
The software of the group controller 6 is configured to form a change command for changing the electricity consumption of the building, and also to select for use in the first instance from the plurality of different alternatives a run plan, when implementing which run plan the sum PΣ of the electric powers of the hoisting machines 5, together with the changed electricity consumption of devices external to the elevator installation, smooth the power variation occurring in the electricity supply of the building in such a way that the maximum power in the electricity supply of the building does not exceed the set power limit. In this way an adequate level of elevator service can be ensured for users of the building particularly during an electricity outage or reduced distribution capacity of the electricity distribution network.
In the run plan presented in
In the run plan presented in
The solution presented in
In one embodiment, more particularly when driving in the light direction, the deceleration during the initial phase of deceleration is adjusted, in which case the braking power returning to the electricity distribution network 1 from the hoisting machine 5 is at its greatest.
Utilizing the control methods according to the description, the peak value of instantaneous power of the electricity supply of a building can be significantly reduced. In one case the greatest instantaneous power of the electricity supply of a building fell from 1500 kilowatts to 950 kilowatts with the control method according to the description.
The elevator installation of
The power management unit 14 first reads from one of the group controllers 6A, 6B an estimate for the sum PΣ of power consumptions during a run of the hoisting machines of the elevator group. The group controller 6A, 6B forms the aforementioned sum PΣ of power consumptions in the same way as was presented in embodiment 1. After this the power management unit 14 forms a group-specific power limit for that one of the group controllers 6A, 6B in such a way that the sum data PΣ of the power consumptions received from the first group controller, together with the aforementioned group-specific power limit, smoothes the power variation occurring in the electricity supply of the building. The power management unit 14 sends the group-specific power limit to the second group controller, and the second group controller further optimizes the power consumption of the elevators within the scope of its elevator group, endeavoring to ensure that the power consumption of the elevators of the group would not exceed the aforementioned group-specific power limit. The solutions described in connection with embodiment 1 are further used also in this group-specific optimization.
The solution according to embodiment 2 is advantageous particularly in large buildings, in which there are a number of elevator groups. By means of the power management unit 14 the power consumption of the different elevator groups can be optimized centrally, in which case the power variation in the electricity supply of a building can be smoothed even more than before.
The power management unit 14 can also be connected to the building automation apparatus 9 in such a way that with the power management unit the power variation in the electricity supply of a building can be smoothed more efficiently than before by changing the power consumption of electrical devices 18 that are external to the elevator installation in the same way as was presented in the embodiment 1.
In some further developed embodiments the power limit 20 for the electricity supply of the building according to embodiment 1 is recorded in the memory of the power management unit 14. The power management unit 14 compares the sum PΣ of the power consumptions received from the first group controller to the power limit 20 for the electricity supply of the building recorded in memory and, on the basis of the comparison, forms a group-specific power limit for the second group controller 6A, 6B in such a way that the sum data PΣ of the power consumptions received, together with the group-specific power limit, smooth the power variation occurring in the electricity supply of the building in such a way that the maximum power in the electricity supply of the building does not exceed aforementioned power limit 20.
In some further developed embodiments the power management unit 14 is connected to a data transfer bus 17 extending to outside the building, via which the power management unit 14 receives control commands for changing the power limit 20 of the electricity supply of the building in the same way as is presented in connection with the embodiment 1.
The electricity supply in the buildings 25, 26 to devices 18 that are external to the elevator installation are controlled with the building automation apparatuses 19.
The electricity supply 11 to both buildings 25, 26 occurs with the same supply transformer 28 from the public electricity network 27.
The power management unit 14 is further connected with an internet connection 27 to an electricity provider of the public electricity network.
In the building 25 the group controllers 6A, 6B receive service requests from the call-giving devices 10A, 10B (see
Correspondingly, in the building 26 the group controllers 6A, 6B receive service requests from the call-giving devices 10A, 10B and allocate via the data transfer bus 13A, 13B the service requests received to be served by elevator cars belonging to the elevator group 16A, 16B. Both the group controllers 6A, 6B of both the buildings 25, 26 are configured to form a group-specific run plan in the same way, in terms of its basic principles, as was presented in connection with embodiment 1.
The group controllers 6A, 6B of the different buildings 25, 26 function in cooperation via the internet connection 17 coordinated by the power management unit 14. The power management unit 14 first reads from the group controllers 6A, 6B of the building 25 (or alternatively from the group controllers 6A, 6B of the building 26) an estimate for the sum PΣ of power consumptions during a run of the hoisting machines of the elevator group. The group controller 6A, 6B forms the aforementioned sum PΣ of power consumptions in the same way as was presented in embodiment 1. After this the power management unit 14 forms a group-specific power limit for the group controllers 6A, 6B of the building 26 (or alternatively for the group controllers 6A, 6B of the building 25) in such a way that the sum data PΣ of the power consumptions received from the group controllers of the building 25, together with the aforementioned group-specific power limit, smoothes the power variation occurring in the common electricity supply 11 of the buildings 25, 26. The power management unit 14 sends the group-specific power limit via the internet connection 17 to the group controllers 6A, 6B of the building 26, and the group controllers 6A, 6B of the building 26 both further optimize the power consumption of the elevators within the scope of their own elevator group, endeavoring to ensure that the power consumption of the elevators of the group does not exceed the aforementioned group-specific power limit. The solutions described in connection with embodiment 1 above are used also in this group-specific optimization.
The solution according to embodiment 3 enables the power variation in the shared electricity supply 11 of the buildings 25, 26 to be further reduced, in which case, inter alia, the dimensioning of the supply transformer 28 can be reduced.
In some further developed embodiments the power limit 20 for the electricity supply common to the buildings 25, 26 according to embodiment 1 is recorded in the memory of the power management unit 14. The power management unit 14 compares the sum PΣ of the power consumptions received from the group controllers of the building 25 to the power limit 20 recorded in memory and on the basis of the comparison forms a group-specific power limit for the group controllers 6A, 6B of the building 26 in such a way that the sum data PΣ of the power consumptions received, together with the group-specific power limit, smooth the power variation occurring in the common electricity supply 11 of the buildings 25, 26 in such a way that the maximum power in the electricity supply 11 does not exceed aforementioned power limit 20.
In some embodiments the electricity provider can adjust the aforementioned power limit 20 via an internet connection in the same way as is described in embodiments 1 and 2.
In some embodiments the power management unit 14 also adjusts the electricity supply of devices 18 external to the elevator installation by giving change commands to the building automation apparatuses 19, in the same way as is described in embodiments 1 and 2.
In embodiment 3, instead of two different buildings 25, 26, at issue can also be two functional parts 25, 26 of the same building that are clearly separate from each other. On the other hand, embodiment 3 is suited for use also in an entity comprising more than two buildings 25, 26, when the buildings belonging to the entity have a shared electricity supply 11. Consequently, these can be e.g. all the buildings of the same block that are supplied with a shared supply transformer 28.
With the solution of embodiment 3 a particularly large advantage is achieved if the functional purposes of the clearly separate functional parts 25, 26 of the buildings/of the same building differ from each other e.g. in such a way that the electricity consumption of the different buildings/functional parts 25, 26 is at its greatest at different times of day. In this case e.g. an office building and a hotel have a differing functional purpose. In an office building the power requirement of the elevators is at its greatest during the morning rush hour, when people arrive in the building. On the other hand, in the morning people leave a hotel, in which case when people leave the elevators convert the potential energy back into electrical energy. In hotels, on the other hand, the power requirement is generally highest in the afternoon when passengers arrive. Correspondingly, in the afternoon people leave an office building to go to their homes, in which case when people leave the potential energy is converted back into back electrical energy by the elevators. When the electric power of the office building and of the hotel is in this case taken from behind the same electricity supply 11, the power variation in the electricity supply 11 can be smoothed more than before by utilizing the electrical energy being released in the hotel in the morning for driving people up in the office building with an elevator and also, on the other hand, by utilizing the electrical energy being released in the office building in the afternoon for driving people up in the hotel.
In the description, public electricity network 27 means a common electricity network for a larger area, in which one or more electricity providers produce electric power. Electricity providers can be e.g. one or more of the following: a coal-fired power station, nuclear power station, wind power station, hydroelectric power station, solar power station, wave power station, gas-fired power station, diesel power station functioning with a diesel generator.
The invention is not only limited to be applied to the embodiments described above, but instead many variations are possible within the scope of the inventive concept defined by the claims.
This application is a continuation of PCT International Application No. PCT/FI2013/050856 which has an International filing date of Sep. 5, 2013, the entire contents of which are incorporated herein by reference.
Number | Name | Date | Kind |
---|---|---|---|
5894910 | Suur-Askola et al. | Apr 1999 | A |
8083033 | Kallioniemi | Dec 2011 | B2 |
8714313 | Harkonen | May 2014 | B2 |
20080105499 | Tyni | May 2008 | A1 |
20080185234 | Harkonen | Aug 2008 | A1 |
20130075199 | Kauppinen et al. | Mar 2013 | A1 |
20150144434 | Herkel | May 2015 | A1 |
20160145075 | Hanninen | May 2016 | A1 |
Number | Date | Country |
---|---|---|
2013-184773 | Sep 2013 | JP |
WO-9617798 | Jun 1996 | WO |
WO-0165231 | Sep 2001 | WO |
WO-2011148043 | Dec 2011 | WO |
Entry |
---|
International Search Report PCT/ISA/210 for International Application No. PCT/FI2013/050856 Dated Feb. 20, 2014. |
Written Opinion of the International Searching Authority PCT/ISA/237 for International Application No. PCT/FI2013/050856 Dated Feb. 20, 2014. |
Number | Date | Country | |
---|---|---|---|
20160145075 A1 | May 2016 | US |
Number | Date | Country | |
---|---|---|---|
Parent | PCT/FI2013/050856 | Sep 2013 | US |
Child | 15011143 | US |