Claims
- 1. A method for providing production optimization of reservoir completions having a plurality of completed intervals via available production analysis and production logging data provides a quantitative analysis procedure for reservoir and fracture properties of a commingled reservoir system, comprising the steps of:
a. measuring pressure for specific zones in a reservoir; b. selecting a pressure traverse model; c. computing midzone pressures using the traverse model; d. comparing the computed midzone pressures with the measured pressures; e. modeling the bottomhole pressure of the reservoir based on the traverse model.
- 2. The method of claim 1, wherein the comparison step includes accepting the comparison if the computed midzone pressures are within a predefined tolerance of the measured pressures and rejecting the comparison if the computed midzone pressures are outside of the predefined tolerance.
- 3. The method of claim 2, wherein upon rejection the selecting step and the computing step and the comparing step are repeated until acceptance is achieved.
- 4. The method of claim 1, wherein the reservoir is separated in to defined intervals from top to bottom, each having a top point, midpoint and a bottom point, and wherein the wellbore pressure traverse is computed using the total reservoir commingled production flow rates to the midpoint of the top completed interval.
- 5. The method of claim 4, wherein the fluid flow rates of the wellbore between the midpoint of the top and a second completed intervals are computed using the total fluid phase flow rates of the commingled reservoir minus the flow rates from the top completed interval.
- 6. The method of claim 5, wherein the pressure traverse in the wellbore between the midpoints of the second and lower completed intervals is computed using the fluid phase flow rates that are the difference between the commingled reservoir system total fluid phase flow rates and the sum of the phase flow rates from the top, second and lowercompleted intervals.
- 7. The method of claim 6, wherein the mathematical relationships that describe the fluid flow phase flow rates of each of the completed intervals for oil, gas, and water production of the jth completed interval are as follows:
- 8. The method of claim 7, wherein the corresponding fluid phase flow rates in each interval of the wellbore are defined mathematically for oil, gas and water for the nth wellbore pressure traverse segment as follows:
- 9. The method of claim 1, wherein the flow rate and pressure traverse computation in the computation step are performed in a sequential manner for each interval, starting at the wellhead and proceeding to the deepest completed interval.
- 10. The method of claim 1, wherein the measured pressures of step a are obtained from production logs or from pressure gauge recordings.
- 11. The method of claim 1, wherein the measured fluid phase flow rates of step a are obtained from spinner measurements or from production logs.
- 12. The method of claim 1, wherein the measured pressures of step a are permanent downhole guage measurements.
- 13. The method of claim 1, wherein the measured fluid phase flow rates of step a are obtained from permanent downhole flow meter measurements or spinner survey measurements.
CROSS REFERENCE TO RELATED PROVISIONAL APPLICATION
[0001] This application is based on Provisional Application Ser. No. 60/231788 filed on Sep. 12, 2000.
Provisional Applications (1)
|
Number |
Date |
Country |
|
60231788 |
Sep 2000 |
US |