The present invention concerns improved methods and devices for construction of permanent perimeter foundations and anchorage therefore, especially for pre-situated structures, such as mobile homes and modular housing. Specifically, the present invention particularly concerns an improved method using pre-hung corrugated steel wall panels that is cast-in-place with footing concrete thus creating a structural foundation wall. The relevant components and methods allowing this new method are also disclosed.
Conventionally, perimeter foundation walls are built from the bottom up. After a site is prepared, the geometry for that foundation is typically created by careful measurement and the setting-up of strings which each define a face of the foundation. Then the foundation walls are built as close as practical to these string lines, while attention is paid to level and plumb, et cetera.
A procedure such as this is typically followed for a perimeter foundation of a prefabricated modular structure, which must subsequently be positioned upon that foundation. Unless a crane of suitable capacity is available, setting the modular unit(s) upon the finished foundation involves a difficult process of sliding, adjusting, lowering, fitting, blocking, and attaching. Quite often the foundation will have enough deviation in accuracy to cause problem with fit of the modular unit(s).
The use of corrugated panels, by themselves, as bearing walls is a practice known to be utilized in light steel building construction to a limited degree. Corrugated steel sheet-piles are common in earth-work as temporary or permanent load-bearing and retaining walls.
U.S. Pat. No. 3,820,295, by M. Folley, June 1974, discloses the use of corrugated steel foundation walls cast into concrete, as part of a system for constructing a corrugated panel building. Inverted “T” sections of corrugated panels are set into a trench, then partially cast into concrete, and finally remain as foundation walls. These panel “T” assemblies are built of perpendicular (horizontal) panel elements attached along the bottom edge of the wall (vertical) panel elements with continuous gusset elements each side, by welding upon each flute of each corrugated element to each flange of both continuous gussets. Multiple holes are also placed in the gussets and the horizontal corrugated panels, apparently to help allow some flow of the concrete throughout the assemblage.
The “T” panels disclosed cause considerable and unnecessary manufacturing expense and storage difficulties, while presenting an obstruction to the placement of concrete within the confines of a trench. The continuous “T” element causes difficulty in the required pre-support of the panels by adding extra weight, requiring extraordinarily accurate or over-sized footing trenches, and especially because the horizontal plane presence will catch the concrete being placed so creating a devastatingly high load upon the temporary support to the panels.
It could be assumed that the intended general construction sequence is conventional, but no disclosure is given for a method of pre-situating the panels. This aspect of that invention's foundation is the most important because the panels would have to be cast in place exactly, straightly, and precisely where required to be of any use for the continuing construction of the building above, which is of pre-fabricated elements. In addition, the complications of the “T” base require that the pre-support also remain perfectly in place while under the very high loads of concrete placement. No adjustment or tolerance of significance would be possible after the panels are cast in-situ.
The Folley patent emphasis is on the unique construction above the foundation walls. Based upon the disclosure given, that foundation method appears to have not succeeded in construction practice, let alone provide cost efficiency.
U.S. Pat. No. 6,076,320, by M. Butler, June 2000, the disclosure of which is hereby fully incorporated by reference, discloses a perimeter wall foundation that is created by attaching galvanized-steel corrugated panels to an in-place structure. The freely having bottom edges of the panels, which have continuous deformation specific to the enhancement of bearing and anchorage within concrete, are cast in-situ with footing concrete, so becoming a cast-in-place perimeter-wall foundation, capable of residential-scale bearing and shear loadings.
However, there is still a need for improvements cast-in-place foundations for use in multi-unit modular buildings and off-frame prefabricated modular housing.
The present invention involves an improved manner of constructing a perimeter-wall foundation for multi-unit modular housing and off-frame prefabricated modular housing.
Prefabricated Modular Structures
For the case of a pre-fabricated/modular structure, such as a mobile home, the unit(s) is set upon its own internal piers by conventional methods, such as utilizing stacked concrete blocks upon treated-wood or concrete pads. Additional, permanent internal piers are placed at structural load bearing points, especially for multi-unit modular buildings. Then any number of variously-selected-height corrugated panels may be hung from the perimeter or interior of the unit(s) and so dangling partially into a trench, contiguously attached, along a location where is desired a foundation wall. The action of gravity keeps the panels vertical, then in-situ concrete is placed into the trench, flowing about the specially deformed lower edge of the panels and permanent internal piers. The panels and internal permanent piers are adjusted more finely to vertical before the concrete hardens, so creating a true foundation wall having superior anchorage to the concrete footing, with a minimum of effort and cost.
Site-Built Structures
For the case of a site-built structure, a linear element is pre-situated along a location of perimeter or interior line of support. The element can be initially supported by conventional means such as wood stakes, or by any suitable proprietary method. The element can be removable, or be a stay-in-place member such as a rim-joist. The method of casting-in-place the foundation wall panels is essentially identical to above, as is the result.
Thermal Isolation
For foundations of metal buildings in cold climates, this invention contemplates improvement of the thermal isolation in connection of the metal foundation-wall to the metal building-structure, whereby heat transmission from the metal structure to its foundation interface is minimized.
A common practice in metal building construction is to wrap exterior walls externally with a layer of insulating foam, and economic factors often dictate sheathing that foam with a stucco-cement product. This invention provides apparati and method for allowing this same cost-effective foam-wrap and sheathing method to occur on the foundation walls, while providing a barrier preventing capillary transportation up those wall layers, and where that barrier is also a screed (thickness-guide) for placement of that stucco-cement.
System for Variable Sites
For all embodiments of this invention, variable building heights and sloping sites can both be addressed by creating a system of panels of discrete standardized lengths, so that a panel length can be selected from this system which will suit the needs of varied foundation height at according to particular location, as the concrete footing can accommodate the resulting relative differences of adjacent-stepped panel extension into footing trenches. This standardization of lengths allows manufacture of a limited number of distinct parts to serve all foundation wall cases, within the height limits of that panel strength. To greatly facilitate the determination of panel lengths and quantities, especially for sloping sites, software is utilized which accepts building geometry and relative grade heights as input, and then provides panel location and quantity by length, as output.
Labor Savings and Improvement
This is a perimeter foundation that can be built without any: geometry definition, concrete forming, form stripping, foundation pony-wall framing nor sheathing. Besides missing all of these steps, the method improves: accuracy (by geometry-duplication), foundation anchorage to concrete-footings, strength and longevity (over conventional wood-framed ponywalls that rot and become eaten by insects), ventilation options, and thermal performance.
The present invention offers distinct improvement apparati for supporting load bearing points of modular buildings, especially multi-unit modular buildings.
In summary, this foundation offers improved structure for less cost.
Specific Objects and Advantages
More specific objects and advantages of this invention include the following:
Provide an improved method allowing construction of the lowest cost permanent, continuous, perimeter foundation and permanent internal pier for a multi-unit prefabricated modular structure or the like. This method allows construction of foundation walls which provide lateral strength and uplift anchorage that is superior to any other presently available proprietary method of founding modular structures.
Provide an internal pier unit that is used in supporting load bearing points of a multi-unit prefabricated modular building system.
Provide the lowest cost method whereby three sides of the pre-hung foundation are poured and set, followed by removal of any off-frame frameworks being removed, followed by the fourth side of the pre-hung foundation poured and set. Finally, grade backfilling can occur about the perimeter of a structure that is at or above grade. This allows installation of a modular structure to inexpensively be of a low-profile set, while diverting surface water from the structure.
Provide a combination structural-wall/permanent internal pier structure and visually-appealing-screen foundation panel that can be installed before any footing concrete is placed, thus avoiding any need to fit panels to planes dimensionally confined by previous concrete placement, and also providing superior anchorage of the panels to concrete.
Provide a single, simple, quickly-installed component that can provide load bearing support thus providing permanent internal support of load bearing points, where the footing for the load bearing component is pour after the load bearing component is attached to the housing unit.
The novel features that are considered characteristic of the invention are set forth with particularity in the appended claims. The invention itself, however, both as to its structure and its operation together with the additional object and advantages thereof will best be understood from the following description of the preferred embodiment of the present invention when read in conjunction with the accompanying drawings. Unless specifically noted, it is intended that the words and phrases in the specification and claims be given the ordinary and accustomed meaning to those of ordinary skill in the applicable art or arts. If any other meaning is intended, the specification will specifically state that a special meaning is being applied to a word or phrase. Likewise, the use of the words “function” or “means” in the Description of Preferred Embodiments is not intended to indicate a desire to invoke the special provision of 35 U.S.C. §112, paragraph 6 to define the invention. To the contrary, if the provisions of 35 U.S.C. § 112, paragraph 6, are sought to be invoked to define the invention(s), the claims will specifically state the phrases “means for” or “step for” and a function, without also reciting in such phrases any structure, material, or act in support of the function. Even when the claims recite a “means for” or “step for” performing a function, if they also recite any structure, material or acts in support of that means of step, then the intention is not to invoke the provisions of 35 U.S.C. §112, paragraph 6. Moreover, even if the provisions of 35 U.S.C. §112, paragraph 6, are invoked to define the inventions, it is intended that the inventions not be limited only to the specific structure, material or acts that are described in the preferred embodiments, but in addition, include any and all structures, materials or acts that perform the claimed function, along with any and all known or later-developed equivalent structures, materials or acts for performing the claimed function.
Commencing in the drawings
Foundation panel assembly 11 is primarily made up of a corrugated foundation panel 12, with some type of component for attachment of panel 12 to a pre-situated element, such as a pre-attached perimeter channel 14 shown here. In this case the attachment component consists of a shear strip 13, which can either be continuous or of segmental lengths according to installation needs. For pre-attachment of strip 13 to panel 12, strip should be of lengths corresponding to panel widths. Break locations in segmental strips need not align directly with panel breaks, as overlap of the elements can be beneficial. These elements are described in detail below.
Panel 12 is a common galvanized steel corrugated decking panel such as those commonly used for roof decking or floor decking in building construction. The particular panel shown is a roof decking (“B-deck”) panel such as is made by any of the commercial decking manufacturers (Verco, BHP, etc), having a 38 mm (1.5″) corrugation depth, with corrugation pattern repeating at 152 mm (6″), and is typically made in 914 mm (36″) panel widths. It is not essential that this particular choice of decking be used. It is commonly available at a very competitive price due to large existing markets, and this panel serves the typical structural needs of most perimeter foundations, and it has benefit to use as a ventilated foundation wall in its pattern of corrugation.
In use as decking, these panels are conventionally oriented horizontally, as utilized to support an in-situ concrete slab roof. The “B”-deck panel has an alternating series of relatively narrow (“bottom”) and wide (“top”) flutes designed for the purposes of optimizing deck concrete usage. This alternating pattern can be utilized to advantage as a foundation wall by either maximizing potential flute-ventilation area (described below for
Lengths (heights) of panel 12 are those to suit given projects, grades, and specific location along the perimeter. As the bottom edge of panel 12 is to be cast in concrete, the exact location of that edge can vary. Thus panels can be of standardized incremental (stepped) lengths to suit any specific grades (heights), as described in the invention summary above.
Most any corrugated panel design which is adequate for the imposed loads, will serve the purpose of this perimeter foundation structural wall panel, without the presence of any other foundation wall structure such as ponywall framing, if the flutes are oriented vertically as shown. For example, corrugated panels of symmetrical sinusoidal wave pattern can also be utilized perfectly well as foundation panels in the manner shown here. Also, the panels can be of any material and design (uncorrugated) so long as foundation structural requirements are satisfied. The material chosen as structurally cost-effective for our product development is ASTM A446 Grade A (hot-dip-galvanized coil-sheet-steel), where the yield strength is at least 225 MPa (33 KSI). Most of the manufacturers of “B-deck” typically provide it with a yield strength of 258 MPa (38 KSI). A galvanizing of the standard “G-90” zinc weight, as opposed to the more common “G-60”, is preferred for the materials of panel assembly 11 installed in damp environments.
For modular housing units imposing significant gravity loads as well as lateral loads, steel panel 12 is typically of a thickness of 1.10 mm (18 gage) or as thick as 1.44 mm (16 gage) material. For manufactured homes built to the Department of Housing and Urban Development Code (HUD Code) commonly referred to as “mobile homes”, which are primarily supported along the interior chassis, panel 12 at the perimeter would then be subject primarily to lateral loads with only relatively minor gravity loads, or possibly roof snow loads. It could then be as light as about 0.720 mm (22 gage), depending upon specific lateral load, any soil retaining forces, snow loads, and geometry factors.
Panel assembly (and connection components) 11 exterior surfaces are best protected, in addition to the galvanizing, by an application of roofing tar (room temperature or hot), or water emulsified coal tar, or the like. The tar can be field applied, or the panels can be factory coated. An immediately placed, subsequent covering of sand, can provide inexpensive texture finish as it binds into the tar. The combination of these two provide long term protection of the panel combined with an aesthetically pleasing, UV resistant, foundation wall finish. Any color of paint can of course be applied over. Alternatively, any compatible texture/paint product can be applied over the cured tar.
Panel 12 is best made in incremental heights (lengths) for reasons described below, starting with a practical minimum height of very roughly 300 mm (12″). Individual panel width is not crucial, it can be an industry standard for roof decking panels such as that of 900 mm (36″), thus providing the benefits of conformity with presently available material.
Analysis of the structural properties and buckling strength of this type of decking can be quite complex, considering the combination of loadings as: a bearing wall, a beam element from out-of-plane loads such as those by retained earth, and in-plane shear loads. Decking panel testing performed at West Virginia University for combined wall-bearing parallel to the flutes and out-of-plane loadings, have shown that the specimen follow theory closely enough to confirm validity of structural formulae developed by the American Iron and Steel Institute (AISI) which have been adopted by the model building codes. The shear force within the limits of building-code-approved decking shear-strength tables can be safely superimposed, as the shear-action within these limits contributes very little to overall element stress for panels of this type. The 1.14 mm (18 gage) “B-deck” panels have a code-allowed shear-strength (while under maximum flexure) of approximately 1400 Kg force per running meter (1000 PLF), which is about four times that of common plywood shear panels that are conventionally placed upon conventional wood-framed foundation ponywalls.
Presently the structural safety of for this new use of these panels has been justified by extensive calculation based upon the AISI formulae. The strength of the panel connection and the concrete footing itself is justified by similar calculation based upon known properties of concrete. A simple calculation for the bearing strength of the panel at the footing follows. It is included to show that the panel with the simple deformation pattern disclosed is adequate for residential scale bearing loads without the need for some sort of an attached horizontal element such as Folley's “T” described in “Prior Art” above.
The series of tab 46 provides support to bottom extent of panel 12 for downward vertical loads. Considering that in this loading condition, a resulting compression zone of concrete can be considered to have an upper boundary, each side of the loading element, sloping at 45° downward. Thus tab 46 best serves bearing purposes when bent at least 45° so as to remain at the top of this compression zone, but when bent over 90° tab 46 would impart a lateral component contributing to a possible longitudinal the cracking of the concrete. Given that in-situ concrete is can be considered to be of at least 13.6 MPa (2000 PSI) design strength, each approximately 38 mm×80 mm tab can bear about 800 Kg force (1800 lb), if only 20% of the bearing area is considered effective (that nearest the panel plane). This equates to 2650 Kg force per running Meter of perimeter (3600 PLF). Soil/footing design loading is typically a third of that for residential construction, so this panel deformation pattern is clearly adequate for residential-scale bearing-wall loads.
Continuing in the drawings
Simple-cut-edge panels (
A length of reinforcing bar 42 can be secured adjacently to panel 12′ with a wire tie 38, or the like. Tie 38 can be secured around a flute via apertures 40. For panel 12, rebar can also tie to flute foot 48 via the diverging cuts discussed above. Again, this divergence helps, in this case by keeping tie 38 from slipping off foot 48.
The shear connections between adjacent panels can be the conventional steel-decking male-female seam connections, and so are not shown here. It is worth noting that conventional welded connections are best avoided here in that corrosion would be promoted at those locations. Also, foundation-wall panel access/orientation circumstances can make conventional “button-punching” of the male-female seams more difficult than it is for the conventional (horizontal) configuration of the decking. Alternatively, common panel male-female seam connections can be simply inserted, but left uncrimped, where shear-loading requirements will allow. An optimal shear interconnection for foundation-wall utilization of the panels is that made by use of an appropriate adhesive placed along the male-female seam connections. This adhesive can be most any common “construction adhesive” compound, or an urethane type adhesive-caulk, or like compound which adheres to sheet steel. This type of panel interconnection can seal one or both panel edges (ungalvanized) from potential atmospheric corrosion, and can prevent possible moisture intrusion through the foundation wall at the panel seams.
Panels can of course simply be overlapped, and just fastened together if necessary, such as is commonly done with sinusoidal-pattern corrugated-roofing material. To accommodate this type of panel lap, pre-attached connector strip 13 must of course be appropriately shorter than the panel 12 to which it is connected.
Continuing in the drawings,
Shear strip 13 is a galvanized steel strip of about 1.44 mm (16 gage) or the like that serves the purpose of attaching panel 12 to a pre-attached perimeter channel 14. The profile of channel 14 can vary considerably from that shown here, while the same concept of attachment of panels remains. Where a lower flange 23 of channel is less wide than panel 12 is thick, ventilation into the crawl-space is possible through the tops of the panel flutes, and so a continuous screen can be inserted between panel 12 and flange 23 at panel installation, if desired, similar to the screen arrangement (shown in
Bottom flange 23 can also be considered the bottom of any like perimeter element. It can be the bottom edge of a wood nailer that is often found at the perimeter of wood-framed mobile home undersides, or the bottom edge of the rim-joist described above.
Continuing in the drawings
Continuing in the drawings
Continuing in drawings
A pre-attached (factory attached) perimeter wood nailer 28, which is common to most wood-constructed modular-structures, is shown above a vented foundation panel assembly 11′. Any pre-situated member can substitute for nailer 28 for this embodiment of panel installation. Assembly 11′ includes a screened-shear-strip-assembly 30 along the interface between panel 12 and member 28.
Screened assembly 30 is of a bearing channel 32, a shear strip 13′, and a screen 34. Assembly 30 can be field-attached or factory-attached to panel 12. For any pre-attachment, any length of assembly 30 must be less than panel 12, for convenience of installation. Bearing channel 32 is a cold-formed galvanized-steel section or the like. It provides a bearing surface for nailer 28 and creates a space, approximately 18 mm (¾″) high, between nailer and top of panel 12, allowing ventilation to occur via the vertically oriented flutes of panel 12. A continuous vent slot is so created, which would otherwise be choked off by presence of nailer 28.
Bearing channel 32 upper flange can be made wider than the bottom flange, so that flute-ventilation area is decreased less by the channel presence, while bearing area presented to nailer 28 is increased. If an asymmetrical channel design is chosen, the effects of resulting eccentricity must be considered in the design of connections to panel 12 and to nailer 28.
A screen 34 can be utilized to prevent vermin access to a crawl space foundation via the vents created by the flutes in panel 12. Screen 34 can be galvanized or plastic. A heavily galvanized version has an advantage in that the presence of the extra zinc will create a field of corrosion protection for the cut edge of panel 12, although this edge is best protected with at least a spray-coating of zinc-rich paint anyway. Screen 34 is best attached to strip 13′ by placing it between strip 13′ and channel 32, as strip is factory attached to channel with a series of a rivet 20, or metal-deformity press-connections such as the “Tog-L-Loc” patented metal joining system, registered trademark of the BTM corporation of Marysville, Mich. Any other appropriate factory-made connections can of course be considered, for this or other panel assembly attachments.
Screened assembly typically comes in convenient lengths for field installation of panels 12, and can be a length corresponding to each panel width, aligning with panel seams, and with appropriate end clearances, so that each panel assembly 11′ can be installed as a unit, contiguously. Alternatively, assembly 11′ segment joints can stagger, that is, strip 13 joints can exist offset of panel 12 seams, while channel 32 joints align with panel 12 seams. This allows benefit of shear strip 13 overlap while avoiding detriment of bearing channel 32 extension, which if present, must be considered to have to be inserted between the previous panel top and member 28. Irregularities of member 28 and the previous-adjacent panel installation make this insertion potentially impossible.
Screen 34 can have a hem 36 that provides linearity and weight, thus keeping screen consistently close enough to flute ends to serve its purpose. Alternatively, screen can have a fold, and this fold can have an upward bend of very approximately 12 mm high which serves to hold up any sagging plastic vapor barrier which may be factory-installed underneath a manufactured home, thus preventing potential blockage to perimeter vent area.
Continuing in the drawings
This panel assembly 11′ is of corrugated foundation panel 12, as described for
With present material technology, panel 12 is structurally most cost-efficient if of (heat conducting) steel, thus avoidance of thermal bridging at strip 15 is certainly warranted for metal buildings to prevent heat loss in cold climates. For wood structures, the thermal isolation features at the foundation panel 11 connection are probably not necessary, but the thermal insulation from the exterior to the crawl-space, and the labor minimization and other design efficiencies of this system still pertain.
Panel 11′ is shown attached to a metal perimeter member 21 of a pre-situated metal structure. The perimeter member 21 shown here specifically is a light gage, approximately 1.44 mm (16 gage) thick, steel channel or “track” section that is at the periphery of a pre-situated floor grid system. This perimeter member 21 can vary considerably. A field floor-framing member 29 is covered with a flooring panel 31. Some type of a wall framing 33 typically attaches along the perimeter.
In an ideally thermally efficient embodiment, panels are sheathed with a rigid insulating foam 25, such as polystyrene bead or isocyanate or any other suitable type, which subsequently is covered with something such as a stucco layer 64 for weather and moisture protection. For foundation-walls below-grade at wet sites, foam 25′ can appropriately be sub-grade quality, such as closed cell urethane, extruded polystyrene, or the like. This type of a foam and stucco-product finish of course provides optimum protection and insulation for the foundation wall. It is cost-effective to stucco-sheath here if a stucco type covering is to be applied over the structure exterior anyway. Foam is conventionally installed in this manner over the exterior of metal framing in cold climates. Stucco lath wire and its attachment to thin steel is a contemporary practice, the only variation here is that foundation wall stucco lath is attached to panel 12 rather than to wall studs as above. This conventional stucco wire attachment is not part of this invention, and is not shown here for clarity.
Alternatively, the insulated panels can be of contemporary structural-insulated-wall-panels manufactured with outer laminations of metal and with expanded foam inside. These panels are commonly made with relatively minor surface fluting or even flat.
Of course where a crawl space is thermally insulated from the exterior, venting should be omitted or at least controlled. Minimal vent openings which are automatically controlled to close during cold temperatures is a conventional construction technology which is beneficial to the present foundation designs. The presence of a vapor barrier 70 on grade (
If foundation wall is to have other finishes, or no finish or insulation at all, is given to panel 11, then thermal isolation at panel connection to structure above becomes more important in cold climates.
Panel 11 is best made in incremental heights (lengths) and is connected as described above for
Strip connector assembly 15 can vary in construction. The embodiment shown in
Strip 13 is of 1.44 mm (16 gage) galvanized steel such as type ASTM A446 with a yield strength of 340 MPa (50 ksi), or the like, depending upon specific load and force considerations discussed further below. Strip 13 must be of a width that spans any distance between panel 12 and flange 23 and allows overlap with panel 12 minimally sufficient for the connection of a (field or factory installed) fastener 16, and overlap at perimeter 21 minimally sufficient for the connection of a field fastener 18. Each of these distances should be approximately a minimum of 12 mm (0.5″) for the practical considerations of making connections.
Bearing channel 20 is appropriately of 1.44 (16 gage) or 1.81 mm (14 gage) thickness galvanized steel of similar quality to the other like components, but again thickness and strength requirements will vary according to geometry and loads, discussed further below. Bearing channel vertical face 39 is of a dimension necessary to create a space below perimeter 21 for rigid insulating foam 25. Foam is of a thickness necessary for underfloor insulation for given circumstances, with or without any batt insulation between floor framing members (With underfloor foam 25, thermal conductance through metal framing members is not significant). Face 39 does have a maximum practical height that will vary considerably according to loads. A height of approximately 25 mm to 40 mm (1″ to 1.5″) suits underfloor foam insulation requirements and is generally structurally feasible.
Ledger flange 37 is of a minimum practical dimension that allows suitable bearing of structure above. This minimum dimension is roughly 10 mm (⅜″), depending upon size and weight of structure above, as well as the choice of material for isolating strip, due to its variations in bearing capacity, cost, and thermal efficiency. The practical considerations of this dimension, and that of the overlapping fastening edge of strip 13, are those related to the field installation of the panels under imperfect site conditions by potentially hasty workers.
A cover flange 41 is dimensioned to bear upon the top edge of panel 12 of given manufacture. Lip 43 acts to support the inside surface of panel directly, from out-of-plane loads, such as soil backfill 52. This reduces fastener 16 prying and tension force criteria at panel somewhat and deformation to panel 12 of a given weight from given loads, allowing lighter weight panel selection. These out-of-plane loads cause significant shear force to fastener 18, due to cantilever geometry of assembly 15. Thus panel assembly 11 fastener installation, quantity of fasteners, and bearing strip strength, must take out-of-plane loads into account. Lip 43 does not reduce tension force at fasteners 16, connecting strip 13 to bearing channel 20, thus the criteria for amount and location of fasteners 16 that connect strip 13 to bearing channel 20 depend upon this out-of-plane loading. Two horizontal rows of this fastener would be justified for a given height of channel 20, the amount of out-of-plane load, and bearing channel thickness, et cetera.
A more detailed discussion of the structural considerations of these connections and of the vertical column aspect of strip 15 follows below in the description of an insulating plastic connecting strip of
The combined contact area to structure perimeter 21 of both strip 13 and ledge 37 must be minimized to reduce the surface area that must be thermally isolated, thus minimizing both conductive and radiant heat exchange for a given expenditure in relatively expensive isolator material.
Isolator strip 27 can be one of many materials, each having some tradeoff with regard to cost and efficiency. The actual isolating material is not part of this invention. The present invention discloses a structural foundation wall connection design that minimizes contact area with a metal structure, thus giving the opportunity to cost effectively use relatively more expensive materials as isolators. It is anticipated that many technological breakthroughs in the field of thermal isolators are impending, and that widespread commercial availability of highly efficient such materials will soon follow. Heat loss is proportional to this contact area, for any type of insulating material, so this invention has improvement in use with more common, less efficient isolators.
For situations where the supported structure does not impose tremendous concentrated bearing loads at any point along the perimeter, isolating strip 27 can be of an adhesive foam strip, or possibly two strips for ease of installation, one along ledge 37 and one along strip 13. Isolating strip 27 can be of relatively high density (50 shore A) closed cell vinyl foam such as 3M™ 4500 series foam tape which has minimal water absorption properties. This is a relatively economical isolator. It has a conductivity (u) of 0.043 W/m*K, which is about one thousandth the conductivity of steel at 46 W/m*K, and so it presents a virtual “brick wall” to conductive heat loss through the steel structure. A thickness of 3 mm (0.125″) presents an R value of 0.41 ft2*F*h/Btu, which is low compared to fiberglass batt insulation of a few inches thick, but the area presenting heat loss is very small. Where this juncture is within a perimeter-insulated controlled-vented crawl space, the temperature difference between the steel elements is rarely going to exceed about 20° Fahrenheit, so the heat loss is less than is for a 230 mm (9″) wide strip of R20 insulated exterior wall assembly at a 40° Fahrenheit temperature difference. Thus the total heat loss through the foundation can be shown to be relatively minimal, even utilizing low-cost isolators.
Controlled-vented crawl spaces are typically minimally vented with heat-sensitive shuttered vents that remain closed during cold periods to avoid heat loss. This type of vent can be utilized with this crawl space foundation, by making an appropriate vent installation at a penetration in panel 12 where necessary.
The nature of structure perimeter 21 and panel 11 interface is such that concentrated loads are spread out over long lengths of perimeter, so that a fairly compressible isolating strip 27 can be utilized at ledge 37 typically, without concern about effects of isolator “bottoming out” from concentrated loads. Each field fastener 18 would typically be capable of roughly 1 kN of shear through vertical face of isolator 27, and thus can generally be expected accommodate the gravity loads in shear. The compressibility, or stiffness, of isolator should be such that it will start to take up relatively large downward loads well before fastener 18 connections start to fail, considering that some amount shear-slip will occur at the fasteners 16 connecting into ductile steel through the thickness of a soft isolator.
Presently available firm-hardness isolator materials include: polyvinyl such as contemporary vinyl windows and vinyl stucco-screeds are made of; “tire inner-tube rubber” or the like; silicone-treated ceramic fabric tape (such as 3M™ Nextel™ 312 fabric of Alumina-Boria-Silica); and silicone-treated fiberglass tape, about 3 mm (0.125″) thick. Because the isolator can get wet during construction, and will frequently be at the dew point in damp climates, water-absorbing materials must be avoided. The silicone-treated ceramics and fiberglass fabrics are more costly for a given amount of thermal isolation and insulation, but they allow far higher bearing force without detrimental compression.
Screed/waterstop 19 is of non-heat-conductive material that can provide enough structure to withstand the stucco-type finish process while remaining adequately true to act as a screed. Polyvinyl (such as UV-resistant rigid reinforced PVC extrusion) sections are commonly utilized for stucco screeding presently; and, either that or a pultruded UV-resistant glass-fiber-reinforced polyester-resin section will work here as well. Screed 19 also serves as a waterstop that breaks capillary and hygroscopic moisture transportation within either foam 25′ or stucco, and along foam-to-stucco interface. Capillary transportation will not occur as greatly at foam-to-panel interface, because panel 12 contact with foam 25′ is intermittent. However, setting screed 19 in caulk or tape at panel 12 surface will terminate any upward capillary action at the foam-to-panel interface, which may still be present at screed height.
Screed 19 has a fastening lip 58 that is kept in place by the factory connection of strip 13 to panel 12 and so serves to thermally isolate panel from strip 13. A horizontal flange 60 is of a width matching combined foam and stucco thickness, as its outer edge physically defines the stucco surface plane. An optional return flange 62 is of a width that returns back to outer surface of foam 25′, to hold top edge of that foam in place, thus aiding installation. Return 62 also acts as a keeper for a spline/barrier 72, which is of similar material as screed 19, but sufficiently slender to fit within screed return. Spline is preferably less than about 1.5 mm thick, but this depends upon inside radius of horizontal flange 60 to return 62 “bend”. Spline 72 serves to keep each screed 19 aligned to the adjacent other at panel 11 joints. Spline 72 substitute-performs screed 19 waterstop function at panel joints, and so preferably is of a width that fits fairly snugly to panel outer flute face.
Screed 19 can be field-installed, as can the entire insulating assemblage, to improve panel nesting and space requirements until installed.
The heat loss via conduction through the metal fasteners located along either edge of strip 13, while difficult to calculate, will certainly contribute significantly to the amount of heat transfer through isolator 27. A solution to this loss is to replace the composite-element strip 15 with an element consisting solely of insulating-structural material, as is discussed below for
The bottom of panel 11′ has a deformation pattern along its bottom as described for
A subsequently-placed backfilled-soil-material 52 is shown at the exterior side of the foundation wall (
A length of reinforcing bar 42 can be secured adjacently to panel 11 with a wire tie, or the like, about top of foot 48. Tie wire not shown here for clarity.
The modified strip connector assembly 15′ is for applications where a stucco finish is not being used, and so has no screed 19 (
Where a recess for supporting foam is not necessary or desired, a strip connector assembly 86 without foam space is appropriate. Assembly 86 consists of: shear strip 13′ (which is of a lessor width due to the lack of a foam space); a thermal isolator strip 76 that matches strip 13′; and a thermal isolator bearing strip 74′ that matches panel 12 pattern thickness.
Isolator 76 can pre-adhere to strip 13′ for convenience. Bearing isolator 74′ has further concern about localized stress and tears than isolator 74, due to specific floor framing members potentially pressing flange 23 downward at particular locations. In addition, isolator 74′ is acting alone without the benefit of the foam space and isolator 27 above. For these two reasons, isolator 74′ should be more substantial than isolator 74, and in most cases cannot be of solely a soft foam type product. Isolator 74′ is suitably of a solid polyvinyl material of least 3 mm (0.125″) thick, or the like. A hard rubber product will seal off air infiltration at the top of panel flutes.
To effectively eliminate heat conduction from the row of fasteners 18 to the row of fastener 16, a strip connector of insulating material 80 is utilized. Strip connector 80 replaces both strip 13′ and isolator 76 with a structural vertical strip element 82, and it replaces bearing strip 74′ with an integral thermal isolator bearing strip 84. Strip element 82 and bearing isolator 84 do not have to be integral as shown, but can be each of separate extrusions and of different materials. If integral, isolator 84 is physically kept in place at the top of panel 12 before panel installation. Integral connector 80 is appropriately of high quality RPVC extrusion, or of construction-structural quality glass-fiber-reinforced plastic pultrusion such as Extren® by Ryerson Steel Inc. of Chicago, Ill. In either case, connector 80 must be of a high enough connection strength to satisfy requirements of fastener 16 and fastener 18 for given prescribed lateral loading conditions, et cetera. Vertical strip element 82 must be capable of resisting the greater of either prescribed or actual uplift forces at structure perimeter 21. For this reasons and that of a potential prying action resulting from backfill loads (described more fully below), strip 82 typically cannot be of a solely unidirectionally-reinforced plastic, such as “fiberglass” battens are typically made of.
The best performing thermal isolator is one entirely of insulating material that also creates an insulating space that can be filled with foam. A strip connector of insulating material 88 with a foam space is consists of entirely integral elements of the same extrusion. Strip connector 88 is also best of material such as high quality RPVC or GRP as described just above. Because these materials are expensive compared to steel, and connector strip 88 is relatively substantial in configuration, careful structural analysis of it is justified to minimize sectional area and therefore cost. As well as providing adequate fastener connection strength as described above, it must have adequate flexural strength, perpendicular to its longitudinal axis, to accommodate forces described below. Reinforcement within plastic section thus cannot be solely unidirectional, as a following discussion treats more thoroughly.
Elements of strip connector 88 at the connection to structure above are a vertical fastening flange 92 and a horizontal bearing flange 94.
Due to out of plane, primarily inward, loads to panel from soil backfill, et cetera, strip connector 88 tends to be rotated inwardly about the bottom of perimeter 21. This causes fastening flange 92 to experience a downward force promoting tear out type failure at any fastener 18 location, thus a solely unidirectionally reinforced plastic, such as “fiberglass battens” are typically made of, would be structurally inadequate for fastening flange 92, any possible uplift forces on structure perimeter 21 notwithstanding.
This rotational force on strip connector 88 causes downward force to bearing flange 94, the fulcrum of the rotational action. This bearing pressure is in addition to, and conceivably exceeds, gravity loads. Thus bearing flange 94 must be designed as a short cantilever for this combined loading criteria.
Insulating strip connector 88 connects to panel 12 with fasteners 16 at a vertical fastening flange 93, and also bears on panel 12 at a horizontal bearing/closure flange 96. Both fastening flange 93 and closure flange 96 must consider much of the same structural requirements discussed above for fastening flange 92 and bearing flange 94 respectively, except that inwardly-applied out-of-plane loads from backfill do not increase these forces. These loads would cause prying action at the connections made with fastener 16 without the presence of a closure lip 98. Entire cantilever distance of closure flange 96 should not be considered in determining bending force at its root because panel 12 can easily take all load at its outer face, and so flange stress-relief strain is acceptable.
The main body of connector strip 88 is a vertical structural web 90. Web 90 must be capable of withstanding flexural forces described above, combined with vertical-axial and flexural forces from eccentrically imposed gravity loads from structure perimeter 21 and flange 23. Thus web 90 can be thought of as a column stabilized from collapse by virtue of its “fixed-end” moment connections. The upper fixed moment connection is good only for inwardly-imposed out-of-plane loads to panel 12, unless bearing flange 94 is fastened to structure flange 23.
An optional integral-screed/waterstop flange 95 would be of a projecting dimension as required in description of screed/waterstop horizontal flange 80 (
Screed/waterstop flange 95 can have a return flange such as flange 62 as does screed/waterstop 19 (
Operation
An improvement necessary for supporting large or multi-unit modular structures are internal permanent load supporting piers 110. The internal permanent piers 110 comprise a central pier 115, which is preferably a standard pipe, having a cap plate 120 with at least one securing apertures 121, preferably four, located at one end 111 and a base plate 125 located at the opposite end 112. Attached on an undersurface 126 of the base plate 125 and projecting outward from the central pier 115 are at least one concrete anchor 130, preferably four concrete anchors. This embodiment is a fixed length pier where the central pier 115 has no length variability.
In another preferred embodiment, there is height adjustability of the internal permanent piers 110. Accordingly there is a pier height adjustment mechanism 140. In one embodiment, the pier height adjustment mechanism 140 is provided by splitting the central pier 115 into two nesting pipes, an internal pipe 115′ and an external pipe 115″. Located in the internal pipe 115′ are a series of radial stop aperture sets 116 which are sized to accept at least one stop 117. Thus, by placing at stop 117 into any one of the set of radial stop apertures 116 one is able to adjust the height of the internal permanent piers 110 to any reasonable height desired.
The internal permanent load supporting piers 110 are preplaced under modular building floor joists at points of load in large or multi-unit modular structures. These internal permanent piers 110 are attached to the floor joists via bolts (not shown) that are driven through the securing apertures 121 located in the cap plate 120 and into the building frame or floor joists. The at least one concrete anchors 130 are placed into a trench that is predug under the building load location. Concrete is then poured into the trench and allowed to cure, thereby providing support along the internal load line(s).
This foundation method varies according to conditions of support during and after modular-structure or floor-member installation. The foundation panel necessary strength and thickness will change according to types and amounts of superimposed loads, and will change to a lesser degree according to panel height for given loads. Also, the internal permanent pier necessary strength and central pier thickness and diameter will change according to types and amounts of superimposed loads, and will change to a less degree according to central pier height for given loads.
To determine the necessary length for each panel and internal permanent pier in order to create a structural-foundation kit, one must have site grade information (as trenched), and know the height at which the structure will be set. A simple floor plan with dimensions down to grade at certain intervals, building corners and at breaks in grade, will suffice. Panel and pier lengths should be such that they clear the bottom of the trench by at least about 100 mm (4″) to allow footing in-situ concrete placement from only the outside. A minimum clearance of 150 mm (6″) makes concrete placement from the outside only easier.
Mobile home (HUD code home) permanent installations can of course be made without a foundation perimeter of genuine structure, where State-approved moment-resisting-pier and/or cable-anchoring systems are utilized at the chassis beams. These systems do not meet the model building codes (such as for site-built structures) however, as does the present invention.
A perimeter-structure of the present invention, which is only partially about the perimeter, would be acceptable structurally in most situations in lieu of internal lateral/uplift support systems, according to typical criteria of State-approvals. Panels set only or mostly at locations where backfill is desired anyway, and/or where required structurally, is a viable cost-optimized foundation design. A continuous structural-paneled perimeter is generally preferred, however, for reasons of: allowing backfill grading, keeping out surface water and rain, heat loss control, fire safety, visual screen, allowing low-profile sets, and satisfying model building codes, et cetera.
Mobile homes generally support most or all of their weight via interior supports, which can be simple-supports, such as concrete-block or steel-tripod pier supports, at the chassis beams. Thus the structural-perimeter panels of the present invention can usually be relatively thinner and weaker than that required for normal site-built bearing walls. In general the mobile home panels are preferably installed after all permanent interior simple-supports have been completed, in other words, the mobile home is set first. Keeping in mind that sequence can vary, this method would typically be as follows:
Prepare site as required for interior and perimeter footings. Temporary interior supports, interior permanent piers and footing design can be of any conventional of proprietary means, and simple support is sufficient. Trenching for the paneled perimeter and permanent piers can be imprecise, so that layout effort is easy. Interior and perimeter trenches can conceivably be omitted altogether if the soil conditions and prevalent codes allow, and the concrete is made sufficiently stiff, but an interior and perimeter trench for the footing makes the best foundation.
Place interior pads, if in-situ concrete is to be utilized for them.
Set mobile home section(s) in place by conventional trailering methods, and onto usual interior simple-supports by conventional methods. If the interior pads are soil-contact treated-wood, then they are set concurrently with the piers.
Make utility connections, if preferable to do so now.
Hang the foundation panels, all around the perimeter, or as required by structural design. For the case where each panel assembly 11 or 11′ (of
Panel installation begins at a strategic location, keeping in mind that panels are installed in adjacent-contiguous sequence, as each with a male seam-flange interlocks to the previous-adjacent female seam (per conventional decking seam geometry). As explained in the description section above, the male-female seam shear-attachment is most easily accomplished with an adhesive. When installed continuously about the unit, the last panel must usually be cut to fit up to the edge of the first panel, and can then be attached to it by any manner. When the panel attachment is not continuous, terminal edges of panel can be reinforced with a channel-column element. For access-door openings, a single panel (with a top of cap 54,
Building corners can be followed by simply vertically saw-kerfing enough of a panel to bend at the corner location, and cutting out enough of the top strip to allow the bend. Thus the panels simply wrap around the corner and keep going. Alternatively, the panels can be cut altogether and started again at the corner, but a corner-reinforcing element should be added for this practice.
It is possible that panels could be width-dimensioned to suit particular buildings, so corner elements would accept each adjacent panel coming into a corner, and so field cutting of the panels could be avoided altogether.
Place rebar. A course of rebar is attached to panels, and can be utilized for straightening the panels to a true plane (much as the building itself does along the top) if necessary. The bar can be wire-tied to the flute feet 48, or it can be set upon the tab anchors 46 and tied where necessary. For the purposes of truing panels, the rebar is best of about 16 mm (⅝″) diameter.
Another course of rebar can also be set on spacer-blocks in the trenches, but this is not necessary to this design.
Place perimeter footing concrete, very preferably with a pump. The concrete is most easily placed from the outside when a plastisizing agent is added, adjusting the mix to create a standard truncated-cone concrete slump-test at about 7″ (180 mm). Panels are checked for plumb, and adjusted, if necessary, while the concrete is still fluid.
Install any vents, if required over what may be built into panels. These vent openings can be cut into the panels, or the vent openings can be installed at the perimeter (floor framing) above the panels.
Apply a protective finish to the exterior of panels, if desired. At locations of penetrations or cuts exposing ungalvanized edges of the panels, a zinc-rich paint can first be applied, and any recesses resulting from the cuts be caulked flush. The adjacent panel seams exposed to the exterior can be caulked, before or after any tar treatment. Then one can apply a texture finish or insulation and/or a cement-stucco, if desired.
Adjust site grades and backfill against panels as appropriate.
Non-HUD code Modular homes differ from HUD mobile homes in that they do not have a trailer-chassis built it. So generally a significant portion of the structure weight must be supported along the perimeter, and this weight must of course be considered in panel top configuration and in panel thickness. Interior supports (if any), perimeter panels, and concrete are optimally placed concurrently while modular units are on temporary supports. This could also be a two phased, interior to exterior, operation. The single-concrete-placement method would typically be as follows:
Note that because panel attachment goes very quickly, it is preferably closed-in simultaneously with, or after, any interior concrete placement, for either mobile or modular structures. This allows better access to the interior work, and tighter scheduling possibilities. Removal of temporary support is aided by creating larger-than-normal crawl space access opening(s) or by not enclosing the entire perimeter with panels, if desired. Normal minimum building code required crawl space access openings will generally allow removal of temporary supporting elements, however.
For site-built structures the panels attach to a pre-situated (by any method) linear member such as a conventional wood rim-joist, or they can attach to a pre-situated planar-floor-assembly of any type. Where these attachments allow easy access to each side of the panels for concrete placement, any need to use concrete plastisizer is avoided, and it is more practical to place the concrete without a pump, if desired. The steps to take for installing panels of this embodiment are easily determined from the description above.
This invention is independent of the method of geometry definition for the structure or element that is holding the panels in place. It is simply one that effectively exploits that geometry presence for the construction of a foundation. Thus, the geometry defining structure can be any object capable of being physically pre-supported in its finished position, and benefits by having a permanent foundation.
While most of the disclosure continuously mentions “perimeter” in association with these foundation wall panels, they can be used identically, or in different embodiments, as interior foundation walls.
The design of these apparati and methods is made to be as generally applicable as possible. This described method is possible with an assortment of existing products put to new types of use. For example, a panel of most any corrugation pattern will be able to: make the same type of top connections; utilize the same benefits of the diverging cuts along the bottom edge; and provide ventilation via the flutes, if desired.
In so far as breadth of applications, here is yet another example: These panels provide the most efficient means of placing a retrofit perimeter foundation beneath an older home (which was originally built upon now-inadequate piers). With the use of these panels, the home does not have to be lifted up and set back down. Concrete forms do not have to be set and stripped (or block-work is omitted), so avoiding all that difficult work that must be done with great difficulty in a cramped crawl space. Ponywalls do not have to be built (and made to fit into tight, irregular spaces), and then shear-sheathed.
With this new method of retrofit, the perimeter posts and piers are shifted clear of the panel location (as must be done anyway), then the panels are then simply attached and cast in concrete, etc.
Of course the variations in panel connection and in pre-situated member type can vary considerably from the operation described herein, given the permutations resulting from various panel embodiments and applications, all utilizing the same basic principles and methods presented. Although the description above contains many specificities, these should not be construed as limiting the scope of the invention, but merely as providing illustration of the preferred embodiments. The specifics shown merely depict illustration of a few of the possible configurations that utilize these cost-effective foundation panels beneficially. Variations and adaptations of this new foundation construction method will suggest themselves to a practitioner of the construction method and material arts. For example, the deformation pattern examples shown here can easily be varied considerably, or omitted altogether where load conditions allow.
It must be stressed that the present invention is independent of the physical guide, which is required to be pre-situated for the attachment and collocation of these structural panels. A few examples of that guide are given, but it can be just about anything structurally capable.
The preferred embodiment of the invention is described above in the Drawings and Description of Preferred Embodiments. While these descriptions directly describe the above embodiments, it is understood that those skilled in the art may conceive modifications and/or variations to the specific embodiments shown and described herein. Any such modifications or variations that fall within the purview of this description are intended to be included therein as well. Unless specifically noted, it is the intention of the inventor that the words and phrases in the specification and claims be given the ordinary and accustomed meanings to those of ordinary skill in the applicable art(s). The foregoing description of a preferred embodiment and best mode of the invention known to the applicant at the time of filing the application has been presented and is intended for the purposes of illustration and description. It is not intended to be exhaustive or to limit the invention to the precise form disclosed, and many modifications and variations are possible in the light of the above teachings. The embodiment was chosen and described in order to best explain the principles of the invention and its practical application and to enable others skilled in the art to best utilize the invention in various embodiments and with various modifications as are suited to the particular use contemplated.