Generally there are two types of mast nowadays: tower-type mast and horizontal mast. Both types are assembled parts by parts. Since they are assembled and dismantled parts by parts, so they have long preparation period before installation and mobilization. It is dangerous when assembling tower-type mast because it has to be operated in the air. The assembling of horizontal mast requires enough space, therefore, occupies a large area.
This new type of gate vertical elevated mast will solve the above technical problems. The mast is divided into several sections, each section has two parts, one is on the left and the other is on the right. It can be elevated vertically in a small area. It takes less time to prepare before mobilization and, it is assembled on a ground base so it avoids overhead operation, therefore, it is safe, economic and easy to install.
A gate type vertical elevated mast with open front, including: several sections. It is assembled section by section from bottom to the top. The first section is a welded integrated structure and the remaining parts are divided into two parts, the left parts and the right parts. Each part of the section is assembled by connecting front upright posts, back upright posts, upper beams, lower beams and brace rods. Then the left and right parts are connected with back beams and brace rods to form a gate type section with beams and brace rods at the left, right and back sides.
The abutting ends of the sections are positioned by inserting die nipples into die collars. Then connect the two sections with connecting pins and safety pins. The safety pins are used to prevent the looseness of the connecting pins.
Assemble the two parts of sections before install the mast. Then install a hoisting device on the substructure of the mast which is used to raise the first section of the mast. When the first section is on the supporter, connect the first section and the second section. Then raise the second section and connect the third section with the second section. Repeat the action until finishing the installation of the mast.
The sequence of dismantling the mast is the reverse to that of installation.
Each section of the mast has two parts, left part and right part, which can be connected quickly to form a mast section. Then the whole mast can be installed quickly by connecting sections in a given order. It can also be dismantled quickly and easily, therefore, greatly reduces time for preparation.
The entire installation procedure is performed on a ground base. Therefore, the whole process of the installation of the mast requires a minimum of the area and avoids the overhead operation. It takes less time to prepare before transportation. It is practical and economical and, very welcomed by people in city, mountain and farmland with limited areas.
a) and (b) show the structure of the vertical elevated gate type mast with open front with
The description of the following procedure of the new practical patent is according to
Refer to
a) and 1(b) illustrate back beams 14 and brace rods 15 of the 2nd section respectively, the racking platform 16 and the connecting beam 17 for rotary table. Please install according to
As shown in
As shown in
Then as shown in
When assembling the above mentioned sections, the abutting ends of adjacent sections are positioned by inserting die nipples 18N into die collars 18C. Then connect the two sections with connecting pins 18 or safety pins.
Descriptions of other parts illustrated in
The sequence of dismantling the mast is the reverse to that of installation.
Number | Name | Date | Kind |
---|---|---|---|
792924 | Fosgate | Jun 1905 | A |
4838191 | Corlett et al. | Jun 1989 | A |
5515945 | Smith et al. | May 1996 | A |
Number | Date | Country | |
---|---|---|---|
20070240622 A1 | Oct 2007 | US |