The present invention concerns a method and apparatus for controlling production run sequences of insulating glass units.
Window manufacturers typically receive orders that include a variety of different sizes and types of windows and/or patio doors. The different sizes and types of windows and/or patio doors require different sizes and types of insulating glass units (IGs) that are assembled into a frame or sash to form a completed window or patio door at one or more glazing lines. The window manufacturers separate and group the orders for the IGs into regular or planned production runs. The regular or planned production runs are scheduled to be manufactured in a certain sequence on a certain future date, usually within one to three business days ahead.
Variables in the manufacturing process rarely allow the regular production runs to be manufactured in the exact planned sequence. For example, rush orders for important customers and remake orders that occur when IGs break are often prioritized, changing the sequence of the production runs. The operational status of machines used to make the components of the IGs may also cause the sequence of the regular or planned production runs to be altered. Further, demand fluctuations, such as a shortage at one of the glazing lines may cause the sequence of the regular or planned production runs to be altered. As a result, a supervisor of an IG production line must constantly monitor each of the manufacturing variables and modify the sequence of the production runs accordingly.
Current methods employed by IG supervisors for monitoring IG manufacturing variables and modifying production run sequences are slow, inaccurate and confusing. The existing methods typically rely on informal communications, such as word of mouth, handwritten documents and manual data entry. Use of these non-automated forms of communication often confuse operators, tie up machines and delay standard manufacturing procedures. Use of these informal communication methods cause production efficiencies to drop even further while new employees are being trained or new machines are being commissioned.
The glass lites that are needed to construct the IGs are separated and grouped into scheduled production batches or runs. For each production batch, the glass lites are further grouped and arranged to be cut from large stock glass sheets to achieve the highest yield. The process of grouping and arranging glass lites to be cut from stock glass sheets to achieve the highest yield is called glass optimization.
Glass optimization is usually performed by a computer executing a computer program. The output from the glass optimization process is a control program that is sent to a computer-controlled cutting table. The glass optimization software outputs a computer program that optimizes one or more production batches containing patterns of lites arranged on stock glass sheets. The cutting table automatically scores the glass according to each pattern. Each production batch normally contains one or more glass layout patterns that provide a lower yield than desirable.
These Low Yield Patterns or Low Yield Sheets significantly reduce the yield of entire production batches resulting in higher manufacturing costs due to wasted glass. Waste is particularly expensive when manufacturing windows from increasingly popular specialty glasses such as Low-E or self-cleaning materials.
Today, there are several existing methodologies used to increase glass yields. Unfortunately, each method presents one or more problems to manufacturing operations. The methods and their resulting problems are described below.
This allows the glass optimization software to pick the size of stock sheets that produce the best yield. Although this method enhances yield, it also increases inventory space and costs while decreasing throughput (more glass sizes to shuttle in and out).
Although these features provide flexibility and increase yield, they also cause the cutting table to remain idle during the manual entry process.
This greatly reduces production throughput and efficiency.
In accordance with one exemplary embodiment of the claimed invention is a method for optimizing material flow and equipment utilization in the fabrication of insulating glass units in a production operation. The method comprises compiling a plurality of orders and converting the plurality of orders into production schedules for operating a plurality of processes that fabricate the insulating glass units over a prescribed period of time. The method further includes releasing the production schedules to the plurality of processes used to fabricate insulating glass units. The production schedules are accessible to users through a computer network. The method also includes monitoring production operations data produced as a result of the releasing the production schedules to the plurality of processes used to fabricate the insulating glass units and providing reports used by the monitoring production operations having image readable indicia that are imaged for providing real-time data for tracking material flow to, from, and through the processes used in the fabrication of insulating glass units.
In accordance with another exemplary embodiment of the claimed invention includes computer-readable media having computer-executable instructions for performing a method optimizing material flow and equipment utilization in the fabrication of insulating glass units in a production operation, the instructions comprising the step of producing a plurality of production schedules for equipment and assembly operations used to fabricate windows and window components over a prescribed period of time. The instructions further comprise releasing the production schedules to the equipment and assembly operations used to fabricate window and window components. The production schedules are accessible to users through a computer network. The instructions also comprise calculating production operations data associated with the productions schedules. The calculating of the production operations includes using information from continuous real-time data collected from tracking material and components through the equipment and assembly operations used to fabricate window and window components.
In accordance with yet another exemplary embodiment of the claimed invention is a method for controlling production schedules of insulating glass units, components, and materials in equipment and assembly operations comprising the steps of compiling a plurality of new, remake, and rush orders used to fabricate insulating glass units and converting the plurality of orders into production schedules for operating a plurality of equipment and assembly operations that fabricate the insulating glass units over a prescribed period of time. The method further includes releasing the production schedules to the plurality of equipment and assembly operations that fabricate insulating glass units, the production schedules being accessible to operators and management through a computer network and monitoring production operations data produced as a result of the releasing the production schedules to the plurality of equipment and assembly operations and real-time feedback information. The monitoring production operations data includes: monitoring individual machine production rates used to fabricate the insulating glass units; monitoring individual machine completion rates used to fabricate the insulating glass units; monitoring individual kanban arrival times having a known amount of material used to fabricate the insulating glass units; monitoring individual kanban consumption rates of the known amount of material used to fabricate the insulating glass units; and monitoring individual machine start times used to fabricate the insulating glass units. The method further includes the steps of alerting operators and/or management should the materials supplied to one or more of the plurality of equipment or assembly operations fall below a prescribed material queue threshold, creating a material notice condition based on the monitoring production operations data and altering one or more of the production schedules based on the material notice condition.
These and other objects and advantages of the system constructed in accordance with an exemplary embodiment of the invention is more completely described in conjunction with the accompanying drawings.
The disclosed invention provides an integrated software and apparatus solution used in the manufacture of windows and/or doors for dynamically monitoring manufacturing variables and controlling production sequences using central production control workstation 10 (
The production control terminal 18 receives the orders 16 as input and creates a sequence of runs of insulating glass units to be produced at an insulating glass unit (IG) department 26. In the illustrated embodiment, the IG department includes several insulating glass component processing machines or stations that construct IG components and assemble the IG components to create IGs. In the illustrated embodiment, the IG component processing stations include a glass cutting station 28, a spacer frame production station 30, a muntin bar production station 32, a muntin bar assembly station 34, a glass washing station 36, an IG assembly station 38, an oven 40, a gas fill station 42, and a patching station 44. Glass lites 46, spacer frames 48, and muntin bars 50 are constructed at the glass cutting station 28, the spacer frame production station 30, and the muntin bar production station respectively. The glass lites, spacer frames, and muntin bar grids 50 are assembled to form IGs at the IG assembly station 38. The IGs are fed through the oven/press 40, which presses the IG to a predetermined thickness and heats the adhesive/sealant that secures the lites to the spacer frame. The IGs are then filled with an inert gas at the gas fill station 42 and patched at the patching station 44. An IG department supervisor 45 is responsible for managing each of the IG component processing stations to ensure that demands for IGs by a glazing department 60 are met.
To simplify the disclosure of this inventive method and apparatus, the term glazing is to be interpreted as installing a glass lite or IG in any window or door component and the term sash is to be interpreted as any window or door component that surrounds a glass lite.
Once patched, the finished IGs are placed on carts 54 in a staging area 56. The carts 54 in the staging area 56 form a visual kanban system 55, providing production personnel with a visual signaling system by monitoring the number of carts in the staging area assigned to an assembly line in a glazing department 60. More specifically, the IGs are taken from the carts 54 and are assembled with window sash and frames or doors in the glazing department 60 to construct completed windows and/or doors 58. Assembly of an IG to a window or door sash and/or a frame is broadly referred to herein as glazing. The glazing department 60 includes several discrete glazing lines 62.
In the exemplary embodiment, the production control terminal 18 is a controller or ancillary computer including a programmable device in communication with a programmable device 80 located at each window component processing station and a programmable device 82 located at the plurality of glazing lines. In the exemplary embodiment, programmable devices 80 are electrically coupled to controllers of window component processing stations that include compatible machine controllers. This allows the sequence of these window processing stations to be altered automatically. Compatible machines automatically run the next production run in the sequence, if configured for Auto Sequencing. Such window component processing stations include the glass cutting station 28, the spacer frame production station 30, the muntin bar production station 32, and the oven 40, in the exemplary embodiment. Non-compatible machines utilize the satellite programmable devices 80 to alert the operator of the new production run sequence. Such stations may include a muntin bar assembly station 34, the glass washing station 36, an IG assembly station 38, a gas fill station 42, and a patching station 44.
Referring to
The screen of
The screen illustrated by
The IG supervisor alters the sequence of runs based on one of the status of the runs, the status of one or more of the glass processing machines, and the queue of insulating glass units at the glazing line at the production control terminal. In the exemplary embodiment, the following manufacturing variables can all be monitored at the production control terminal 18:
Referring to the flow chart of
The IG supervisor may view 92 the IG Department Queue at the Central Workstation 18 (see
In the exemplary embodiment, a change of the production run sequence at the central workstation, immediately changes the corresponding sequences in a database maintained at the workstation 18 and display of compatible machine controllers and satellite programmable devices. Compatible machines automatically run 110 the next production run in the sequence, if configured for auto sequencing. Non-compatible machines utilize satellite programmable devices to alert the operator of the new production run sequence.
In the exemplary embodiment, required labels and reports are automatically printed 112 for each production run using a compatible printer. A parameter in the setup menu determines how far in advance to print labels and reports for each production run. The IG supervisor may manually print selected reports via a user-friendly menu. The labels and reports will accompany the IG through the manufacturing process. In the exemplary embodiment, an operator may use the graphical display to print and/or display 114 labels, reports, and/or low queue condition statistics.
A number of factors dictate whether the IG supervisor (or the computer program loaded on the control terminal 18) needs to change the production run sequence. Examples include ease of production, delivery priority, component availability and glazing line requirements. Based on these factors, the IG supervisor uses a graphical “drag and drop” function on the screen of the control terminal 18 to change the production run sequence. In the exemplary embodiment, the system will not allow the IG supervisor to change the sequence of any completed or partially completed production runs. A partially completed production run has either been started at the machine or is reserved using a Production Run Look-Ahead Parameter. This parameter reserves a specific number of the next available production runs for glass optimization purposes or to give the IG supervisor sufficient time to print and deliver labels and reports to the production floor. The Production Run Look-Ahead Parameter is entered via a setup menu.
In the exemplary embodiment, the system may allow the IG supervisor to display the glazing line queue (see
If the “low queue condition” is met, the system automatically highlights the next available production run for that glazing line in red at the central workstation 18. This highlighting alerts the IG supervisor that he should change the sequence to prevent shutting down the glazing line.
In one embodiment, glazing line personnel may also use satellite programmable devices 82 located at each glazing line to force a “low queue condition”. This feature allows the glazing line personnel to request the next available production run for that glazing line from the IG Department at the terminal 18. Glazing line personnel may also use satellite programmable devices to prioritize specific regular, rush or remake production runs. The request alerts the IG supervisor by highlighting the corresponding production run on the display of the central workstation 18.
In the exemplary embodiment, the invention allows the IG supervisor to react to manufacturing variables by modifying the sequence of the production runs using a graphical drag and drop function. The software uses the input from the drag and drop function to create a new or altered production run sequence. Once the software has completed creating the new production run sequence, the system automatically performs the following tasks:
a) Changes the sequence of the production runs in the central workstation 18 database and updates the display (see
b) Changes the sequence of the production runs in each manufacturing machine with a compatible database and updates the display (see
c) Changes the sequence of the production runs in the database of each satellite programmable device adjacent to non-compatible machines or manual production areas and updates the display (see
d) Changes the sequence of the production runs in the database of each satellite programmable device at the glazing lines (see
e) Prints the appropriate production paperwork and labels to accompany the corresponding IG.
The system includes three software tools that help manage each glazing line queue. The first tool provides a parameter in the setup menu to dictate the minimum number of production runs staged for each glazing line. The system uses this parameter to automatically alert the IG supervisor of a “low queue condition” by highlighting the next available production run for that glazing line in red when the number of production runs in queue falls below the set minimum number. The IG supervisor will then make the decision to change the priority of that production run.
The second tool provides statistics describing the number of “low queue conditions” for each glazing line over time. This provides the IG supervisor with information to increase or reduce the size of the queue limit for each glazing line These tools help the IG supervisor optimize the size of the glazing line queues to achieve the highest throughput.
The third tool allows glazing line personnel to use a satellite programmable device 82 to force a “low queue condition” or to prioritize a specific regular, rush or remake production run for a particular glazing line. The request alerts the IG supervisor by highlighting the corresponding production run on the display of the central workstation.
The disclosed system provides the IG supervisor with real-time, accurate and simple tools to monitor manufacturing variables and control production run sequences. The supervisor will easily accomplish existing tasks in a fraction of the time, using accurate real-time data. Production run sequences will be set in plenty of time to continue standard manufacturing procedures without any loss of production efficiency.
One component of the disclosed system is a glass optimization module for increasing the yield of glass cutting runs during window or door manufacture, or other manufacture requiring glass lites. An exemplary glass optimization module or program automatically recognizes and optimizes Low Yield Sheets by adding glass lites from other production batches as well as lites entered or selected at the cutting station 28. The exemplary glass optimization module also automatically creates, tracks, selects and re-cuts remnant sheets of glass if the process is unable to add sufficient lites to eliminate Low Yield Sheets from a production batch.
The
In addition, the system tracks and reports yield, throughput and filler lite information in real-time to the cutting table display or monitor 214 as well as other computers by means of a network 216 which allows the controller 212 to communicate with other computers in the manufacturing facility, including the central control terminal 18. These other computers include computer-controlled manufacturing devices at other workstations and computer software for controlling the entire manufacturing process.
The sheet 222 is removed by an operator from one of two racks 240, 241 (
As seen in
The controller 212 or ancillary computer is capable of recognizing and adjusting to under utilized glass sheets. In accordance with one exemplary embodiment of the invention, under utilized glass sheet is any sheet where less than 70% of the sheet has lites allocated for a given job. The sheet 222 depicted in
As explained more fully below, the controller 212 or ancillary computer responds to recognition of such an underutilized sheet by laying out a pattern of lites to be cut to fulfill other lite requirements, possibly the other requirements one or more additional batches in a queue of such batches. The controller utilizes at least some of the free space 260 on the underutilized glass sheets of a first batch by designating usage of the free space 260 for other batches. The controller 212 or ancillary computer then completes the designated lites for those other or subsequent batches by laying out other glass sheets from which to cut other lites in that subsequent batch(es). This process, of course, takes into account the lites that have already been designated from the underutilized sheet or sheets of the previous batch or batches.
Operation of the Cutting Station 28
The software running on the controller or ancillary computer of the cutting station begins heuristically optimizing a next production batch in a queue of such batches by identifying a Low Yield Sheet if it exists. The controller or ancillary computer automatically calculates how to fill the sheet according to a list of priorities exemplified by the flowchart 310 in
The highest priority is a regular production batch lite P. A next highest priority is a local remake or MDI lite L. Three such lites 31 are depicted in
A next highest priority lite inserted into the Low Yield Sheet is a production run look ahead lite LA. Two such lites 232 are depicted in
The next priority lite added to a Low Yield Sheet is a filler lite F. Filler lites are certain sizes and glass types that are commonly used in production. The system adds filler lites to Low Yield Sheets to increase yield. They are stored in close proximity to the cutting table. The number of filler lites needed is noted on the display. (See
The next priority added to a Low Yield Sheet is a temporary lite T. A temporary lite is designated as a lite to be stored in a temporary cart until a cart for it's production batch has been placed at the cutting table in the positions illustrated in
The next priority added to a Low Yield Sheet is a remnant R. A remnant is designated as the remaining area of the large stock glass sheet that can be stored and used later in the optimization process. The invention will instruct the cutting table if and how to cut the remnant for easier storage and store the position and size information of the remnant for subsequent optimization.
During the glass optimization process 310 (which takes place prior to cutting) depicted in the flow chart of
The cutting table operator presses 312 a function key on the controller. The controller responds by displaying 314 a graphical display 270 similar to
The display 270 (
The operator views the Filler Lites Needed table 276 and enters the desired number of filler lites. Whenever possible, the invention adds the sizes of filler requested to Low Yield Sheet until the requested amount of filler lites is satisfied.
The operator views the Auto Sequencing Parameter. If “off”, the operator cannot change the order of the production batches in the queue. The order of the production batches will be determined by external software. If “on”, the operator may rearrange 322 the order of any production batches not started. Color coding of the display of
The operator then presses 324 the cycle start button. The cutting table will begin the next production run in the queue. The invention automatically identifies Low Yield Sheets and will calculate how to get the best yield. The sequence of steps 330 depicted in
After the cutting table scores the sheet and it remains a Low Yield Sheets and the Remnant Management Parameter is “on” and there is room to store another remnant sheet on the remnant sheet cart, the system scores the largest rectangle possible in the unused area of the Low Yield Pattern. Via the breakout monitor, the system alerts the operator to transfer the remnant sheet to a manual, semi-automatic or automatic remnant storage and retrieval system 245. The breakout monitor also indicates which cart and slot (standard or temporary cart) to place each lite via text and color coding.
The operator presses another function key at the cutting table controller to return to the previous screen.
The invention also tracks and reports yield, throughput and filler lite information in real-time to the cutting table display as well as other computers, computer-controlled devices and computer software.
Glass Demand System
In the first operation of the demand system 500 the software 510 is executed in the network 216 at 512. The software 510 supports user created merge files 514 comprising regular production orders 20, rush orders 22 and remake orders 24. The merge files 514 are structured to conveniently allow for frequent changes and/or creation of new merge files for each day or shift of production as depicted at 516. For each shift of production or during a production run, the software 510 converts the merge files into machine readable programs or machine schedules 524 at 520. The machine schedules 524 are then placed into a demand pre-release folder 518 at 522.
The demand pre-release folder 518 containing the machine schedules 524 are now readily accessible by a supervisor and/or operator via the software 510 at 526 linked to the computer network 216. At this point 528, the supervisor and/or operator can evaluate whether the machine schedules 524 are satisfactory or require modification. In one embodiment, the machine schedules 524 would be modified before the start of a shift, however, it would not depart from the spirit and scope of the claimed invention to enable the supervisor and/or operator to modify the machine schedules after a shift has started or during production run.
If the machine schedules 524 are not satisfactory the supervisor and/or operator will resequence or reassign (to alternate machines or kanbans) the machine schedules 524 to modified schedules 530 at 532. Several factors in the production operation could render the machine schedules 524 unsatisfactory requiring resequencing or reassignment 532. For example, changes in production orders 16, including regular production orders 20 and/or rush orders 22 and/or remake orders 24 could influence such required changes, low queue 76 signals or indications in the IG runs 74 for particular glazing lines 62 could provoke a change, or machine breakdown in the IG department 26 or glazing department 60. The resequencing or reassignment 532 by the supervisor or operator can be achieved at any network 216 terminal by a similar “drag and drop” application in the software 510, as previously discussed. The resequencing or reassignment 532 may change the order or amount of materials being processed at any individual line or machine within the IG department 26. This could include for example, changes to the assembly operation 38, cutting station 28, or oven 40 in the IG department 26. Similarly, changes may occur at the glazing lines 62 as a result of the resequencing or reassignment process 532.
The modified schedules 530 or satisfactory machine schedules 524 mature into final schedules 534 and are released to the machines, equipment, IG lines located within the IG department 26 or computer workstations on computer network 216 at 536. The software 510 then calculates operations data 538 based on the final schedules 534 and the sequences are released to the equipment and assembly lines. The software 510 further uses the calculated operations data 538 to perform several different computations relating to the production operations shown in
The calculated operations data 538 relating to the various operations described above, are monitored at 542 to help prevent future Out-of-Glass conditions 544 that could arise. For example, if the kanban 55 staging area 56 has only one hour of glass left in a particular glazing line 62 based on the KCR and the next cart 54 with IG units is scheduled to arrived at the kanban 55 in two hours an Out-of-Glass condition 544 is detected and the software 510 will issue an Out-of-Glass Alert 550, indicating and notifying production personnel when the kanban staging area 56 will run out of glass. In one embodiment, the software 510 will calculate which schedule or schedules 524 will be advanced 552 in the production sequence upon issuing the alert 550. In another embodiment, as shown at 554, the software 510 in anticipation of the alert 550 will calculate which schedule or schedules 524 will be advanced in the production sequence and may be automatically advanced at 556 by the software 510. In yet another embodiment, the operator or supervisor manually elects at 558 which schedule or schedules 524 will be advanced in the production sequence as a result of the calculation 552 provided by the software 510 or based on the supervisor/operator's own independent decision or instruction by another person or source.
The software 510 additionally supports a printing operation 600 that provides a number of reports that are used by both production personnel and management. The reports assist in providing real-time information 539 to the production operations data 538 via manual and automatic scanning of material throughput (discussed further below) during the manufacturing process.
The print operation 600 produces an IG Cart Report 610 for schedules 524 having at least one cut glass lite. The IG Cart Report is printed typically near the cutting glass station 28 when the schedule starts to assist production personnel in tracking the schedules 528 through the production operation. The print operation 600 also produces an IG Cart Office Report 620 for schedules 528 with all purchased glass. The IG Cart Office Report 620 is typically printed in a manager's office 625 when the schedule is released to the cutting glass station 28 for assisting management personnel in tracking the schedules 528 through the production operation. The print operation 600 also produces a Purchased Glass Report 630 for schedules 528 with at least one purchased glass lite. The Purchased Glass Report 630 is typically printed near the cutting glass station 28 when the schedule 528 starts. The Purchased Glass Report 630 assists production personnel in tracking the glass used by the various schedules 528. The print operation 600 also provides a Purchased Glass Office Report 640 for schedules 528 with all purchased glass. The Purchased Glass Office Report 640 is typically printed in the manager's office 625 when the schedule is released to the cutting glass station 28 for assisting management personnel in tracking the schedules 528 through the production operation. The print operation 600 also provides a Production Muntin Report 650. The Production Muntin Report 650 typically prints near the muntin bar station 32. The Production Muntin Report 650 assists production and management personnel in tracking the raw materials used in forming the muntin bars. The print operation 600 also provides a Production IG Report 660. The Production IG Report 660 typically prints near the spacer frame production station 30. The Production IG Report 660 assists production and management personnel in tracking the raw materials being used to make the IG assemblies in the spacer frame production stations 30. The print operation 600 also provides a Glass Label Report 670 consisting of one or more individual glass labels. The Glass Label Report 670 typically prints near the spacer frame production station 30. The Glass Label Report 670 assists production and management personnel in tracking the IG assemblies as they are routed through the production operation.
The above reports can also be used to assist in the accuracy of the calculated operations data 538 by providing real-time data. For example, a patch operator assigned to the patch station 44 will scan data (using either a stationary or portable scanner device) such as a bar code relating to the IG assemblies on the Production IG Report 660 or glass label 670 as it leaves the patching station 44. The content associated with the bar code on the Production IG Report 660 or glass label 670 is then automatically imported from the scanner to a computer on the network 216, and used by the software 510 to update the calculated operation data 538. The scanned Production IG Report and associated cart 54 is then tracked and rescanned as it enters the kanban 55 staging area 56 in the assigned glazing line 62, thereagain updating the calculated operation data 538. The software 510 and calculated operation data 538 accounts for all of the IG units listed in the cart 54 report and the operator provides further reassurance during the report or label scanning operation. A glazing line 62 operator will then scan the Production IG Report 660 or glass label 670 as it leaves the kanban 55 staging area 56, automatically initiating an update to the calculated operations data 538.
The MCT will be visually displayed on any terminal associated with the computer network 216 and displays the estimated machine completion time for each machine schedule 528 in the IG department 25 and glazing department 60. For example, the operator at a particular machine may select, for example a fourth schedule in the cutting glass station 28 in the list of schedules 528 for the cutting machine. The terminal would display the MCT in the fourth schedule in the example, showing 1 hour 20 minutes, indicating that the glass cutting for the forth schedule is calculated to be completed in 1 hour and 20 minutes. The calculated MCT can be altered to include or exclude scheduled production breaks, such as lunch, time between shifts, or breaks. The calculated MCT time excludes unscheduled machine downtime. The amount of time scheduled for production breaks could be altered in the software 510.
The MST for the spacer frame production station 30 represents the earliest possible time it could be started based on components being supplied from the glass cutting station 28 and muntin bar station 32. For example, if the MST for the spacer frame production station 30 indicates a time of 2 hours and 10 minutes at a network terminal 216, this corresponds to glass and muntin components that are required will be completed in 2 hours and 10 minutes for that particular schedule.
The MPR monitors actual machine output, excluding delays that exceed an Anomaly Threshold (AT). For example, an AT is set at 10 minutes, and the cutting glass station 28 has been producing schedules 528 at an average rate of 400 lites per hour for the previous three hours. If a 30 minute lunch break were to subsequently occur, which exceeds the AT, the software 510 would average the lites produced per hour until lunch started and store the average as the MPR value. Monitoring would not commence again until after the lunch break and cutting resumed. A new MPR would not be stored until units ran for a prescribed period of time, for example, one hour without a breach of the AT.
The AT is a prescribed period that can be varied for each machine, staging area 56 such as the kanban area 55, or line based particular needs. Any time below the AT is considered normal production delays and is averaged in the MPR. Any time above the AT is considered an irregularity and will be excluded from the MPR. The AT prevents lunches, breaks, and time between shifts from influencing the MPR time.
The MPR can further be calculated over a number of machines and assembly lines. For example, the MPR can be measured from the time a schedule 528 starts at the cutting glass station 28 until the cart 54 is scanned into the kanban 55 staging area 56. In this example, the MPR captures glass cutting, spacer fabrication, glass washing, IG assembly, IG carting, IG patch, and IG fill.
Although an exemplary embodiment of the invention has been described with a degree of particularity, it is the intent that the invention includes all modifications and alterations from the disclosed design falling within the spirit or scope of the appended claims.
The present application is a Continuation-in-Part application of currently pending U.S. application Ser. No.: 10/751,382 having a filing date of Jan. 5, 2004 entitled “Glass Production Sequencing” claiming priority as a Continuation-in-Part of U.S. application Ser. No. 10/646,191, entitled “Glass Optimization” filed Aug. 22, 2003. The present application claims priority to, and incorporates in their entireties both of the above-identified applications for all purposes.
Number | Date | Country | |
---|---|---|---|
Parent | 10751382 | Jan 2004 | US |
Child | 11652747 | Jan 2007 | US |
Parent | 10646191 | Aug 2003 | US |
Child | 10751382 | Jan 2004 | US |