This invention relates to a ground engineering method. In particular, it relates to a method for modifying geotechnically unsuitable soils at a site so as to render the site capable of load bearing.
Traditionally, when undertaking construction work at site with geotechnically unsuitable soils (i.e. soils incapable of bearing substantial loads or stresses due), a number of possible solutions exist, which can be selected to attempt to overcome the issue. Such conventional solutions include the use of structural fill (also known as “dig and dump”), by-passing the area of geotechnically unsuitable soils by piling, pre-loading the ground, or designing the structure to be built so as to minimise the effect on the ground.
In conventional piling techniques, piles are driven into the ground, down to strata with load-bearing capabilities. The depth of piling required can vary considerably in depth, as the principle behind this solution is to transfer the load imparted by a building constructed on the site via the piles to the underlying strata. The upper layers of weaker soil which are incapable of supporting either the building load or the pile stresses are therefore effectively by-passed
Piling is however a time consuming, labour intensive, and costly procedure which moreover does not necessarily alleviate all of the problems presented by the presence of geotechnically unsuitable soils. In particular, because the weaker upper layers of soil are left unchanged, they continue to exhibit undesirable properties—most notably in the case of clay soils the tendency to expand and contract in the presence or absence of water, and in the case of soils having air pockets or ‘voids’ therein, the tendency to settle. Because the geotechnically unsuitable soil layers are not uniform, such expansion, contraction and settlement may occur to differing degrees across a site. This leads to differential settlement of the site, which can ultimately lead to subsidence in the foundations of the buildings constructed thereon, causing cracks in masonry, and damage to drains and other subterranean infrastructure.
Where the condition of the soil at a site is marginal, alternatives to piling have been proposed, directed to modifying the properties of the geotechnically unsuitable and marginal soils so as to render them capable of bearing a load. These proposed alternatives centre around two basic principles: consolidation, which requires the removal of water from the soils; and compaction, which requires the removal of air from the soils.
Consolidation of marginal soils, has been carried out in one form or another for many years, and is embodied in the process of soil stabilisation. Soil stabilisation is primarily used to dry out material which is too wet, and to modify chemically the make-up of the soils to enhance their weight-bearing capabilities. This process typically involves treating a hydrated clay soil with an anhydrous material such as lime, so as to reduce the water content of the soil, and to initiate a chemical reaction resulting in modification of the chemical structure of the soil so as to remove its capacity to shrink or heave in the future. Ultimately, this can enable the soil to be modified so as to exhibit granular rather than cohesive properties.
Compaction requires the physical application of a load to the ground, so as to force the soil particles closer together, thereby expelling air. A number of compaction techniques are available, the type selected being determined by the depth of influence required.
Standard compaction techniques involve mechanically driving a cylindrical roller over an area of ground so as continuously to compact the soil layers therebeneath.
Dynamic compaction (DC) improves the mechanical properties of the soil by repeated application of very high intensity impacts to the surface, achieved by dropping a weight across the surface to be compacted. The effective depth of the treatment will be determined by the magnitude of the weight and the height of the drop. Dynamic compaction has been found to have an influence on soils in excess of 20 m below ground level. The type of dynamic compaction selected will depend on the geotechnical conditions to be addressed.
A variation of this technique, known as rolling dynamic compaction (RDC) has been developed, in which a roller having a non-circular cross-section is used. RDC rollers have been developed having generally polygonal cross-sections with 3, 4, or 5 sides. The principle behind rolling dynamic compaction is that as the non-circular roller is driven across the ground and caused to rotate, one apex after another will be raised to a zenith, thus effectively gaining potential energy, before being released by compression springs to fall under gravity. The potential energy is thus converted into kinetic energy, which in turn is transferred to the soil when the apex reaches the lowest point of its cycle upon impact with the surface of the ground.
Rolling dynamic compaction is capable of delivering significantly greater loads to the soil than dead weight or vibrating compaction, due to the height and weight multiplier factor which is inherent in its design. As a result, whilst other compaction methods are capable of delivering a high degree of compaction to soil layers near the surface of the ground, rolling dynamic compaction has been found to achieve compaction of soils in excess of 5 m below the surface.
Both soil stabilisation and rolling dynamic compaction produce satisfactory results in modifying marginal soils, though the processes work in substantially different ways. However, in situations where the soil at a site is geotechnically unsuitable, neither soil stabilisation nor rolling dynamic compaction alone can modify the soil properties to such a degree that piling is no longer required. Instead, so-called “dig and dump” techniques must be utilised, in which the geotechnically unsuitable soil is excavated, removed from the site, and disposed of. Dig and dump techniques are undesirable due to their environmental impact both in terms of lorry movements and use of landfill sites, as well as being costly, time consuming and labour intensive.
Hitherto, no single method has been developed which is capable of modifying geotechnically unsuitable soils to such a degree that the need for piling is disposed of altogether. Furthermore until now, the prevailing conventional wisdom within the construction industry has held that the effects of soil stabilisation and rolling dynamic compaction are competing processes which cannot be utilised in tandem.
The present invention stems from the realisation that, contrary to the beliefs of many within the construction industry, the techniques of soil stabilisation and rolling dynamic compaction can be adapted to work together in synergy. The present invention therefore seeks to combine these two traditionally disparate techniques in a single ground engineering method, whereby geotechnically unsuitable soils are modified so as to render them capable of load bearing. The present invention further seeks substantially to reduce or eliminate the need for piling and “dig and dump” techniques to be carried out at sites comprising geotechnically unsuitable soils. This will result in construction projects benefiting from significant cost savings, shorter construction times and reduced environmental impact. The present invention further seeks to deliver a method whereby a geotechnically unsuitable site is modified such that the risk of differential settlement following construction on the site is substantially reduced or eliminated.
According to the present invention, there is provided a method of modifying geotechnically unsuitable soils at a site so as to render the site capable of load bearing, said method comprising steps of soil stabilisation and rolling dynamic compaction.
The present invention is not limited to the application of any particular theory or hypothesis. However, it is believed that the synergistic effect observed when combining soil stabilisation and rolling dynamic compaction according to the method of the present invention, results from the soil stabilisation processes breaking down the structure of the soil, thus enabling the rolling dynamic compaction step(s) to expel air and water, thus causing compaction and consolidation. It is also believed that soil stabilisation improves the soil strength, so that more dynamic force can be applied during rolling dynamic compaction, thereby increasing the compaction and consolidation effect. In order to achieve this synergistic effect however, the soil stabilisation process must be adapted from conventional treatments—that is to say, the soils must be modified in excess of normal techniques, and in particular must have a moisture content of less than the standard optimum moisture content.
Preferably, the method of the present invention is performed according to a sequence comprising the following steps:
The soil stabilisation treatments in steps (b) and (c) preferably involve treating the soil with one or more powder or binder materials selected from cement, lime (calcium oxide), pulverised fuel ash (PFA) and ground granulated blast-furnace slag (GGBS). The powder or binder materials are preferably selected so as to provide autogenous ‘healing’ properties, to enable the soil to recover its strength after the application of RDC.
The use of lime is particularly preferred, since anhydrous calcium oxide reacts with the water of hydration in the soil so as effectively to remove water from the soil, according to the following exothermic reaction, in which the heat produced also causes further drying of the soil by evaporation:
CaO+H2O→Ca(OH)2
In the in situ soil stabilisation treatment in step (b), the calcium oxide is preferably mixed into the soil at the base of the excavated site by rotavation, to a depth of substantially 300 mm. The soil stabilisation treatment applied to the excavated soil in step (c) also preferably includes a step of mixing the calcium oxide with the excavated soil.
The soil stabilisation treatments in steps (b) and (c) are preferably continued until the moisture content of the treated soil is reduced to substantially 3% less than the standard optimum moisture content for the type of soil being treated.
The rolling dynamic compaction treatment carried out in steps (d) and (h) may be performed with any suitable construction of RDC roller, however it is currently preferred to use a 4-sided, 8 or 12-tonne roller for this treatment. Rolling dynamic compaction is preferably continued until effective refusal is achieved (i.e. until no further compaction of the underlying ground is possible). In practice, this is likely to be achieved after in the range of 20 to 40 passes of the RDC roller for the base layer in step (d) and after 20 passes for the compound layers in step (h).
The compaction applied in step (f) need not be rolling dynamic compaction, since only the individual layers of backfilled material are required to be compacted in this step, rather than compacting areas deeper below the site surface, as in steps (d) and (h). The required zone of compaction influence is in step (f is therefore typically only in the range of from 300 to 600 mm. Preferably therefore, compaction with a vibrating cylindrical roller is utilised in step (f), and is continued until substantially 95% compaction of the layer formed in step (e) is achieved, as measured by the Proctor dry density test.
The method of the present invention eliminates the need for costly or environmentally unsound techniques such as piling or ‘dig and dump’ at a site comprising geotechnically unsuitable soils, by excavating, modifying, backfilling, compacting and consolidating the soils. The resultant backfilled site then comprises a system of re-engineered soils, which, in addition to exhibiting load-bearing capabilities sufficient to allow construction on the site, also effectively acts as a single mass due to the extensive consolidation and compaction. This effectively eliminates the risk of differential settlement, and hence subsidence, at the site.
The re-engineering of the site so as to produce a consolidated and compacted mass makes the method of the present invention particularly applicable to sites comprising expansive clay soils. In this situation, the soil stabilisation steps (b) and (c) preferably include soil modification treatment so as to prevent the subsequent swelling and contraction of the clay soils in the presence of water.
In a variation of the method of the present invention, an additional step is included, between steps (d) and (e), whereby there is introduced into the excavated site an additional layer having pipes for connection to a geothermal heating system.
In order that the present invention may be more fully understood, a preferred embodiment thereof will now be discussed in detail, though only by way of example, with reference to the following drawings in which:
Referring first to
As can be seen from
The reinforced concrete beams 26 and piles 25 serve to transfer the load imparted by the building 30 to the load-bearing strata 24, effectively by-passing the upper strata of geotechnically unsuitable soils 21, and the intermediary natural ground strata 23. However, since drainage and paving 31 is located in the zone of geotechnically unsuitable soils 21, it must be formed with a flexible construction so as to account for any differential settlement, expansion or contraction of the upper strata 21.
Referring now to
As can be seen in
The method of the present invention eliminates the need for reinforced concrete beams 26 and piles 25 and instead allows the building 30 to be constructed on traditional foundations 33 incorporating a stone slab 34 and strip footings 35 set into the raft 32 of re-engineered soils. Since the drainage and paving 31 are now located within the raft 32 rather than in the surrounding zone of geotechnically unsuitable soils 21, they can now be formed with a fixed, rather than a flexible, construction. The raft 32 of re-engineered soils will exhibit uniform properties of settlement, expansion and contraction, thus effectively eliminating the risk of subsidence.
An example of the method of the present invention will now be described with reference to
The method of the present invention begins with the preliminary steps of: (i) investigating the site to determine the characteristics of the soils in the various strata 21, 23, 24; and (ii) determining the building load and design requirements. From the data acquired in these steps a further preliminary step (iii) is carried out, in which the parameters of the ensuing process are determined. These parameters included the required excavation depth x, the required composition of the soil stabilisation treatment formulations, the required individual backfill layer thickness, the required compound layer thickness, and the required backfill level, as will be described in more detail below.
Referring now to
The excavation of the site 40 in this way also provides a number of further opportunities which may be incorporated into the method of the present invention. For example, any contaminated materials identified during the preliminary site investigation step (i) can be modified to make them safe from leaching, and then buried at the bottom 41 of the excavated site, away from possible human contact, and isolated from drainage and other services. Another option is the incorporation of pipes (not shown) for a geothermal heating system, which can be incorporated at the base 41 of the excavated site, i.e. at a depth x of around 3 m. This is particularly advantageous since the depth of installation is key to the efficiency of such systems, whilst the pipes would also be protected deep under the building 30, away from other services and infrastructure.
After each main method step, a supplementary step (iv) is carried out, wherein the condition of the soil is tested and monitored so as to ascertain and verify the extent of consolidation and compaction.
Following excavation of the site 40, method steps (b) and (c) are performed, wherein soil stabilisation treatments are applied, respectively, to the newly exposed base surface 41 at the bottom of the excavated site 40, and to the volume of soil excavated from the site 40. Both steps involve treating the soil with a formulation comprising calcium oxide or other suitable binders, and mixing said formulation into the soil.
Having applied the soil stabilisation treatment to the exposed base surface 41 in step (b), the exposed base surface 41 is then subjected to rolling dynamic compaction (RDC) in step (d), using a four-sided RDC roller 42, as represented schematically in
Referring now to
The next step (g) of the method involves repeating steps (e) and (f) of forming layers 43 of re-introduced treated soil and applying standard compaction 45 to the newly exposed surface 44. This cycle is repeated until the total depth of the formed layers 43 reaches a pre-determined thickness y, generally in the range of from 1.0 to 1.5 m, as shown in
The multiple layers 43 are then subjected to a step (h) of applying rolling dynamic compaction 42 to the newly formed exposed surface 44 so as to form a compound layer 46, as can be seen in
Referring now to
The surface 22/44 of the site 20/40 is then subjected to a final treatment of rolling dynamic compaction 42 so as to compact the new layers 43 and compound layer 46 to form a raft 32 of modified soils, with a depth substantially equal to x as shown in
Number | Date | Country | Kind |
---|---|---|---|
0608901.5 | May 2006 | GB | national |
Filing Document | Filing Date | Country | Kind | 371c Date |
---|---|---|---|---|
PCT/GB2007/050228 | 5/1/2007 | WO | 00 | 11/6/2008 |