Claims
- 1. A ground facility for changing a wheel-spacing of a truck, comprising:
- a narrower track gauge railway,
- a wider track gauge railway,
- a junction railway including two rails connecting the narrower track gauge railway with the wider track gauge railway and including a middle portion having a varying track gauge and end portions, each end portion having a constant track gauge, and
- two running paths for auxiliary wheels arranged within a region of the junction railway in such a manner as to maintain a predetermined positional gauge relation to rails of the junction railway in a plan view and to maintain a top surface of each of the running paths higher than a top surface of each rail of the junction railway beyond the middle portion of the junction railway, each of the running paths having end portions continuously inclined downwards, a gauge of the running paths decreasing towards the wider track gauge railway.
- 2. A ground facility as claimed in claim 1 further comprising a pair of inside guide rails arranged inside of the rails of the junction railway and extending beyond a whole length of the running paths within the region of the junction railway in such a manner as to maintain a predetermined positional relation of the rails of the junction railway in a plan view and to maintain a top surface of each of the inside guide rails higher than the top surface of each of the rails of the junction railway.
- 3. A ground facility claimed in claim 1, further comprising a pair of outside guide rails arranged outside of the rails of the junction railway and extending beyond a whole length of the running paths within the region of the junction railway in such a manner as to maintain a predetermined positional relation to the rails of the junction railway in a plan view and to maintain a top surface of each of the outside guide rails higher than the top surface of each of the rails of the junction railway.
- 4. A ground facility as claimed in claim 1 further comprising a pair of inside guide rails arranged inside of the rails of the junction railway and extending beyond a whole length of the running paths within the region of the junction railway in such a manner as to maintain a predetermined positional relation to the rails of junction railway in a plan view and to maintain a top surface of each of the inside guide rails higher than the top surface of each of the rails of the junction railway, and a pair of outside guide rails arranged outside of the rails of the junction railway and extending beyond the whole length of the running paths within the region of the junction railway in such a manner as to maintain a predetermined positional relation to the rails of the junction railway in a plan view and to maintain a top surface of each of the outside guide rails higher than the top surface of each of the rails of the junction railway.
- 5. A ground facility as claimed in claim 1 wherein the running paths are arranged inside of the rails of the junction railway.
- 6. A ground facility claimed in claim 1 wherein the running paths are arranged outside of the rails of the junction railway.
- 7. A ground facility as claimed in claim 1 wherein each running path is parallel to one of the rails of the junction railway in the middle portion.
- 8. A ground facility for changing a wheel-spacing of a truck, comprising:
- a first railway having a first gauge,
- a second railway having a second gauge larger than the first gauge,
- a junction railway including two rails connecting the first and second railways and having a region with a varying gauge, and
- two running paths for auxiliary wheels extending alongside the junction railway and having a gauge which decreases towards the second railway, each running path having a top surface higher than a top surface of an adjoining rail of the junction railway in the region with a varying gauge and two end portions inclined downwards.
- 9. A ground facility as claimed in claim 8, wherein each of the running paths is parallel to one of the rails of the junction railway in the region with a varying gauge.
- 10. A ground facility as claimed in claim 8, wherein the junction railway includes two end portions of constant gauge disposed at opposite ends of the region with a varying gauge.
Priority Claims (2)
Number |
Date |
Country |
Kind |
4-308151 |
Oct 1992 |
JPX |
|
4-308152 |
Oct 1992 |
JPX |
|
Parent Case Info
This application is a division of patent application Ser. No. 08/421,267, filed on Apr. 13, 1995, now U.S. Pat. No. 5,546,868, which is a division of patent application Ser. No. 08/139,175, filed Oct. 21, 1993, now U.S. Pat. No. 5,421,265.
US Referenced Citations (12)
Foreign Referenced Citations (8)
Number |
Date |
Country |
208295 |
May 1907 |
DEX |
2738046 |
Feb 1978 |
DEX |
2739670 |
Mar 1979 |
DEX |
16326 |
Dec 1884 |
ITX |
54-47221 |
Apr 1979 |
JPX |
16256 |
Jan 1884 |
GBX |
18292 |
Jan 1911 |
GBX |
1173069 |
Apr 1969 |
GBX |
Non-Patent Literature Citations (1)
Entry |
"Talgo Trains On Two Gauges", The Railway Gazette, 1969, pp. 136-138 and 142. |
Divisions (2)
|
Number |
Date |
Country |
Parent |
421267 |
Apr 1995 |
|
Parent |
139175 |
Oct 1993 |
|