This is a continuation of International Application PCT/GB2011/050507 with an international filing date of Mar. 15, 2011.
The invention relates to hollowcore apparatus for forming a concrete hollowcore slab, a method of forming a concrete hollowcore slab, and a hollowcore slab formed using such apparatus and/or such a method.
Hollowcore slabs are well known and used in numerous applications and situations. A hollowcore slab is a reinforced or prestressed precast concrete slab which is used as a floor or wall slab/panel in applications in residential, commercial and industrial structures.
The known slab is rectangular in cross section with hollow voids at its central depth which have the effect of lightening the slab without significantly reducing its strength. Commonly, the slabs are between 150 mm and 600 mm in depth but deeper slabs are being considered.
The voids or cores in the cross section of the slabs are prismatic in cross section and are commonly circular, particularly in the shallow slabs, with deeper slabs using oval or square cores. The voided percentage of the unit cross section is commonly in the range of 40% to 60%.
Voided prestressed and reinforced concrete slabs are not new. Originally they were made by having lost inserts to form the voids. The cast in lost inserts have been card or plastics.
In known applications, the concrete has been a conventional mix and has been compacted by vibration.
Hollowcore slabs are manufactured using four main methods: extrusion; slip-forming; shear compaction; and hydraulic extruder. However as the slabs were developed to be deeper and the spans therefore became longer a number of disadvantages became apparent and which either limit further development, or make the slab inappropriate for its intended application.
Conventionally, a hollowcore slab is cast on a prestressing bed of length depending on the production system to be used. The bed is usually fixed but can be moveable and is usually in the order of 50 to 200 metres in length. The casting line is topped with a steel pallet upon which the product is cast and beneath which, commonly, pipes to carry steam, hot water or hot oil are provided to assist the curing of the concrete unit once it is made. Other means of curing may also be provided.
For the manufacture of prestressed hollowcore slabs, jack heads of concrete and steel are provided and between these the steel tendons/strands are run and which eventually provide the prestress in the unit. The strands are stressed by pulling them with jacks, either individually or together and are anchored to the jack heads. The thrust onto the jack heads from the prestress may be in the order of a few hundred tons and this is carried in the floor or in part of the manufacturing bed between the jack heads at each end of the production line.
When the line has been stressed the hollowcore manufacturing machines are started, filled with concrete and generally, automatically, pass down the line.
The prestress in the steel strands is eventually transmitted into the hollowcore slabs by surface bond and therefore it is important that strong well consolidated concrete is always used.
For the slip forming technique, the hollowcore machine is towed or is driven along the production line leaving the hollowcore slab behind. The machine, being independent of the mix it is casting, creates the possibility of inferior final slab quality.
For the extrusion technique, the hollowcore machine is propelled along the line by exerting pressure in the fresh concrete of the hollowcore slab that it leaves behind. The machine is neither self propelled or pulled. The slab is therefore extruded. European Patent Application 92305088.4 describes the hollowcore extrusion method of manufacture.
For the shear compaction technique, an adaptation of the extrusion process specifically developed to try and reduce noise and wear of main parts of the machine whilst operating is provided. Strength of the resultant concrete is compromised, however, necessitating the reduction of the stressing load on the strands requiring proportionally more strand than the pure extrusion process.
For the hydraulic pulsating extruder technique, the hollowcore machine is pushed along the line by the action of forcing concrete into a chamber with steel cores/tubes passing there through. The continuous forcing action, for example, a pulse every 5 to 10 seconds, moves the machine away from the compacted concrete. Spare parts replacements are reduced with this new technology when compared to the Extrusion process.
These aforementioned mechanical processes have several great disadvantages.
As the machine can only pass over longitudinal prestressing strand reinforcement it is impossible to provide transverse reinforcement horizontally or vertically. Secondary binding steel, links, stirrups, ties, and so forth also cannot be provided during forming. These secondary unstressed reinforcements are essential in parts of the world where seismic events are expected and have to be considered in the design. These factors limit the use of hollowcore slabs in buildings where high accidental forces may occur.
The only way that these kinds of unstressed reinforcements can be inserted is by manual labour following behind the machine to remove the freshly cast concrete locally, insert the reinforcement or other fittings and manually repack the void with more fresh concrete which can then be consolidated. Even with this method, it is impossible to install rectangular links or stirrups which are conventionally used in concrete elements to carry shearing forces, making hollowcore slabs less suitable for long span applications.
It is also impossible to cast in any form of fitting, inserts, threaded sockets, conduits and conduit lines, or temperature/humidity sensors because they would interrupt the operation of the machine.
Hollowcore machines must make a continuous uninterrupted length of product, usually to the full length of the long casting line. It is impossible for discreet short lengths to be manufactured because of the extreme difficulty and cost of removing under-utilised lengths of steel strand.
The continuous cast length of hollowcore slab formed using the known methods must then be cut, after curing, into individual lengths by a mechanical cutter. Saws are expensive and use a continuous supply of large diameter saw blades. A large quantity of potable water is also required to cool the blades resulting in an environmentally and difficult to manage slurry which has to be disposed of. The sawing process is a serious time constraint on the manufacturing process. Currently, health and safety regulations demand that saw cutting operators are confined in a secure control cabin, generally mounted on the saw to eliminate noise and ingress of the detritus from cutting, further increasing the capital cost of the saw.
The saw, in many respects, is therefore as complicated a piece of machinery as the hollowcore machine. These two machines, in symbiosis with each other, are fundamental to a present modern hollowcore production facility. Both machines devour spare parts and consumables at alarming rates, with a continuing use of electricity and large volumes of potable water, attended by highly competent operators, mechanics and electricians to ensure they operate effectively with the minimum of downtime.
Hollowcore machines commence casting as near as possible to one end of the line. The first batch of concrete passes through the machine before the machine can make a suitable first slab length. Similarly before the machine reaches the end of the line it continues casting past the end of the first slab length to ensure it maintains a satisfactory shape. The wasted mix at both ends of the line is also bonded with the prestressing strand. Once the strands are de-stressed and the slabs removed, the wasted ends have to be crushed, disposed of and the strand cut up to be possibly used as off-cuts. Again, this causes increased expense in terms of wasted time and environmental impact.
Presently known hollowcore machines also have the disadvantage that they are expensive to maintain and continually need spare parts because of the great wear that the reciprocating, vibrating and slipping parts experience from contact with the fresh concrete.
Present hollowcore machines also have the great disadvantage that they are very noisy requiring great care in protection of the operatives from hearing damage.
Present hollowcore machines also have the disadvantage that they can cause injury to the operatives as some machine types vibrate excessively as they place the concrete, necessitating protective cages around the machines.
The known hollowcore machines also have the disadvantage that they are generally used in large fixed factory locations which require expensive cranes and gantries to lift and service them and supply them with fresh concrete. They are not suitable for use in temporary site locations or for sites which are very distant from the factory unless there is an individual site requirement for upwards 20,000 m2.
Prestressing strands used in hollowcore slabs have a precisely designed location. Despite the fact that special locking devices endeavour to maintain the strands in the correct location inevitably because of the compacting pressure and vibration imparted by the hollowcore machine, very often the strands as they leave the locating device become out of alignment. Slabs where these strands are misplaced could possibly be rejected as being out of the strict dimensional specification.
Hollowcore slabs are lifted from the production line by special scissor clamps connected to a lifting beam held by an overhead crane. Again, this necessitates a large and permanent structure, making use unsuitable for temporary sites. Safety devices, such as chains surrounding the slab at both ends to ‘catch’ the slab in the event of the slab shearing away from the clamp on the slab sides are mandatory. For long slabs, scissor clamps are now rarely used and expensive hydraulic clamps are the preferred option. However, health and safety officers are increasingly looking for even safer means of handling long individual slabs. The only solution is a time consuming operation to remove the concrete, immediately after casting the concrete, on the upper surface of the slab to expose the cores set back from the four corners of each slab. Heavy duty lifting loops are then cast into the void using additional vibrated fresh concrete enabling the slab to be lifted safely without the need for additional safety procedures such as chains.
There is very often a requirement to make a horizontal cross connection between adjacent voids/cores in a hollowcore slab. This allows the passage of air to pass uninterrupted from one core to another and even possibly to a third core. Using existing methods of hollowcore manufacture, the only means of creating a cross connection is to manually core drill the slab after it has been removed from the casting line and installed on site.
As well as cross connections between the cores there is also a requirement to drill 120 to 160 mm diameter holes directly into the soffit of the slabs. This operation also takes place on site generally involving ‘vacuum anchoring’ upwards core drilling apparatus. All on site core drilling operations involve expensive health and safety managed labour operations, machinery and cleaning apparatus to remove unwanted detritus.
It would be an advantage to add steel fibres into a hollowcore mix, effectively introducing the equivalent of secondary reinforcement and dramatically improving the shear capacity of a typical hollowcore slab allowing for longer spans. Current hollowcore machines preclude the use of steel fibres because the low water content in the mix creates a very stiff mix essential to allow efficient compaction of the mix by the hollowcore machine. The mix is therefore not fluid enough to distribute the fibres evenly creating bunching of fibres and the action of rotating or reciprocating devices to create the cores/voids of the slab would also compromise the operation of the machine.
The invention seeks to provide a unique method of manufacturing a hollowcore precast concrete slab which allows the slab to have a number of features which are impossible to provide in a conventionally machine-cast hollowcore slab, and which provides a solution to the above mentioned problems.
According to a first aspect of the invention, there is provided hollowcore apparatus for forming a concrete hollowcore slab, the apparatus comprising a casting bed, side wall elements extending longitudinally of the casting bed which define sides of a casting mould, at least one non-sacrificial inflatable core former, at least one non-sacrificial sleeve in which at least part of the core former is receivable, the core former and the sleeve being interconnected and the in use sleeve being turnable inside out by removal of the core former from the casting bed, and at least one holder which prevents or limits uplift of the in use inflated core former and sleeve relative to the casting bed.
According to a second aspect of the invention, there is provided a method of forming a concrete hollowcore slab, the method comprising the steps of: a) preparing a casting mould; b) locating at least one non-sacrificial inflatable core former having a non-sacrificial sleeve connected thereto in the casting mould; c) providing at least one holder for preventing or limiting uplift of the inflated core former and sleeve; d) inflating the core former; e) pouring concrete into the casting mould to cover the core former and sleeve; f) deflating the core former and the sleeve once the concrete hardens, and removing the core former and the sleeve by drawing the core former out causing the connected sleeve to turn inside out and thus also be drawn out; and g) removing the hollowcore slab from the casting bed.
According to a third aspect of the invention, there is provided a method of forming a concrete hollowcore slab, the method comprising the step of pouring concrete into a casting mould having therein at least one non-sacrificial inflated core former having a non-sacrificial sleeve therearound, the core former and sleeve being interconnected at one end so that on withdrawal of the core former the sleeve is turned inside out, the inflated core former and sleeve being restrained against substantial uplift by a holder in or on the casting mould.
According to a fourth aspect of the invention, there is provided a hollowcore slab formed in accordance with the first aspect of the invention and self-compacting concrete, having a fluid-flow pipe therein whereby the hollowcore slab is adapted for use as a thermal energy store and/or secondary radiator.
The invention will now be more particularly described, by way of example only, with reference to the accompanying drawings.
a shows a diagrammatic perspective view of part of one embodiment of hollowcore apparatus, in accordance with the first aspect of the invention;
b is a lateral cross-section in elevation of the hollowcore apparatus, shown in
c is a lateral cross-section of the casting bed and longitudinal side wall shutters, showing the shutters pivoting;
d is a lateral elevation showing a joint between opposing sides of two cast hollowcore slabs;
e shows prior art lifting clamps required for a plurality of different depths of hollowcore slabs formed using known casting techniques;
f is a lateral end view of the hollowcore apparatus, in accordance with the first aspect of the invention;
a is a perspective view of the hollowcore apparatus as shown in
b is a diagrammatic perspective view of a divider of the hollowcore apparatus, shown in
a and 4b show elevational lateral views of a flexible unit which is locatable on the divider between spaced walls;
a diagrammatically shows in perspective view further parts of the hollowcore apparatus of the present invention;
b and 5c are top plan views of apparatus for first and second methods, respectively, of deploying inflatable core formers and sleeves;
d is an elevational longitudinal view of one end of the casting bed and shutters, showing parked carriage;
e is a perspective representation of a carriage;
a shows a perspective view of a capping piece utilised as part of the hollowcore apparatus of the invention;
b is an elevational lateral cross-section of part of the hollowcore apparatus showing the capping piece in use;
a) shows a second kind of holder having extended loops;
b) is a diagrammatic representation of the hollowcore slab of the third aspect of the invention having holders with extended loops and being lifted by a lifting device, such as a crane and by multiplying similar loops in a typical hollowcore slab they can act as shear connectors to a structural topping screed.
a is a perspective view showing mesh reinforcement of the hollowcore apparatus of the present invention;
b is an elevational lateral cross-section of a cast hollowcore slab showing an interconnection between upper steel bar and lower strand wires;
c shows an end of a horizontal reinforcing bar with angled ends to locate in a portion of a shutter;
a, 12b, 12c and 12d show representations of half-jointed ends of hollowcore slabs, formed using hollowcore apparatus of the invention;
e is a perspective view of part of the hollowcore apparatus of the invention, showing block outs for forming access openings to the cores or voids;
f is a lateral end view of a block out in relation to an inflatable core former, sleeve and shutter;
a is an elevational view showing two opposing walls with corbels and a hollowcore slab located thereon;
b shows a half-jointed end of a hollowcore slab formed using hollowcore apparatus of the invention and engaged with a wall corbel;
c and 13d show perspective views of voided areas of the ends of hollowcore slabs formed using hollowcore apparatus of the invention;
a and 14b are diagrammatic views of inserts which can be provided in a casting mould of the hollowcore apparatus prior to casting the hollowcore slab;
a to 15c show the provision of water pipes in the casting mould of the hollowcore apparatus prior to casting the hollowcore slab;
a to 16c shows perspective views of typical access openings into hollowcore slabs;
d to 16q show cross-connections or galleries between cores or voids, and formers for forming the cross-connection and access openings;
a shows a feed skip above the hollowcore apparatus of the present invention;
b and 17c show two kinds of restraining bar utilised for preventing uplift of the inflatable core formers and sleeves during concrete pouring;
d is a perspective view of part of the casting bed and shutters of the hollowcore apparatus, showing the restraining bars;
e shows the carriage with reeling drum and curing sheet;
a shows elements of the hollowcore apparatus of the invention used in a first method of extracting the inflatable core formers and sleeves from the cast hollowcore slab of the present invention;
b to 19e show elements of the hollowcore apparatus of the invention used in a second method of extracting the inflatable core formers and sleeves from the cast hollowcore slab of the present invention,
f to 19j shows elements of the hollowcore apparatus of the invention used in a fourth method of extracting the inflatable core formers and sleeves from the cast hollowcore slab of the present invention;
a shows part of the hollowcore apparatus, in accordance with the first aspect of the invention, and a guide for guiding the core formers and sleeves being extracted;
b to 20g show in diagrammatic form the problems associated with the fifth method of extracting a deflated core former and sleeve from a cast hollowcore slab of the present invention;
a to 21d show an alternative method of sealing the ends of a typical hollowcore floor slab; and
a to 25c depict ruching techniques of the present invention for the sleeves of the hollowcore apparatus.
The process described hereinafter is a complete production cycle. By way of example, this description starts with a clean hollowcore casting bed and explains the preparation of the bed to make hollowcore slabs; the casting of the hollowcore slab; and the specific ‘off’ critical path preparation necessary to remove the slab from the casting area creating a clean hollowcore bed once again.
The process described is by way of example only, and various options are provided which largely depend on the size of the casting bed and the size of the hollowcore slabs required. However, the embodiments and modifications described herein and throughout are provided by way of examples only, and various other modifications will be apparent to persons skilled in the art without departing from the scope of the invention as defined by the appended claims.
a) shows a 300 to 2400 mm wide from 10 to 200 metre long casting line 1, utilised to produce individual hollowcore slabs. Casting line 1 has shutters 2 attached to each side of and running along the full length of casting line 1. The shutters 2 may be manually movable or driven by motors and/or hydraulic/pneumatic. Shutters 2 create the angled sides of a typical length of hollowcore slab hollowcore slab 3 to be cast. See
Indents, in the side of shutters 2, ultimately formed in the side of all individual hollowcore slabs 3 to meet requisite design codes, are provided to form an anchoring key or wedge for cement mortar grout 5 to be poured between two adjacent hollowcore slabs 3 once installed on site. See
f) shows preferable 250 mm deep shutters 2 to make 150 mm, 200 mm and 250 mm depth of hollowcore slabs 3 by way of example. Shutters 2, once folded in to their casting condition, will always have a fixed set angle for the variety of accommodated slab depths. In other words, for the range of slab depths, the shutters do not have to be set at different angles for different slab depths. The width of the top of hollowcore slab 3, being 1170 mm for the 250 mm deep hollowcore slab 3, would make the top width of the 200 and 150 mm hollowcore slabs 3 some 3 to 5 mm wider. However, as the new hollowcore technology does not use or require independent lifting clamps 6, varying top widths of hollowcore slabs 3 can always be accommodated. Not only does this enable the engineer to specify different sizes of grout spacing 5 but the factory is not encumbered with numerous sets of varying sized lifting clamps 6.
Individual lengths of shutters 2, up to for example 6 metres long, can be hinged independently from adjacent lengths of shutters 2, at each side of casting line 1. Elongate round metal rail 2a is supported by the top surface of the shutter 2. See
Factory personnel prepare casting line 1 to cast individual lengths of hollowcore slabs 3 as follows. Shutters 2 remain hinged outwards as in
Although separate dividers 9 and 10 are suggested on base plate 7, a single lower divider having a strand cutting slot therein could be utilised.
A laser sighting target 12 is placed on the edge of the outer surface of divider 9 and the operator walks along casting line 1 and measures by a mobile laser device the exact length of the first individual hollowcore slab 3. Equally a tape measure could be used instead of a laser. At this point a second base plate 7 is preferably magnetically anchored to casting line 1 with the divider 10 positioned at the theoretical proposed lateral end of the individual hollowcore slab 3. The operation is then repeated down the full length of casting line 1 to end 13 of casting line 1 with the operator ensuring all base plates 7 are laid at right angles to the longitudinal extent of casting line 1. Thus, the lateral ends of each cast hollowcore slab 3 are 90 degrees to their longitudinal sides. It should be noted that the initial base plate 7 is set at the end 8 of casting line 1, thereby keeping strand wastage to a minimum, as will be understood hereinafter. As much of casting line 1 as possible will be utilised to cast individual hollowcore slabs 3, of varying lengths to the nearest centimetre, to suit the production schedule. For example, there could be up to twenty eight base plates 7 for each casting line 1, entirely dependent on the individual hollowcore slab lengths required and the overall length of casting line 1.
Prestressing elongate flexible elements, typically being the strand wires 14, are then laid down the length of casting line 1. The laterally spaced apart bottom curved recesses 15 of dividers 9 and 10 form the future underside radiused locations of the core or void formers. The dividers 9 and 10 provide suitable locators 18 to ‘run’ groups of strand wires 14 down casting line 1. When strand wires 14 have been anchored to the strand locator plates 16 and 17 at the ‘dead end’ of the casting line 1, see
The single strand wires 14 configuration between each proposed core/void as shown in
A polyurethane unit or similar of flexible material forming a guide unit 21, shown in
Shutters 2 along the full length of casting line 1 are now hinged inwards to their substantially vertical positions, as shown in
The sleeve 24 is always pulled or drawn along the casting line 1 from end 13 to end 8. One core former 23 and sleeve 24 is provided for each proposed core or void 19 of a particular hollowcore slab 3 to be cast. By way of example,
Core formers 23 and sleeves 24 are laid over the bottom curved recesses 15 of base plates 7. Flexible guide unit 21 with walls 22 serve to retain core formers 23 and sleeves 24 within the boundary of their final inflated shape despite the fact that they are not, as yet, inflated. Without flexible guide unit 21, deflated core formers 23 and sleeves 24 would possibly spread horizontally and haphazardly over the stressed strand wires 14, making it difficult to insert the support shutter at each end of the individual hollowcore slabs 3 to be cast, which are at the outer faces of the dividers 9 and 10. For clarity, strand wires 14 are omitted in
Continuous core former 23 and associated sleeve 24 can be made in lengths from 8 metres up to 200 metres.
There are three methods of winching along the core formers 23 and sleeves 24.
In the first method, an elongate flexible element, such as a connector 26, being in this case a rope, and around 2 to 4 meters longer than the full length of the particular core formers 23 and sleeves 24 to be pulled is attached to the end of each core former 23 and sleeve 24 via a lanyard 25. The operator then pulls connector 26 along casting line 1 which draws the attached core former 23 and sleeve 24 there behind until it reaches end 8, as seen in
The second method involves the same connector 26 or other elongate flexible element, but instead of being loose, each connector 26 is initially wound around a separate reel fixed to central shaft 27 held by a carriage 27a resting on a plurality of wheels, for example, four, which in turn lies on each rail 2a across casting line 1, see
Beneficially, to enable the carriage 27a to be moved along the longitudinal extent of the casting line 1 by providing the carriage 27a with extended or outboard axles and either movable wheels or sets of inboard and outboard wheels, the closed and open conditions of the shutters 2 can be accommodated.
The third method again involves a similar shaft 27 and carriage 27a. However, in this case, the carriage 27a is pulled along rails 2a by a powered, such as electric, winch connected to carriage 27a with a rope or other suitable elongate flexible element, and located behind end 16. Ropes 26 unwind from shaft 27 whilst the core formers 23 and sleeves 24 remain stationary at end 13. Once carriage 27a is locked into place past end 16, ropes 26 are mechanically rewound onto shaft 27 at the same time pulling the core formers 23 and sleeves 24 along the casting line 1.
Carriage 27a remains on rail 2a on support frames 2b past end 16, see
The ends of core formers 23 and sleeves 24, at end 8 in
The base of upper divider 30 covers the protruding top semi circular section of the exposed bottom strand wires 14 nestling in locators 18. Upper divider 30 in
Upper dividers 30 for making 150 or 200 mm deep hollowcore slabs 3 will have a wider top width as previously explained above. This will ensure that the sloping surface edges of the upper dividers 30 will have a tight sealed fit to the rigid sides of shutters 2.
A single metal u-shaped capping piece 31, shown in
Shutters 2 along the full line of casting line 1 are now anchored into place by, typically steel, supports 32, seen in
All core formers 23 are now fully inflated with the addition of more compressed air. Each valve 28, see
Self-Compacting Concrete, hereinafter referred to as SCC and to this point which has not been usable with cast hollowcore slabs, is then merely poured into a complete mould so there is ample scope to insert many key features into a typical hollowcore slab 3 before casting. This therefore allows these features to be bonded, formed and provided in the concrete mix at the time of pouring, rather than traditionally post-pouring. For example all secondary reinforcement links, stirrups or mesh, anchoring devices, water pipes and conduits, and so forth to meet requisite specifications can be provided for at the time of pouring, and this has not been possible using traditional known methods. Shear reinforcement can very often be combined with mandatory reinforcement that has to be inserted into individual mould lengths so as to ensure that the stability of the core formers 23 and sleeves 24 is maintained at all times during the casting and curing phases of production.
At the ends of each hollowcore slab 3, strand wires 14 are rigidly anchored in place over the lengths of the hollowcore slabs 3, typically being of up to 7 to 8 metres. Strand wires 14 therefore can provide a strong tensile restraint that can be used to eliminate the uplift from the light weight core formers 23 and sleeves 24 during the concrete casting operation.
Consequently, specially bent or hooped reinforcing bar holders 36, seen in
In each individual length of hollowcore slab 3 four hooped bars 36 will be adapted to incorporate extended loop 40, seen in
For longer spans of hollowcore slabs 3 where the overall depth is above 300 mm it may be necessary to provide additional restraint to the strand wires 14 to limit their uplift. A, preferably steel, lateral anchor or lateral prong device 42, shown in
Heavily loaded and deep hollowcore slabs 3, for example, 340 mm depth and greater, can be constructed with additional shear reinforcement to create a truss action. Top reinforcement 44 could be used and a layer of, for example, steel, mesh 45, shown in
There is an additional method of restraining uplift of the core formers 23 and sleeves 24 that could be used in certain situations.
Referring to
There is very often a requirement to insert additional reinforcement at the supporting end of a hollowcore slab 3 which is not possible with machinery cast hollowcore slabs 3a.
To enhance the strength of concrete used for hollowcore slabs 3, it is also possible to add reinforcing, such as steel fibres into the concrete mix effectively introducing the equivalent of secondary reinforcement and dramatically increasing the shear capacity of a typical hollowcore slab 3. This allows for longer spans and higher impact loads, thus meeting specifications which would not be possible without such an additive. Steel or other kinds of fibres incorporated in the hollowcore slab mix would reduce and in some cases negate the requirements for additional reinforcement 49, as detailed in
Poly-fibres can also, additionally or alternatively, be added to mitigate a fire risk. During a fire, the poly fibres tend to melt, allowing for steam migration through the slab and thus preventing or limiting the risk of spalling.
Voided area 48 is created by placing an additional base plate 7 to be laid on casting line 1 immediately adjacent to the inner surface of the end of the proposed hollowcore slab 3 at upper divider 30, see
Cores or voids 19, shown in
The support required for all hollowcore slabs 3, from both ends, is typically around 10 cm and is generally the top of a beam or, if only a wall is available, on a corbel extending from the face of the wall. There are very often aesthetic reasons to try to eliminate the unsightly beam below hollowcore slab 3 as achieved in
The voided area 60 at the end of hollowcore slab 3 is formed around the inflated core formers 23 and sleeves 24 before casting of hollowcore slab 3. However, with traditional machinery-made hollowcore slabs 3a, the voided area can only be removed after the casting operation, thus involving removal and disposal of the concrete mix.
Connections and fittings for a variety of purposes, for example, surface plates with embedded anchoring reinforcement, threaded sockets, conduits, sensors, lifting loops and water pipes can easily be cast into the hollowcore slab 3 during the new casting process, as shown in side elevation
Electrical conduit boxes 67a and cable 68 can also be located on any of the surface or soffit area and boxes 67a and cable 68 can be inserted to cross the width of hollowcore slab 3 before casting of the concrete. With traditional machinery-produced hollowcore slabs 3a, it is only possible to lay boxes and cables down the inside of the cores or voids 19 lengthwise. Boxes 67a and cables 68 also have to be exposed on the soffit in the event of wanting to cross between cores or voids 19, leading to unsightly clutter on the smooth soffit surface of hollowcore slabs 3a.
It is also possible to use a simplified alternative method of fixing lifting loops 40 as previously described with reference to
b) shows a part section through
A primary energy transfer source of hot or cold water, pumped through small diameter pipes cast into a solid concrete floor, allows concrete to be the secondary energy transfer medium providing radiant heating or cooling in a building. The system, known as Thermocast®, can now be utilised in hollowcore slabs 3 instead of solid concrete, reducing capital costs and overall self-weight of the finished floor.
TermoDeck® is another means of providing radiant heating or cooling in a building. However, air is used instead of water as the primary energy transfer medium. Treated air is passed into and out of the hollowcore slabs 3, on the one hand reducing the amount of concrete and self-weight of hollowcore slab 3 and on the other conveniently using large size cores or voids 19 in a typical slab section 20. Hollowcore slab 3 becomes the secondary energy transfer medium and as the air leaves hollowcore slab 3 it beneficially also ventilates the room.
Hot or cold water pipes in the Thermocast® process have the advantage over TermoDeck® of being able to rapidly change the slab temperature, and therefore room temperature, to suit demand. The major disadvantage however is that Thermocast®, lacks any means of providing ventilation. In a Thermocast® building the capital and maintenance costs substantially increase to accommodate two independent systems, being water heating and cooling on the one hand and a ventilation system on the other.
Using the new hollowcore technology, TermoDeck® and Thermocast® can be combined in one hollowcore slab section. This has major advantages. On the one hand, a more rapid response time for temperature change requirements in a room are possible and on the other adequate and economical ventilation can be provided for the occupants. A series of interconnected small diameter water pipes can be inserted into an individual hollowcore slab mould prior to casting, which to date has not been possible with traditional techniques. Large diameter core formers 23 and sleeves 24, which can be selected from amongst a plurality of core formers of different sizes to suit not only the span load requirements of the particular hollowcore slab 3 but also the required volume of air for adequate ventilation in the room below, are also inserted as previously described.
a) shows the principle of combining small diameter water pipes 72 with core formers 23 and sleeves 24 of a diameter to suit the energy and ventilation volume demand for a particular room. The water pipes 72 could also be located in the top or bottom halves of a typical slab section 20. Water pipes 72 are interconnected with one inlet and one outlet for each hollowcore slab 3 shown by way of example in plan view
A set of water pipes 72 are individually installed in each proposed length of hollowcore slab 3. In
Whilst
To allow air to pass into and out of the soffit or top surface of a TermoDeck® hollowcore slab 3, in
d) shows a typical plan view of a hollowcore slab 3 with three cores or voids 19 marked 19a, 19b and 19c. Inlet 74 provides an entrance into core or void 19c, and it is necessary to provide a cross connection feed 75 from core or void 19c to core void 19b and a further cross connection 75 to core void 19a. This allows the air to pass uninterrupted through the three cores or voids 19a, 19b and 19c, finally exiting from the hollowcore slab 3 at outlet 77 in core void 19a into the room below or above.
It is also essential in all individual TermoDeck® hollowcore slabs 3 that the air passing into and out of the hollowcore slab 3 via inlet 74 and outlet 77 does not leak at either end of the core or void 19a, 19b or 19c
The installation for linear outlets 77a and 77b (
An inlet air supply duct is attached to the opening inlet 74 and is conventionally inserted after the hollowcore slab 3a has been installed on-site. The holes to be drilled at location inlet 74 are initially set out by the on-site core drilling crew ensuring that along a continuous line of adjacent hollowcore slabs 3a all the centre lines of inlets 74 will be in the same plane.
The errors 79 are therefore replicated with the centres of inlet 74 and outlet 77 in each hollowcore slab 3. MEP on site staff would therefore not be able to fix a continuous straight line of inlets 74 and outlets 77. However by using an oval opener plug 78 any dimensional errors on the setting out of individual hollowcore slabs 3 can be adjusted by moving the inlet air supply duct inlet 74 and outlet 77 by plus or minus 10 to 20 mm in either direction along cores or voids 19a and 19c. This ensures a continuous straight line of inlets 74 and outlets 77 is created in a series of adjacent hollowcore slabs 3, despite the possible positional error of the hollowcore slabs 3. Sectional elevation in
d) shows by way of example two openings, being air supply inlet 74 and air outlet 77. A special proprietary diffuser may be inserted into the outlet 77 once the hollowcore slabs 3 have been installed on-site. Once again, opener inlet 78 for the diffuser is preferably oval and the width of opener 78 suits the design width of the diffuser. Top surface 80, shown in
j)(1) shows a plan view and
To install linear outlets 77a and 77b, see
k) shows a cross section of a typical magnetised linear outlet/diffuser 83 anchored to casting bed 1 beneath core former 23 and sleeve 24. Whilst for round outlets 77 the oval opener 78 is removed before installation of the outlet 77 the linear diffuser 83 can be cast directly into the hollowcore slab 3. The bottom flange 84 would therefore be flush with the soffit 1 of the hollowcore slab 3. Equally a void for linear outlet/diffuser 83 can be created by a temporary magnetised opener similar to oval plug 78 and linear diffuser 83 inserted on site once hollowcore slab 3 has been installed. In this case the flange 84 for the linear diffuser 83 is exposed from the soffit of the hollowcore slab 3, FIG. 16(1). The top surface of linear diffuser 83 is radiused similar to top surface 80 in
The installation of linear diffuser 77b,
Cover plate 87 which once again can be magnetised is placed over the three number outlets/diffusers 86 to provide an aesthetic view when looking up from the floor below of the linear outlet diffuser 77b, as shown in
Once the core formers 23 and sleeves 24 are removed and the hollowcore slab 3 removed and installed on site the airflow will be directed downwards through each of the three number outlets/diffusers 85 through the three cores or voids 19. However it is important that the supply air entering core or void 19x and 19b is restricted from moving down the length of the two core voids and instead redirected downwards through the outlets/diffusers 86. It is therefore necessary to introduce an additional concrete plug 88 into each of the two cores or voids 19x and 19b,
When all additional reinforcement, anchors and such like have been appropriately positioned into the individual mould lengths of hollowcore slabs 3 and finally rechecked, concrete is poured into all the moulds down the whole length of casting line 1. It should be noted that all items that have been inserted in the individual mould lengths of hollowcore slab 3 can be transported to their relevant locations with the storage trolley carriage 27a as previously described. SCC can be delivered via ready mix concrete truck or by overhead crane containing a feed skip in an independent factory. Generally, in dedicated factories the concrete would be batched in the factory batching plant. For a very small quantity of hollowcore slabs 3 to be made on a short length of casting line 1 a separate on-site batch plant could deliver the mix. In all cases, the mix is directed to fall into the mould between the core formers 23 and sleeves 24, thereby filling up the mould area from the surface of casting line 1 upwards. SCC will flow easily around the strand wires 14 and the inflated core formers 23 and sleeves 24.
The feed skip 91, shown in
On many typical hollowcore slabs 3 to be cast there would be no need for any additional reinforcement as previously described in
Frame 94 resting and anchored onto rail 2a can be designed to lock into place as many restraining plates 93 that maybe required. The number of restraining plates 93 along the length of an individual hollowcore slab mould could also be reduced by incorporating bar 96, preferably being rigid, continuous and formed from steel. The bar 96 is locked between adjacent restraining plates 93. Frame 94 can be made with four wheels 95 allowing 94 to move down the casting line 1 to another appropriate centralised discharging point over each mould length. Before moving, frame 94 would be raised from the fresh cast concrete manually or mechanically.
Once the casting operation has been completed, the top surfaces of all the hollowcore slabs 3 are covered with a suitable curing membrane over the entire length of casting line 1. Once again, carriage 27a is used to transport a special reeling drum 27f in
Some four to five hours after the casting of casting line 1 has been completed air valve 28 in
There are five methods of removing the core formers 23 and sleeves 24. The first method, shown in
The other four methods are mechanically operated involving a separate storage apparatus and maybe used when casting line 1 is from 10 to 200 m in length. To simplify the explanation of the originality of the removal and relaying of core formers 23 and sleeves 24, with lengths from 10 to 200 m, the typical section 20 in
For the second and third methods a simplified storage apparatus can be employed where the hollowcore factory has a small production capacity or is in a remote site with limited infrastructural facilities. The principle of removing core formers 23 and sleeves 24 however remains the same for all four remaining methods except that in the second and third methods core formers 23 and sleeves 24 are removed individually whilst in the fourth and fifth they are removed in multiples of up to possibly six simultaneously. This reduces operating work times which is of critical importance in a large hollowcore factory complex.
In the second method hooked rope 98, once again, is attached to the end of ring eye 29 of the relevant core former 23 and sleeve 24, and is initially passed through a guidance and flattening device 99 and thereafter attached to the central shaft of a horizontal reel 100, shown in
Guidance and flattening device 99 can be locked into the pathway of either of the centre lines from core formers 23 and sleeves 24 located at A, B, C and D,
To move guidance and flattening device 99 horizontally a spring mounted latch 109 mounted on top of the two support bars 105 is pulled back to release its end from notch 106. Guidance and flattening device 99 is then moved manually or mechanically and relocated into another notch 106, for example to align guidance and flattening device 99 over the centreline of D. When in approximately the right position the spring mounted latch 109 is released into the notch 106 and guidance and flattening device 99, support bar 105 and second support bar 107 are locked into place. Centerline of hinges 108 for bars 105 and 107 and the line of horizontal roller 110 on guidance and flattening device 99 form a quadrilateral rectangle such that regardless of the fixed location of guidance and flattening device 99 with each of A, B, C or D it will always be at a normal to the individual centrelines of these four core formers 23 and sleeves 24. Passing over roller 110 held by guidance and flattening device 99 core former 23 and sleeve 24 are kept in tension and then turned through 90 degrees to be tightly wound on horizontal reel 100. Spring located brake device 111 can be operated to ensure that compaction of the core former 23 and sleeve 24 wound onto horizontal reel 100 is maintained at all times.
Once a complete core former 23 and sleeve 24 have been wound onto the horizontal reel 100 the reel is removed, by crane or manual labour, from the vertical central support 112 supported from frame 101 and moved to the stock yard area for re-use for the next production cycle. An empty horizontal reel 100 is now placed over shaft 112 and guidance and flattening device 99 is lined up for removal of a further core former 23 and sleeve 24.
As core formers 23 are removed from the last cast core,
In the third method, hooked rope 98 once again is attached to the end of ring eye 29, of the relevant core formers 23 and 24 and once again is initially passed through a guidance and flattening device 99 and thereafter attached to a central shaft of a vertical reel 100 instead of horizontal, shown in
Once core former 23 and sleeve 24 have been fully wound onto vertical reel 100, the reel is removed in a similar method as horizontal reel 100. Vertical reel 100 in this case being lifted from the two support arms 114. Support frame 101, on which 114 rests, is in line with 114 to allow the operator to stand close to the vertical reel 100 whilst it is removed. Chequered plate floor platform 115 or similar is shown in
As previously explained the fourth and fifth removal methods of core formers 23 and sleeve 24 involve simultaneous removal of multiple horizontal reels 100 as the fourth method, and multiple vertical reels 110 for the fifth and final method. The explanation for multiple removal of core formers 23 and sleeve 24 for the fourth and fifth method uses the same four number core formers 23 and sleeve 24 located at A, B, C and D, in
f) and 19(g) show two horizontal reels 100 which are positioned one above the other and both supported by frame 101, with a further two adjacent reels 100 supported by another frame 101. Both frames 101 rest on one platform 102.
Once past end 13, core formers 23 and sleeves 24 pass into tube 116 at opening 116a, shown in
With all four sets of core formers 23 and sleeves 24 fully wound onto reels 100, the ropes 26 will continue for at least a further 3 to 4 metres and remain protruding out of the opening of each tube 116 in
The now empty shaft 27, resting on carriage 27a on rail 2a behind end 16,
Platform 102 in
For the fifth method of removal of core formers 23 and sleeves 24, once again a separate storage apparatus is used but hooked rope 98 this time is attached to a vertical reel 100, which is identical in all other respects to the horizontal reel 100 used in the third removal method. For clarity, the same related numbers for the third method of removal are used throughout this description of the fifth method of removal.
Vertical reel 100 is supported by frame 101 in turn resting on platform 102, see
From
The solution therefore for the fifth method of removing both round and oval horizontally flattened core formers 23 and sleeves 24 but wound onto vertical reels 100 is to remove them alternately across slab section 20, leaving an immediately adjacent core former 23 and sleeve 24 to be removed in a second operation. This two phase principle will apply to all sizes of slab sections 20 running from 150 mm deep up to 600 mm regardless of the number of core formers 23 and sleeves 24 used.
In the removal mode of core formers 23 and sleeves 24, all four ropes 26 are fully wound onto their respective reels on shaft 27 so as to be ready to be unwound. However, before hooked ropes 98, core formers 23 and sleeves 24 are wound up by the vertical reels 100, for the first phase removal, the two separating pins 26b on each connector 26 for core formers 23B, D and sleeves 24B, D must be joined. They have been left separated from the previous laying operation. Ropes 26 for the second phase removal of core formers 23A, C and sleeves 24A, C are already joined from their reels on shaft 27 directly to lanyard 25. However if the first phase removal was core formers 23A, C and sleeves 24A, C, pins 26b on ropes 26 for core formers 23A, C and sleeves 24A, C would be separated and would have to be joined, and those for core formers 23B, D and sleeve 24 B, D, now being the second phase, would already be joined.
Core formers 23 and sleeves 24 leave the last upper divider 30, dividers 9 and hollowcore slab 3 at end 13 and pass into circular tube 116 at opening 116a as previously described. At end 116b tube is once again oval shaped in
With deep slab sections 20, for example, as can be seen in
Using vertical reels 100 once again tensioning devices 111a ensure that core formers 23 and sleeves 24 are consistently flat and tightly packed to minimise the overall diameter of core formers 23. Sleeve 24 with connector 26 inside following behind core former 23 is a lighter weight material and its precise location on the surface of core formers 23 around reel 100, as it is wound up, is not so critical. Tensioning device 111a in
The now empty shaft 27, resting on carriage 27a is transported back from end 16, as previously described, and removed from carriage 41a and placed on the ends of arms 118 and arms 118a, seen in
After some 6 hours depending on the strength of the concrete, the destressing operations and entire stripping of hollowcore slabs 3 from casting line 1 proceeds. Empty reeling drum 27f is now relocated onto carriage 27a and carriage 27a is run down the length of casting line 1 from either end 13 or end 8 with the operators winding up manually or mechanically sheet 27g in
Thereafter individual strand wires 14 in the gap between the ends of each hollowcore slab 3 are cut either manually or mechanically by hydraulically operated cutters or cutting disc.
Individual hollowcore slabs 3 are then removed from casting line 1 and transported into the stock area for distribution to site. In the stock area, cutting discs are used to trim off the ends of strand wires 14 protruding from the end of each hollowcore slab 3.
As previously mentioned at this stage of the production process it is now possible to seal the ends of cores or voids as required where the cores or voids are used as a thermal mass medium as previously described and shown in
a) shows a cross section through a core or void at the end of a typical hollowcore slab 3 which requires to be sealed. And an appropriate baffle 89 similar to that shown in
Each individual core or void would have a separate individual end apparatus 120. Once the concrete inside the core or void has set the end apparatus 120 can be prised from the end of the hollowcore slab 3 having first released the string/wire 119. The end apparatus can then be cleaned and reused at a later date. The string/wire 119 is then cut at the end of each of the core or void in the individual hollowcore slab 3 that has been sealed leaving a clear end seal at the end of each core or void.
During the extended curing time that platform 102, using either the fourth or fifth removal method of core formers 23 and sleeves 24, is retained in the stock area, factory operatives can prepare the core formers 23 and sleeves 24 for relaying along casting line 1 prior to the next production cycle. Shaft 27 for horizontal reels 100 is now rotated manually or mechanically anticlockwise winding up ropes 26. As the ends of sleeves 24 approach the ends 116b, the two strings on each connector 26 are untied and released from ring eyes 117,
Horizontal rollers 110 can be raised or lowered as necessary, see
The methodology for the preparation of core formers 23 and sleeves 24 for relaying down casting line 1 using vertical reels 100 is also carried out and is identical to the relaying of core formers 23 and sleeves 24 using the horizontal reels 100 except the process is in two phases.
The ropes 26 for core formers 23A, C and sleeves 24A, C attached to shaft 27 are wound onto shaft 27 and the entire winding and ruching operation as previously described is carried out.
The factory operators then prepare casting line 1 for the next cast. If the next production requirement is for a similar length and slab section 20 of hollowcore slabs 3 as the previous cast, base plates 7 and strand wire locator plates are left in position. However if there are different slab sections 20 or lengths of hollowcore slabs 3 to be cast, all the base plates 7 and strand wire locating plates are removed, once again availing the use of carriage 27a as previously described. The factory operators once again measure individual hollowcore slab 3 lengths required to be cast as previously described.
The factory production cycle as previously described is now repeated.
Ruching tubes 116 have not been described or shown in the second and third method of preparing the individual horizontal or vertical reels 100 resting on 101 and storage platform 102. See
The laying of the core former 23 and sleeve 24 down casting bed 1 would follow immediately the core former 23 and sleeve 24 has been ruched onto the tube 116. Thereafter the empty horizontal or vertical reel 100 is removed and another reel 100 located onto the platform 102 and the second core former 23 and sleeve 24 is ruched up and immediately laid down casting bed 1.
Ruching operations for the hand method of removing core former 23 and sleeve 24 as shown in
The fourth and fifth method of laying core formers 23 and sleeves 24 in
Core formers 23 and sleeves 24 on vertical reels 100 are unwound and laid down casting line 1 in a similar but two phase operation. For the first phase empty carriage 27a is again moved down from end 16 and parked at end 13.
Platform 102, shown in
The second phase of laying core formers 23 and sleeves 24 is then carried out. Platform 102 is moved along rails 104 to line up tube 116 to remove core formers 23A, C and sleeves 24A, C. Pins 26b are separated on ropes 26 for core formers 23B, D and sleeves 24B, D whilst shaft 27 on carriage 27a remains past end 16. Thereafter carriage 27a is brought back to end 13. The loose ends of ropes 26 on the two reels on shaft 27 for core formers 23A, C and sleeve 24A, C are joined to the ropes 26 via pins 26b, in
Although the core formers and sleeves are round or oval, other shapes can be considered, such as square. The core formers and sleeves are also preferably of uniform lateral cross-section along the majority of their longitudinal extents.
Although the shutters are pivotable, they may be fixed side walls. Additionally and/or alternatively, the shutters may be raisable and lowerable.
The prestressing elongate flexible elements are preferable, but may be dispensed with in some circumstances.
It is thus possible to provide hollowcore apparatus and a method of forming hollowcore slabs which is compact, utilises a low-pressure compressed air system, and which can incorporate cross-reinforcement, cross-galleries, and lifting hooks prior to casting. Production of hollow core slabs can be doubled, and far less environmentally damaging by-products are produced. Different dimensions of hollowcore slabs can also be produced easily from a single casting bed and single set of shutters.
The present invention enable the manufacture of individual hollowcore slabs in the any length in a range between 5 to 25 metres to the nearest centimetre without the need for high capital cost hollowcore machinery and complicated saws. The invention further eliminates the current modern day health and safety issues, since the process is virtually silent and will require very little mechanical or hydraulic machinery to manufacture the hollowcore slabs. Multiple discrete slabs can also be cast on a single casting bed.
There is little or no wastage of materials in the production process. The casting operation is environmentally friendly and allows for small on site mobile plants to be set up quickly and economically. Equally large production facilities can be readily set up in distant locations in hot climates and in the open air, without the need for extensive factory sheds to shade the production area; essential with conventionally made Hollowcore slabs 3a to prevent shrinkage. This obviates the need, in some instances, of building an independent factory where necessary planning permission may not be granted. Further on site manufacture eliminates entirely complex road delivery problems and related costs, one reason why long span hollowcore slabs cannot be practically used in dense urban areas, not to mention the substantial savings in CO2.
The concrete mix used in the new process is preferably Self Compacting Concrete (SCC), a type of concrete which is fluid at the time of placing and does not need compacting effort to consolidate it in the mould.
The hollowcore slabs of the invention are made using prestressing strands stressed in short or long casting lines, but in the new process, secondary unstressed reinforcement can be fitted, together with connectors and any other embedded fittings before or after the core formers are in position. The concrete is then simply poured into the mould and needs no vibration to produce the required strength.
The core formers, circular or oval, can be inflated, or otherwise deployed in position so that they may be readily disassembled before the slab is demoulded. The inflated core former can be inflated to a sufficient pressure to ensure that the weight of the fluid concrete around it does not distort it to an unintended cross section. The core former is held down by holders to stop flotation in the fluid concrete with either externally fixed steel clips or collars which are linked to stressed tendons in the slab.
The core formers use modern materials and may be made of nylon or similar material. The former is be sleeved, typically with a modern composite material, again nylon or similar, to ensure that the inner inflated core former and or mechanism is not contaminated by the wet concrete.
The apparatus of the invention also has the advantage that end plates or stop ends can be fitted into the line before the slabs are cast to allow them to be cast discretely, not continuously, removing the need for a concrete hydraulic saw. The only cutting that is required is to separate the steel strands linking the slabs after the line is detensioned and this is simply done using hand held tools or automated machinery; or if desired mechanised cutting apparatus, specifically to cut steel only, in large factories with a high production output can be used.
There is a substantial reduction in the use of electricity and potable water reducing CO2 emissions from the overall production process.
The apparatus of the invention ensures that all the wires and strands located in the individual slabs are precisely located to meet design and fire regulations.
The apparatus of the invention allows for the incorporation of special linking steel bars or welded mesh to ensure hollowcore slabs meets all earthquake zone codes of practice as well as meeting all European, American and Asian building codes. Special adaptors can be bonded into the sides of the hollowcore slab before casting to allow for a simple ‘mechanical’ connection between adjacent hollowcore slabs at any required distance along the length of any hollowcore slab.
All the necessary lifting sockets or loops essential to lift and move a slab, according to current health and safety regulations can be incorporated into the hollowcore slab before casting.
Water pipes, as required, can now be inserted into individual moulds before casting. Cores or voids can also be created in the same hollowcore section, allowing two technologies, for example, Thermocast® and TermoDeck®, a ventilation technology, using the cores or voids as a means to assist in heating and cooling as well as providing the necessary fresh air for the occupants of a room below to be incorporated together into a single slab.
Cross connections between adjacent voids/cores to allow passage of air between individual voids or cores or multiple voids or cores can now be simply incorporated into individual slab lengths before casting. This entirely eliminates the need for on-site drilling operations. Provision for inlets and outlets into the soffit of the hollowcore slab can also be inserted in the slab before casting, again obviating all need for vacuum-anchoring upwards special core drilling equipment, for example.
SCC may blend in steel fibres as an additive during the mixing process. There will be no segregation or bunching of the fibres giving even distribution over the complete hollowcore section and reducing the need for secondary reinforcement for longer spans of hollowcore slabs.
The block-out elements, whether they are providing access to an exterior of the slab or are interconnecting adjacent cores, are preferably oval, but may be circular or polygonal, such as square or rectangular.
The prestressing elongate flexible elements or wires are preferably multi-stranded, but may be single stranded, especially in the case of smaller slabs, such as for walls.
The gallery between cores is intended to provide for gas movement, typically being air. However, it could potentially provide for liquid movement.
Although not in the embodiments described, the sleeves may be sacrificial and therefore may be retained and lost in the finished hollowcore slab. To this end, the material that the sleeves are formed from may be chosen accordingly.
The present invention also allows hollowcore slabs to be made which are kinked or cranked in elevation. These units are of particular use in multi storey car parks where hollowcore currently cannot make ramp slabs without having columns and cross beams at each change of slope. A hollowcore cranked ramp slab formed using the method and apparatus of the present invention is significantly more cost-effective to produce.
A hollowcore slab can also now be cast with half jointed end by using the present invention so that its soffit does not automatically have to be placed on top of supporting beams or walls.
The use of Self Compacting Concrete in the present invention dispenses with the necessity of vibrational compacting presently utilised and the associated health risks to employees. However, vibration units can be utilised if by chance self compacting mix constituents are not available locally.
Number | Date | Country | Kind |
---|---|---|---|
1004333.9 | Mar 2010 | GB | national |
Number | Date | Country | |
---|---|---|---|
Parent | PCT/GB2011/050507 | Mar 2011 | US |
Child | 13653646 | US |