The present invention relates to the general art of geotechnical engineering, and to the particular field of overfilled arch structures.
Frequently, overfilled bridges formed of precast or cast-in-place concrete are used to support one pathway over a second pathway, which can be a waterway, a traffic route or the like. The terms “overfilled arch” or “overfilled bridge” will be understood from the teaching of the present disclosure, but in general, an overfilled bridge or an overfilled arch is a bridge formed of arch elements that rest on the ground or on a foundation and has soil or the like resting thereon and thereabout to support and stabilize the bridge. The arch form is generally cylindrical in circumferential shape, and in particular a prolate shape; however, other shapes can be used. An example of an overfilled bridge is disclosed in U.S. Pat. Nos. 3,482,406 and 4,458,457, the disclosures of which are incorporated herein by reference.
Presently, reinforced concrete overfilled arches are usually constructed by one of two methods. The first method includes completing the entire arch structure in place, with formwork used to create the arch profile. This method generally requires formwork on both the inside and the outside of the arch profile as the sides of the arch are generally too steep to be cast without the support provided by formwork. Formwork on the outside of the arch may generally be omitted at the apex of the arch where the gradient of the arch shell is less than about 20° to 30° from horizontal. The provision of such outside form work is both costly and time consuming and may reduce the finished quality of the formed concrete. Furthermore if outside formwork is used, there are restrictions on the thickness of the vault, such as to ensure good quality concrete the arch vault cannot be less than roughly one foot thick.
A second common method of constructing reinforced concrete overfilled arches is to pre-cast the complete arch or arch halves in sections (elements) and to subsequently place the pre-cast elements onto prepared footings. An example of this type of construction method is disclosed in U.S. Pat. No. 3,482,406. This construction method requires construction of re-usable molds and the transport and lifting of the finished arch profiles into their permanent locations. The aforementioned re-usable mounds are a significant initial investment. This renders this method of construction uneconomical if the molds cannot be re-used to supply elements for the construction of many arch bridges. Investment in such molds is therefore made by pre-casting manufacturers and the arch elements are produced in their factories and transported to the bridge construction site. Problems associated with the transport of such arches and the requirement of a construction crane large enough to lift complete arch elements are disadvantages of this method.
Furthermore, transporting large pre-cast structures may involve complex and expensive transportation problems. Roadways, permits, escorts and clearance requirements must be accounted for, as well as traffic problems and schedules. Still further, in some constructions, very large cranes are required which further exacerbates all of the above-mentioned problems.
Therefore, there is a need for an economical and efficient overfilled bridge and method of constructing an overfilled bridge.
Pre-cast structures are not as versatile as possible, especially if unusual terrain or specifications are present. In particular, precast structures are limited in the forms of curtailment which can be applied at the ends of the bridge. Therefore, there is a need for an overfilled bridge and method of constructing an overfilled bridge that is versatile and amendable to design variations.
It is a main object of the present invention to provide an economical and efficient bridge structure and method of forming an arched overfilled bridge structure.
It is another object of the present invention to provide a reinforced concrete arch bridge that can be constructed completely on the construction site.
It is another object of the present invention to provide an overfilled arched bridge and method of construction therefor which incorporates small pre-cast components.
It is another object of the present invention to provide an overfilled arched bridge and method of construction therefor which is amenable to including various arch profiles and shapes.
It is another object of the present invention to provide an overfilled arched bridge and method of construction therfor which is more versatile with respect to the formable geometry at the ends of the arched bridge.
It is another object of the present invention to provide an overfilled arched bridge and method of construction therefor which is flexible and versatile and amenable to design variations.
It is another object of the present invention to provide an overfilled arched bridge and method of construction therefor which is amenable to including various arch profiles using the same formwork.
It is another object of the present invention to provide an overfilled arched bridge and method of construction therefor which reduces dependence on large element transportation.
It is another object of the present invention to provide an overfilled arched bridge and method of construction therefor which reduces initial capital investment required.
It is another object of the present invention to provide an overfilled arched bridge and method of construction therefor which is expeditious to produce.
These, and other, objects are achieved by a hybrid arched overfilled bridge structure and method for constructing the same which combines pre-cast elements with cast-in-place sections. The hybrid bridge thus realizes the advantages associated with precast elements and with cast-in-place elements while omitting most, if not all, of the disadvantages associated therewith. The pre-cast elements can be small and thus will avoid the aforediscussed transportation-related costs and problems, and the cast-in-place sections will avoid the above-discussed formwork problems. The hybrid bridge embodying the present invention thus takes advantage of both methods of construction while avoiding most, if not all, the problems associated with each of the methods of construction.
Furthermore, since the pre-cast side elements make up a shorter sector of the arch than is the case with prior bridges, it is possible to pre-cast them lying flat (that is, comparable to a curved slab) rather than vertical (comparable to a curved wall). This makes casting simpler and cheaper than prior methods and the required forms are much cheaper than the forms required by prior methods. Furthermore, as compared to prior methods of construction of overfilled bridges, it is more feasible to perform the side element casting operation locally on the construction site at which the arch is being built using the pre-cast side elements of the present invention.
Still further, the pre-cast components of the present invention are lighter, less unwieldy and easier to work with than prior elements and thus are easier to cast, stock, transport, unload and erect than prior bridge components.
Still further, since the upper part of the bridge structure (the crown sector) is cast in place, it can be continuous and thus the distribution of loads on the structure will be enhanced by shell action. Trimming the ends (battered ends) along the plane of the embankment is much simpler with the bridge structure of the present invention than with prior bridge structures where both spandral and wing walls were required. Because the crown sector of the present invention is cast in place, it will be less costly than prior bridge structures, yet will still be high quality and have a desired aesthetic appearance.
Other objects, features and advantages of the invention will become apparent from a consideration of the following detailed description and the accompanying drawings.
The hybrid arched overfilled bridge structure and method of construction embodying the present invention includes a concrete arch span with three major components: side elements, with one sector on each side of the arch formed of pre-cast side elements; and one sector located between the side elements formed of cast-in-place concrete. The concrete can be reinforced if desired.
Shown in
Bridge structure 10 includes an overall width dimension W measured from a first side edge Si of first pathway P1 to a second side edge S2 of first pathway P1 when bridge structure 10 is in a set up configuration. First pathway P1 has a lengthwise dimension L1 extending in the direction of first and second side edges S1 and S2, and first pathway P1 includes a centerline PCL located midway between first and second side edges S1 and S2 of first pathway P1 and extends along lengthwise direction L1 of first pathway P1. For purposes of reader orientation, it is noted that first pathway P1 contains a first plane PL1 containing a portion of lengthwise dimension L1 of first pathway P1. Pathway P1 can be rectilinear or curved.
As shown in
Bridge structure 10 includes a widthwise shape that is arcuate in the set-up configuration and has a radius of curvature defined by a unit radian 16 extending from first pathway P1 toward second pathway P2 in the set-up configuration of bridge structure 10. The overall curvature of the bridge structure is defined as unit radian 16 moves in a vertical plane through an angle of approximately π radians (180°) with the instantaneous curvature being defined at any particular location according to unit radian 16, and can be a compound curvature if suitable. Bridge structure 10 further includes an overall arc length 20 in the set-up configuration which corresponds to the radius of curvature as defined by unit radian 16 at any particular location, overall width dimension W and overall height dimension 14. As will be understood by those skilled in the art, arc length 20 is a function of the radius of curvature R and the included angle θ traversed by unit radian 16, that is arc length is a function of Rθ, with θ being measured in radians. As the radius of curvature normally varies as the unit radian moves through angle θ so the overall arc length of bridge structure will be an arithmetic sum of a plurality of arc lengths each determined as discussed above.
Bridge structure 10 further includes first and second end treatments E1 and E2 respectively, with each end treatment located adjacent to an end of running length dimension 12 in the set-up configuration of the bridge structure. Bridge structure 10 thus has an overall length dimension 17 measured along running length dimension 12 between end treatments E1 and E2. The end treatments can be any of a wide variety of shapes and components, and two such end treatments are shown in
As shown in
Bridge structure 10 further includes a plurality of side elements, such as side element 50. As shown in
Each side element is arcuate and includes a radius of curvature defined by a unit radian 64 of each side element. As discussed above, while one form of the bridge structure includes a uniform curvature for each side element, a compound curvature is also possible without departing from the scope of the present disclosure. Each side element further includes a side element arc length 66 which corresponds to radius of curvature of the body of each side element and extends from first end 58 on body 52 of each side element 50 to second end 60 on body 52 of each side element 50. As discussed above, the arc length of each side element is a function of the radius of curvature of the side element body and the angular extent of the body.
As can be understood from
As can be understood from
Each side element of the plurality of side elements is pre-cast before it is placed in the set-up configuration of the bridge structure. The pre-casting process will be discussed below.
Bridge structure 10 further includes a plurality of crown sector elements, such as crown sector elements 80 shown in
Body 82 of each crown sector element 80 further includes two sides 94 and 96 which are spaced apart from each other along running length dimension 12 in the set-up configuration of the bridge structure, and a length dimension 98 of body 82 of each crown sector element 80 is measured between the two sides 94 and 96 of body 82 of each crown sector element 80. Length dimension 98 of body 82 of each crown sector element 80 is equal to or smaller than overall length dimension 17 of bridge structure 10 in the set-up configuration of bridge structure 10. The overall length of bridge structure 10 is generally made up of a multiple of length dimensions 98 of bodies 82 of crown sector elements 80, with some adjustment made at each end of the bridge structure to account for the shapes of end treatments E1 and E2. Furthermore, length dimension 98 of body 82 of each crown sector element 80 is equal to or greater than length dimension 74 of body 52 of each side element 50. Length dimension 98 of body 82 of crown sector element 80 is normally a multiple of length dimension 74 of body 52 of each side element 50.
Each crown sector element 80 of the plurality of crown sector element is cast-in-place after at least some of the side elements 50 have been placed in the set-up configuration. Thus, the set-up bridge structure is a hybrid which includes pre-cast side elements and cast-in-place crown sector elements.
It is noted that the crown sector elements can be cast on site, in place, with the attendant advantages. It is also noted that the crown sector elements pass through an arc such that the gradient of the arc is always less than the castable gradient of the concrete mix being used for the bridge construction. The gradient is illustrated in
In order to minimize the arc length of the side elements, the span of the crown sector can be chosen as the maximum possible without exceeding the aforementioned gradients. As some reinforced concrete arch bridges do not pass through an arch of more than 180°, and given that appropriate concrete mixes, such as low slump concrete mix, can be produced that enable placement and compaction of up to a 30° gradient; casting the crown at a slope of 30° gradient results in side elements which can also be cast without counter forms. The length dimension 74 of body 52 of each side elment 50 is determined by practical and economical considerations, including weight of the elements as dictated by the equipment available on the construction site for lifting and placing such elements. When cast on site, the length dimension 74 of body 52 of each side element 50 may be relatively long. When cast off site, the length dimension 74 of body 52 of each side element 50 is limited by transportation requirements. Standard length dimension 74 will be chosen for the body 52 of each side element 50 for each arch type such that a multiple of side elements match both the length dimension 98 of body 82 of crown sector element 80 as well as other considerations associated with the bridge structure. The length dimension 98 of body 82 of crown sector element 80 is determined to ensure a practical construction sequence, as each individual crown sector element 80 of overfilled bridge structure 10 is produced in one distinct construction stage, and the concrete in each element placed and allowed to harden (“cast”) prior to the construction of the next element. For conventional bridge lengths, the length dimension 98 of body 82 of crown sector element 80 is normally in the order of 10 m to 12 m. Experience shows that this length is the practical concrete casting length for similar shell forms. The ends adjacent to end treatments E1 and E2 of overfilled brdiges structure 10 can be formed to comply with the shapes associated with those end treatments during the casting of the adjacent crown sector elements.
The interfaces at sides 94 and 96, between adjacent crown sector elements 80 are formed by cold joints which may or may not be continuously reinforced. The cast-in-place crown sector, formed by a series of crown sector elements 80 is thus a continuous element once completed. In order to control shrinkage cracking within the case-in-place crown sector, shrinkage joint 102, which may or may not be continuously reinforced, is to be formed in crown sector elements 80 at regular intervals along running length dimension 12. The spacing of shrinkage joints 102 is normally determined such that shrinkage joints 102 divide crown sector element 80 into even intervals. One form of the bridge structure includes shrinkage joints every 4 m to 6 m. The location along running length 12 of shrinkage joints 102 is also normally determined such that they may occur at a location along the running length 12 of sides 70 and 72 of side elements 50. Beveled edges may or may not be applied to all aformentioned edges and joints of crown sector elements 80 and side elements 50.
Waterproofing of the overfilled bridge structure 10 may be facilitated by either the placement of waterproofing elements, such as sealing strips, such as sealing strip 104 shown in
As can be understood from the foregoing, the connecting elements 76 (see
Referring to
In the situation where the average of angles α and β is more than the concrete mix castable gradient, special casting tables can be used to pre-cast the side elements. Shown in
As shown in
Shown in
In order to construct each crown sector element 80, frame 170 is first located such that form surface 174 is in the correct position. Precast side elements 50 are placed against each side of form surface 174 with ends 58 of the side elements accommodated in channels 44 of footing strips 22 and 24. Ends 60 of side elements 50 are located above the footing strips, and due to the curvature of bodies 52 of side elements 50, ends 60 are positioned toward centerline PCL of the bridge structure 10 when the side elements are in the set-up configuration. The contact between ends 60 of side elements 50 and the form surface 174 includes seals 176 and 178 to prevent loss of concrete from within the form during casting of the crown sector element 80. A crown sector element 80 is cast onto the form surface 174 to close the arch between the positioned side elements 50. The side elements 50 are supported by the form surface 174 during the placement and crown sector casting process.
Conventional methods such as immersion, float or form vibrators or the like can be used to compact the placed concrete.
Frame 170 can be constructed of metal, reinforced concrete, timber or a combination thereof as suitable. Frame 170 can be easily set up into the
Subject to system optimization, the crown form surface 174 and supporting frame 170 may be made generally applicable to several arch types to enable re-use of the same frame and formwork for several projects. To enable this, the form surface may be adjustable to different radial profiles, different arch lengths, and different frame heights. The form and frame should be re-usable and de-mountable to enable transportation to other construction sites. Material used in the crown sector form surface 174 could be either curved or paneled and made of timber, steel, or concrete plates, or any appropriate system of joinable panels. The joints in abutting form panels are formed to ensure a good concrete finish and are adjustable to enable their use for various profile radii. It is also noted that the connecting elements 76 are normally detailed to ensure proper connection between side elements 50 and the cast-in-place crown sector elements 80.
Referring to
It is anticipated that the just-described method could be achieved in a 24-hour turnaround period. To this end, heating elements included in the various elements ensure curing temperature is high enough in the cast-in-place crown sector elements, especially during cold weather. The above-described cycle is repeated several times as necessary to complete the required length of bridge structure. At each end of the structure, the crown sector and side elements are formed such that their geometry matches that of the chosen bridge end treatment.
The overfilled bridge structure is completed by backfiling of the bridge structure. This backfiling operation may progress at completed sections of the bridge structure while other sections of the bridge structure are being constructed.
A construction crane may be required on the construction site to place the various elements discussed above. The pre-casting and casting in place permits these elements to be within the limits of the crane.
The above disclosure has been directed to a rectilinear bridge structure; however, the above-disclosed means and methods can be applied to curved or angular shapes as well without departing from the scope of the present disclosure.
It is understood that while certain forms of the present invention have been illustrated and described herein, it is not to be limited to the specific forms or arrangements of parts described and shown.
This application is a divisional of application Ser. No. 09/983,561, filed Oct. 25, 2001 now U.S. Pat. No. 6,640,505.
Number | Name | Date | Kind |
---|---|---|---|
2372187 | Davison | Mar 1945 | A |
4173856 | Fricker | Nov 1979 | A |
4271555 | Mingolla et al. | Jun 1981 | A |
4558969 | FitzSimons | Dec 1985 | A |
4639345 | Olsen | Jan 1987 | A |
4953280 | Kitzmiller | Sep 1990 | A |
5032197 | Trimble | Jul 1991 | A |
5281053 | Matiere | Jan 1994 | A |
6149844 | Graham | Nov 2000 | A |
6161342 | Barbier et al. | Dec 2000 | A |
6205717 | Shall et al. | Mar 2001 | B1 |
6406220 | Thomson | Jun 2002 | B1 |
6408581 | Monachino | Jun 2002 | B1 |
6425213 | Lachapelle | Jul 2002 | B1 |
6655037 | Gotz et al. | Dec 2003 | B1 |
Number | Date | Country | |
---|---|---|---|
20040062609 A1 | Apr 2004 | US |
Number | Date | Country | |
---|---|---|---|
Parent | 09983561 | Oct 2001 | US |
Child | 10657375 | US |