The present invention relates to a hydraulic system for a work machine such as a hydraulic excavator.
A work machine such as a hydraulic excavator can exhibit excellent combined operability by connecting a boom directional control valve and a swing directional control valve to the same pump line in parallel and driving a swing motor and a boom cylinder by a common pump. The “excellent combined operability” means a characteristic that, in a case of, for example, a so-called swing boom raising operation for simultaneously implementing swing and boom raising, a swing acceleration becomes lower as a boom raising operation amount is larger, compared with a case of a sole swing operation. This characteristic results from the higher inertia of a swing structure than the inertia of a boom, and the characteristic is obtained since a swing load pressure is higher than a boom load pressure at initial swing to allow a more hydraulic fluid to flow into the boom cylinder. Under this characteristic, if a swing distance is short relative to a height of a soil discharge position, a boom raising speed increases but a swing increasing rate decreases as the boom raising operation amount is larger, so that the soil discharge position is advantageously easy to adjust during gravel loading work or the like. On the other hand, if the boom load pressure differs from the swing load pressure, a divergence loss can be generated in response to a difference in the load pressure.
Meanwhile, there is known a work machine configured such that a swing motor and a boom cylinder are driven by different pumps and that a swing speed decreases during a swing boom raising operation (refer to Patent Document 1 and the like). Specifically, the work machine is configured such that a delivery rate control valve for controlling a delivery rate of each pump is used to cause a delivery pressure of the pump corresponding to the boom cylinder to act on the delivery rate control valve of the pump corresponding to the swing motor when a boom raising operation is detected, and to decrease a supply flow rate for the swing motor at a time of a swing boom raising operation.
Patent Document 1: JP-2004-36865-A
However, the hydraulic system of Patent Document 1 does not always simultaneously achieve the abovementioned excellent combined operability and the reduction of loss. The reason is as follows. The configuration of the hydraulic system of Patent Document 1 is to simply turn on or off a command pressure to the delivery rate control valves depending on whether the boom raising operation is present, and not to cause the swing speed to decrease in proportion to a boom raising operation amount during the swing boom raising operation. For achieving the excellent combined operability, the hydraulic system of Patent Document 1 needs to control, for example, the delivery rate control valves in such a manner as to suppress a flow rate to be supplied to the swing motor as the boom raising operation amount is larger, and to supply a higher flow rate to the boom cylinder. In this case, however, the pressure loss increases between the hydraulic pump and the boom cylinder, resulting in the degradation of fuel economy.
An object of the present invention is to provide a hydraulic system for a work machine capable of realizing excellent combined operability while suppressing a divergence loss during a swing boom raising operation and suppressing degradation of fuel economy.
To attain the object, a hydraulic system for a work machine according to the present invention is a hydraulic system for a work machine including a track structure, a swing structure swingably mounted on the track structure, and a work device that includes a boom attached to the swing structure, the hydraulic system including: a swing hydraulic motor causing the swing structure to swing; a boom cylinder driving the boom; a first hydraulic pump delivering a hydraulic fluid for driving the swing hydraulic motor; a second hydraulic pump delivering a hydraulic fluid for driving the boom cylinder; a swing operation device instructing an operation of the swing hydraulic motor; a boom operation device instructing an operation of the boom cylinder; a first pump displacement increase valve controlling a volume of the first hydraulic pump; a swing operation amount detector detecting a swing operation amount of the swing operation device; a boom raising operation amount detector detecting a boom raising operation amount of the boom operation device; and a controller controlling a first pump flow control signal that is a command signal to the first pump displacement increase valve on the basis of the swing operation amount detected by the swing operation amount detector and the boom raising operation amount detected by the boom raising operation amount detector. The controller controls the first pump flow control signal in such a manner that a delivery rate of the first hydraulic pump becomes higher as the swing operation amount of the swing operation device is larger and an increasing rate of the delivery rate of the first hydraulic pump becomes lower as the boom raising operation amount of the boom operation device is larger if a swing operation by the swing operation device and a boom raising operation by the boom operation device are performed simultaneously.
According to the present invention, it is possible to realize excellent combined operability while suppressing a divergence loss during a swing boom raising operation and suppressing degradation of fuel economy.
Embodiments of the present invention will be described hereinafter with reference to the drawings.
1. Work machine
The work machine exemplarily shown in
The track structure 8 includes left and right crawlers 31 each having an endless track crawler belt in the present embodiment, and travels by driving the left and right crawlers 31 by left and right travel motors 32, respectively. For example, hydraulic actuators are used as the travel motors 32.
A cab 33 into which an operator gets is provided in a front portion of the swing structure 9. A power chamber 34 accommodating an engine, a hydraulic drive device, and the like is provided in rear of the cab 33 of the swing structure 9. A swing hydraulic motor 3 is provided in a swing frame that couples the swing structure 9 to the track structure 8. Left and right operation levers 1a and 1b for instructing a swing operation of the swing structure 9 and a operation of the work device 10 are provided in the cab 33. Furthermore, the power chamber 34 accommodates a hydraulic pump device 2 that delivers a hydraulic fluid for driving each hydraulic actuators, a control valve device 20 that controls a flow of the hydraulic fluid supplied from the hydraulic pump device 2 to the hydraulic actuator, and the like.
The work device 10 is coupled to the front portion of the swing structure 9 (a right side of the cab 33 in the present embodiment). The work device 10 is a multijoint work device that includes a boom 35, an arm 36, and a bucket 7. The boom 35 is vertically rotatably coupled to the frame of the swing structure 9 and coupled to the frame of the swing structure 9 via a boom cylinder 4. The arm 36 is rotatably coupled to a tip end of the boom 35 and coupled to the boom 35 via an arm cylinder 5. The bucket 7 is rotatably coupled to a tip end of the arm 36 and coupled to the arm 36 via a bucket cylinder 6. The boom cylinder 4, the arm cylinder 5, and the bucket cylinder 6 are hydraulic actuators.
In the work machine shown in
2. Hydraulic system
Hydraulic Pump Device
The hydraulic pump device 2 includes a first hydraulic pump 2a, second hydraulic pumps 2b and 2c, and a pilot hydraulic fluid source 17, and is driven by, for example, an engine that is not shown. The first hydraulic pump 2a and the second hydraulic pumps 2b and 2c are variable displacement hydraulic pumps. While swash plate type hydraulic pumps are described by way of example in the present embodiment, inclined shaft type hydraulic pumps may be used. Moreover, while a case where the hydraulic pump device 2 includes the two second hydraulic pumps is exemplarily shown, the hydraulic pump device 2 often includes one second hydraulic pump. The first hydraulic pump 2a delivers the hydraulic fluid for driving the swing hydraulic motor 3 to a first pump line 21a. The second hydraulic pumps 2b and 2c deliver the hydraulic fluids for driving the boom cylinder 4, the arm cylinder 5, and the bucket cylinder 6 to second pump lines 21b and 21c, respectively. While the arm cylinder 5 and the bucket cylinder 6 are not shown in
Control Valve Device
The control valve device 20 includes boom directional control valves 22 and 23, a swing directional control valve 24, a bucket directional control valve 25, and an arm directional control valve 26. In the present embodiment, the control valve device 20 configured to include the two boom directional control valves 22 and 23 is exemplarily shown since the hydraulic pump device 2 is configured such that the hydraulic fluids delivered from the second hydraulic pumps 2b and 2c are combined to be supplied to the boom cylinder 4. However, the control valve device 20 often includes one boom directional control valve.
The boom directional control valve 22 and the bucket directional control valve 25 are provided in the second pump line 21b in series. The boom directional control valve 22 is located downstream of the bucket directional control valve 25. Likewise, the boom directional control valve 23 and the arm directional control valve 26 are provided in the second pump line 21c in series. The boom directional control valve 23 is located downstream of the arm directional control valve 26. The swing directional control valve 24 is provided in the first pump line 21a. The boom directional control valves 22 and 23 control a flow of the hydraulic fluid supplied to the boom cylinder 4. The arm directional control valve 26 controls a flow of the hydraulic fluid supplied to the arm cylinder 5, the bucket directional control valve 25 controls a flow of the hydraulic fluid supplied to the bucket cylinder 6, and the swing directional control valve 24 controls a flow of the hydraulic fluid supplied to the swing hydraulic motor 3.
While a case where the bucket directional control valve 25 is provided in the second pump line 21b and the arm directional control valve 26 is provided in the second pump line 21c is described by way of example, the bucket directional control valve 25 may be provided in the second pump line 21c and the arm directional control valve 26 may be provided in the second pump line 21b. Further, a case where the bucket directional control valve 25 as well as the boom directional control valve 22 is provided in the second pump line 21b and the arm directional control valve 26 as well as the boom directional control valve 23 is provided in the second pump line 21c is described by way of example. Alternatively, a travel directional control valve, for example, (not shown) controlling a flow of the hydraulic fluid supplied to each of the travel motors 32 (
Operation Levers
The operation levers 1a and 1b are operation devices instructing operations of the swing structure 9 and the work device 10. While electric levers are often used as the operation levers 1a and 1b, pilot lever devices are exemplarily shown as the operation levers 1a and 1b in the present embodiment.
The left operation lever 1a is a swing operation device instructing an operation of the swing hydraulic motor 3. When being operated in, for example, a horizontal direction, the left operation lever la delivers a left swing pilot pressure P1 or a right swing pilot pressure Pr in response to an operation direction (left operation direction or right operation direction), and outputs the left swing pilot pressure P1 or the right swing pilot pressure Pr to a pilot pressure receiving section of the swing directional control valve 24. When the left swing pilot pressure P1 is input to the swing directional control valve 24, then a position of the swing directional control valve 24 is changed over to a left-side position in
The right operation lever 1b is a boom operation device instructing an operation of the boom cylinder 4. When being operated in, for example, the longitudinal direction, the right operation lever 1b outputs a boom lowering pilot pressure Pd or a boom raising pilot pressure Pu in response to an operation direction (front or back operation direction), and outputs the boom lowering pilot pressure Pd or the boom raising pilot pressure Pu to pilot pressure receiving sections of the boom directional control valves 22 and 23. When the boom raising pilot pressure Pu is input, then positions of the boom directional control valves 22 and 23 are changed over to right-side positions in
Furthermore, the pilot pressures delivered from the operation levers 1a and 1b are output to the pump driving device 50 via the shuttle valve group in addition to the corresponding directional control valves. The pump driving device 50 controls tilting angles of the first hydraulic pump 2a and the second hydraulic pumps 2b and 2c by the pilot pressures and the like from the operation levers 1a and 1b. The pump driving device 50 will be described later.
Shuttle Valve Group
The shuttle valve group is configured from shuttle valves 11a to 11f. The shuttle valve 11a supplies, as a first pump flow control pressure Pf1, a higher one of the right swing pilot pressure Pr and the left swing pilot pressure P1 to the pump driving device 50. The shuttle valve 11b supplies a higher one of the arm dumping pilot pressure and the arm crowding pilot pressure to the shuttle valve 11c. The shuttle valve 11d supplies a higher one of the boom raising pilot pressure Pu and the boom lowering pilot pressure Pd to the shuttle valves 11c and 11e. The shuttle valve 11c supplies, as a second pump flow control pressure Pf3, a higher one of the pilot pressures supplied from the shuttle valves 11b and 11d to the pump driving device 50. The shuttle valve 11f supplies a higher one of the bucket dumping pilot pressure and bucket crowding pilot pressure to the shuttle valve 11e. The shuttle valve 11e supplies, as a second pump flow control pressure Pf2, a higher one of the pilot pressures supplied from the shuttle valves 11d and 11f to the pump driving device 50. The first pump flow control pressure Pf1 is a command signal (positive control pressure) to a first pump displacement increase valve 51a (
Operation Amount Detector
The operation amount detector includes a swing pilot pressure sensor 12, a boom raising pilot pressure sensor 13, and second pump flow control pressure sensors 14a and 14b. The swing pilot pressure sensor 12 is a swing operation amount detector that detects a swing operation amount (the left swing pilot pressure P1 or the right swing pilot pressure Pr in this example) of the left operation lever 1a, and is provided in a hydraulic line between the shuttle valve 11a and the pump driving device 50. The boom raising pilot pressure sensor 13 is a boom raising operation amount detector that detects a boom raising operation amount (the boom raising pilot pressure Pu in this example) of the right operation lever 1b, and is provided in a hydraulic line between the right operation lever 1b and the shuttle valve 11d in a boom raising pilot pressure output line. The second pump flow control pressure sensor 14a is a first maximum operation amount detector that detects a maximum value of a boom operation amount and a bucket operation amount (a first maximum operation amount, which is the second pump flow control pressure Pf2 in this example), and is provided in a hydraulic line between the shuttle valve 11e and the pump driving device 50. The second pump flow control pressure sensor 14b is a second maximum operation amount detector that detects a maximum value of the boom operation amount and the bucket operation amount (a second maximum operation amount, which is the second pump flow control pressure Pf3 in this example), and is provided in a hydraulic line between the shuttle valve 11c and the pump driving device 50.
Pump Control Valve
The pump control valve includes a pump flow control valve 15 and pump torque control valves 16a and 16b. The pump flow control valve 15 is a control valve that controls the first pump flow control pressure Pf1. This pump flow control valve 15 plays a role of controlling a delivery rate of the first hydraulic pump 2a, and is provided in the hydraulic line between the shuttle valve 11a and the pump driving device 50. The pump torque control valve 16a is a control valve that controls a first pump torque control pressure Pt1 (to be described later) and a second pump torque control pressure Pt2 (to be described later) input to the pump driving device 50. This pump torque control valve 16a plays a role of controlling absorption torques of the first hydraulic pump 2a and the second hydraulic pump 2b, and is provided in a hydraulic line between the pilot hydraulic fluid source 17 and the pump driving device 50. The pump torque control valve 16b is a control valve that controls a second pump torque control pressure Pt3 input to the pump driving device 50. The pump torque control valve 16b plays a role of controlling an absorption torque of the second hydraulic pump 2c, and is provided in the hydraulic line between the pilot hydraulic fluid source 17 and the pump driving device 50. The pump flow control valve 15 and the pump torque control valves 16a and 16b are each configured with a pressure reducing normally open valve.
Controller
The controller 100 computes and outputs a pump flow control valve command Sf1 and pump torque control valve commands St12 and St3 on the basis of the swing pilot pressure, the boom raising pilot pressure, and the second pump flow control pressures Pf2 and Pf3 input from the swing pilot pressure sensor 12, the boom raising pilot pressure sensor 13, and the second pump flow control pressure sensors 14a and 14b to drive the pump flow control valve 15 and the pump torque control valves 16a and 16b. The controller 100 will be described later in detail.
3. Pump Driving Device
The first pump displacement increase valve 51a and the second pump displacement increase valves 51b and 51c are each urged by a spring from one side (right side in
The first pump displacement reduction valve 52a and the second pump displacement reduction valves 52b and 52c each include a pilot pressure receiving section on one side (right side in
Furthermore, a pressure of the pilot hydraulic fluid source 17 directly acts on a right side in
4. Controller
4-1. Boom-Raising Pilot Pressure Selection Section
4-2. Swing target power arithmetic section
4-3. Swing Target Flow Rate Arithmetic Section
4-4. Pump Flow Control Section
4-5. Boom Target Power Arithmetic Section
4-6. Arm Target Power Arithmetic Section
4-7. Bucket Target Power Arithmetic Section
4-8. Pump Torque Control Section
When the boom target power Hbo1 and the bucket target power Hbu are input, higher power of the boom target power Hbo1 and the bucket target power Hbu is selected in the selector 108a, and the selected power is added to the swing target power Hs in the adder 108b to compute pump target power Hp12. When the pump target power Hp12 is computed, the pump torque control valve command St12 in response to the pump target power Hp12 is computed using the map 108c and output to the pump torque control valve 16a.
On the other hand, when the boom target power Hbo2 and the arm target power Har are input, higher power of the boom target power Hbo2 and the arm target power Har is selected as pump target power Hp3 in the selector 108d. When the pump target power Hp3 is set, the pump torque control valve command St3 in response to the pump target power Hp3 is computed using the map 108e and output to the pump torque control valve 16b.
The maps 108c and 108e make setting in such a manner as to increase the pump torque control valve commands St12 and St3 and reduce the delivery pressures (that is, the first pump torque control pressure Pt1 and the second pump torque control pressures Pt2 and Pt3) of the pump torque control valves 16a and 16b as the pump target power Hp12 and Hp3 is higher. As the configuration of the pump driving device 50 is previously described, when the delivery pressure of the pump torque control valve 16a becomes lower, the delivery rates of the second hydraulic pump 2b and the first hydraulic pump 2a increase, and when the delivery pressure of the pump torque control valve 16b becomes lower, the delivery rate of the second hydraulic pump 2c increases.
5. Effect
(1) Excellent Combined Operability
According to the hydraulic system configured as described above, the swing target power Hs computed by the swing target power arithmetic section 102 becomes higher as the swing operation amount (that is, the swing pilot pressure P1 or Pr) is larger. In this case, during the swing boom raising operation (that is, when the swing pilot pressure P1 or Pr and the boom raising pilot pressure Pu are simultaneously input to the controller 100), the swing target power Hs is calculated to be corrected to be lower than a value in response to the swing operation amount as the boom raising operation amount (that is, the boom raising pilot pressure Pus) is larger. The increasing rate of the swing target flow rate Fts computed by the swing target flow rate arithmetic section 103 is corrected to be lower than a value in response to the swing operation amount as the swing target power Hs is lower. As a result, during the swing boom raising, the swing acceleration becomes lower as the boom raising operation amount is larger, compared with a case of the sole swing operation. Therefore, “excellent combined operability” is attained during the swing boom raising operation.
(2) Energy Efficiency
Since the swing hydraulic motor 3 and the boom cylinder 4 are driven by the different hydraulic pumps (the first hydraulic pump 2a and the second hydraulic pumps 2b and 2c), it is possible to suppress the divergence loss that may be generated in the configuration of driving the swing hydraulic motor and the boom cylinder by the common hydraulic pump. Furthermore, since the delivery rate of the first hydraulic pump 2a is controlled in response to not only the swing operation amount but also the boom raising operation amount, it is possible to suppress degradation of fuel economy without increasing a pressure loss between the first and second hydraulic pumps 2b and 2c and the boom cylinder 4 at a time of adjusting the swing speed.
(3) Reliability
If the determiners 101a to 101c determine that a failure occurs in the boom raising pilot pressure sensor 13, the higher signal of the second pump flow control pressures Pf2 and Pf3 is output, as an alternative signal to the boom raising pilot pressure Pu, from the boom-raising pilot pressure selection section 101, as described above. As is obvious from a connection relationship among the shuttle valves 11b to 11f, the boom raising pilot pressure Pu is one of candidates of the second pump flow control pressures Pf2 and Pf3 and, therefore, the second pump flow control pressures Pf2 and Pf3 are generated when the boom raising operation is performed. Therefore, inputting the second pump flow control pressures Pf2 and Pf3 to the boom-raising pilot pressure selection section 101 makes it possible to detect that there is a probability that the boom raising operation has been performed even if a failure occurs in the boom raising pilot pressure sensor 13. Owing to this, even if a failure occurs in the boom raising pilot pressure sensor 13, it is possible to ensure the excellent combined operability during the swing boom raising operation by using the second pump flow control pressure Pf2 or Pf3 as an alternative to the boom raising pilot pressure Pus.
Furthermore, the hydraulic system is configured such that the delivery pressure Pd2 of the second hydraulic pump 2b acts on the first pump displacement reduction valve 52a. In other words, when the boom raising operation is performed and the boom cylinder 4 communicates with the second hydraulic pump 2b, a load pressure of the boom cylinder 4 acts on the first pump displacement reduction valve 52a as the delivery pressure Pd2 of the second hydraulic pump 2b. Therefore, whether a failure occurs in the boom raising pilot pressure sensor 13, by causing the load pressure of the boom cylinder 4 to act on the first pump displacement reduction valve 52a during the swing boom raising operation, it is possible to suppress the delivery rate of the first hydraulic pump 2a and suppress the swing acceleration. In this respect, it is possible to ensure the excellent combined operability.
(4) Others
The map 105a in the boom target power arithmetic section 105 makes setting in such a manner as to reduce the computed boom target power Hbo for the boom raising pilot pressure Pus as the swing target flow rate Fts is higher, as described above. It is thereby possible to slow down the boom raising speed when the swing speed increases and a swing load pressure decreases at the time of the swing boom raising operation. This can also contribute to improving the combined operability.
6. Alternatives
While the case of using the pilot operation levers 1a and 1b is taken as an example in the present embodiment, electric levers may be used as various types of operation devices such as the swing operation device and the boom operation device. If the electric levers are used as the swing operation device and the boom operation device, the pump flow control valve 15 and the pump torque control valves 16a and 16b can be omitted. Moreover, in the operation amount detector, potentiometers that directly detect electric lever operation amounts, for example, can be used as an alternative to the swing pilot pressure sensor 12, the boom raising pilot pressure sensor 13, and the like. In this case, if each potentiometer is configured, for example, such that the pilot pressure of the pilot hydraulic fluid source 17 (or another pilot hydraulic fluid source) is reduced by a solenoid valve similarly to the first pump torque control pressure Pt1 and the second pump torque control pressures Pt2 and Pt3, the solenoid valve is controlled by a command signal computed by the controller 100 on the basis of a signal of the potentiometer, and control pressure signals corresponding to the first pump flow control pressure Pf1 and the second pump flow control pressures Pf2 and Pf3 are generated, it is possible to realize similar functions to those of the embodiment described above.
Moreover, if the electric levers are used as the swing operation device and the boom operation device, the hydraulic system may be possibly configured such that the pump flow control valve 15 and the pump torque control valves 16a and 16b are omitted, electromagnetically-driven valves are used as the first pump displacement increase valve 51a and the second pump displacement increase valves 51b and 51c, and electromagnetic pilot valves are used as the first pump displacement reduction valve 52a and the second pump displacement reduction valves 52b and 52c. In this case, if the hydraulic system is configured such that control pressure signals corresponding to the first pump flow control pressure Pf1, the second pump flow control pressures Pf2 and Pf3, the first pump torque control pressure Pt1, and the second pump torque control pressures Pt2 and Pt3 are computed by the controller 100 on the basis of the signals of the potentiometers, and the control pressure signals are output to solenoid drive sections of the first pump displacement increase valve 51a, the second pump displacement increase valves 51b and 51c, the first pump displacement reduction valve 52a, and the second pump displacement reduction valves 52b and 52c, it is possible to realize similar functions to those of the embodiment described above.
Filing Document | Filing Date | Country | Kind |
---|---|---|---|
PCT/JP2015/077188 | 9/25/2015 | WO | 00 |
Publishing Document | Publishing Date | Country | Kind |
---|---|---|---|
WO2017/051483 | 3/30/2017 | WO | A |
Number | Name | Date | Kind |
---|---|---|---|
6020651 | Nakamura | Feb 2000 | A |
20070271913 | Ikeda | Nov 2007 | A1 |
20120324875 | Edler | Dec 2012 | A1 |
20160251833 | Kondo et al. | Sep 2016 | A1 |
Number | Date | Country |
---|---|---|
1 512 798 | Mar 2005 | EP |
2002-005109 | Jan 2002 | JP |
2004-036865 | Feb 2004 | JP |
2008-038587 | Feb 2008 | JP |
2013-181286 | Sep 2013 | JP |
2015-86959 | May 2015 | JP |
Entry |
---|
International Preliminary Report on Patentability received in corresponding International Application No. PCT/JP2015/077188 dated Apr. 5, 2018. |
International Search Report of PCT/JP2015/077188 dated Nov. 10, 2015. |
Extended European Search Report received in corresponding European Application No. 15904740.6 dated Jun. 3, 2019. |
Number | Date | Country | |
---|---|---|---|
20180058042 A1 | Mar 2018 | US |