The invention relates generally to indoor air quality and specifically to ventilation systems to achieve certain air changes per hour for residential and commercial buildings.
As technology and building practices have evolved to build structures that are more airtight, the need for adequately ventilating these structures has increased. Without proper ventilation, pollutants and moisture trapped in a building can create an unhealthy living environment.
In one embodiment, the invention provides an indoor air quality system for a building. The system includes a plurality of exhaust fans and a plurality of controllers. The exhaust fans each have a predetermined exhaust rate. The controllers are configured to monitor an actual volume of air exhausted by the indoor air quality system, and to automatically operate the exhaust fans to exhaust a desired volume of air during a time period.
In another embodiment, the invention provides a method of exchanging air in a building. The method comprises establishing a volume of air to be exhausted from the building in a time period, tracking a volume of air actually exhausted, calculating a remaining volume of air to be exhausted in the time period, determining a length of time needed to exhaust the remaining volume of air, and then exhausting the remaining volume of air during the time period.
In another embodiment, the invention provides a method of controlling an exchange of air in a building. The method includes setting parameters in a plurality of controllers, the parameters including an exhaust rate for a plurality of fans, a time period, and a volume of air to exchange during the time period. The method also includes communicating to the controllers an operating state of the fans and determining a time at which to energize the fans such that the volume of air to exchange during the time period is exchanged during the time period. Finally, the method includes energizing the fans at the determined time.
This summary does not set forth all embodiments and should not be construed as limiting of embodiments of the invention. In addition, other aspects of the invention will become apparent by consideration of the detailed description and accompanying drawings.
Before any embodiments of the invention are explained in detail, it is to be understood that the invention is not limited in its application to the details of construction and the arrangement of components set forth in the following description or illustrated in the following drawings. The invention is capable of other embodiments and of being practiced or of being carried out in various ways. Also, it is to be understood that the phraseology and terminology used herein is for the purpose of description and should not be regarded as limiting. The use of “including,” “comprising,” or “having” and variations thereof herein is meant to encompass the items listed thereafter and equivalents thereof as well as additional items. Unless specified or limited otherwise, the terms “mounted,” “connected,” and “coupled” and variations thereof are used broadly and encompass both direct and indirect mountings, connections, supports, and couplings. Further, “connected” and “coupled” are not restricted to physical or mechanical connections or couplings.
Newer airtight building practices effectively seal indoor air from outdoor air, affecting the quality of the indoor air. Thus, a need to address the ventilation and air-exchange needs of new buildings has arisen.
The American Society of Heating, Refrigerating, and Air-Conditioning Engineers, Inc. (“ASHRAE”) has developed standards for ventilation systems. ASHRAE Standard 62.2-2004 provides guidelines for achieving acceptable indoor air quality in low-rise residential buildings, and defines a minimum ventilation rate for a residence based on the size of the residence and the number of people occupying the residence. To calculate the minimum ventilation rate for a residence, ASHRAE assumes that one person occupies the house for each bedroom in the house. ASHRAE also assumes that two people occupy the master bedroom. The formula ASHRAE uses in its standard to determine the desired rate of ventilation for a residence is:
V
MOVE=(0.01×S)+(7.5×(BR+1))
where:
VMOVE is the rate at which air is to be exchanged in cubic feet per minute (“CFM”),
S is the size of the residence in square feet, and
BR is the number of bedrooms in the residence.
For example, for a residence with 2,000square feet (“ft2”) of living space and three bedrooms, the ventilation rate required by the standard is:
V
MOVE=(0.01×2,000)+(7.5×(3+1)) or
VMOVE=50 CFM
The ASHRAE standard does not require continuous ventilation (e.g., the 50 CFM of the example). Instead, the ASHRAE standard requires that the total volume of air exchanged over a period of time (the ASHRAE standard sets the time period at three hours) be equal to the volume of air that would have been exchanged had there been continuous ventilation at the calculated rate. For the residence in the example above, the amount of air that must be exchanged is calculated by taking the ventilation rate (VMOVE) and multiplying it by the time period (TPER). In this example, VMOVE has been calculated in cubic feet per minute. In order to normalize all of the variables, the time period is converted to minutes as well. Thus, the three hour time period becomes 180 minutes. Multiplied by VMOVE, 50 CFM in the example, the volume of air that must be exchanged every three hours to meet the ASHRAE standard is:
V
PER
=V
MOVE
×T
PER=50 CFM×180 minutes=9,000 cubic feet (“CF”)
Therefore, to meet the ASHRAE standard, a three bedroom, 2,000 square foot residence must have a ventilation system capable of exchanging a minimum of 9,000 CF of outdoor air for indoor air every three hours.
With today's airtight buildings, it is no longer possible to rely on passive ventilation systems to achieve a level of air exchange sufficient to meet the ASHRAE standard. An active ventilation system typically must be employed to ensure the level of air exchange necessary to maintain adequate indoor air quality (“IAQ”).
Each of the above types of ventilation systems—supply, balanced, and exhaust—can be used to achieve the volume of air exchange required by the ASHRAE standard or by other standards or design requirements. In trying to meet the ASHRAE standard, for example, home builders have generally used supply and balanced ventilation systems. Cost of equipment used in these systems can be relatively high. In addition, because of the design and installation of the ducting involved, professional heating ventilation and air conditioning (“HVAC”) designers and installers must participate in the building process, adding cost to the overall system.
Embodiments of the invention relate to systems and methods for improving the quality of indoor air by exchanging a desired volume of relatively lower quality indoor air for an equivalent volume of relatively higher quality outdoor air over a selected time period. The volume of air to be exchanged and the time period are chosen based on several factors including the type of structure, the number of people occupying the structure, and environmental factors. The time periods repeat continuously with a new volume of air being exchanged each time period. Embodiments of the invention are illustrated using an exhaust ventilation scheme. It should be apparent, however, that the invention can be applied in supply and balanced ventilation schemes as well. In addition, some of the embodiments shown represent IAQ systems for meeting the ASHRAE standard for low rise residences. The invention, however, has application in many other structures, including office buildings, commercial buildings, and clean rooms. Further, although embodiments discussed herein refer to the ASHRAE standard, other embodiments of the invention do not pertain to that standard.
Embodiments of the invention use bathroom fans to exhaust indoor air from a building. The exhausted indoor air is replaced by outdoor air that infiltrates the building. In some embodiments of the invention, the fans are controlled by smart switches which monitor the operation of the fans in the building and ensure that a sufficient amount of air is exchanged to maintain the quality of the indoor air.
Embodiments of the invention relate to systems and methods of using an exhaust ventilation mode to achieve indoor air quality. The embodiments can use existing components in a building and be installed by non-HVAC professionals. The embodiments thus provide a means to achieve desired indoor air quality, in a building, without incurring significant cost in the construction of the building.
In some embodiments, existing bathroom or other exhaust fans, vented to the outdoors, are used to exhaust indoor air to the outside of a building. The bathroom fans function in place of the exhaust blower 140 of
In some embodiments, the duct 180 for a fan includes a damper. The damper can help to insulate the building from the outside air. The damper can be passive (air from the fan blows the damper open) or active (a controller can open the damper via a motor when the fan is energized).
In some embodiments of an IAQ system, one or more controllers operate the system. The controllers can be incorporated into the fans, the switches, or can stand alone. In addition, each controller can control a single fan or multiple fans.
In one embodiment of the invention, each fan is controlled by a controller incorporated in a smart switch (e.g., Model INSTEON SwitchLinc V2 Relay, manufactured by Smarthome, Inc.).
As
An embodiment of a smart switch 350 is shown in schematic form in
The hot power line 280 and the neutral power line 285 of a building's electrical system are connected to the power source module 355. The power source module 355 converts the electric signal between the hot power line 280 and the neutral power line 285 to a low voltage direct current signal, +Vs (e.g., +5 VDC), for use by the integrated circuits of the smart switch 350.
The RF transmitter and receiver module 365 receives digital signals from the microcontroller 360 and converts the digital signals to RF signals. The RF signals are then transmitted wirelessly to be received by other smart switches in the IAQ system. The RF transmitter and receiver module 365 also receives RF signals (e.g., from other smart switches in the IAQ system or a programming module) and converts the RF signals to digital signals. The digital signals are then provided to the microcontroller 360.
Similarly, the power-line transmitter and receiver module 370 receives digital signals from the microcontroller 360 and converts the digital signals to a modulated signal that is carried on the power lines and received by other smart switches in the IAQ system 245. The power-line transmitter and receiver module 370 also receives modulated signals carried on the power lines (e.g., from other smart switches in the IAQ system 245 or a programming module) and converts the modulated signals to digital signals. The digital signals are then provided to the microcontroller 360.
Both the RF transmitter and receiver module 365 and the power-line transmitter and receiver module 370 can send and receive the same messages. Transmissions sent by the microcontroller 360 are provided to both the RF transmitter and receiver module 365 and the power-line transmitter and receiver module 370 for transmission. Messages received by the RF transmitter and receiver module 365 and the power-line transmitter and receiver module 370 are provided to the microcontroller 360, which compares the messages to check for reception errors. This dual mode communication scheme can provide highly reliable communications. In other embodiments, a single mode communication scheme (e.g., RF or power-line communications only) may be employed.
In the embodiment shown in
The microcontroller 360 is connected to the normally open switch 380. A second lead on the normally open switch 380 can be connected to ground. In this configuration, the input of the microcontroller 360 is high when the normally open switch 380 is open and low when the normally open switch 380 is closed. In some embodiments, the microcontroller 360 can detect that the normally open switch 380 has been closed by a user and can then apply power to the coil 385 of the normally open relay 375, causing the normally open contacts to close. This connects the hot wire 280 to the load lead 290 and causes the fan to energize. When the normally open switch 380 is opened by a user, the input to the microcontroller 360 goes high. The microcontroller 360 detects this high level at its input and removes power from the coil 385 of the normally open relay 375. This opens the normally open contacts, disconnecting the hot line 285 from the load lead 290, and de-energizing the fan.
In some embodiments, the smart switches are programmed after being installed in a building. Each smart switch can be preprogrammed with a unique address, and in embodiments using 16-bit addresses, there can be over 17,000,000 unique addresses available for the smart switches.
In some embodiments, the smart switch is preprogrammed with several (e.g., ten) preset VPER ranges. Once the programming indicator 395 is lit, and the smart switch is in the programming mode, the user can select the VPER range appropriate for the building. In some embodiments, VPER values can range from 5,500 CF (e.g., for a one bedroom, 1,500 ft2 residence) to 22,000 CF (e.g., for a six bedroom, 6,000 ft2 residence). In some embodiments, the smart switch includes a switch which allows both up and down selections. The user can press an upper portion of the switch to increase the VPER range or a lower portion of the switch to decrease the VPER range. The microcontroller 360 checks (step 515) if the upper portion of the switch has been pressed. If the upper portion of the switch is pressed, the microcontroller 360 increases (step 520) the VPER range by one. The microcontroller 360 also checks (step 525) if the lower portion of the switch has been pressed. If the lower portion of the switch is pressed, the microcontroller 360 decreases (step 530) the VPER range by one. Once the user has selected the appropriate VPER, the user can again press the programming button 390. In some embodiments, when the microcontroller 360 detects (step 535) that the programming button 390 has been pressed, the microcontroller 360 can flash (step 540) the programming indicator 395 a quantity of times reflective of the chosen VPER. The microcontroller 360 can then leave the programming indicator 395 lit and enter (step 545) a registration mode.
In some embodiments, the smart switch assumes that all of the fans in the IAQ system have a default exhaust rate (e.g., 100 CFM). If the fans in the IAQ system have a different exhaust rate than the default, the VPER range can be adjusted to compensate for the difference. The user totals the exhaust rate for all of the fans in the IAQ system and divides this total by the number of fans in the IAQ system multiplied by 100. This provides a ratio of the exhaust rate assumed by the VPER range and the actual exhaust rate. The user can then divide the VPER calculated for a building by the calculated ratio. This adjusted VPER can then be used for setting the VPER range, and the IAQ system can achieve the actual VPER desired.
Referring again to
After all of the smart switches in the IAQ system have been registered, the user can press the programming button 390 on the master switch again. In some embodiments, once the microcontroller 360 detects (step 560) that the programming button 390 has been pressed, the microcontroller 360 flashes (step 565) the programming indicator 395 (e.g., once for each smart switch registered) and then turns off the programming indicator 395. Programming of the IAQ system is then complete.
It can be necessary, in certain circumstances (e.g., errors in setting parameters or when changes occur in the IAQ system), to reset the master smart switch and remove its VPER range setting and smart switch registrations. In some embodiments, resetting the master switch can be accomplished by pressing the programming button 390 for an extended period (e.g., 10 seconds). The microcontroller 360 can monitor the programming button 390, and if the microcontroller 360 detects that the programming button 390 has been pressed for the extended period, the microcontroller 360 can reset the parameters stored in the smart switch to the factory defaults.
In some embodiments, a programming module (not shown) can be used to program an IAQ system. To program the IAQ system, the programmer is set to a read mode and links to the smart switches of the IAQ system via either RF or power-line means or both. For each fan in the IAQ system, a user manually energizes the fan, one fan at a time, by closing the normally open switch 380 of the smart switch for the fan. When a smart switch energizes a fan, the smart switch transmits, from its RF module and its power-line module, a communication specifying, for example, the address and operational status of the smart switch.
The programming module receives the communication from the smart switch and sends information to the smart switch including, for example, whether the smart switch should be a master or a slave; the exhaust rate, in CFM, of the fan associated with that smart switch; and the VMOVE and TPER of the IAQ system. In one embodiment, each smart switch in the IAQ system can monitor and store information transferred between the programming module and the other smart switches in the IAQ system.
The IAQ system can be configured by programming each of the smart switches in the system. In some embodiments, the master switch can be the last smart switch to be programmed. After programming, the master switch can interrogate the system to determine the configuration of the IAQ system. When the master switch interrogates the system, the slave switches can respond individually. Each slave switch can delay a unique time period (e.g., based on its address) such that two or more slave switches do not respond to the master switch's interrogation at the same time. In response to the master switch's interrogation, each slave switch can provide its address and the exhaust rate (in CFM) of the fan it controls.
In addition to the master switch, each slave switch can monitor the interrogations and save information about all or some of the smart switches in the system. Should the master switch fail, each slave switch can have the data necessary to assume the responsibilities of the master switch.
The master switch can periodically interrogate the system to ensure that no existing slave switches have failed and/or that no new slave switches have been added. If a slave switch does not respond when interrogated, the master switch adjusts its operation in an attempt to meet the VPER with the remaining slave switches and their associated fans.
The slave switches can also monitor the system for the master switch's interrogation. If the master switch does not interrogate the system for a predetermined period, the slave switches can determine that the master switch has failed, and a designated slave switch can assume the master switch's role.
In other embodiments, the smart switches are programmed using dip switches, either alone or in combination with other means. In some embodiments of an IAQ system, the fans store their exhaust rating and the smart switches read the exhaust rating directly from the fans instead of receiving it through programming. In still other embodiments, the controllers are located in the fans. In such embodiments, the fans can assume some or all the functionality of the smart switches as explained herein, and the switches can function as standard normally open switches.
In some embodiments of an IAQ system, the smart switches can leave the fans energized for a predetermined period of time following a user manually turning the fans off
In some larger buildings, power-line communication between smart switches can be inhibited when the electrical system of the building uses more than one phase of electricity. In such buildings, power-line communications of smart switches on one phase of electricity may be isolated from power-line communication of smart switches on a second phase of electricity. In some embodiments, a power-line communication coupler (e.g., model Hardwired SignaLinc™ Phase Coupler manufactured by Smarthome, Inc.) can be used to effectively couple the different phases of electricity for power-line communications, enabling smart switches on one phase of electricity to communicate with smart switches on another phase of electricity.
In addition, power levels of the RF transmitters in the smart switches may not be sufficient for a smart switch on one end of a building to reliably communicate with a smart switch on the opposite end of the building. In some embodiments, this situation can be resolved through the use of one or more RF repeaters. An RF repeater can receive messages from each of the smart switches and retransmit the messages received. The RF repeater can be located centrally in the building and enable the RF repeater to receive relatively weak signals from smart switches located at the ends of the building. The RF repeater then retransmits the messages at a relatively strong signal strength. This can ensure that messages from the smart switches are transmitted at a signal strength sufficient to be received by the other smart switches.
Generally, a bathroom fan removes indoor air from the bathroom and, to a lesser extent, from surrounding rooms. In some instances, it is desirable to circulate air throughout the entire building to ensure that the indoor air in the building is evenly exchanged. In some embodiments, a furnace blower can be energized automatically, whenever a fan of an IAQ system is energized, to disperse the indoor air throughout the building. Other embodiments energize the furnace blower when a fan of an IAQ system is energized automatically (or at some time prior to the fan being automatically energized) and do not energize the furnace blower when a fan of the IAQ system is energized manually.
During operation of the IAQ system, the fans can be energized manually by a user closing the normally open switch 380 (see
Turning to the embodiment of
V
MOVE=(0.01×2000)+(7.5×(3+1))=50 CFM or 0.8333 cubic feet per second (“CFS”)
F
NUM=2 (one fan in each bathroom)
F
1CAP=50 CFM (0.8333 CFS)
F
2CAP=75 CFM (1.25 CFS)
F
CAP
=F
1CAP
+F
2CAP=125 CFM (2.0833 CFS)
TPER=3 hours or 10,800 seconds
TELAPSE=0
V
PER
=V
MOVE
×T
PER=0.8333 CFS×10,800 seconds=9,000 CF
VACT=0
VMOVE is the rate at which air is to be exchanged in CFM;
FNUM is the number of fans in an IAQ system;
F1CAP and F2CAP are the rated exhaust capacities of fan #1 and fan #2 respectively;
FCAP is the exhaust capacity of the entire IAQ system;
TPER is the time period in which the air exchange is to take place;
TELAPSE is the amount of time elapsed in the present TPER;
VPER is the total volume of air to be exchanged during TPER; and
VACT is the volume of air actually exchanged during TELAPSE.
In this embodiment, the process executes once each second, and all time variables are adjusted to be in seconds. Other embodiments can execute at faster or slower rates.
Following initialization, the microcontroller 360 can update (step 605) a total volume of air actually exchanged from the beginning of the present time period until the present (VACT). This can be calculated by checking each fan in the system to determine if it is running and for each fan that is running, adding the volume of air that can be moved by that fan each second to VACT. For example, fan #1 (F1) is checked to see if it is running (either automatically or manually). If F1 is running, then the volume of air it moves each second, which is equal to its exhaust rate (F1CAP) in CFS, is added to VACT. VACT is updated for each fan in the IAQ system.
Once the actual volume of air exchanged, VACT, has been updated, a length of time that all of the fans must be turned on to meet the ASHRAE standard (TON) can be determined (step 610). TON is calculated using the following formula:
T
ON=(VPER−VACT)/FCAP
In this example, the volume of air to be exchanged per time period is 9,000 CF. At the beginning of the time period, the actual volume exchanged is 0 CF. The volume capacity of all of the fans combined is 2.0833 CFS. Plugging these numbers into the formula provides the result:
T
ON=(9,000 CF−0 CF)/2.0833 CFS=4,320 seconds
Therefore, if none of the fans were run manually during the time period, all of the fans would need to be energized for 4,320 seconds to reach the 9,000 CF desired. The microcontroller 360 then determines (step 615) the latest time that the fans can be started (TSTARTALL) to achieve the goal of 9,000 CF. This is calculated using:
T
STARTALL
=T
PER
−T
ON
Again substituting the 10,800 seconds for the time period and the on time of 4,320 seconds gives:
T
STARTALL=10,800−4,320=6,480 seconds
Therefore, to move 9,000 CF of air, all of the fans can start after 6,480 seconds (108 minutes) if none of the fans has been run in manual mode prior to that time. When one or more fans have been run in manual mode, the value VACT increases, which in turn reduces TON and delays TSTARTALL. Because some of the 9,000 CF that must be moved was moved manually, the amount of time all the fans must be automatically energized to meet the standard is reduced.
Next, TSTARTALL is compared (step 620) to the elapsed time in the period (TELAPSE). If TELAPSE is greater than or equal to TSTARTALL, the microcontroller 360 energizes (step 625) all of the fans in the IAQ system.
After energizing the fans (step 625) or if TELAPSE was less than TSTARTALL (step 620), the microcontroller 360 can check (step 630) if TELAPSE is greater than or equal to TPER. If TELAPSE is greater than or equal to TPER, the present time period is over and the microcontroller 360 can turn off (step 635) all the fans not being run manually, initialize (step 600) the IAQ system parameters, and start the next time period. If the present time period is not complete, the microcontroller 360 can wait (step 640) until the start of the next second, then update (step 605) the actual volume, and continue processing.
Turning to
RPER=5 minutes
RTIME=RPER
FCURR=FNUM
RPER is the period of time each fan will be run automatically before switching to the next fan;
RTIME is a timer value indicating how long the fan presently running automatically has been running; and
FCURR is the number of the fan being run automatically (during initialization FCURR is set such that fan #1 will be the first fan run automatically as will be shown below).
In this embodiment, the process executes once each second and all time variables are adjusted to be in seconds. Other embodiments can execute at faster or slower rates.
Next, the microcontroller 360 updates (step 705) a total volume of air actually exchanged from the beginning of the present time period until the present (VACT). This can be calculated by checking each fan in the IAQ system to determine if it is running and for each fan that is running, adding the volume of air that can be moved by that fan each second to VACT. For example, fan #1 (F1) is checked to see if it is running (either automatically or manually). If F1 is running, then the volume of air it moves each second, which is equal to its exhaust rate (F1CAP) in CFS, is added to VACT. VACT is updated for each fan in the system.
Once the actual volume of air exchanged, VACT, has been updated, a length of time that all of the fans must be turned on to achieve the ASHRAE standard (TON) can be determined (step 710). TON can be calculated using the following formula:
T
ON=(VPER−VACT)/FCAP
In this example, the volume of air to be exchanged per time period is 9,000 CF. At the beginning of the time period, the actual volume exchanged is 0 CF. The volume capacity of all of the fans combined is 2.0833 CFS. Plugging these numbers into the formula above provides the result:
T
ON=(9,000 CF−0 CF)/2.0833 CFS=4,320 seconds
Therefore, if none of the fans were run manually during the time period, all of the fans would need to be energized for 4,320 seconds to reach the 9,000 CF desired. The microcontroller 360 then determines (step 715) the latest time that the fans can be started (TSTARTALL) to achieve the goal of 9,000 CF. This is calculated using:
T
STARTALL
=T
PER
−T
ON
Again substituting the 10,800 seconds for the time period and the on time of 4,320 seconds gives:
T
STARTALL=10,800−4,320=6,480 seconds
In this embodiment, the fans can be run individually in succession to achieve the desired volume of air to exchange in TPER. It was previously determined that each fan needs to run for 4,320 seconds to reach the 9,000 CF. Since the fans are not energized at the same time in this embodiment, a start time (TSTART) is calculated using the formula:
T
START
=T
PER−(TON×FNUM)
Again substituting the total of 10,800 seconds for the time period, the on time of 4,320 seconds for each fan, and the number of fans in the IAQ system (two in this example) gives:
T
START=10,800−(4,320×2)=2,160 seconds
Therefore, to move 9,000 CF of air, automatic operation of the fans starts after 2,160 seconds (36 minutes), if none of the fans has been run in manual mode prior to that time. When one or more fans have been run in manual mode, the value VACT increases, which in turn reduces TON and delays TSTART. Because some of the 9,000 CF that must be exchanged was moved manually, the amount of time all the fans must be energized to meet the standard is reduced.
Next, TSTART is compared (step 720) to the elapsed time in the period (TELAPSE). If TELAPSE is greater than or equal to TSTART, the microcontroller 360 compares (step 725) TSTARTALL to the elapsed time in the period (TELAPSE). If TELAPSE is greater than or equal to TSTARTALL, the microcontroller 360 energizes (step 730) all of the fans.
After turning on the fans (step 730), the microcontroller 360 checks (step 735) if TELAPSE is greater than or equal to TPER. If TELAPSE is greater than or equal to TPER, the period is over and the microcontroller 360 can turn off (step 740) all the fans not being run manually, as well as initialize (step 700) the IAQ system parameters and start the next period. If the period is not complete, the microcontroller 360 can wait (step 745) until the start of the next second, then update (step 705) the actual volume, and continue processing.
If, at step 725, TELAPSE is less than TSTARTALL, the microcontroller 360 compares (step 750) the run time (RTIME) to the run period (RPER). RTIME is a timer that continuously counts up. The RPER is the amount of time an individual fan will run before switching to the next fan. This enables the fans to cycle on and off for relatively short periods rather than running each fan for the full TON (4,320 seconds in this example). This can result in a more even exchange of air throughout the building. In this example, RPER can be set to five minutes.
The first time the comparison of step 750 is made, RTIME can be greater than or equal to RPER. RTIME is then set (step 755) to zero. The fan currently running in automatic mode (FCURR) is turned off (step 760). Next, FCURR is incremented (step 765) by one. If FCURR is greater than FNUM (step 770), FCURR is set to one (step 775). Next, FCURR is energized (step 780) and the microcontroller 360 checks (step 735) if TELAPSE is greater than or equal to TPER. If TELAPSE is greater than or equal to TPER, the present time period is over and the microcontroller 360 can turn off (step 740) all the fans not being run manually and initialize (step 700) the IAQ system parameters and start the next time period. If the present time period is not complete, the microcontroller 360 can wait (step 745) until the start of the next second, then update (step 705) the actual volume, and continue processing.
If, at step 720, TELAPSE is not greater than or equal to TSTART, the microcontroller 360 turns off (step 785) all fans being run automatically and sets (step 790) the run time RTIME equal to the run period RPER.
In some embodiments of the IAQ system, the fans are automatically energized as late in TPER as possible to meet the ASHRAE standard. This can result in higher energy efficiency as any manual operation of the fans will be factored into the calculation for the amount of time the fans are run and will prevent the fans from running for an additional period of time, exceeding the requirements of the ASHRAE standard. Other embodiments can automatically energize the fans for periods throughout TPER and can achieve more consistent air exchange throughout TPER. Still other embodiments can monitor environmental conditions (e.g., humidity, carbon monoxide, etc.) and can automatically energize the fans when, for example, the monitored condition(s) exceed a threshold or drop below a threshold. The fan or fans that are energized can be local to the monitored condition and/or can include all or some other fans within the building.
In some embodiments, the IAQ system can link to other systems in the building (e.g., environmental, computer, phone). For example, the IAQ system can link to a make-up air system which draws outdoor air into a building. In some embodiments, the make-up air is distributed through the building via the building's HVAC ducting. The IAQ system can monitor all of the exhaust fans (e.g., bathroom fans and range hoods) in the building and can communicate to the make-up air system the rate at which air is being exhausted throughout the whole building. The make-up air system can then draw outdoor air into the building at a rate sufficient to replace the air being exhausted. Such embodiments can reduce backdraft issues in buildings.
Other embodiments of the IAQ system can sense the presence of people in the building (e.g., with motion or heat sensors) and can adjust system operation accordingly. For example, if there are no people in the building, the IAQ system can reduce the number of air exchanges that will be performed. Reducing the number of air exchanges rather than eliminating the air exchanges may be desirable. Conversely, if the IAQ system detects more (or fewer) people in the building than the number that was used in calculating VMOVE (i.e., the number of people detected does not equal the number of bedrooms plus one for a residence), the IAQ system can recalculate VMOVE based on the actual number of people detected and adjust system operation up or down accordingly.
In some embodiments, the IAQ system can operate in a set back mode. In one embodiment of a set back mode, the IAQ system can reduce the number of air exchanges during periods when the building is unoccupied and resume normal operation when the building is occupied. In some embodiments, the IAQ system can automatically energize the fans for a predetermined period prior to the expected return of people to the building after a period in which the building was unoccupied.
In some embodiments, the IAQ system can operate based on a set of zones. For example, a residence may have bedrooms upstairs and living quarters downstairs. During daytime operation, the IAQ system can automatically energize fans located downstairs to exchange the indoor air where people are more likely to be present and can automatically energize fans located upstairs in the evening and nighttime when people are more likely to be present in the bedrooms.
In some embodiments, the IAQ system can keep a historical record of its operation. The historical data can be provided to another device (e.g., a computer) for display and/or analysis.
Various features and advantages of the invention are set forth in the following claims.