1. Field of the Invention
The present invention relates to inflatable packers having utility in downhole operations, particularly inflatable packers adapted for use in formation fluid sampling.
2. Background of the Related Art
Once an oil well has been drilled, it is often necessary for the operator to obtain downhole data, such as pressure measurements and downhole fluid samples for analysis. These tasks are commonly accomplished with downhole tools, such as modular wireline tools or drilling tools with evaluation capabilities, that employ probes for engaging the formation and establishing fluid communication to make the pressure measurements and acquire the fluid samples. Fluid is topically drawn into the downhole tool through an inlet in the probe. In some instances, such as for tight, low permeability, formations, sampling probes are often replaced by dual inflatable packer assemblies. Examples of such probe and packer systems are depicted, for example, in U.S. Pat. Nos. 4,860,581 and 4,936,139 assigned to Schlumberger, the entire contents of which are hereby incorporated by reference.
When inflating the packer elements (typically made of rubber), their ends often sustain large amounts of deformation and bending stresses, which may lead to circumferential tearing, and system failure. Additionally, since it is not uncommon for boreholes to exhibit high temperatures, particularly at great depths, the packer elements are often subjected to significant thermal stresses.
Attempts have been made to prevent packer failures. Accordingly, inflatable packer bodies or elements are often equipped with reinforcements in the form of metal cables or slats. While these reinforcements may be used to increase the life of the packer elements, the reinforcements may plastically deform and permit undesirable extrusion (as shown in
Despite the advances in packer technology, there remains a need for a packer with a long life under harsh wellbore conditions. It is desirable that such a packer limit or constrain the deformation that the packer undergoes during borehole operations so as to achieve a “milder” inflation profile (e.g., avoid the extruded profile of
A further issue that arises in dual packer assemblies relates to the axial separation distance between the packer elements. As this distance is increased, e.g., to increase the isolated area of the borehole wall, the risk of buckling at the mandrel that separates the packers typically increases. Accordingly, a need exists for a solution to the buckling risk in spaced dual packer assemblies.
Certain terms are defined throughout this description as they are first used, while certain other terms used in this description are defined below:
“Deployable” means movable from one position or configuration to another position or configuration, particularly by way of expansion or spreading out.
“Inwardly-facing” means facing towards the center or middle of an article or a set of articles (e.g., facing towards the center of a packer).
“Lower” means positioned deeper within a borehole (e.g., a lower end support of a packer having two end supports).
“Mandrel” means a bar, shaft, spindle or tubular member about which other components are arranged, assembled, or carried, particularly for performing one or more operations within a borehole.
“Outer” means positioned or located at a physical extreme or limit.
“Outwardly-facing” means facing away from the center or middle of an article or a set of articles (e.g., facing away from the center of a packer).
“Upper” means positioned shallower within a borehole (e.g., an upper packer of a dual packer configuration).
In one aspect, the present invention provides an inflatable packer assembly, including a first expandable tubular element having a pair of ends, and a first pair of annular end supports for securing the respective ends of the first tubular element about a mandrel disposed within the first tubular element. A first annular bracing assembly is deployable from one of the end supports for reinforcing the first tubular element upon pressurization and expansion thereof.
Preferably, the first annular bracing assembly is deployable by being pivotally-connected at one of its ends to one of the end supports. Alternatively, the deployable characteristic could be provided by other suitable extending or spreading means such as a piston-like engagement between the first annular bracing assembly (as a whole or by separate components thereof) with one of the end supports. Such alternatives are foreseen by the present invention and are considered to be within the scope thereof.
Preferably, one of the end supports is movable and the other end support is fixed with respect to the mandrel. However, the present invention extends to embodiments wherein both end supports are fixed with respect to the mandrel.
The first tubular element includes a flexible or elastomeric material that is known in the art. The end supports are preferably metallic and each include an annulus for receiving an end of the first tubular element.
The first annular bracing assembly is preferably expandable at its end opposite the pivotally connected end. Various embodiments of the annular bracing assembly employ a plurality of fingers or slats arranged in an annular configuration and each pivotally connected at one of its ends to either the movable end support or the fixed end support.
Where slats are employed by the annular bracing assembly, it is preferred that each of the slats has a width that increases from its pivotally connected end to its other end, and that the slats be arranged so that each slat partially overlaps an adjacent slat.
The packer assembly may include a pair of annular bracing assemblies each pivotally-connected at one of its ends to one of the first annular pair of end supports for reinforcing the first tubular element upon pressurization and expansion thereof.
The packer assembly will typically employ a mandrel adapted for use in a downhole tool in support of dual inflatable packers. Accordingly, the packer assembly may further include a second expandable tubular element having a pair of ends, and a second pair of annular end supports for securing the respective ends of the second tubular element about the mandrel. The first and second pair of end supports cooperate to define an axial separation distance between the first and second tubular elements. A second annular bracing assembly is pivotally connected at one of its ends to one of the second pair of end supports for reinforcing the second tubular element upon pressurization and expansion thereof.
Preferably, one of end supports of the second pair of end supports is movable and the other end support is fixed with respect to the mandrel.
In the packer assembly embodiments that employ dual packers, the lower end support of each of the first and second pairs of end supports is preferably a movable end support. Alternatively, the outer end supports among the first and second pairs of end supports are movable end supports.
Particular embodiments of the packer assembly are further equipped with a first retraction assembly for moving a movable end support of the first pair of end supports from an expanded position to a retracted position. Such embodiments may be further equipped with a second retraction assembly for moving a movable end support of the second pair of end supports from an expanded position to a retracted position. In these embodiments, it is preferred that the movable end support associated with each of the first and second retraction assemblies be equipped with an inwardly-facing surface area that exceeds its outwardly-facing surface area, whereby borehole fluid pressure imposes a net force above a low-pressure chamber that moves the movable end supports outwardly when the first and second tubular elements are depressurized and contracted.
Particular embodiments of the inventive packer assembly further include an expandable centralizer carried by the mandrel in the axial separation distance intermediate the first and second tubular elements for resisting buckling of the mandrel.
In another aspect, the present invention provides an inflatable packer assembly, including a first expandable tubular element having a pair of ends, and a first pair of annular end supports for securing the respective ends of the first tubular element about a mandrel disposed within the first tubular element. One of the end supports is movable and the other end support is fixed with respect to the mandrel. A first stop member is provided for limiting the axial movement of the movable end support.
In particular embodiments, the movable end support is equipped with an inwardly-facing surface area that exceeds its outwardly-facing surface area, whereby borehole fluid pressure imposes a net force that moves the movable end support outwardly when the first tubular element is depressurized and contracted.
The packer assembly and the movable end support may be disposed for axial movement about a sleeve fixed to the mandrel. The sleeve has a stepped radius that corresponds to the inwardly-facing and outwardly-facing surface areas of the movable end support.
The packer assembly may further include a first annular bracing assembly pivotally-connected at one of its ends to one of the end supports for reinforcing the first tubular element upon pressurization and expansion thereof.
The packer assembly will typically employ a mandrel adapted for use in a downhole tool in support of dual inflatable packers. Accordingly, the packer assembly may further include a second expandable tubular element having a pair of ends, and a second pair of annular end supports for securing the respective ends of the second tubular element about the mandrel. One of the end supports is movable and the other end support is fixed with respect to the mandrel. A second stop member is provided for limiting the axial movement of the movable end support.
In particular embodiments, the movable end support is equipped with an inwardly-facing surface area that exceeds its outwardly-facing surface area, whereby borehole fluid pressure imposes a net force that moves the movable end support outwardly when the first tubular element is depressurized and contracted. The first and second pairs of end supports cooperate to define an axial separation distance between the first and second tubular elements. Such embodiments of the packer assembly may further include a second annular bracing assembly pivotally-connected at one of its ends to one of the end supports for reinforcing the second tubular element upon pressurization and expansion thereof.
In a still further aspect, the present invention provides an inflatable packer assembly, including a pair of inflatable packers disposed about a mandrel adapted for use in a downhole tool disposed in a borehole, the packers being spaced apart by an axial separation distance. An expandable centralizer is carried by the mandrel in the axial separation distance intermediate the first and second packers for resisting buckling of the mandrel.
The centralizer may include a pair of supports carried along the mandrel, with at least one of the supports being axially-movable along the mandrel. The centralizer of these embodiments further includes a plurality of (preferably at least three) pairs of hinged arms. The arms of each pair have first ends pivotally connected to the respective supports and second ends pivotally connected to each other. An actuator is carried by the mandrel for inducing axial movement of each movable support such that the pivotally-connected second ends of each pair of arms is moved radially outwardly to exert a force on the borehole wall that substantially centers the mandrel in the borehole.
The centralizer may further include a plurality of spring blades each having ends pivotally connected to the respective supports so as to position the spring blades between the respective pairs of hinged arms and the borehole wall. The spring blades and hinged arms cooperate to exert forces on the borehole wall that substantially centers the mandrel in the borehole.
A still further aspect of the present invention relates to a method of deploying a pair of spaced-apart inflatable packers carried about a mandrel disposed in a borehole penetrating a subsurface formation. The method includes the steps of pressurizing the packers so as to isolate an annular portion of the borehole wall, collecting one or more samples of formation fluid via the isolated portion of the borehole wall, and depressurizing the packers so as to permit movement of the mandrel within the borehole. The method further includes one or more of the following steps: restricting deformation of the packers during the pressurizing step using an annular bracing assembly; limiting the axial movement of the movable end support; and substantially centralizing the mandrel intermediate the packers so as to resist buckling of the mandrel.
Each packer may include a first expandable tubular element having a pair of ends, and a first pair of annular end supports for securing the respective ends of the first tubular element about the mandrel. Preferably, one of the end supports is movable and the other end support is fixed with respect to the mandrel. The deformation-restricting step is achieved in these embodiments using an annular bracing assembly pivotally connected at one of its ends to one of the end supports for reinforcing the first tubular element upon pressurization and expansion thereof.
In particular embodiments, the method further includes the step of actively retracting the packers using ambient borehole pressure. Accordingly, each packer may include an expandable tubular element having a pair of ends, and a pair of annular end supports for securing the respective ends of the tubular element about the mandrel. One of the end supports is movable and the other end support is fixed with respect to the mandrel. The movable end support is equipped with an inwardly-facing surface area that exceeds its outwardly-facing surface area. Borehole fluid pressure imposes a net force that moves the movable end support outwardly when the first tubular element is depressurized and contracted, thereby actively retracting the packer using the borehole fluid pressure.
The centralizing step may also be achieved using a centralizer that employs a plurality of hinged arms.
Other aspects and advantages of the invention will be apparent from the following description and the appended claims.
So that the above recited features and advantages of the present invention can be understood in, detail, a more particular description of the invention, briefly summarized above, may be had by reference to the embodiments thereof that are illustrated in the appended drawings. It is to be noted, however, that the appended drawings illustrate only typical embodiments of this invention and are therefore not to be considered limiting of its scope, for the invention may admit to other equally effective embodiments.
Turning now to prior art
As shown in the embodiment of
The hydraulic power module C includes pump 216, reservoir 218, and motor 220 to control the operation of the pump 216. Low oil switch 222 also forms part of the control system and is used in regulating the operation of the pump 216.
The hydraulic fluid line 224 is connected to the discharge of the pump 216 and runs through hydraulic power module C and into adjacent modules for use as a hydraulic power source. In the embodiment shown in
The pump-out module M, seen in
The pump out module M has the necessary control devices to regulate the piston pump 292 and align the fluid line 254 with fluid line 295 to accomplish the pump out procedure. It should be noted here that piston pump 292 can be used to pump samples into the sample chamber module(s) S, including overpressuring such samples as desired, as well as to pump samples out of sample chamber module(s) S using the pump-out module M. The pump-out module M may also be used to accomplish constant pressure or constant rate injection if necessary. With sufficient power, the pump out module M may be used to inject fluid at high enough rates so as to enable creation of microfractures for stress measurement of the formation.
Alternatively, the dual inflatable packers 228 and 230 shown in
Having inflated the packers 228 and 230 and/or set the probe 210 and/or the probes 212 and 214, the fluid withdrawal testing of the formation can begin. The sample flow line 254 extends from the probe 246 in the probe module E down to the outer periphery 232 at a point between the packers 228 and 230 through the adjacent modules and into the sample modules S. The vertical probe 210 and the sink probe 214 thus admit formation fluids into the sample flow line 254 via one or more of a resistivity measurement cell 256, a pressure measurement device 258, and a pretest mechanism 259, according to the desired configuration. Also, the flowline 264 allows entry of formation fluids into the sample flowline 254. When using the module E, or multiple modules E and F, the isolation valve 262 is mounted downstream of the resistivity sensor 256. In the closed position, the isolation valve 262 limits the internal flow line volume, improving the accuracy of dynamic measurements made by the pressure gauge 258. After initial pressure tests are made, the isolation valve 262 can be opened to allow flow into the other modules via the flowline 254.
The sample chamber module S can then be employed to collect a sample of the fluid delivered via the flow line 254 and regulated by the flow control module N, which is beneficial but not necessary for fluid sampling. With reference first to the upper sample chamber module S in
The inflatable packer assembly 410 includes the expandable tubular packer element 412 having a pair of ends 414, 416, and a first pair of annular end supports 420, 422 having respective annuluses 419, 421 for securing the respective ends 414, 416 of the first tubular packer element 412 about a mandrel 424 at least partially disposed within the first tubular packer element 412. The lower end support 422 is movable and the upper end support 420 is fixed with respect to the mandrel 424. Alternatively, both of the upper and lower end supports may be fixed (not shown) given that the packer element 412 is suitably constructed to allow for additional elastic deformation.
The first annular bracing assembly 426 is deployable from the lower end support 422 by being pivotally-connected at one of its ends 430 to the lower end support 422 for reinforcing the first tubular packer element 412 upon pressurization and expansion (i.e., inflation) thereof. Those having ordinary skill in the art will appreciate that other means of deployment (e.g., sliding translatory movement) may be employed to advantage. The annular bracing assembly 426 functions as an external mechanical support to the tubular packer element 412, and effectively bridges the gap between the end support 422 (which is metallic) and the borehole wall 418. This works to relieve the flexible tubular packer element 412 from having to provide the mechanical strength to support itself (e.g., via reinforcing inserts such as slats). The bracing assembly provides support to assist the tubular packer element 412 in forming a seal between the borehole wall 418 and the packer mandrel 424.
The first annular bracing assembly 426 is expandable at its end 432 opposite the pivotally connected end 430, whereby the assembly 426 becomes frustoconically-shaped upon inflation of the tubular packer element 412 (see
Various embodiments of the annular bracing assembly may employ a plurality of fingers or slats arranged in an annular configuration and pivotally connected at least one of its ends to either the movable end support and/or the fixed end support.
Thus, inflation of the tubular packer element 412 expands the outer diameter of the element from a diameter D1 to a diameter D2, as indicated in
One or more spring braces 442 each having an appropriate spring stiffness are employed to assist in restoring the annular bracing assembly and the tubular packer element 412 back to their original running positions of
The packer assembly 610 operates differently from the packer assembly 410 described above, particularly in the manner in which the annular bracing assembly 626 is deployed from the end support 622. Thus, the annular bracing assembly comprises a plurality of slats 634 disposed for sliding translator movement within a plurality of respective channels 635 formed about the end support 622. Hydraulic fluid is provided via one or more flow line(s) 633 from the mandrel 624, in a manner that is known in the art (e.g., under manipulation of pumps and valves carried within or operatively connected to the mandrel 624), so as to induce concerted movement of the slats 634 between the retracted, running position of
The packer assembly 710 operates similarly to the packer assembly 410 described above, except for the manner in which the packer assembly 710 is retracted to its running position upon deflation of the tubular packer element 712. In particular, the spring brace 442 of the previously-described embodiment is replaced with a sliding sleeve 742 that is moved downwardly (e.g., under manipulation of pumps and valves carried within or operatively connected to the mandrel 724) to a lower position to permit expansion of the tubular packer element 712 and the outer ends 732 of the slats 734 that substantially make up the annular bracing assembly 726, which is shown in
The packer assembly 810 operates similarly to the packer assemblies 410 and 710 described above, except for the manner in which the end 830 of the annular bracing assembly is pivotally connected to the lower end support 822, and the manner in which the packer assembly 810 is retracted to its running position upon deflation of the tubular packer element 812. Thus, the end 830 of the annular bracing assembly 826 defines a flange that is closely fitted within a recess 821r of the annulus 821 of the lower end support 822.
Additionally, the spring brace 442 and sleeve 742 of the previously-described embodiments are replaced with a bonding agent 842 applied between tubular packer element 812 and the slats 834 that substantially make up the annular bracing assembly 826. Accordingly, the slats 834 follow the tubular packer element 812 to the retracted running position of
While the packer assembly embodiments of
In the embodiment of
The sleeve 944 is preferably equipped with a mechanical stop member 946 disposed in the sealed low-pressure chamber 948 for limiting the axial movement of the movable end support 922 along the sleeve. The stop member 946 prevents the bottom part of the lower end support 922 from ascending too much and losing the bottom sealing engagement with the sleeve 944 upon inflation of the tubular packer element 912. Additionally, by limiting the upward movement of the lower end support 922, the stop member 946 reduces the deformation experienced by the tubular packer element 912 near its lower end 916 where the bending radius is short and the stress concentrations are significant. The resulting (milder) deformation is intended to extend the useful life of the packer element 912 by avoiding the square-like transition zone that otherwise occurs in conventional inflatable packers when. e.g., the packer element bends near the movable end support. Additionally, limiting the upward movement of the lower end support 922 via the mechanical stop member 946 is designed to increase the tensile force developed in the packer element 912 and inhibit plastic deformation of the packer element or the metallic inserts therein (if used).
The stop member described herein provides independently utility within a packer assembly, and, accordingly, may be used independently of the packer retraction assembly. Additionally, the stop member need not be embodied by a hard stop mechanism, as shown by stop member 946, but instead may be compliant (e.g., including a spring component) so as to apply a more gradual limiting force over a longer axial displacement of a movable end support.
The movable end support 1022 is equipped with an inwardly-facing surface area (A1+A2) that preferably exceeds its outwardly-facing surface area A3, whereby ambient borehole fluid pressure (which acts on these areas) imposes a net force that moves the movable end support outwardly (i.e., downwardly in the case of lower end support 1022) when the tubular packer element 1012 is depressurized and contracted (i.e., deflated).
The movable end support 1022 moves axially about a sleeve 1044 fixed to the mandrel 1024. The sleeve 1044 has a stepped radius that defines minimum and maximum diameters which correspond to the inwardly-facing surface area (A1+A2) and outwardly-facing surface area A3 of the movable end support 1022. A sealed low-pressure chamber 1048 permits movement of the movable end support 1022 relative to the sleeve 1044 under ambient borehole fluid pressure. The sleeve 1044 is preferably equipped with a mechanical stop member 1046 (essentially an expanded ring about its maximum diameter portion) that is disposed in the low-pressure chamber 1048 for limiting the axial movement of the movable end support 1022 along the sleeve. The stop member 1046 prevents the bottom part of the lower end support 1022 from ascending too much and losing the bottom sealing engagement with the sleeve 1044 upon inflation of the tubular packer element 1012.
An annular bracing assembly 1026 is pivotally-connected at one of its ends 1030 to the lower end support 1022 for reinforcing the first tubular packer element 1012 upon pressurization and expansion (i.e., inflation) thereof. The annular bracing assembly 1026 functions as a mechanical support to the tubular packer element 1012, and effectively bridges the gap between the end support 1022 (which is metallic) and the borehole wall 1018. This relieves the flexible tubular packer element 1012 from having to provide the mechanical strength to support itself (e.g., via reinforcing inserts), and allows the tubular packer element 1012 to function more reliably to affect the appropriate seal between the borehole wall 1018 and the packer mandrel 1024.
The annular bracing assembly 1026 is expandable at its end 1032 opposite the pivotally connected end 1030, whereby the assembly 1026 becomes frustoconically-shaped upon inflation of the tubular packer element 1012 (see
An expandable centralizer 1160 is carried by the mandrel 1150b in the axial separation distance intermediate the first and second packers 1110 for resisting buckling of the mandrel during fluid sampling operations. The mandrel 1150b represents at least a portion of the so-called “spacer string” between the packer elements 1112, which provides the desired axial separation distance between the packer elements. Accordingly, the centralizer 1160 serves as an element of the spacer string. The centralizer 1160 includes a pair of supports 1162, 1164 carried along the mandrel 1150a, with at least one of the supports being axially-movable along the mandrel. The centralizer of these embodiments further includes a plurality of (preferably at least three) pairs of hinged arms 1166. The arms of each pair have first ends pivotally connected to the respective supports 1162, 1164 and second ends pivotally connected to each other at a pivotal joint 1168.
An actuator (not shown) is carried by one of the interconnected mandrels 1150a/b/c for inducing axial movement of each movable support (among supports 1162, 1164) such that the pivotally-connected second ends 1168 of each pair of arms is moved radially outwardly to exert a force on the borehole wall 1118 that substantially centers the mandrel in the borehole.
In open hole (i.e., uncased) sampling operations, the centralizer 1160 preferably further includes a plurality of spring blades 1170 each having ends pivotally connected to the respective supports 1162, 1164 so as to position the spring blades 1170 between the respective pairs of hinged arms 1166 and the borehole wall 1118. The spring blades 1170 and hinged arms 1166 cooperate to exert forces on the borehole wall that substantially centers the mandrel (preferably all three mandrels 1150a/b/c) in the borehole. Other aspects of the centralizer are known to those having ordinary skill in the art, e.g. as evidenced by the teachings of U.S. Pat. No. 5,358,039—although such centralizers are not believed to have been previously applied to packer assemblies as described herein.
Thus, the upper packer element 1212a employs a movable upper end support 1220a and a fixed lower end support 1222a. Conversely, the lower packer element 1212b employs a fixed upper end support 1220b and a movable lower end support 1222b. The movable end supports 1220a, 1222b cooperate with respective sleeves 1244a, 1244b, in analogous fashion to the movable end support 922 and sleeve 944 of
The downhole tool of
In this embodiment, the lower support 1264 is fixed and the upper support 1262 is movable. The upper support 1262 is moved axially along the mandrel 1250 by an actuator that includes a piston 1280 and piston rod 1282. The piston is reciprocated within a cylinder 1284 by hydraulic fluid pressure, thereby moving the upper actuator upwardly and downwardly as desired to extend or retract the pivotally-connected ends 1268 of the hinged arms 1266. Upon such extension, the ends 1268 contact the borehole wall 1218 with sufficient force to hold the centralizer 1260 firmly within the borehole center. A helical spring 1286 secured about a reduced-diameter portion of the mandrel 1250 biases the upper support 1262 towards it upper position, whereby the ends 1268 are moved inwardly to a running position in a default condition.
The side of the piston 1280 opposite the cylinder pressure has interval pressure (i.e., the pressure in the borehole interval isolated by the packer elements 1212a,b when inflated) acting on it. Thus, as the pressure drops in the interval, the force applied by the piston 1280 to piston rod 1282 will increase, even thought the piston cylinder pressure remains constant. This provides increasing force to the stabilizing arms 1266 and ends 1268 to counter the increasing buckling forces generated as the interval pressure drops. In applications where the centralizer piston 1280 does not require a significant pressure differential to achieve adequate centralizing force, the piston cylinder 1284 could be pressurized by the same fluid used to pressurize the packer elements 1212a,b (not necessarily on the same flow line) and the side of the piston 1280 opposite the cylinder pressure could be connected to hydrostatic pressure (i.e., the borehole pressure outside the packer interval). This way, the pressure on the piston 1280 would only be the packer inflation pressure.
The use of two or more actuating pistons would allow independent deployment of the centralizing arms 1266. This would, e.g., allow for centralization in a non-circular section of the borehole. Additionally, a plurality of such stabilizer sections could be used at the same time, which would allow any desired packer spacing or interval length.
In summary, several aspects of the present invention provide for reliably deploying a pair of spaced-apart inflatable packers carried about a mandrel disposed in a borehole penetrating a subsurface formation. Conventional formation evaluation with dual inflatable packers includes the steps of pressurizing the packers so as to isolate an annular portion of the borehole wall, collecting one or more samples of formation fluid via the isolated portion of the borehole wall, and depressurizing the packers so as to permit movement of the mandrel within the borehole. The present invention provides a sampling method and apparatus that utilize one or more of the following to advantage: restricting deformation of the packers during inflation using an annular bracing assembly; actively retracting the packers using ambient borehole pressure; and substantially centralizing the mandrel intermediate the packers so as to resist buckling of the mandrel.
It will be understood from the foregoing description that various modifications and changes may be made in the preferred and alternative embodiments of the present invention without departing from its true spirit.
This description is intended for purposes of illustration only and should not be construed in a limiting sense. The scope of this invention should be determined only by the language of the claims that follow. The term “comprising” within the claims is intended to mean “including at least” such that the recited listing of elements in a claim are an open group. “A,” “an” and other singular terms are intended to include the plural forms thereof unless specifically excluded.
Number | Date | Country | |
---|---|---|---|
Parent | 10981204 | Nov 2004 | US |
Child | 12025874 | US |