Abstract
An approach for infrastructure asset management is provided. This approach comprises an end-to-end analytics driven maintenance approach that can take data about physical assets and additional external data, and apply advanced analytics to the data to generate business insight, foresight and planning information. Specifically, this approach uses a maintenance analysis tool, which is configured to: receive data about a set of physical assets of an infrastructure, and analyze the data about the set of physical assets to predict maintenance requirements for each of the set of physical assets. The maintenance analysis tool further comprises an output component configured to generate a maintenance plan based on the predicted maintenance requirements for each of the set of physical assets.
Description
FIELD OF THE INVENTION

The present invention generally relates to infrastructure asset management. Specifically, the present invention provides an approach for an end-to-end analytics driven asset management.


BACKGROUND OF THE INVENTION

Many entities in the Smarter Planet arena run asset intensive businesses, e.g., water and power utilities, transportation operators, hotels, oil and gas companies, power plants, etc. One of the most significant components of their operating cost tends to be maintenance. Current solutions to the problem use a manual approach to managing maintenance operations (e.g., scheduling, preventive maintenance, operating parameter control, etc). This approach, while leveraging human experience, does not fully involve historical and sensor data sources to inform the decision making around these efforts.


SUMMARY OF THE INVENTION

In one approach, there is a method for infrastructure asset management. In this approach, the method comprises: receiving data about a set of physical assets of an infrastructure; analyzing the data about the set of physical assets to predict maintenance requirements for each of the set of physical assets; and generating a maintenance plan based on the analyzing.


In a second approach, there is a system for infrastructure asset management. In this approach, the system comprises at least one processing unit, and memory operably associated with the at least one processing unit. A maintenance analysis tool is storable in memory and executable by the at least one processing unit. The maintenance analysis tool comprises: an analysis component configured to: receive data about a set of physical assets of an infrastructure; and analyze the data about the set of physical assets to predict maintenance requirements for each of the set of physical assets. The maintenance analysis tool further comprises an output component configured to: generate a maintenance plan based on the predicted maintenance requirements for each of the set of physical assets.


In a third approach, there is a computer program product for infrastructure asset management, the computer program product comprising a computer readable storage media, and program instructions stored on the computer readable storage media to: receive data about a set of physical assets of an infrastructure; analyze the data about the set of physical assets to predict maintenance requirements for each of the set of physical assets; and generate a maintenance plan based on the predicted maintenance requirements for each of the set of physical assets.


In a fourth approach, there is a method for infrastructure asset management, comprising: providing a maintenance analysis tool within a computing infrastructure having functionality to: receive data about a set of physical assets of an infrastructure; analyze the data about the set of physical assets to predict maintenance requirements for each of the set of physical assets; and generate a maintenance plan based on the predicted maintenance requirements for each of the set of physical assets.





BRIEF DESCRIPTION OF THE DRAWINGS


FIG. 1 shows a schematic of an exemplary computing environment in which elements of the present invention may operate;



FIG. 2 shows a maintenance analysis tool that operates in the environment shown in FIG. 1;



FIG. 3 shows a more detailed view of the maintenance analysis tool according to embodiments of the invention; and



FIG. 4 shows a flow diagram of an approach for infrastructure asset management according to embodiments of the invention.





The drawings are not necessarily to scale. The drawings are merely schematic representations, not intended to portray specific parameters of the invention. The drawings are intended to depict only typical embodiments of the invention, and therefore should not be considered as limiting the scope of the invention. In the drawings, like numbering represents like elements.


DETAILED DESCRIPTION OF THE INVENTION

Exemplary embodiments now will be described more fully herein with reference to the accompanying drawings, in which exemplary embodiments are shown. This disclosure may, however, be embodied in many different forms and should not be construed as limited to the exemplary embodiments set forth herein. Rather, these exemplary embodiments are provided so that this disclosure will be thorough and complete and will fully convey the scope of this disclosure to those skilled in the art. In the description, details of well-known features and techniques may be omitted to avoid unnecessarily obscuring the presented embodiments.


The terminology used herein is for the purpose of describing particular embodiments only and is not intended to be limiting of this disclosure. As used herein, the singular forms “a”, “an”, and “the” are intended to include the plural forms as well, unless the context clearly indicates otherwise. Furthermore, the use of the terms “a”, “an”, etc., do not denote a limitation of quantity, but rather denote the presence of at least one of the referenced items. It will be further understood that the terms “comprises” and/or “comprising”, or “includes” and/or “including”, when used in this specification, specify the presence of stated features, regions, integers, steps, operations, elements, and/or components, but do not preclude the presence or addition of one or more other features, regions, integers, steps, operations, elements, components, and/or groups thereof.


Embodiments of this invention are directed to infrastructure asset maintenance management. This approach comprises an end-to-end solution that can take data about physical assets (e.g., maintenance records, usage records) and additional external data (e.g., weather, demographics), and apply advanced analytics to the data to generate business insight, foresight and planning information. Specifically, this approach uses a maintenance analysis tool to improve work management, reduce down time through preventive maintenance, and provide effective demand management. In one embodiment, the maintenance analysis tool is configured to: receive data about a set of physical assets of an infrastructure; and analyze the data about the set of physical assets to predict maintenance requirements for each of the set of physical assets. The maintenance analysis tool further comprises an output component configured to: generate a maintenance plan based on the predicted maintenance requirements for each of the set of physical assets.



FIG. 1 illustrates a computerized implementation 100 of the present invention. As depicted, implementation 100 includes computer system 104 deployed within a computer infrastructure 102. This is intended to demonstrate, among other things, that the present invention could be implemented within a network environment (e.g., the Internet, a wide area network (WAN), a local area network (LAN), a virtual private network (VPN), etc.), or on a stand-alone computer system. In the case of the former, communication throughout the network can occur via any combination of various types of communications links. For example, the communication links can comprise addressable connections that may utilize any combination of wired and/or wireless transmission methods. Where communications occur via the Internet, connectivity could be provided by conventional TCP/IP sockets-based protocol, and an Internet service provider could be used to establish connectivity to the Internet. Still yet, computer infrastructure 102 is intended to demonstrate that some or all of the components of implementation 100 could be deployed, managed, serviced, etc., by a service provider who offers to implement, deploy, and/or perform the functions of the present invention for others.


Computer system 104 is intended to represent any type of computer system that may be implemented in deploying/realizing the teachings recited herein. In this particular example, computer system 104 represents an illustrative system for infrastructure asset management. It should be understood that any other computers implemented under the present invention may have different components/software, but will perform similar functions. As shown, computer system 104 includes a processing unit 106 capable of receiving data regarding a set of physical assets 115 of an infrastructure 119, and sending the data to a maintenance analysis tool 153. Also shown is memory 108 for storing maintenance analysis tool 153, a bus 110, and device interfaces 112.


Computer system 104 is shown communicating with a set (i.e., one or more) of sensor devices 122 that communicate with bus 110 via device interfaces 112. As shown in FIG. 2, sensor devices 122 monitor and receive data from infrastructure 119. In one embodiment, as will be further described below, infrastructure 119 may include all the components of a large water and sewer authority. However, it'll be appreciated that in other embodiments, infrastructure 119 may comprise power utilities, transportation operators, hotels, oil and gas companies, power plants, etc. Sensor devices 122 include one or more sensor devices for capturing data regarding physical assets 115 (e.g., metering units, pipes, fire hydrants, drainage units, etc.) within infrastructure 119. Sensor device 122 can include virtually any type of sensor capable of capturing information and attributes of assets 115 with sufficient quality to support the methods of the invention as described herein.


Processing unit 106 (FIG. 1) collects and routes signals representing outputs from sensor devices 122 to maintenance analysis tool 153. The signals can be transmitted over a LAN and/or a WAN (e.g., T1, T3, 56 kb, X.25), broadband connections (ISDN, Frame Relay, ATM), wireless links (802.11, Bluetooth, etc.), and so on. In some embodiments, the data signals may be encrypted using, for example, trusted key-pair encryption. Different sensor systems may transmit information using different communication pathways, such as Ethernet or wireless networks, direct serial or parallel connections, USB, Firewire®, Bluetooth®, or other proprietary interfaces. (Firewire is a registered trademark of Apple Computer, Inc. Bluetooth is a registered trademark of Bluetooth Special Interest Group (SIG)).


In general, processing unit 106 executes computer program code, such as program code for operating maintenance analysis tool 153, which is stored in memory 108 and/or storage system 116. While executing computer program code, processing unit 106 can read and/or write data to/from memory 108 and storage system 116. In one embodiment, as shown in FIG. 2, storage system 116 contains information about set of physical assets 115, including failure data 131, maintenance data 132, usage data 133, weather data 134, graphical information system (GIS) data 135, and demographic data 136. Storage system 116 can include VCRs, DVRs, RAID arrays, USB hard drives, optical disk recorders, flash storage devices, image analysis devices, general purpose computers, video enhancement devices, de-interlacers, scalers, and/or other visual or data processing and storage elements for storing and/or processing data regarding set of physical assets 115 of infrastructure 119.


Although not shown, computer system 104 could also include I/O interfaces that communicate with one or more external devices 118 that enable a user to interact with computer system 104 (e.g., a keyboard, a pointing device, a display, etc.). In one embodiment, an output is generated by maintenance analysis tool 153 to prioritize the dispatch of preventive maintenance personnel. The output may display key performance indicators of infrastructure 119, including but not limited to: comprehensive query and reporting, dashboarding/reporting, score carding, temporal analysis reporting, spatial analysis reporting, and mapping displays to help you understand and visualize data.


Referring now to FIGS. 2-3 maintenance analysis tool 153 will be described in greater detail. As discussed above, maintenance analysis tool 153 provides an end-to-end, analytics driven approach for asset maintenance management. Maintenance analysis tool 153 explores large complex data sets from disparate sources, performs complex analysis of an event or action to improve maintenance performance, and provides data relationships graphically/visually to aid in comprehension and implementation. To accomplish this, maintenance analysis tool 153 comprises an analysis component 155 configured to receive data about set of physical assets 115 of infrastructure 119. Specifically, analysis component 155 receives data from sensor devices 122, as well as data about physical assets 115 gathered from other sources and stored within storage system 116. In this embodiment, analysis component receives failure data 131, maintenance data 132, usage data 133, weather data 134, graphical information system (GIS) data 135, and demographic data 136.


In one non-limiting example, data regarding a set of fire hydrants within infrastructure 119 is collected and sent to analysis component 155. This data may comprise location data, demographic data, past work order history, usage data, hydrant manufacturer data, weather data, etc. Analysis component 155 is configured to analyze the data about set of physical assets 115 to predict maintenance requirements for each of set of physical assets 115. To accomplish this, in one embodiment, analysis component 155 performs at least one of the following analytics: predictive modeling (e.g., predictive analytics and data mining), optimization (e.g., failure-risk optimization), and spatio-temporal analysis. It will be appreciated that many types and combinations of advanced analytics are possible within the scope of the invention for the purpose of gaining insights, foresights and prescribing actions in support of improved infrastructure maintenance. For example, maintenance analysis tool 153 may provide analysis of the data using one or more of the following: customer and usage analytics (e.g., customer segmentation, usage anomaly detection, usage forecasting, etc.), work management analytics (e.g., spatio-temporal manual scheduling, automated spatial scheduling, automated task level rolling scheduling, dynamic mobile work management, etc.), predictive maintenance analytics (e.g., large scale failure association analysis, asset life time analysis for preventive maintenance optimization, strategic replacement planning, risk estimation and failure prediction, etc.), and space-time analytics (e.g., spatio-temporal pattern detection, user defined alerting, spatio-temporal visualization, multi-dimensional visualization, etc.).


Analysis component 155 performs advanced analytics to produce information 140 regarding the assets 115, as shown in FIG. 3. In this embodiment, analysis component 155 generates failure association data 141, maintenance prediction data 142, event clustering data 143, and usage forecasting data 144. For example, failure association data 141 and event clustering data 143 may comprise data about the failure rates and locations of fire hydrants within infrastructure 119. In this example, analysis component 155 performs a failure association analysis, which examines large volumes of data to discover fire hydrant failure correlations. The failure association analysis may discover, for example, that fire hydrants from manufacturer ‘X’ fail more often than fire hydrants from manufacturer ‘Y’ when the average temperature is between 75 and 91 degrees Fahrenheit. Or, the analysis discovers a higher rate of failure clustered in certain geographic area. As such, a city having an average temperature in that range may wish to purchase fire hydrants from manufacturer ‘Y’ in the future, or modify the preventive maintenance routes and schedules accordingly.


As shown in FIG. 3, information 140 is sent to an output component 160 configured to generate a maintenance plan based on the predictive maintenance requirements for each of the set of physical assets 115, as well as the infrastructure as a whole. In one embodiment, output component 160 is configured to create at least one of the following: a work order schedule 161, and a maintenance route plan 162. For example, based on the failure association data 141 that determined that fire hydrants from manufacturer ‘X’ fail more often than fire hydrants from manufacturer ‘Y’ when the average temperature is between 75 and 91 degrees Fahrenheit, output component 160 may generate an automated scheduling and maintenance plan, as well as an automated routing plan to provide location based dynamic work assignments for maintenance personnel with respect to fire hydrants from manufacturer ‘X’.


Furthermore, as shown in FIG. 3, maintenance route plan 162 may be combined with GIS data 135 to provide location information about physical assets 115. GIS data 135 is commonly presented in the form of a visual map, which provides “layers” of information. GIS maps combine layers of information about a given asset or location, thereby providing an infrastructure operator with a better understanding of specific locations in infrastructure 119. GIS data 135 may be represented as a visual overlay, which provides information about the location of objects such as fire hydrants from manufacturer ‘X’, for example. Output component 160 is configured to apply GIS data 135 to visual media to determine and display street address information, thereby presenting a detailed view of the location of infrastructure objects.


It can be appreciated that the methodologies disclosed herein can be used within a computer system for infrastructure asset management, as shown in FIG. 1. In this case, maintenance analysis tool 153 can be provided, and one or more systems for performing the processes described in the invention can be obtained and deployed to computer infrastructure 102. To this extent, the deployment can comprise one or more of (1) installing program code on a computing device, such as a computer system, from a computer-readable medium; (2) adding one or more computing devices to the infrastructure; and (3) incorporating and/or modifying one or more existing systems of the infrastructure to enable the infrastructure to perform the process actions of the invention.


The exemplary computer system 104 may be described in the general context of computer-executable instructions, such as program modules, being executed by a computer. Generally, program modules include routines, programs, people, components, logic, data structures, and so on that perform particular tasks or implements particular abstract data types. Exemplary computer system 104 may be practiced in distributed computing environments where tasks are performed by remote processing devices that are linked through a communications network. In a distributed computing environment, program modules may be located in both local and remote computer storage media including memory storage devices.


The program modules carry out the methodologies disclosed herein, as shown in FIG. 4. According to one embodiment, at S1 data about a set of physical asset of an infrastructure is received. At S2, the data about the physical assets is analyzed to predict maintenance requirements for each of the set of physical assets. At S3, a maintenance plan is generated based on the predicted maintenance requirements for each of the set of physical assets.


The flowchart of FIG. 4 illustrates the architecture, functionality, and operation of possible implementations of systems, methods and computer program products according to various embodiments of the present invention. In this regard, each block in the flowchart may represent a module, segment, or portion of code, which comprises one or more executable instructions for implementing the specified logical function(s). It should also be noted that, in some alternative implementations, the functions noted in the blocks may occur out of the order noted in the figures. For example, two blocks shown in succession may, in fact, be executed substantially concurrently. It will also be noted that each block of flowchart illustration can be implemented by special purpose hardware-based systems that perform the specified functions or acts, or combinations of special purpose hardware and computer instructions.


Furthermore, an implementation of exemplary computer system 104 (FIG. 1) may be stored on or transmitted across some form of computer readable media. Computer readable media can be any available media that can be accessed by a computer. By way of example, and not limitation, computer readable media may comprise “computer storage media” and “communications media.”


“Computer storage media” include volatile and non-volatile, removable and non-removable media implemented in any method or technology for storage of information such as computer readable instructions, data structures, program modules, or other data. Computer storage media includes, but is not limited to, RAM, ROM, EEPROM, flash memory or other memory technology, CD-ROM, digital versatile disks (DVD) or other optical storage, magnetic cassettes, magnetic tape, magnetic disk storage or other magnetic storage devices, or any other medium which can be used to store the desired information and which can be accessed by a computer.


“Communication media” typically embodies computer readable instructions, data structures, program modules, or other data in a modulated data signal, such as carrier wave or other transport mechanism. Communication media also includes any information delivery media.


The term “modulated data signal” means a signal that has one or more of its characteristics set or changed in such a manner as to encode information in the signal. By way of example, and not limitation, communication media includes wired media such as a wired network or direct-wired connection, and wireless media such as acoustic, RF, infrared, and other wireless media. Combinations of any of the above are also included within the scope of computer readable media.


It is apparent that there has been provided with this invention an approach for infrastructure asset management. While the invention has been particularly shown and described in conjunction with a preferred embodiment thereof, it will be appreciated that variations and modifications will occur to those skilled in the art. Therefore, it is to be understood that the appended claims are intended to cover all such modifications and changes that fall within the true spirit of the invention.

Claims
  • 1. A method for water and sewer infrastructure asset management, comprising: providing a set of sensor devices configured for capturing data about a set of physical assets of an infrastructure, the set of physical assets comprising at least one of: a water or sewer metering unit, a water or sewer pipe, a fire hydrant, or a water or sewer drainage unit;providing a graphical information system;receiving, at the set of sensor devices, data about the set of physical assets of an infrastructure located in a geographic region, the data comprising at least one weather condition that previously necessitated maintenance for each of the set of physical assets;capturing, by the set of sensor devices, the data about the set of physical assets;encrypting the data about the set of physical assets;receiving, by at least one computer, over a network, the encrypted data about the set of physical assets from the set of sensor devices, the network comprising at least one of a local area network, a wide area network, a broadband network, or a wireless network;correlating, by the at least one computer, historical data comprising a manufacturer of each of the set of physical assets, a geographic location of each of the set of physical assets, and at least one weather condition that previously necessitated maintenance for each of the set of physical assets;analyzing, by the at least one computer, the correlated data, the data about the set of physical assets, and data from the graphical information system;predicting, by the at least one computer, based on the analysis, maintenance requirements for each of the set of physical assets arising from an anticipated weather condition similar to the at least one weather condition;identifying, by the at least one computer, based on the analyzing, a subset of the set of physical assets, the subset being of a particular manufacturer and clustered within a portion of the geographic location, the subset comprising a higher rate of previously necessitated maintenance during the at least one weather condition, as compared to other physical assets within the set;generating, by the at least one computer, a maintenance plan for the subset of the set of physical assets based on the analyzing and the identifying; andprioritizing, by the at least one computer, a dispatch of maintenance personnel based on the maintenance plan.
  • 2. The method according to claim 1, the data about the set of physical assets further comprising at least one of the following: failure data, maintenance data, usage data, graphical information system (GIS) data, and demographic data.
  • 3. The method according to claim 1, wherein the analyzing comprises correlating, by the at least one computer, the at least one weather condition that previously necessitated maintenance for each of the set of physical assets with a geographic location of each of the set of physical assets.
  • 4. The method according to claim 1, the analyzing comprising at least one of the following analytics: predictive modeling, optimization, and spatio-temporal analysis.
  • 5. The method according to claim 1, wherein the analytics generates information about the set of physical assets, the information comprising at least one of the following: failure association, maintenance prediction, event clustering, and usage forecasting.
  • 6. The method according to claim 1, the generating comprising creating, by the at least one computer, at least one of the following: a work order schedule, and a maintenance route plan.
  • 7. The method according to claim 1, wherein a service solution provider provides a computer infrastructure that performs the method for one or more consumers.
  • 8. A system for infrastructure asset management comprising: a set of sensor devices in communication with a bus of a computer system, the set of sensor devices configured to capture data about a set of physical assets comprising at least one of: a water or sewer metering unit, a water or sewer pipe, a fire hydrant, or a water or sewer drainage unit;at least one processing unit;memory operably associated with the at least one processing unit;the bus; anda maintenance analysis tool storable in memory and executable by the at least one processing unit, the maintenance analysis tool comprising: an analysis component configured to: receive, at the set of sensor devices, data about the set of physical assets of an infrastructure located in a geographic region, the data comprising at least one weather condition that previously necessitated maintenance for each of the set of physical assets;provide a graphical information system;receive, at the set of sensor devices, data about the set of physical assets of an infrastructure located in a geographic region, the data comprising at least one weather condition that previously necessitated maintenance for each of the set of physical assets;capture, by the set of sensor devices, the data about the set of physical assets;encrypt the data about the set of physical assets;receive, over a network, the encrypted data about the set of physical assets from the set of sensor devices, the network comprising at least one of a local area network, a wide area network, a broadband network, or a wireless network;correlate historical data comprising a manufacturer of each of the set of physical assets, a geographic location of each of the set of physical assets, and at least one weather condition that previously necessitated maintenance for each of the set of physical assets;analyze the correlated data, the data about the set of physical assets, and data from the graphical information system;predict, based on the analysis, maintenance requirements for each of the set of physical assets arising from an anticipated weather condition similar to the at least one weather condition;identify, based on the analyzing, a subset of the set of physical assets, the subset being of a particular manufacturer and clustered within a portion of the geographic location, the subset comprising a higher rate of previously necessitated maintenance during the at least one weather condition, as compared to other physical assets within the set;generate a maintenance plan for the subset of the set of physical assets based on the analyzing and the identifying; andprioritize a dispatch of maintenance personnel based on the maintenance plan.
  • 9. The maintenance analysis tool according to claim 8, the data about the set of physical assets further comprising at least one of the following: failure data, maintenance data, usage data, weather data, graphical information system (GIS) data, and demographic data.
  • 10. The maintenance analysis tool according to claim 8, the analysis component configured to perform at least one of the following analytics: predictive modeling, optimization, and spatio-temporal analysis.
  • 11. The maintenance analysis tool according to claim 8, the analysis component configured to generate information about the set of physical assets, the information comprising at least one of the following: failure association, maintenance prediction, event clustering, and usage forecasting.
  • 12. The maintenance analysis tool according to claim 8, the output component configured to create at least one of the following: a work order schedule, and a maintenance route plan.
  • 13. A computerized system comprising: a set of sensor devices in communication with a bus of a computer, the set of sensor devices configured to capture data about a set of physical assets comprising at least one of: a water or sewer metering unit, a water or sewer pipe, a fire hydrant, or a water or sewer drainage unit; anda computer program product for infrastructure asset management, the computer program product comprising a computer readable storage media, and program instructions stored on the computer readable storage media, which when executed by a processor cause the computer to:receive, at the set of sensor devices, data about the set of physical assets of an infrastructure located in a geographic region, the data comprising at least one weather condition that previously necessitated maintenance for each of the set of physical assets;provide a graphical information system;receive, at the set of sensor devices, data about the set of physical assets of an infrastructure located in a geographic region, the data comprising at least one weather condition that previously necessitated maintenance for each of the set of physical assets;capture, by the set of sensor devices, the data about the set of physical assets;encrypt the data about the set of physical assets;receive, over a network, the encrypted data about the set of physical assets from the set of sensor devices, the network comprising at least one of a local area network, a wide area network, a broadband network, or a wireless network;correlate historical data comprising a manufacturer of each of the set of physical assets, a geographic location of each of the set of physical assets, and at least one weather condition that previously necessitated maintenance for each of the set of physical assets;analyze the correlated data, the data about the set of physical assets, and data from the graphical information system;predict, based on the analysis, maintenance requirements for each of the set of physical assets arising from an anticipated weather condition similar to the at least one weather condition;identify, based on the analyzing, a subset of the set of physical assets, the subset being of a particular manufacturer and clustered within a portion of the geographic location, the subset comprising a higher rate of previously necessitated maintenance during the at least one weather condition, as compared to other physical assets within the set;generate a maintenance plan for the subset of the set of physical assets based on the analyzing and the identifying; andprioritize a dispatch of maintenance personnel based on the maintenance plan.
  • 14. The computer program product of claim 13, the data about the set of physical assets further comprising at least one of the following: failure data, maintenance data, usage data, graphical information system (GIS) data, and demographic data.
  • 15. The computer program product of claim 13, further comprising program instructions stored on the computer readable storage media to perform at least one of the following analytics: predictive modeling, optimization, and spatio-temporal analysis.
  • 16. The computer program product of claim 13, further comprising program instructions stored on the computer readable storage media to generate information about the set of physical assets, the information comprising at least one of the following: failure association, maintenance prediction, event clustering, and usage forecasting.
  • 17. The computer program product of claim 13, further comprising program instructions stored on the computer readable storage media to create at least one of the following: a work order schedule, and a maintenance route plan.
CROSS REFERENCE TO RELATED APPLICATIONS

The present patent document is a continuation of U.S. patent application Ser. No. 12/983,556, filed Jan. 3, 2011, entitled “INFRASTRUCTURE ASSET MANAGEMENT”, the disclosure of which is incorporated herein by reference. The present application is related in some aspects to commonly owned and co-pending application entitled “A SYSTEM AND METHOD FOR FAILURE ASSOCIATION ANALYSIS,”, and U.S. patent application Ser. No. 12/984,019, filed on Jan. 4, 2011; and commonly owned and co-pending application entitled “A SYSTEM AND METHOD FOR RISK OPTIMIZED, SPATIALLY SENSITIVE PREVENTIVE MAINTENANCE SCHEDULING FOR ASSET MANAGEMENT,”, and U.S. patent application Ser. No. 12/954,051, filed on Nov. 24, 2010, the entire contents of which are herein incorporated by reference.

US Referenced Citations (69)
Number Name Date Kind
4827394 Wanner May 1989 A
5615341 Agrawal et al. Mar 1997 A
6026348 Hala Feb 2000 A
6192325 Piety et al. Feb 2001 B1
6226634 Ogihara et al. May 2001 B1
6324533 Agrawal et al. Nov 2001 B1
6385608 Mitsuishi et al. May 2002 B1
6393387 Adriaans et al. May 2002 B1
6496814 Busche Dec 2002 B1
6581045 Watson Jun 2003 B1
6925418 Fujiyama et al. Aug 2005 B2
6952680 Melby et al. Oct 2005 B1
7135956 Bartone et al. Nov 2006 B2
7152035 Suhy, Jr. Dec 2006 B1
7219067 McMullen May 2007 B1
7479875 Fehling et al. Jan 2009 B2
7480640 Elad et al. Jan 2009 B1
7580912 Carlbom Aug 2009 B2
7613804 Raden et al. Nov 2009 B2
7716077 Mikurak May 2010 B1
7746794 Sink Jun 2010 B2
7945524 Anderson et al. May 2011 B2
20020038307 Obradovic et al. Mar 2002 A1
20020042687 Tracy et al. Apr 2002 A1
20020065698 Schick May 2002 A1
20020069035 Tracy et al. Jun 2002 A1
20020087345 Bly et al. Jul 2002 A1
20020116157 Markle et al. Aug 2002 A1
20020143421 Wetzer Oct 2002 A1
20030004765 Wiegand Jan 2003 A1
20030023466 Harper Jan 2003 A1
20030023612 Carlbom et al. Jan 2003 A1
20030154144 Pokorny et al. Aug 2003 A1
20030158702 Busche et al. Aug 2003 A1
20030158703 Lumme et al. Aug 2003 A1
20050027710 Ma et al. Feb 2005 A1
20050143956 Long Jun 2005 A1
20050149570 Sasaki et al. Jul 2005 A1
20050278052 Bett et al. Dec 2005 A1
20060106797 Srinivasa et al. May 2006 A1
20060217993 Anderson Sep 2006 A1
20060282362 Nasr Dec 2006 A1
20070124000 Moughler et al. May 2007 A1
20070142928 Moughler et al. Jun 2007 A1
20070174154 Roberts et al. Jul 2007 A1
20070198586 Hardy et al. Aug 2007 A1
20070203779 Tveit Aug 2007 A1
20070225850 Kamisuwa Sep 2007 A1
20070247789 Benson Oct 2007 A1
20080061959 Breed Mar 2008 A1
20080133300 Jalinous Jun 2008 A1
20080177613 Chan Jul 2008 A1
20080177678 Di Martini et al. Jul 2008 A1
20080306799 Sopko, III et al. Dec 2008 A1
20090002148 Horvitz Jan 2009 A1
20090070338 Spitzig et al. Mar 2009 A1
20090112525 Adani Apr 2009 A1
20090138238 Bakshi et al. May 2009 A1
20090187284 Kreiss et al. Jul 2009 A1
20090204245 Sustaeta et al. Aug 2009 A1
20090271354 Kitayama et al. Oct 2009 A1
20100088141 Hill Apr 2010 A1
20100152910 Taft Jun 2010 A1
20100153156 Guinta et al. Jun 2010 A1
20100179704 Ozog Jul 2010 A1
20110029824 Scholer et al. Feb 2011 A1
20120130759 Davenport et al. May 2012 A1
20120173301 Dong et al. Jul 2012 A1
20150073862 Davenport et al. Mar 2015 A1
Non-Patent Literature Citations (43)
Entry
Modelling preventive maintenance for auxiliary components. Salman T Al-Mishari, S M A Suliman. Journal of Quality in Maintenance Engineering. Bradford: 2008. vol. 14, Iss. 2; p. 148.
A crystal ball for maintenance. David Cullen. Fleet Owner. Overland Park: Oct. 2005. vol. 100, Iss. 10; p. 168, 4 pgs.
U.S. Appl. No. 12/983,556, Office Action, Aug. 6, 2014, 7 pages.
U.S. Appl. No. 12/954,051, Office Action, Aug. 25, 2014, 4 pages.
Timothy Padot, USPTO Office Action, U.S. Appl. No. 12/983,556, Mail Date Apr. 11, 2012, 27 pages.
Timothy Padot, USPTO Final Office Action, U.S. Appl. No. 12/983,556, Mail Date Jul. 24, 2012, 14 pages.
Timothy Padot, USPTO Office Action, U.S. Appl. No. 12/983,556, Mail Date Oct. 24, 2012, 12 pages.
Timothy Padot, USPTO Final Office Action, U.S. Appl. No. 12/983,556, Mail Date Feb. 14, 2013, 17 pages.
Timothy Padot, USPTO Office Action, U.S. Appl. No. 12/983,556, Mail Date Jun. 26, 2013, 19 pages.
Timothy Padot, USPTO Notice of Allowance and Fee(s) Due, U.S. Appl. No. 12/983,556, Mail Date Jan. 10, 2014, 32 pages.
David Cullen, “A Crystal ball for maintenance”, Fleet Owner: Oct. 2005, vol. 100, Iss. 10, 4 pages.
Lorena R. Feacher, USPTO Office Action, U.S. Appl. No. 12/984,019, Mail Date Jul. 3, 2012, 38 pages.
Lorena R. Feacher, USPTO Final Office Action, U.S. Appl. No. 12/984,019, Notification Date Jan. 17, 2013, 61 pages.
Lorena R. Feacher, USPTO Office Action, U.S. Appl. No. 12/984,019, Notification Date Oct. 4, 2013, 57 pages.
Terry Martin, “Modeling System Leverages GIS to Assess Critical Assets”, Waterworld, Apr. 2005, 2 pages.
Anna C. Gilbert et al., “Domain-Driven Data Synopses for Dynamic Quantiles”, IEEE Transactions on Knowledge and Data Engineering, vol. 17, No. 7, Jul. 2005, 12 pages.
Younghee Kim et al., “Mining Association Rules for RFID Data with Concept Hierarchy”, ICACT, Feb. 15-18, 2009, pp. 1002-1006.
IBM, “The SmarterCities Leadership Series Smarter Water”, Nov. 2010, http://www.ibm.com/smarterplanet/global/files/gb—en—uk—cities—smarterplanet—DC—WASA.pdf, 2 pages.
L.H. Cui et al., “The WebGIS Based Jiangsu Oilfield Management System Implemented With a Spatio-Temporal Data Model”, Nanjing University, Nanjing, 210093, PRC and Key Laboratory of Regional Climate-Environment Research for Temperate East Asia, Bejing, Jun. 2008, pp. 773-778.
Johnna Ronee Loftis, USPTO Office Action, U.S. Appl. No. 12/954,051, Mail Date Mar. 29, 2012, 10 pages.
Johnna Ronee Loftis, USPTO Final Office Action, U.S. Appl. No. 12/954,051, Mail Date Jul. 30, 2012, 7 pages.
Johnna Ronee Loftis, USPTO Office Action, U.S. Appl. No. 12/954,051, Mail Date Dec. 19, 2012, 7 pages.
Johnna Ronee Loftis, USPTO Final Office Action, U.S. Appl. No. 12/954,051, Notification Date Apr. 11, 2013, 10 pages.
Johnna Ronee Loftis, USPTO Office Action, U.S. Appl. No. 12/954,051, Notification Date Sep. 24, 2013, 8 pages.
Johnna Ronee Loftis, USPTO Final Office Action, U.S. Appl. No. 12/954,051, Notification Date Mar. 18, 2014, 8 pages.
U.S. Appl. No. 12/983,556, Office Action Communication, Nov. 24, 2014, 22 pages.
U.S. Appl. No. 12/984,019, Office Action Communication, Jan. 16, 2015, 40 pages.
Padot, U.S. Appl. No. 12/983,556, Office Action dated Mar. 31, 2015, 11 pages.
Miloucheva et al., Spatio-Temporal Qos Pattern Analysis in large scale Internet environment, Salzburg Research, Austria and Telefonica, Spain, Sep. 16, 2003.
Romer, “Distributed Mining of Spatio-Temporal Event Patterns in Sensor Networks”, Euro-American Workshop on Middleware for Sensor Networks 2006, 103-116.
U.S. Appl. No. 12/984,019, Final Office Action dated Aug. 12, 2015, 37 pages.
Loftis, U.S. Appl. No. 12/954,051, Office Action dated Feb. 27, 2015, 5 pages.
Loftis, U.S. Appl. No. 14/536,960, Office Action dated Jun. 4, 2015, 12 pages.
U.S. Appl. No. 14/536,960, Office Action dated Jan. 30, 2015, 23 pages.
U.S. Appl. No. 12/954,051, Notice of Allowance dated Jun. 6, 2014, 8 pages.
Al-Mishari et al., “Modelling preventive maintenance for auxiliary components”, Journal of Quality Maintenance Engineering, vol. 14, Iss.2, p. 148, Bradford: 2008.
Zhang et al., “Spatio-Tennoral Modeling in Road Network Change Detection and Updating”, Commission II, WGII/1,2,7 and Commission VII, WG VII/6, 2005, 6 pages.
Lorena R. Feacher, USPTO Final Office Action, U.S. Appl. No. 12/984,019, Notification Date May 13, 2014, 75 pages.
Jeremy Mennis et al., “Mining Association Rules in Spatio-Temporal Data: An Analysis of Urban Socioeconomic and Land Cover Change”, Transactions in GIS, 2005, vol. 9, Issue 1, pp. 5-17.
Padot, U.S. Appl. No. 12/983,556, Notice of Allowance dated Sep. 16, 2015, 25 pages.
Intelligent wireless condition-based maintenance. (Machine Monitoring/Networking) Sensors 19.6 (Jun. 2002): 14(10).
Choi et al., On-line condition monitoring and diagnostics of power distribution equipment, Proceedings of 2008 International Conference on Condition Monitoring and Diagnosis CMD 2008; 692-692, IEEE Computer society, (Dec. 1, 2007).
Loftis, U.S. Appl. No. 12/954,051, Examiner's Answer dated Dec. 3, 2014, 7 pages.
Related Publications (1)
Number Date Country
20140236650 A1 Aug 2014 US
Continuations (1)
Number Date Country
Parent 12983556 Jan 2011 US
Child 14259528 US