Abstract
Nuclear fuels are taken from a nuclear reactor pressure vessel, a rail for running is mounted under the reactor pressure vessel drain piping in parallel with a horizontal portion of the reactor pressure vessel drain piping inside a pedestal positioned on the lower side of the reactor pressure vessel, an inspection apparatus is mounted on the-rail, and the inspection apparatus is moved along the rail to inspect the reactor pressure vessel drain piping, whereby the reactor pressure vessel drain piping can be surely inspected while reducing radiation exposure to an inspector.
Description




BACKGROUND OF THE INVENTION




The present invention relates to an inspection method of piping in a nuclear power plant and, more particularly, to a method and apparatus for inspecting reactor pressure vessel drain piping inside a pedestal on the lower side of the reactor pressure vessel.




As a conventional pipe inspection method (non-destructive inspection technique) in a nuclear power plant, a method using X-ray transmission and RT (radiographic test) calculation tomography (CT) is disclosed in JP A 9-304303. Further, JP A 6-27092 discloses an ultrasonic test (hereunder, referred to as UT), using an apparatus which is absorbed on piping by utilizing suction force of a vacuum pump and moves.




When the above-mentioned conventional technique is applied for inspection of reactor pressure vessel drain piping inside a pedestal in a nuclear power plant, the following problems occur.




Several hundred control rod drive housings each fixed to the reactor pressure vessel stand inside the pedestal, and a distance therebetween is about 145 mm and narrow. Cables for operating the control rod drives are connected to lower sides of the control rod drive housings. An automatic exchanger of the control rod drives is disposed on the bottom of the pedestal, and there is little gap between the cables and the automatic exchanger. Further, a gap between the reactor pressure vessel drain piping and the ceiling of the pedestal is only about 300 mm, and an elbow portion to be inspected, which is a part of the reactor pressure vessel drain piping, is disposed at a central portion separated about 2 m from a side wall of the pedestal. Further, an ambient atmospheric dose is high, being influenced by deposits in reactor water, so that it is difficult to work inside the pedestal (particularly at the central portion) for a long time.




In this manner, the reactor pressure vessel drain piping inside the pedestal is disposed in surroundings in which it is very difficult for person to approach and directly inspect. When the conventional technique disclosed in JP A 9-304303 is applied thereto, the inspection apparatus is moved in manual, so that it is necessary for an inspector to approach to the reactor pressure vessel drain piping to be inspected and install the inspection apparatus. Therefore, it is impossible to really apply this conventional technique thereto.




Further, in the case where the conventional technique disclosed in JP A 6-27092 is applied, it is necessary to cause the inspection apparatus to be absorbed to the reactor pressure vessel drain piping, however, since the drain piping has metal heat insulator wound thereon and the heat insulator has a convex and concave shape formed on the surface thereof, sufficient absorption force can not be obtained and there is the possibility that the inspection apparatus is fallen during the inspection. That is, it is difficult to surely inspect the drain piping with high reliability.




SUMMARY OF THE INVENTION




An object of the present invention is to provide an inspection method and an inspection apparatus for piping, each of which is able to surely inspect reactor pressure vessel drain piping inside a pedestal in a nuclear power plant while reducing exposure of radiation to an inspector.




In the present invention, nuclear fuels are taken out from a nuclear reactor pressure vessel, a rail for running is mounted under reactor pressure vessel drain piping in parallel with a horizontal portion of the reactor pressure vessel drain piping inside a pedestal positioned on the lower side of the reactor pressure vessel, an inspection apparatus is mounted on the rail, and the inspection apparatus is moved along the rail to inspect the reactor pressure vessel drain piping.




Under the condition that the nuclear fuels are taken out from the inside of the reactor pressure vessel, the rail and the inspection apparatus each are mounted, whereby it is possible to reduce exposure of radiations to an inspector. Further, the reactor pressure vessel drain piping can be surely inspected by moving the inspection apparatus along the rail mounted under the drain piping in parallel to the horizontal portion of the drain piping.




Preferably, the rail is mounted at a peripheral portion inside the pedestal.




The exposure of radiations to the inspector can be further reduced by mounting the rail at the peripheral portion inside the pedestal.




Further, preferably, the inspection apparatus is provided with a mechanism for preventing the inspection apparatus from being fallen from the rail.




The reactor pressure vessel drain piping can be surely inspected by providing the mechanism for preventing the inspection apparatus from being fallen from the rail.




Further, preferably, the rail is fixed to control rod drive housings.




The rail is sufficiently fixed without providing any new fixing member.




In another invention, nuclear fuels are taken out from a nuclear reactor pressure vessel, an inspection apparatus is mounted on a beam preset under reactor pressure vessel drain piping in parallel with a horizontal portion of the reactor pressure vessel drain piping inside a pedestal positioned on the lower side of the reactor pressure vessel, and the inspection apparatus is moved along the beam to inspect the reactor pressure vessel drain piping.




Since the beam preset under the reactor pressure vessel drain piping is used as a rail for traveling the inspection apparatus, the work can be simplified in addition to the above-mentioned effects.




Another invention comprises a carriage set on a rail arranged under reactor pressure vessel drain piping in parallel with a horizontal portion of the drain piping inside a pedestal, a driving means for moving the carriage along said rail, a falling prevention mechanism for preventing the carriage from falling from the rail, a camera mounted on the carriage and monitoring a relative position between the camera and the drain piping, and a thickness measuring means mounted on the carriage and measuring the thickness of the drain piping.




Preferably, a control means for controlling the driving means, a displaying means for displaying an image monitored by the camera and an outputting means for outputting a measurement result obtained by the thickness measuring means are provided for installation outside the pedestal. Thereby, the reactor pressure vessel drain piping can be inspected by remote operation from the outside of the pedestal.











BRIEF DESCRIPTION OF THE DRAWINGS





FIG. 1

is a flow chart showing an embodiment in which an inspection method of piping according to the present invention is applied to reactor pressure vessel drain piping inside a pedestal in a nuclear power plant;





FIG. 2

is a rough vertical sectional view of the inside of a reactor pressure vessel;





FIG. 3



a


is a rough vertical sectional view of the inside of a pedestal;





FIG. 3



b


is a perspective view of an elbow portion of reactor pressure vessel drain piping inside the pedestal in

FIG. 3



a;







FIG. 3



c


is a rough plane view of the inside of the w pedestal shown in

FIG. 3



a;







FIG. 4



a


is a perspective view of an example of a rail for running;





FIG. 4



b


is a view of “A” portion of

FIG. 4



a


, showing the rail when it is carried in/out;





FIG. 4



c


is a view of “A” portion of

FIG. 4



a


, showing the rail when it is set;





FIG. 4



d


is a perspective view of a carriage set on the rail in

FIG. 4



a;







FIGS. 5



a


to


5




d


each are a view showing a mounting procedure of the plate type rail;





FIGS. 6



a


and


6




b


each are a view of another example of the rail;





FIG. 6



c


is a plan view of the rail shown in

FIGS. 6



a


and


6




b;







FIG. 7



a


is a perspective view of a carriage of inspection apparatus mounted on the wire type rail;





FIG. 7



b


is a front view of a wheel mounted on the carriage, indicated by A in

FIG. 7



a;







FIG. 7



c


is a side view of the portion of the carriage, indicated by A in

FIG. 7



a;







FIG. 8



a


is a rough perspective view of an inspection apparatus in which a RT method is used;





FIG. 8



b


is a side view of a part of the inspection apparatus shown in

FIG. 8



a;







FIG. 8



c


is a plane view of the inspection apparatus in

FIG. 8



a;







FIG. 9

is views showing main inspection procedures of inspection method using the RT method;





FIG. 10



a


is a rough perspective view of an inspection apparatus in which the UT method is applied;





FIG. 10



b


is a side view of the inspection apparatus in

FIG. 10



a;







FIG. 10



c


is a plane view of the inspection apparatus in

FIG. 10



a;







FIG. 10



d


is a sectional view of an ultrasonic probe construction of the inspection apparatus shown in

FIG. 10



a;







FIG. 11



a


is a rough vertical sectional view of the inside of a pedestal in which beams exist; and





FIG. 11



b


is a plane view of

FIG. 11



a.













DESCRIPTION OF EMBODIMENTS OF THE INVENTION




First, surroundings in which reactor pressure vessel drain piping to be inspected is provided inside a pedestal will be explained.

FIG. 2

is a rough vertical sectional view of the inside of a reactor pressure vessel, and

FIG. 3



a


is a rough vertical sectional view of the inside of the pedestal. As shown in

FIG. 2

, the pedestal


2


is positioned on the lower side of the cylindrical reactor pressure vessel


1


in a reactor primary containment vessel.




As shown in

FIG. 3



a


, the pedestal


2


is a columnar space of diameter of about 5.6 m, height of about 4.5 m, for instance. Several hundred control rod drive housings


3


each fixed to the reactor pressure vessel


1


stand inside the pedestal


2


, the distance therebetween is about 145 mm which is narrow. Cables


5


for operation of the control rod drives are disposed under the respective control rod drive housings


3


and each connected thereto. A control rod drive automatic exchanger


6


is provided on the bottom of the pedestal


2


.




The reactor pressure vessel drain piping


4


for discharging reactor water is connected to the bottom (reactor bottom portion) at a central portion of the reactor pressure vessel


1


. The reactor pressure vessel drain piping


4


extends vertically downwards from the reactor bottom portion, changes the direction to a horizontal direction through an elbow socket


40


positioned at a slightly lowered position (refer to

FIG. 3



b


) and extends horizontally toward the side wall of the pedestal


2


. For example, the reactor pressure vessel drain piping


4


has a diameter of about 60 mm and the elbow socket


40


has a diameter of about 76 mm. A horizontally extending portion (horizontal portion) of the reactor pressure vessel drain piping


4


is covered with heat insulator


41


. A gap between the reactor pressure vessel drain piping


4


and the ceiling of the pedestal


2


is about 300 mm, and the elbow portion to be inspected of the reactor pressure vessel drain piping


4


is positioned at a central portion separated away about 2 m from the side wall of the pedestal


2


.




An embodiment of the present invention will be explained hereunder, referring to drawings.

FIG. 1

is a flow chart showing an embodiment that an inspection method of piping according to the present invention is applied to the reactor pressure vessel drain piping inside the pedestal in the nuclear power plant.




First, in

FIG. 1

, the reactor is shutdown at step S


1


, the reactor pressure vessel


1


is opened and nuclear fuels are taken out and moved to a nuclear fuel pool adjacent to the reactor pressure vessel


1


at step S


2


. A rail


9


(railway) for traveling an inspection apparatus is mounted in the vicinity of the reactor pressure vessel drain piping


4


inside the pedestal


2


. As shown in

FIGS. 3



a


and


3




c


, the rail


9


is mounted, under the reactor pressure vessel drain piping


4


, in parallel with the horizontal portion of the reactor pressure vessel drain piping


4


.




The rail


9


has length extending from one portion of the side wall inside the pedestal


2


to the opposite portion (in

FIGS. 3



a


and


3




c


, from a left end to a right end), and both ends of the rail


9


are fixed to the control rod drive housings


3


adjacent to the both ends by fixing belts


8


in this manner, by fixing the rail


9


to the control rod drive housings


3


, it is unnecessary to provide any new fixing members.




An example of the rail


9


is shown in

FIGS. 4



a


to


4




d


. The rail


9


is made in a multi-layer structure (plate type) in which several plates


10


of light-weight material such as plastic material are laminated and then a magnetic metal plate


11


is laminated thereon. In this case, wheels


32


magnetically adhered to the metal plate


11


can be used as wheels of a running carriage


7




a


of the inspection apparatus. Falling of the carriage


7




a


from the rail


9


can be prevented by providing the wheels


32


with auxiliary wheels


33


. Further, remote operation can be done by controlling a drive motor of the wheels


32


through a cable


29


.




Here, an example of mounting procedures of the plate type rail


9


will be explained, referring to

FIGS. 5



a


to


5




d


. First, in

FIGS. 5



a


and


5




b


, the plate type rail


9


folded is carried in at an inlet


2




a


of the pedestal


2


. The rail


9


has a butt hinge


12


connecting each plate


10


and can fold up when it is carried in as shown in

FIGS. 4



b


and


4




c


. Therefore, the rail


9


can be carried in without interference with structures inside the pedestal


2


.




Next, in

FIG. 5



c


, the folded rail is extended from the one side (left side) in the pedestal


2


to the opposite side (right side). In

FIG. 5



d


, the fixing belts


8


attached to the both ends of the rail


9


are fixed to the control rod drive housings


3


, thereby to fix the rail


9


. The fixing belts


8


each are made of rubber, and dampers are mounted on the sides (insides) adhered to the control rod drive housings


3


.




The control rod drive automatic exchanger


6


of height about 2 m from the bottom is installed in the lower portion of the pedestal


2


, and rotates 360° in the peripheral direction. Therefore, since an inspector can move (along the side wall) in the peripheral direction in the pedestal


2


, a mounting position of the rail


9


is not limited to any specific position as long as it is inside a gap (space) between the side wall of the pedestal


2


and the control rod drive housings


3


. Further, by mounting the butt hinge


12


on the lower side of the rail


9


, the rail


9


does not fold even if the load of the inspection apparatus is applied on the upper surface of the rail.




Another example of the rail


9


will be explained, referring to

FIGS. 6



a


to


6




c


. In this case, wires are used instead of the plates of the plate-type rail. First, fixing frames


13


and


14


for fixing wires which are used as a rail, are arranged as shown in

FIG. 6



c


. The fixing frames


13


,


14


are mounted on the control rod drive housings


3


positioned peripheral portions (around the side wall) inside the pedestal


2


in the direction that the horizontal portion (horizontal direction in

FIG. 6



c


) of the reactor pressure vessel drain piping


4


extends, as in

FIGS. 3



a


,


3




c.






As shown in

FIG. 6



a


, the fixing frame


13


is provided with wire winding winches of 4 in total, two winches at two positions on the upper side and two winches at two positions on the lower side. As shown in

FIG. 6



b


, the fixing frame


14


has 4 wires in total, attached thereto in advance, which are two upper wires


52


and two lower wires


53


. In

FIG. 6



c


, the fixing frame


13


and the fixing frame


14


are installed so that the positions of the winches


17


of the fixing frame


13


oppose the upper wires


52


and lower wires


53


of the fixing frame


14


. Under this condition, the upper wires


52


and lower wires


53


of the fixing frame


14


are extended to the corresponding winches


17


of the fixing frame


13


, and the wire type rail


9


is formed by tightly pulling the wires.




The fixing frames


13


,


14


each are provided with an upper stopper


15


and lower stopper


16


. The upper stopper


15


and lower stopper


16


each are movable as shown by arrows in

FIGS. 6



a


and


6




b


, and the fixing frames


13


and


14


can be carried, with the stoppers


15


,


16


being folded when they are carried into the pedestal


2


. Further, tension of each of the wires can be adjusted by the winches


17


of the fixing frame


13


to be strong or weak. In

FIGS. 6



a


to


6




c


, stoppers for engaging the fixing frames


13


,


14


with the control rod drive housings


3


to fix the fixing frames are omitted.





FIGS. 7



a


to


7




c


show the condition that the carriage


7




a


for the inspection apparatus is mounted on the wire type rail. As shown in

FIG. 7



a


, the carriage


7




a


is provided with detachable hooks


21


at four corners. Hang wires


19


each extend vertically upward from the hook


21


, and a pulley


18


is provided on an end of each hang wire


19


. The pulleys


18


are engaged on the upper wires


52


, whereby the carriage


7




a


can move on the upper wires


52


in parallel with the upper wires


52


. As shown in

FIG. 7



b


, the wheels


20


have grooves


20




a


on the running faces, respectively, and the lower wires


53


are fitted in the grooves


20




a


to be able to run on the lower wires


53


. As shown in

FIG. 7



c


, the wheels each have a stopper


22


for preventing disengagement thereof from the lower wire


53


. Further, the wheels


20


are constructed so as to be detachable.




After the mounting of the rail


9


is completed in the manner as above, the inspection apparatus


7


is mounted on one end of the rail


9


at step S


4


in FIG.


1


. Here, the one end means one end on the side opposite to the side on which the horizontal portion of the reactor pressure vessel drain piping


4


extends, in the case of

FIG. 3



a


, the one end is a left side end.




The inspection apparatus


7


is connected to a control apparatus


49


installed outside the pedestal


2


by cables


29


transmitting control signals. The control apparatus


49


comprises a monitor, an arithmetic unit, a remote operation panel, a memory, etc. The control apparatus


49


can effect remote operation of the inspection apparatus


7


and store data obtained through inspection.




In this manner, under the condition that nuclear fuels are taken out from the reactor pressure vessel


1


, a mounting operation of the rail


9


and the inspection apparatus


7


is practiced at the peripheral portion inside the pedestal


2


, whereby radiation exposure to the inspector can be reduced.




Next, at step S


5


in

FIG. 1

, the inspection apparatus


7


is moved-to a prescribed position on the rail


9


by driving a drive motor built in the inspection apparatus


7


. As shown in

FIG. 8



a


, the inspection apparatus


7


has a CCD camera


26


mounted thereon, and images taken by the CCD camera


26


are displayed on the monitor of the control apparatus


49


as images. Since a position around an object or part to be inspected is directly confirmed by the monitor images, it is possible to move the inspection apparatus


7


to an appropriate position. The inspection apparatus


7


is moved by the remote operation panel of the control apparatus


49


until the reactor pressure vessel drain piping contacts with a tip portion of a positioning plate


27


provided on the inspection apparatus


7


.




In this case, since it is necessary to contact the positioning plate


27


to the elbow portion of the reactor pressure vessel drain piping


4


, only the elbow portion is inspected. However, the inspection apparatus


7


can be moved to the horizontal portion of the reactor pressure vessel drain piping


4


by removing the positioning plate


27


mounted on the inspection apparatus


7


and monitoring by the CCD camera


26


, so that it is possible to inspect the horizontal portion. Further, since the wheels


32


of the inspection apparatus


7


are constructed so as to be detachable, they can be mounted or dismounted according to the plate type or wire type rail


9


.




Next, after the inspection apparatus


7


is moved to a prescribed position by remote operation of the remote operation panel, the reactor pressure vessel drain piping


4


is inspected at step S


6


in FIG.


1


. As an inspection method, the above-mentioned two methods of RT and UT can be used. Here, the principle of each of RT and UT is explained briefly.




In the case of RT, radiations are emitted from a radiation source and impinge on an object to be inspected. A part of the radiations reflects on the object, but another part passes through the object and projects on a screen disposed on the opposite side to the radiation source. Since the radiations have property reflation factor or transmission factor changes according to difference in material of the object, a transmission image of the object is projected on the film. Thickness of the object is obtained on the basis of the transmission image.




Next, the method of UT is explained. This is measurement by difference in time required for reciprocation of ultrasonic pulses in the object. A part of ultrasonic pulses oscillated from a ultrasonic probe reflects on a surface of the object (surface echo), the remaining is reflected on the rear surface (rear surface echo) and they are received by the ultrasonic probe. The thickness of the object is obtained from difference in time required for reaching the ultrasonic probe of the surface echo and the rear surface echo at this time.




Here, an example of a rough construction and its principal operation of the inspection apparatus


7


using the RT method is explained, referring to

FIGS. 8



a


to


8




c


and FIG.


9


.

FIGS. 8



a


to


8




c


each are a view of a rough construction of the inspection apparatus


7


and

FIG. 9

is perspective views showing main procedures of an inspection method.




As shown in

FIGS. 8



a


to


8




c


, this inspection apparatus


7


is provided, as a RT apparatus unit, with a film


28


, a radiation source transmission tube


30


, a radiation source cable


31


, an arm


35


, a radiation source holder


36


, actuators


37


and


38


, a control apparatus


39


, etc. The RT apparatus unit is mounted on the carriage


7




a


, but it is omitted in part in

FIGS. 8



a


to


8




c.






In FIG.


9


(


a


), the inspection apparatus


7


with this construction is run on the rail


9


, and stopped at a prescribed position in FIG.


9


(


b


) In FIG.


9


(


c


), the arm


35


is opened by the actuator


37


, and he radiation source holder


36


is opened by the actuator


38


. In FIG.


9


(


d


), the radiation source is sent out to the top portion


34


through the radiation source transmitting tube


30


embraced by the radiation source cable


31


. In FIG.


9


(


e


), only the radiation source holder


36


is set up vertically.




Next, in FIG.


9


(


f


), the elbow portion of the reactor pressure vessel drain piping


4


is inspected by radiating radiations (X-rays) from the radiation source disposed on the top


34


. Radiation radiated from the radiation source pass through the elbow and project on a film


28


provided on the opposite side. In this case, the reason why the arm


35


is extended horizontally is to secure a distance of some extent between the radiation source and the elbow (an object to be inspected). This is because when the distance between the radiation source and the object to be inspected is too small, the radiations emitted from the point-like radiation source impinge on the object to be inspected before sufficiently dispersing spreading and an inspection range becomes small.




In this manner, the reactor pressure vessel drain piping


4


can be surely inspected by moving the inspection apparatus


7


to the elbow of the reactor pressure vessel drain piping


4


along the rail mounted under the reactor pressure vessel drain piping


4


in parallel with the horizontal portion of the drain piping


4


.




After the above-mentioned taking picture is finished, in FIG.


9


(


g


), the inspection apparatus is moved to the original position, removed from the rail


9


and recovered. FIG.


9


(


g


) corresponds to steps S


7


and S


8


in FIG.


1


. The above all the procedures in FIGS.


9


(


a


) to (


g


) are practiced in remote operation by the remote operation panel of the control apparatus


49


through the cable


29


. After recovering of the inspection apparatus


7


, development treatment of the film is carried out, and thickness conversion is calculated. The thickness conversion is a ratio that the thickness value obtained from the film


28


is divided by the thickness value of piping of standard. In this case, it is possible to watch the condition of the interior. It also is possible to effect the thickness measurement of the piping along the axis of the piping and the condition of the interior at the same time.




Next, in

FIG. 1

, the rail is removed at step S


9


, the nuclear fuels are refueled from the nuclear fuel pool into the reactor pressure vessel


1


at step S


10


and the nuclear reactor is restarted at step S


11


. A series of inspection works is completed by the steps


1


to


11


.




By the way, as shown in

FIG. 8



c


, in the case where the arm


35


and the radiation source holder


36


are horizontal, the control rod drive housings


3


become a bar, so that the inspection apparatus


7


can not be recovered. Therefore, the inspection apparatus has the control apparatus


39


provided thereon. That is, in the case where the arm


35


and the radiation source holder


36


can not be folded by remote operation because of disorder in the electric power supply, etc., the control apparatus


39


actuates the actuators


37


and


38


to automatically fold the arm


35


and the radiation source holder


36


, whereby the inspection apparatus


7


can be recovered.




Next, an example using the UT method is explained, referring to

FIGS. 10



a


to


10




d


.

FIGS. 10



a


to


10




d


are rough construction views of an inspection apparatus


7


in which the UT method is used. As shown in

FIGS. 10



a


to


10




c


, this inspection apparatus


7


is provided with a frame


25


formed by flames


25




a


and


25




b


each mounting an ultrasonic probe


44


thereon, rollers


42


, a gear


43


, a retainer


45


, a rotation driving motor


23


, a belt


24


, etc, as an UT apparatus unit. The UT apparatus unit is constructed so that it can be detachable by one touch.




In this inspection apparatus, also, a positioning plate


27


and a CCD camera


26


are mounted, and it is possible to surely determine the position of piping to be inspected in the same manner as in the RT apparatus unit. The construction of a carriage


7




a


is the same as in

FIGS. 8



a


to


8




c


, so that its explanation is omitted here.




The frame


25


is composed of two members (the frames) each of which has a half-circular section, supported by the retainer


45


. The frame


25


has a groove formed on the outer side, and it also is supported by the rollers


42


. The gear


43


is attached to the lower portion of the frame


25


, the two frames


25




a


and


25




b


are rotated in an opposite direction (peripheral direction) to each other by a gear train including the gear


43


. The gear


43


is driven by the rotation drive motor


23


through the belt


24


. The rotation drive motor


23


can be remotely operated by a remote operation panel


49


through the cable


29


.




The frames


25




a


and


25




b


each have the two ultrasonic probes


44


arranged thereon as shown in

FIGS. 10



b


and


10




c


. With this arrangement of the ultrasonic probes


44


, it is possible to inspect the whole periphery of the piping by rotating 90° the frames


25




a


and


25




b


in the peripheral direction.

FIG. 10



d


is an enlarged view of the ultrasonic probe


44


. As shown in

FIG. 10



d


, a spring


47


, an intermediate plate


48


and the ultrasonic probe


44


are arranged in a case


46


. The movable intermediate plate


48


is pressing the ultrasonic probe


44


by elastic force of the spring


47


. Thereby, the ultrasonic probe


44


can be always in intimate contact with an inspection surface.




Inspection of piping using this apparatus is practiced by the following procedures.




First, at the position of

FIGS. 10



b


and


10




c


, reflection signals from the piping are detected by the ultrasonic probes


44


. The detected signals (reflection signals) detected through a signal line


51


are stored in the memory of the control apparatus


49


through the cable


29


. Next, the frames


25




a


and


25




b


are rotated same angles in the peripheral directions opposite to each other, respectively, to inspect the piping in the same manner. The inspection is repeated until the rotation angle of each frame


25




a


,


25




b


reaches to 90°. The detection signals stored in the memory in this manner are rearranged so as to correspond to peripheral positions of angles 0°-360°, whereby it is possible to obtain section information of piping thickness in the peripheral direction.




Those procedure correspond to step s


6


in FIG.


1


. Steps S


1


-S


5


, S


7


-S


11


are the same as in the RT method, so that their explanation is omitted here.




In a real nuclear reactor, in some cases, a beam corresponding to the rail


9


in

FIG. 3

exist originally. An example of such a case is shown in

FIGS. 11



a


and


11




b


.

FIG. 11



a


is a rough vertical sectional view of the inside of a pedestal in which beams exist, and

FIG. 11



b


is a plan view of

FIG. 11



a


. In this case as shown in

FIG. 11



a


, the beams


9




a


are positioned at a lower side of the reactor pressure vessel drain piping


4


. Further, as shown in

FIG. 11



b


, the plurality of beams


9




a


are arranged in the horizontal portion of the reactor pressure vessel drain piping


4


in parallel with each other. The width of each beam


9


is about 115 mm, for instance.




In this case, since the works in steps S


3




a


nd S


9


can be omitted, inspection working of the reactor pressure vessel drain piping can be further simplified. Further, by providing the inspection apparatus


7


with the falling prevention mechanism such as the auxiliary wheels


33


as shown in

FIG. 8

, there is no fear that the inspection apparatus


7


is fallen from the beam


9




a


by only disposing the inspection apparatus


7


on the beam


9




a


. Further, once the inspection apparatus


7


is installed on the beam


9




a


, in some cases, it is unnecessary to remove the inspection apparatus


7


from the beam


9




a


even after finishing of the inspection. In this case, when the reactor pressure vessel drain piping is inspected next or later, inspection can be effected under the condition that the nuclear fuels are loaded. That is, the inspection working can be further simplified.




By using the above-mentioned method, an inspection of drain piping inside the pedestal


2


, which has been impossible, becomes possible, and it can be greatly contributed to protection and maintenance of piping.



Claims
  • 1. In combination with a nuclear reactor pressure vessel, said nuclear reactor vessel being positioned in a pedestal, reactor pressure vessel drain piping being positioned on the bottom of said nuclear reactor pressure vessel, an inspection apparatus for piping, said inspection apparatus for piping comprising:a carriage set on a rail arranged under said reactor pressure vessel drain piping in parallel with a horizontal portion of said reactor or pressure vessel drain piping inside a said pedestal; a driving means for moving said carriage along said rail; a falling prevention mechanism for preventing said carriage from falling from said rail; a camera mounted on said carriage and monitoring a relative position between said camera and said reactor pressure vessel drain piping; and a thickness measuring means mounted on said carriage for measuring the thickness of said reactor pressure vessel drain piping.
  • 2. An inspection apparatus for piping according to claim 1, further comprising:a control means for controlling said driving means; a displaying means for displaying an image monitored by said camera; and an outputting means for outputting a measurement result obtained by sa d thickness measuring means; and wherein said means each are installed outside said pedestal.
  • 3. An inspection apparatus for piping according to claim 1, wherein said rail is bendable, said carriage is supported by said rail, and said rail has end portions which are fixed.
  • 4. An inspection apparatus for piping according to claim 3, wherein said rail comprises a plurality of plate members and hinge mea s for flexibly connecting adjacent plate members.
  • 5. An inspection apparatus for piping according to claim 3, wherein said end portions of said rail are fixed to control rod drive housings adjacent to said end portions.
Parent Case Info

This application is a divisional application of U.S. Ser. No. 09/492,126 filed Jan. 27, 2000, now U.S. Pat. No. 6,434,207.

US Referenced Citations (8)
Number Name Date Kind
3511091 Thome, II May 1970 A
3930942 Thome, I Jan 1976 A
4336104 Figlhuber et al. Jun 1982 A
4375165 Sterke Mar 1983 A
4385523 Gugel et al. May 1983 A
4795606 Fenemore et al. Jan 1989 A
4825769 Watts May 1989 A
5982839 Hatley Nov 1999 A
Foreign Referenced Citations (2)
Number Date Country
6-27092 Feb 1994 JP
9-304303 Nov 1997 JP