1. Field of the Invention
The present invention relates an installation construction method for boiler facilities, and particularly relates to an installation construction method for improving work efficiency and safety in the installation of the various types of equipment disposed within a steel structure building and accessory members accessory thereto.
2. Description of the Related Art
Secondary air for combustion to the boiler main unit 1 is guided to a furnace combustion chamber with a burner, via a forced draft fan, an air pre-heater 5, a wind box 6, and so on forth. Also, coal fuel transporting air is guided from the air pre-heater 5 to a mill 8 via a primary air duct 7.
Coal to serve as fuel is stored in a bunker 9, and is supplied to the mill 8 while being measured by a stoker 10, and is pulverized to a predetermined particle size. The fine powder coal generated at the mille 8 is supplied to the burner disposed within the wind box 6 through a fuel pipe along with the coal fuel transporting air, and is burned in the furnace combustion chamber.
The hot combustion gas generated by combustion in the furnace combustion chamber is then subjected to heat exchanges within an internal fluid flowing through a secondary superheater 11, a tertiary superheater 12, a reheater 13, a primary superheater 14, an economizer 15, and so on forth, disposed within an air flue of the boiler main unit 1. The combustion gas subjected to heat exchange passes through an economizer discharge gas duct 16, a denitration device, the air pre-heater 5, and an air pre-heater discharge gas duct 17, and is externally discharged from the boiler building 3.
On the other hand, water feed to the boiler main unit 1 is performed by water passing from a condenser outside of the boiler building 3 through a main water pipe to each of the heat exchangers such as the economizer 15, where heat exchange creates high-temperature high-pressure steam, which passes through a main steam pipe and is guided to a high-pressure turbine outside of the boiler building 3.
Steam from a medium-pressure turbine is guided to the reheater 13 via a low-temperature reheating steam pipe, and the reheated steam passes through a high-temperature reheating steam pipe and is guided to a low-pressure turbine outside of the boiler building 3.
As shown in
Subsequently, as shown in
With the conventional boiler facility installation construction method, the series of work from manufacturing the steel beams to installation on-site to construct the boiler building has been performed by a steel fabrication manufacturer. The ducts, bunker, stoker, fuel pipes, soot blower, various types of piping, cable tray, railing, electric panel, and so on forth, to be installed in the boiler building have been carried in and installed following completion of the boiler building.
Boiler facility installation construction methods are described in, for example, Japanese Unexamined Patent Application Publication No. 07-091603, Japanese Unexamined Patent Application Publication No. 08-114302, Japanese Unexamined Patent Application Publication No. 08-261405, Japanese Unexamined Patent Application Publication No. 11-211003, Japanese Unexamined Patent Application Publication No. 2002-098304, and Japanese Unexamined Patent Application Publication No. 2002-213707.
With such conventional boiler facility installation construction methods, ducts, bunker, stoker, fuel pipes, soot blower, various types of piping, cable tray, railing, various types of electric equipment such as electric panels, and so on forth, and accessory members accessory thereto, were carried in and installed following completion of the boiler building.
Accordingly, ducts, piping, and the like, were carried into the boiler building from the side thereof as duct panels, piping pieces, and so on forth, in relatively small sizes, to facilitate carrying into the assembled boiler building, by crane, temporary monorail, chain hoist, and so forth.
This means that the work of carrying in and installing various types of equipment and accessories is concentrated in the period following completion of the boiler building, leading to problems in that all work regarding ducts, piping, and so forth, is high-place work, meaning deterioration in work capability, and in that work within a limited space means work is restricted, requiring a longer construction schedule, and further that the amount of high-risk work at high places is great, leading to higher construction costs, and increased risk of workplace accidents.
Also, with arrangements wherein multiple members are combined to form a unit, and these are hoisted above the installation location using a crane and the lower for installation, already-assembled beams and columns and the like tend to interfere with carrying in and installing the units.
The present invention has been made to solve the aforementioned shortcomings of conventional methods, and accordingly, it is an object of the present invention thereof to provide an installation construction method for boiler facilities with high work efficiency.
According to an aspect of the present invention, with an installation construction method for boiler facilities in which the boiler facilities include a boiler building configured of a steel structure, a boiler main unit to be installed within the boiler building, various types of equipment to be installed to the boiler main unit, and accessory members which are accessory thereto; during construction of the boiler building, the various types of equipment and the accessory members are carried into the boiler building and installed.
Floor units, having at least floor beams and a floor, assembled beforehand within a hoisting limit load of a crane, may be carried in and installed in parallel with construction of the boiler building.
Tie-ins for tying in to tie-in portions of the boiler building may be provided to the floor units.
A duct block, having at least a duct casing panel, internal support, and a damper, assembled beforehand within a hoisting limit load of a crane, may be carried in and installed in parallel with construction of the boiler building.
Thermal insulation and cladding sheets may be installed to the duct block beforehand.
A fuel pipe block, having at least a fuel pipe and a supporting device thereof, assembled beforehand within a hoisting limit load of a crane, may be carried in and installed in parallel with construction of the boiler building.
Piping, fabricated so as to be within a length to allow for transportation from factory to the site, is carried in and installed in parallel with construction of the boiler building.
A piping skid, integrally linking at least piping and a valve, may be carried in and installed in parallel with construction of the boiler building.
A bunker block, in which component parts of a bunker are assembled in a ring-like form beforehand within a hoisting limit load of a crane, may be carried in and installed in parallel with construction of the boiler building.
A floor unit integral article, configured by the floor unit and at least one of the various types of equipment and accessory members accessory thereto being assembled beforehand within a hoisting limit load of a crane, may be carried in and installed in parallel with construction of the boiler building.
The boiler building may be constructed in the shape of a box with one side opened when viewed from above so that one side of the boiler building forms an opening, with the boiler main unit being placed inside the boiler building through the opening and installed therein.
With the present invention, as described above, the various types of equipment and accessory members to be installed within the boiler building are carried in and installed while building the boiler building, so the columns and beams of the boiler building pose little obstruction, and accordingly the various types of equipment and accessory members can be easily carried in an installed. Also, construction of the boiler building and carrying in and installation of the various types of equipment and accessory members are performed in parallel, thereby improving work efficiency.
Moreover, a great part of the various types of equipment and accessory members to be installed within the boiler building can be assembled near the ground rather than at high places, and can be directly assembled by crane as with the steel structure, so work safety can be improved, and costs can be reduced due to standardization of work amount during the construction schedule and improved work efficiency.
Next, an embodiment of the present invention will be described, with reference to the drawings.
First, as shown in
The steel structure is made up of columns and beams, which are fastened at the joints thereof with, for example, L-shaped fasteners and bolts. The columns are vertically divided in to multiple sections, and are assembled on-site for use. Floors are laid on steel beams, and are configured of floor beams, grating, checker plate, or the like, each fixed by welding.
A floor unit has at least floor beams and a floor, and has been assembled beforehand, taking the hoisting limit load of the crane into consideration. Tie-ins are provided to the floor unit to facilitating tying in with the steel beams and columns. The tie-ins are used to dispose the floor units between the steel columns on each level.
A duct block 47, fuel block 48, cable tray 49, mill, and so forth, are carried in above the first floor unit 45, and installed. The duct block 47, fuel block 48, and cable tray 49 may be carried in separately from or together with the first floor unit 45. For example, an arrangement wherein the floor unit 45 and the duct block 47 are integrally formed and carried in, or wherein the floor unit 45 and the fuel block 48 are integrally formed and carried in, would have greater work efficiency.
Forming blocks such as the duct block 47 or the fuel block 48, and integration thereof with the floor unit 45, are performed nearby the installation site, or in a plant.
Rectangular ducts are formed of casing in a box shape, with supports provided inside the ducts and thermal insulation and cladding sheets on the outside, and dampers and expansion joints provided along the way. Round ducts are formed of casing in a cylindrical shape, with thermal insulation and cladding sheets on the outside, and expansion joints provided along the way.
The duct block 47 has at least duct casing panels, internal supports, and dampers, and is configured beforehand in a block form so as to be within the hoisting limit load of the crane.
Fuel pipes are configured of straight piping, bent piping, joints for connection thereof, and supports for supporting these with the steel structure. The fuel block 48 has at least fuel pipes and supporting devices (supporting members) thereof, and is configured beforehand in a block form so as to be within the hoisting limit load of the crane.
A second floor unit 50 is assembled above the first floor unit 45, with a duct block 47 and stoker 51 being carried in an attached.
Next, as shown in
The bunker block 54 (the bunker cone block 57 and later-described bunker cylinder block 60) has been assembled beforehand in a ring-like form, taking the hoisting limit load of the crane into consideration.
The piping 55 is in a long shape, fabricated so as to be within a length that would allow for transportation between the factory and the site.
Next, as shown in
A sixth floor unit 59 is assembled above the fifth floor unit 58, with a piping skid and bunker cylinder block 60 and the like being carried in and installed. The piping skid is configured of integrally linking at least piping and valves.
Next, as shown in
As shown in
While the mill 8 and bunker 9 and the like are exemplarily described as being installed to the front of the boiler building 34 in the above embodiment, these may be disposed to the sides of the boiler building 34.
Number | Date | Country | Kind |
---|---|---|---|
2005-297867 | Oct 2005 | JP | national |